This document is a Return to Service Letter for a fuel storage tank that was inspected in accordance with API 653 standards. The letter states that the tank was inspected by the company and is in suitable condition to be returned to service, with no mandatory repairs required. It provides the dates for the next required API 653 out-of-service and in-service inspections. The document also references the related federal contract opportunity, which is for API 653 internal fuel inspections at two facilities at the Atlantic City ANG in New Jersey, to be performed by the U.S. Army Corps of Engineers, Omaha District.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
[COMPANY Letter Head]
DATE
Subject: RETURN TO SERVICE LETTER
STORAGE TANK NO. [ XXXXX]
Fuel System Inspection, [Location] Contract No. [XXXXX], Task Order [XX] Out-of-Service [API 653] Inspection
Tank [XXX] was inspected for serviceability evaluation in accordance with the requirements of [API STD 653, XX Edition, Date.]. The Inspection was performed by [Company Name] on [ddmmmyy].
The results of the inspection: The tank is in suitable condition for return to service. There are no mandatory repairs that require immediate attention, in order to prevent imminent risk to system operators, equipment integrity, or the adjacent environment.
The Tank was returned to service on [date].
RECOMMENDED FUTURE INSPECTION DATES no later than (NLT):
| API 653 Out-Of-Service tank inspection | [date] | ||
| API 653 In-Service tank inspection | [date] | ||
| …UT Roundness…Corrosion…etc | [date] |
SATE REGULATIONS (N/A if Not Applicable):
[State] Regulations follow [……] State Regulations for API 653 Out-Of-Service tank inspections is NLT [date]
Final documents will be included in the close out documentation as required by the task order.
Prepared by:
[Inspectors Name] [Title] [Company] API 653 Certified Inspector No. [XXXX]
Installation acknowledgement:
[Installation Point of Contact Name] [Title]
[USACE Fuels Project Manager] Fuels Project Manager
USACE-NWO-PMS-C
[USACE Fuels Project Manager Email]@usace.army.mil