Attachment E CEG GFI and Contract Deliverable Timeline 03SEP24.pdf

PDF 230 KB Posted

Attached to
Commercial Ethernet Gateway (CEG) Hawaii Federal contract opportunity
Solicitation number
HC101924R0004
Issued by
Defense Information Systems Agency

About this file

This document appears to be an attachment that outlines the key milestones and contract deliverable timeline for a federal contract opportunity.

The attachment details the timeline for key contract milestones, including the contract award, issuance of task orders for the Gateways and Access Sites, and the installation and acceptance of the Gateways and Access Sites. It also specifies the timeline for the contractor to provide updates to the Contract Implementation Plan (CIP) over the course of the contract. The contract opportunity is for the Defense Information Systems Agency's (DISA) Commercial Ethernet Gateway (CEG) initiative in Hawaii, with the purpose of migrating to Ethernet-based services to eliminate legacy technology and reduce telecommunications costs. The contract will be awarded as a single Indefinite Delivery/Indefinite Quantity (ID/IQ) contract with a 10-year period of performance. The solicitation is being evaluated using the lowest price technically acceptable method, and the NAICS code is 517111.

View the file

Other files for this federal contract opportunity

Other files attached to Commercial Ethernet Gateway (CEG) Hawaii, newest first.
File Type Posted
HC1019-24-R-0004 AMD 0005 20Sep24.pdf PDF
HC1019-24-R-0004 AMD 0004 19Sep24.pdf PDF
HC1019-24-R-0004 AMD 0003 16SEP24.pdf PDF
HC1019-24-R-0004 AMD 0002 13SEP24.pdf PDF
Exhibit 6 Questions and Answers AMD 0002 12Sep24.xlsx XLSX spreadsheet
Exhibit 1 Price Schedule 12SEP24 (LOCKED) AMD 0002.xlsx XLSX spreadsheet
Exhibit 1 Price Schedule 09SEP24 (LOCKED) AMD 0001.xlsx XLSX spreadsheet
Exhibit 3 DD Form 254 printed 06Sep24 AMD 0001.pdf PDF
HC1019-24-R-0004 AMD 0001.pdf PDF
Exhibit 6 Questions and Answers AMD 0001.xlsx XLSX spreadsheet
Attachment B CEG Design Document 03SEP24.pdf PDF
Attachment F CEG Demarcation Definitions 03SEP24.pdf PDF
Exhibit 3 DD Form 254 blank - Draft.pdf PDF
Exhibit 4 DISA Subcontracting Plan Checklist 03SEP24.docx DOCX document
Attachment C CEG Technical Implementation Standards 03SEP24.pdf PDF
Attachment D Notice of Completion Template 03SEP24.xlsx XLSX spreadsheet
Exhibit 1 Price Schedule 03SEP24 (LOCKED).xlsx XLSX spreadsheet
Exhibit 6 Solicitation Questions Template 03SEP24.xlsx XLSX spreadsheet
HC101924R0004 03Sep24.pdf PDF
Exhibit 2 QASP 03SEP24.pdf PDF
Exhibit 5 Mission-Essential Contractor Services 03SEP24.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

KEY

MILESTONES

A= Contract Award T1 = 1st TO award for the Gateways T2 = 2nd TO for the Att A Access Sites Tn = Access Sites awarded as IDIQ

Contractor DISA DISA Internal Process Step

Indicates that data is an input or an output of the step. See Data Requirements List on next slide for detailed description of requirement

Contract Award

Proposal Submission w/ Initial CIP

Initial In- Process Review

A A+10

Gov’t Comments on CIP

Contractor revises CIP

Final

CIP

delivered

Gov’t Approves

CIP

Gateway Installation Completed

Gateway Task Order

Issued

Gateway Accepted

A+30A+15A -

A+35 T1 T1+

Contractor submits Test

Report

T1+

Contractor submits NOC

T1+

Gateway Operational

T1+

Access Site Installation

Commences

Contractor revises CIP w/as-built changes

CIP Update #1 delivered

T1+

CIP Update #2 deliveredCIP Update #3 deliveredCIP Update #4 deliveredCIP Update #5 deliveredCIP Update #6 deliveredCIP Update #7 deliveredCIP Update #n delivered

Access Site #1 Completed

Contractor submits AS#1 Test Report

Access Site #1 Accepted

Contractor submits

AS#1 NOC

Access Site OperationalAccess Site #2

Completed Contractor submits AS#1 Test Report

Access Site #1 Accepted

Contractor submits

AS#1 NOC

Access Site OperationalAccess Site #3

Completed Contractor submits AS#1 Test Report

Access Site #1 Accepted

Contractor submits

AS#1 NOC

Access Site OperationalAccess Site #4

Completed Contractor submits AS#1 Test Report

Access Site #1 Accepted

Contractor submits

AS#1 NOC

Access Site OperationalAccess Site #5

Completed Contractor submits AS#1 Test Report

Access Site #1 Accepted

Contractor submits

AS#1 NOC

Access Site OperationalAccess Site #n

Completed Contractor submits AS#1 Test Report

Access Site #1 Accepted

Contractor submits Site #n NOC

Access Site Operational

Monthly or as req’d

For IDIQ sites NGT 45days

ARO/GFI

<2 days after site completion

For Att A sites 75% NGT 120 days

ARO/GFI

Notification*

<3 days after test report submitted

* Testing timeframe restarts if Gov’t disputes results

<2 days after Gov’t acceptance

Completed TSO

Site POC and access verified

Includes PDC Completed TSO

A

CEG GFI and Contract Deliverable Timeline

CEG R3-7 PWS Attachment E Version 5 dated 2/05/2021

Site Prep completed

Access Site Task Orders

Issued A

Site POC and access verified

To be done by customer or via

CEG Task 5

T2...

n

2 3

7 7

B

B

B

Contractor updates CIP w/operational data

Contractor revises CIP w/as-built changes 4 6

44 6

CEG Regions 3-7 Data Requirements List

1. Data to be provided by the contractor in the Initial CIP (i.e. with proposal submission)

a. Proposed CEG Locations b.Basic Gateway Site Design (Proposed CEG Equipment, physical connections, Rack

Elevations, Electrical Power Requirements)

c. Basic Access Site Design (Proposed Access Site Equipment, typical physical connections) d.Proposed Test Procedures for CEG and Access Sites

e. A draft Implementation Schedule (high-level) for both CEGs and Access Sites. A few

Notional Sites should be used, sufficient to show your understanding of reporting requirements. The following information is required in the schedule:

i. Planned Install Start (For Initial CIP submission assume 1 Sep 2021 Contract Award)

ii. Planned Install Complete iii.Contractor Implementation POC iv.POC Tel#

v. POC Email vi.Contractor NOC/Trouble Reporting Contact Info vii.For Access Sites: VLAN Homing Assignments (i.e., Ref ID# of Gateway to which an Access Site will be connected) – this does not need to be in proposal submission and can be deferred until the Initial IPR

2. Data to be provided by the contractor in the Final CIP (after award and 1st IPR, reflecting Government review/comments) - All of 1 above updated per 1st IPR comments and at a minimum:

a. Updated 1b CEG Site Design showing site specific equipment installation details (e.g.

Rack/shelf/slot/port for Contractor equipment and all connections to site including description of patch panel cross connects and slot/port of connection on customer equipment)*.

b.Updated Access Site Design if applicable

c. Updated 1e Implementation Schedule with all data updated to current plan

i. This should include any issues the contractor has had in locating the site or contacting the site POC. The goal here is to identify government issues preventing installation planning from moving forward and resolving them as quickly as possible.

3. GFI to be provided to the contractor by the Government prior to Gateway Installation

a. Updated Government Gateway Site POC information b.Verification that site personnel are prepared to support upcoming installation

c. VLAN IDs for all NNI VLANs d.CCSDs for all NNIs

CONTRACTING OFFICER ISSUES GATEWAY TASK ORDER TO CONTRACTOR

* Note that if contractor elects to use its own site to host gateway equipment, the fiber path between the contractor’s site and the Government Gateway location must be described in the CEG Design Document to include complete and accurate A location and Z location information, circuit ID and POC information for the service provider location.

4. Data to be provided by Contractor in support of Gateway Acceptance – All are part of next CIP Update unless otherwise noted:

a. As-built CEG Site Design – to include at a minimum:

i. Vendor Circuit ID for each NNI

ii. CCSD for each NNI

iii. VLAN ID(s) for each NNI

iv. Any changes to information provided in 2a if applicable b.Updated Implementation Schedule – if unchanged from 2c then so state

c. Any changes to GFI provided in 3 identified or necessitated during installation – if none so state d.Test Report for every NNI (this is a separate deliverable)

e. Notice of Completion (this is a separate deliverable)

5. GFI to be provided by Government prior to Access Site Installation

a. Updated Government Access Site POC information b.Verification that site personnel are prepared to support upcoming installation

c. VLAN IDs for all VLANs d.CCSDs for EVCs

6. Data to be Provided by the Contractor in CIP (Final or Updates) prior to Access Site Installations

a. Updated Implementation Schedule for Access Sites. The information in 1e must be updated if changed from previous CIP revision.

b.Updated Access Site Design if applicable

CONTRACTING OFFICER ISSUES TASK ORDERs TO CONTRACTOR FOR

ATTACHMENT A SITES AND SUBSEQUENTLY FOR OPTIONAL SITES

IF APPLICABLE

7. Data to be provided by Contractor in support of Access Site Acceptance – All are part of the CIP Update immediately following the installation unless otherwise noted:

a. As-built Access Site Design – to include at a minimum:

i. Vendor Circuit IDs for each EVC

ii. CCSD for each EVC

iii. VLAN ID(s) for every contractor established VLAN on each EVC (VLAN IDs provided by DISA)

iv. Any changes to information provided in 2b if applicable b.Updated Implementation Schedule – if unchanged from previous CIP Updates then so state

c. Any changes to GFI provided in 5 identified or necessitated during installation – if none so state d.Test Report for every EVC (this is a separate deliverable)

e. Notice of Completion for each EVC (this is a separate deliverable)

2a

2b

1e

1b

1e

CEG R3-7 PWS Attachment E Version 5 dated 2/05/2021

CEG Service Request Data Requirement Details

Gateway on Att A DISA will submit DDSF order to create

H Trunk IE73 Reviews and Creates TSO

DITCO receives TSO - selects applicable CEG Contract and CLIN for Service

DITCO Issues Task Order Vendor Provides Service

EVC on Att A User creates DDSF order IE73 Reviews and Creates TSO with applicable VLAN instructions DITCO receives TSO - selects applicable

CEG Contract and CLIN for Service DITCO Issues Task Order Vendor Provides Service

NEW EVC (not on Att A) USER creates DDSF order for type of service= E-line IE73 Reviews and Creates TSO with applicable VLAN instructions DITCO receives TSO - selects applicable

CEG Contract and CLIN for Service DITCO Issues Task Order Vendor Provides Service

Modify Existing EVC (NRC) USER CREATES DDSF order for type of service used for creating VLAN IE73 Reviews and Creates TSO with applicable VLAN instructions DITCO receives TSO - selects applicable CEG Contract and Task 5 CLIN for Service

DITCO Issues Task Order Vendor Provides Service

Modify Existing EVC (no cost) USER CREATES TSR for type of service used to create VLAN IE73 Reviews and Creates TSO with applicable VLAN instructions DITCO receives TSO - Creates/Sends

Contract Record Update Vendor Provides Service Requestor (?) Closes Ticket

N

EW

S

ER

VI

CE

R

EQ

UI

RE

M

EN

T

C us to m er A cc ep ts in se rv ic e

Since this is a service already included in the contract DISA contacts Contractor POC to provide VLAN Assignments DISA provides VLAN assignments with TO.

Contractor provides Gateway Homing

Customer identify in TSR no Converged CE Router; VLANs need to be on seperate interfaces. Identify HAIPE if applicable

Customer identify in TSR Converged CE Router avail - Vendor Trunk terminates there (if not already so configured)

Identify which VLANs are pushed by Vendor, which by customer

DISA POC closes Service Request

CEG R3-7 PWS Attachment E Version 5 dated 2/05/2021

Sheet1

NEW SERVICE REQUIREMENT Gateway on Att A DISA will submit DDSF order to create H Trunk IE73 Reviews and Creates TSO DITCO receives TSO - selects applicable CEG Contract and CLIN for Service DITCO Issues Task Order Vendor Provides Service Customer Accepts /in service

EVC on Att A User creates DDSF order IE73 Reviews and Creates TSO with applicable VLAN instructions DITCO receives TSO - selects applicable CEG Contract and CLIN for Service DITCO Issues Task Order Vendor Provides Service

NEW EVC (not on Att A) USER creates DDSF order for type of service= E-line IE73 Reviews and Creates TSO with applicable VLAN instructions DITCO receives TSO - selects applicable CEG Contract and CLIN for Service DITCO Issues Task Order Vendor Provides Service

Modify Existing EVC (NRC) USER CREATES DDSF order for type of service used for creating VLAN

Murray, Timothy P: Customer identify in TSR no Converged CE Router; VLANs need to be on seperate interfaces. Identify HAIPE if applicable IE73 Reviews and Creates TSO with applicable VLAN instructions

Murray, Timothy P: Identify which VLANs are pushed by Vendor, which by customer DITCO receives TSO - selects applicable CEG Contract and Task 5 CLIN for Service DITCO Issues Task Order Vendor Provides Service

Modify Existing EVC (no cost) USER CREATES TSR for type of service used to create VLAN

Murray, Timothy P: Customer identify in TSR Converged CE Router avail - Vendor Trunk terminates there (if not already so configured) IE73 Reviews and Creates TSO with applicable VLAN instructions DITCO receives TSO - Creates/Sends Contract Record Update Vendor Provides Service Requestor (?) Closes Ticket

Murray, Timothy P: DISA POC closes Service Request

Murray, Timothy P: Customer identify in TSR no Converged CE Router; VLANs need to be on seperate interfaces. Identify HAIPE if applicable

Murray, Timothy P: Identify which VLANs are pushed by Vendor, which by customer

Murray, Timothy P: Customer identify in TSR Converged CE Router avail - Vendor Trunk terminates there (if not already so configured) Contractor provides Gateway Homing

DISA provides VLAN assignments with TO.

Since this is a service already included in the contract DISA contacts Contractor POC to provide VLAN Assignments

&"-,Bold"&12&F

CEG GFI and Contract Deliverable Timeline
CEG Regions 3-7 Data Requirements List
CEG Service Request Data Requirement Details