Attachment E CEG GFI and Contract Deliverable Timeline 03SEP24.pdf
PDF 230 KB Posted
- Attached to
- Commercial Ethernet Gateway (CEG) Hawaii Federal contract opportunity
- Solicitation number
- HC101924R0004
- Issued by
- Defense Information Systems Agency
About this file
This document appears to be an attachment that outlines the key milestones and contract deliverable timeline for a federal contract opportunity.
The attachment details the timeline for key contract milestones, including the contract award, issuance of task orders for the Gateways and Access Sites, and the installation and acceptance of the Gateways and Access Sites. It also specifies the timeline for the contractor to provide updates to the Contract Implementation Plan (CIP) over the course of the contract. The contract opportunity is for the Defense Information Systems Agency's (DISA) Commercial Ethernet Gateway (CEG) initiative in Hawaii, with the purpose of migrating to Ethernet-based services to eliminate legacy technology and reduce telecommunications costs. The contract will be awarded as a single Indefinite Delivery/Indefinite Quantity (ID/IQ) contract with a 10-year period of performance. The solicitation is being evaluated using the lowest price technically acceptable method, and the NAICS code is 517111.
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KEY
MILESTONES
A= Contract Award T1 = 1st TO award for the Gateways T2 = 2nd TO for the Att A Access Sites Tn = Access Sites awarded as IDIQ
Contractor DISA DISA Internal Process Step
Indicates that data is an input or an output of the step. See Data Requirements List on next slide for detailed description of requirement
Contract Award
Proposal Submission w/ Initial CIP
Initial In- Process Review
A A+10
Gov’t Comments on CIP
Contractor revises CIP
Final
CIP
delivered
Gov’t Approves
CIP
Gateway Installation Completed
Gateway Task Order
Issued
Gateway Accepted
A+30A+15A -
A+35 T1 T1+
Contractor submits Test
Report
T1+
Contractor submits NOC
T1+
Gateway Operational
T1+
Access Site Installation
Commences
Contractor revises CIP w/as-built changes
CIP Update #1 delivered
T1+
CIP Update #2 deliveredCIP Update #3 deliveredCIP Update #4 deliveredCIP Update #5 deliveredCIP Update #6 deliveredCIP Update #7 deliveredCIP Update #n delivered
Access Site #1 Completed
Contractor submits AS#1 Test Report
Access Site #1 Accepted
Contractor submits
AS#1 NOC
Access Site OperationalAccess Site #2
Completed Contractor submits AS#1 Test Report
Access Site #1 Accepted
Contractor submits
AS#1 NOC
Access Site OperationalAccess Site #3
Completed Contractor submits AS#1 Test Report
Access Site #1 Accepted
Contractor submits
AS#1 NOC
Access Site OperationalAccess Site #4
Completed Contractor submits AS#1 Test Report
Access Site #1 Accepted
Contractor submits
AS#1 NOC
Access Site OperationalAccess Site #5
Completed Contractor submits AS#1 Test Report
Access Site #1 Accepted
Contractor submits
AS#1 NOC
Access Site OperationalAccess Site #n
Completed Contractor submits AS#1 Test Report
Access Site #1 Accepted
Contractor submits Site #n NOC
Access Site Operational
Monthly or as req’d
For IDIQ sites NGT 45days
ARO/GFI
<2 days after site completion
For Att A sites 75% NGT 120 days
ARO/GFI
Notification*
<3 days after test report submitted
* Testing timeframe restarts if Gov’t disputes results
<2 days after Gov’t acceptance
Completed TSO
Site POC and access verified
Includes PDC Completed TSO
A
CEG GFI and Contract Deliverable Timeline
CEG R3-7 PWS Attachment E Version 5 dated 2/05/2021
Site Prep completed
Access Site Task Orders
Issued A
Site POC and access verified
To be done by customer or via
CEG Task 5
T2...
n
2 3
7 7
B
B
B
Contractor updates CIP w/operational data
Contractor revises CIP w/as-built changes 4 6
44 6
CEG Regions 3-7 Data Requirements List
1. Data to be provided by the contractor in the Initial CIP (i.e. with proposal submission)
a. Proposed CEG Locations b.Basic Gateway Site Design (Proposed CEG Equipment, physical connections, Rack
Elevations, Electrical Power Requirements)
c. Basic Access Site Design (Proposed Access Site Equipment, typical physical connections) d.Proposed Test Procedures for CEG and Access Sites
e. A draft Implementation Schedule (high-level) for both CEGs and Access Sites. A few
Notional Sites should be used, sufficient to show your understanding of reporting requirements. The following information is required in the schedule:
i. Planned Install Start (For Initial CIP submission assume 1 Sep 2021 Contract Award)
ii. Planned Install Complete iii.Contractor Implementation POC iv.POC Tel#
v. POC Email vi.Contractor NOC/Trouble Reporting Contact Info vii.For Access Sites: VLAN Homing Assignments (i.e., Ref ID# of Gateway to which an Access Site will be connected) – this does not need to be in proposal submission and can be deferred until the Initial IPR
2. Data to be provided by the contractor in the Final CIP (after award and 1st IPR, reflecting Government review/comments) - All of 1 above updated per 1st IPR comments and at a minimum:
a. Updated 1b CEG Site Design showing site specific equipment installation details (e.g.
Rack/shelf/slot/port for Contractor equipment and all connections to site including description of patch panel cross connects and slot/port of connection on customer equipment)*.
b.Updated Access Site Design if applicable
c. Updated 1e Implementation Schedule with all data updated to current plan
i. This should include any issues the contractor has had in locating the site or contacting the site POC. The goal here is to identify government issues preventing installation planning from moving forward and resolving them as quickly as possible.
3. GFI to be provided to the contractor by the Government prior to Gateway Installation
a. Updated Government Gateway Site POC information b.Verification that site personnel are prepared to support upcoming installation
c. VLAN IDs for all NNI VLANs d.CCSDs for all NNIs
CONTRACTING OFFICER ISSUES GATEWAY TASK ORDER TO CONTRACTOR
* Note that if contractor elects to use its own site to host gateway equipment, the fiber path between the contractor’s site and the Government Gateway location must be described in the CEG Design Document to include complete and accurate A location and Z location information, circuit ID and POC information for the service provider location.
4. Data to be provided by Contractor in support of Gateway Acceptance – All are part of next CIP Update unless otherwise noted:
a. As-built CEG Site Design – to include at a minimum:
i. Vendor Circuit ID for each NNI
ii. CCSD for each NNI
iii. VLAN ID(s) for each NNI
iv. Any changes to information provided in 2a if applicable b.Updated Implementation Schedule – if unchanged from 2c then so state
c. Any changes to GFI provided in 3 identified or necessitated during installation – if none so state d.Test Report for every NNI (this is a separate deliverable)
e. Notice of Completion (this is a separate deliverable)
5. GFI to be provided by Government prior to Access Site Installation
a. Updated Government Access Site POC information b.Verification that site personnel are prepared to support upcoming installation
c. VLAN IDs for all VLANs d.CCSDs for EVCs
6. Data to be Provided by the Contractor in CIP (Final or Updates) prior to Access Site Installations
a. Updated Implementation Schedule for Access Sites. The information in 1e must be updated if changed from previous CIP revision.
b.Updated Access Site Design if applicable
CONTRACTING OFFICER ISSUES TASK ORDERs TO CONTRACTOR FOR
ATTACHMENT A SITES AND SUBSEQUENTLY FOR OPTIONAL SITES
IF APPLICABLE
7. Data to be provided by Contractor in support of Access Site Acceptance – All are part of the CIP Update immediately following the installation unless otherwise noted:
a. As-built Access Site Design – to include at a minimum:
i. Vendor Circuit IDs for each EVC
ii. CCSD for each EVC
iii. VLAN ID(s) for every contractor established VLAN on each EVC (VLAN IDs provided by DISA)
iv. Any changes to information provided in 2b if applicable b.Updated Implementation Schedule – if unchanged from previous CIP Updates then so state
c. Any changes to GFI provided in 5 identified or necessitated during installation – if none so state d.Test Report for every EVC (this is a separate deliverable)
e. Notice of Completion for each EVC (this is a separate deliverable)
2a
2b
1e
1b
1e
CEG R3-7 PWS Attachment E Version 5 dated 2/05/2021
CEG Service Request Data Requirement Details
Gateway on Att A DISA will submit DDSF order to create
H Trunk IE73 Reviews and Creates TSO
DITCO receives TSO - selects applicable CEG Contract and CLIN for Service
DITCO Issues Task Order Vendor Provides Service
EVC on Att A User creates DDSF order IE73 Reviews and Creates TSO with applicable VLAN instructions DITCO receives TSO - selects applicable
CEG Contract and CLIN for Service DITCO Issues Task Order Vendor Provides Service
NEW EVC (not on Att A) USER creates DDSF order for type of service= E-line IE73 Reviews and Creates TSO with applicable VLAN instructions DITCO receives TSO - selects applicable
CEG Contract and CLIN for Service DITCO Issues Task Order Vendor Provides Service
Modify Existing EVC (NRC) USER CREATES DDSF order for type of service used for creating VLAN IE73 Reviews and Creates TSO with applicable VLAN instructions DITCO receives TSO - selects applicable CEG Contract and Task 5 CLIN for Service
DITCO Issues Task Order Vendor Provides Service
Modify Existing EVC (no cost) USER CREATES TSR for type of service used to create VLAN IE73 Reviews and Creates TSO with applicable VLAN instructions DITCO receives TSO - Creates/Sends
Contract Record Update Vendor Provides Service Requestor (?) Closes Ticket
N
EW
S
ER
VI
CE
R
EQ
UI
RE
M
EN
T
C us to m er A cc ep ts in se rv ic e
Since this is a service already included in the contract DISA contacts Contractor POC to provide VLAN Assignments DISA provides VLAN assignments with TO.
Contractor provides Gateway Homing
Customer identify in TSR no Converged CE Router; VLANs need to be on seperate interfaces. Identify HAIPE if applicable
Customer identify in TSR Converged CE Router avail - Vendor Trunk terminates there (if not already so configured)
Identify which VLANs are pushed by Vendor, which by customer
DISA POC closes Service Request
CEG R3-7 PWS Attachment E Version 5 dated 2/05/2021
Sheet1
NEW SERVICE REQUIREMENT Gateway on Att A DISA will submit DDSF order to create H Trunk IE73 Reviews and Creates TSO DITCO receives TSO - selects applicable CEG Contract and CLIN for Service DITCO Issues Task Order Vendor Provides Service Customer Accepts /in service
EVC on Att A User creates DDSF order IE73 Reviews and Creates TSO with applicable VLAN instructions DITCO receives TSO - selects applicable CEG Contract and CLIN for Service DITCO Issues Task Order Vendor Provides Service
NEW EVC (not on Att A) USER creates DDSF order for type of service= E-line IE73 Reviews and Creates TSO with applicable VLAN instructions DITCO receives TSO - selects applicable CEG Contract and CLIN for Service DITCO Issues Task Order Vendor Provides Service
Modify Existing EVC (NRC) USER CREATES DDSF order for type of service used for creating VLAN
Murray, Timothy P: Customer identify in TSR no Converged CE Router; VLANs need to be on seperate interfaces. Identify HAIPE if applicable IE73 Reviews and Creates TSO with applicable VLAN instructions
Murray, Timothy P: Identify which VLANs are pushed by Vendor, which by customer DITCO receives TSO - selects applicable CEG Contract and Task 5 CLIN for Service DITCO Issues Task Order Vendor Provides Service
Modify Existing EVC (no cost) USER CREATES TSR for type of service used to create VLAN
Murray, Timothy P: Customer identify in TSR Converged CE Router avail - Vendor Trunk terminates there (if not already so configured) IE73 Reviews and Creates TSO with applicable VLAN instructions DITCO receives TSO - Creates/Sends Contract Record Update Vendor Provides Service Requestor (?) Closes Ticket
Murray, Timothy P: DISA POC closes Service Request
Murray, Timothy P: Customer identify in TSR no Converged CE Router; VLANs need to be on seperate interfaces. Identify HAIPE if applicable
Murray, Timothy P: Identify which VLANs are pushed by Vendor, which by customer
Murray, Timothy P: Customer identify in TSR Converged CE Router avail - Vendor Trunk terminates there (if not already so configured) Contractor provides Gateway Homing
DISA provides VLAN assignments with TO.
Since this is a service already included in the contract DISA contacts Contractor POC to provide VLAN Assignments
&"-,Bold"&12&F
| CEG GFI and Contract Deliverable Timeline |
| CEG Regions 3-7 Data Requirements List |
| CEG Service Request Data Requirement Details |