Attachment E - BP#2 - Bid Schedule.pdf

PDF 232 KB Posted

Attached to
Pershing High School Bid Pack 2C- Signage and Final Cleaning
Solicitation number
RFP DET 270000000026 1
Issued by
Wayne County, Michigan

About this file

Attachment E - BP#2 - Bid Schedule Summary

This is a Bid Schedule document for Pershing High School Bid Pack 2C in Michigan, detailing signage and final cleaning services. The bid schedule outlines line items for various signage and cleaning work required to complete the project. The document specifies quantities for each service category, establishing the scope of work that bidders must price and execute. The schedule serves as the pricing template through which qualified contractors will submit their cost proposals for labor, materials, and any associated expenses related to the signage installation and final cleaning requirements at the school facility.

The bid schedule functions as the primary pricing document for competitive bidding and establishes the structure by which all bids will be evaluated on a line-item basis. This format ensures consistency across all submitted bids and allows the awarding authority to compare proposals equitably. Bidders are required to complete the schedule with their proposed pricing for each specified line item, forming the basis for contract award and payment upon completion of the designated signage and cleaning work at Pershing High School.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Activity ID Activity Name Original Duration

Start Finish Subcontractor

Pershing High SchoolPershing High School 631 12-May-25 A 05-Nov-27

MilestonesMilestones 541 12-May-25 A 30-Jun-27

A2080 Construction Duration 539 12-May-25 A 30-Jun-27

A1940 Temporary Heat 0 16-Oct-26*

A1710 Permanent Power 0 29-Oct-26

A1740 Conditioned Air 0 29-Oct-26

A1670 Substantial Completion 0 30-Jun-27*

A1760 Owner Occupancy 0 30-Jun-27*

Design PhaseDesign Phase 0

Design DocumentsDesign Documents 0

Construction DocumentsConstruction Documents 0

Bid Package 1Bid Package 1 0

Bid Package 2Bid Package 2 0

PermittingPermitting 0

School BoardSchool Board 0

Bid Package 1Bid Package 1 0

Bid Package 2Bid Package 2 0

ProcurementProcurement 373 13-Jun-25 A 04-Dec-26

SubmittalsSubmittals 0

Structural SubmittalsStructural Submittals 0

Electrical SubmittalsElectrical Submittals 0

Mechanical SubmittalsMechanical Submittals 0

Exterior Facade SubmittalsExterior Facade Submittals 0

Long Lead ItemsLong Lead Items 373 13-Jun-25 A 04-Dec-26

A1830 Generator 300 13-Jun-25 A 14-Oct-26

A1780 Kitchen Equipment 120 15-Jun-26 A 04-Dec-26

MEP CoordinationMEP Coordination 0

Schedule ImpactsSchedule Impacts 0

ConstructionConstruction 359 16-Mar-26 A 12-Aug-27

Site WorkSite Work 0

Foundation WallsFoundation Walls 0

Underground UtilitiesUnderground Utilities 0

Underground PlumbingUnderground Plumbing 0

Underground ElectricalUnderground Electrical 0

StructureStructure 171 26-May-26 A 28-Jan-27

Structural SteelStructural Steel 0

Sequence 1Sequence 1 0

Sequence 2Sequence 2 0

Sequence 3Sequence 3 0

Sequence 4Sequence 4 0

RoofingRoofing 0

Sequence 1Sequence 1 0

Sequence 2Sequence 2 0

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecJan Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1

2027 2028

Construction Duration

Temporary Heat

Permanent Power

Conditioned Air

Substantial Completion

Owner Occupancy

Generator

Kitchen Equipment

Finish Date: 05-Nov-27

Data Date: 16-Sep-26

Run Date: 22-Sep-26 15:05

Pershing-1

Remaining Level of Effort

Actual Level of Effort

Project Baseline Bar

Actual Work

Remaining Work

Critical Remaining Work

Summary Milestones

Critical Milestones

Baseline Milestone

Milestone

Pershing High School

Start Finish Subcontractor

Sequence 3Sequence 3 0

Sequence 4Sequence 4 0

Exterior MasonryExterior Masonry 21 26-May-26 A 25-Sep-26

S4-B-1030 Brick - Seq. 4 21 26-May-26 A 25-Sep-26 J&J

Curtainwall and StorefrontCurtainwall and Storefront 53 24-Aug-26 A 15-Oct-26

S3-CW-1050 Storefront - Seq. 3 8 24-Aug-26 A 30-Sep-26 Environmental

S3-CW-1060 Curtainwall - Seq. 3 9 24-Aug-26 A 30-Sep-26 Environmental

S4-CW-1070 Storefront - Seq. 4 11 01-Oct-26 15-Oct-26 Enviornmental

S4-CW-1080 Curtainwall - Seq. 4 5 01-Oct-26 07-Oct-26 Environmental

Metal PanelsMetal Panels 84 28-Sep-26 28-Jan-27

S1-MP-1000 Metal Panels - Seq. 1 21 28-Sep-26* 26-Oct-26 Rieckhoff

S2-MP-1010 Metal Panels - Seq. 2 28 27-Oct-26 08-Dec-26 Rieckhoff

S3-MP-1020 Metal Panels - Seq. 3 18 09-Dec-26 05-Jan-27 Rieckhoff

S4-MP-1030 Metal Panels - Seq. 4 17 06-Jan-27 28-Jan-27 Rieckhoff

Slab On GradeSlab On Grade 0

Spray FireproofingSpray Fireproofing 12 17-Sep-26 A 02-Oct-26

S4-FP-1060 Spray Fireproofing - Seq. 3 (Area B) 5 17-Sep-26 A 25-Sep-26 Saylor

S4-FP-1070 Spray Fireproofing - Seq. 4 (Area A) 5 28-Sep-26 02-Oct-26 Saylor

Interior CMU WallsInterior CMU Walls 16 29-Jun-26 A 18-Sep-26

S1-CMU-1000 Non Load Bearing CMU - Seq. 1 16 29-Jun-26 A 18-Sep-26 J&J

S1-CMU-1010 In Wall CMU MEP Rough - Seq. 1 16 29-Jun-26 A 18-Sep-26 J&J

Interior Fit OutInterior Fit Out 236 28-Aug-26 A 12-Aug-27

Sequence 1 - Area GSequence 1 - Area G 236 28-Aug-26 A 12-Aug-27

Rough InRough In 54 28-Aug-26 A 23-Nov-26

S1-G-1000 Overhead Mechanical Rough 15 28-Aug-26 A 18-Sep-26 Quality

S1-G-1350 Overhead Ductwork 20 14-Sep-26 A 09-Oct-26 Quality

S1-G-1050 Overhead Mechanical Piping (Final Branch) 10 05-Oct-26 16-Oct-26 Quality

S1-G-1360 Overhead Plumbing 20 05-Oct-26 30-Oct-26 Danboise

S1-G-1010 Overhead Electrical Rough 20 26-Oct-26 23-Nov-26 DeCal

S1-G-1030 Overhead Fire Protection Rough 10 26-Oct-26 06-Nov-26 Elite

S1-G-1060 Insulate MEP's 10 02-Nov-26 16-Nov-26 Quality

S1-G-1380 Cable Tray 5 17-Nov-26 23-Nov-26 DeCal

FinishesFinishes 192 09-Nov-26 12-Aug-27

S1-G-1370 Tape and Finish Drywall 15 09-Nov-26 02-Dec-26 City

S1-G-1070 Paint - Prime and Final Coat 15 24-Nov-26 16-Dec-26 Classic

S1-G-1440 Pull low voltage wiring 40 24-Nov-26 22-Jan-27

S1-G-1090 Ceiling Grid 10 10-Dec-26 23-Dec-26 City

S1-G-1020 Install Kitchen Hoods 10 17-Dec-26 31-Dec-26 Great Lakes

S1-G-1100 Fire Protection Trim 16 24-Dec-26 18-Jan-27 Elite

S1-G-1120 Mechanical Controls Grid Trim 10 24-Dec-26 08-Jan-27 Quality

S1-G-1130 Epoxy Flooring - Kitchen Areas 10 24-Dec-26 08-Jan-27 Syncon

S1-G-1410 Install Light Fixtures 20 24-Dec-26 22-Jan-27 DeCal

S1-G-1040 Ansul (Chemical Fire Suppression System) 5 04-Jan-27 08-Jan-27 Great Lakes

S1-E-1030 Set Cooler / Freezer 10 04-Jan-27* 15-Jan-27 Great Lakes

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecJan Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1

2027 2028

Brick - Seq. 4

Storefront - Seq. 3

Curtainwall - Seq. 3

Storefront - Seq. 4

Curtainwall - Seq. 4

Metal Panels - Seq. 1

Metal Panels - Seq. 2

Metal Panels - Seq. 3

Metal Panels - Seq. 4

Spray Fireproofing - Seq. 3 (Area B)

Spray Fireproofing - Seq. 4 (Area A)

Non Load Bearing CMU - Seq. 1

In Wall CMU MEP Rough - Seq. 1

Overhead Mechanical Rough

Overhead Ductwork

Overhead Mechanical Piping (Final Branch)

Overhead Plumbing

Overhead Electrical Rough

Overhead Fire Protection Rough

Insulate MEP's

Cable Tray

Tape and Finish Drywall

Paint - Prime and Final Coat

Pull low voltage wiring

Ceiling Grid

Install Kitchen Hoods

Fire Protection Trim

Mechanical Controls Grid Trim

Epoxy Flooring - Kitchen Areas

Install Light Fixtures

Ansul (Chemical Fire Suppression System)

Set Cooler / Freezer

Finish Date: 05-Nov-27

Data Date: 16-Sep-26

Run Date: 22-Sep-26 15:05

Pershing-1

Remaining Level of Effort

Actual Level of Effort

Project Baseline Bar

Actual Work

Remaining Work

Critical Remaining Work

Summary Milestones

Critical Milestones

Baseline Milestone

Start Finish Subcontractor

S1-G-1150 Stainless Steel Sinks 10 11-Jan-27 22-Jan-27 Danboise

S1-E-1040 Rough In to Cooler / Freezer 10 11-Jan-27 22-Jan-27

S1-G-1160 Set Kitchen Equipment 20 11-Jan-27 05-Feb-27 Great Lakes

S1-G-1220 Flooring Cafeteria 10 11-Jan-27 22-Jan-27 Shock

S1-G-1390 Polished Concrete 5 11-Jan-27 15-Jan-27 Syncon

S1-G-1400 Sealed Concrete 5 18-Jan-27 22-Jan-27 Syncon

S3-BC-1370 Signage 5 18-Jan-27 22-Jan-27

S1-G-1170 Kitchen Equipment - Plumbing and Mechanical Connections 10 25-Jan-27 05-Feb-27 Danboise

S1-G-1180 Kitchen Equipment - Electrical Connections 10 25-Jan-27 05-Feb-27 DeCal

S1-G-1190 Final Above Ceiling Inspections 10 25-Jan-27 05-Feb-27

S1-G-1330 Millwork / Casework 20 01-Feb-27 26-Feb-27 Trend

S1-G-1200 Drop Ceiling Tile 10 08-Feb-27 19-Feb-27 City

S1-G-1210 Install Doors and Hardware 20 08-Feb-27 05-Mar-27 City

S1-G-1110 Electrical / LV / FA Grid Trim 10 22-Feb-27 05-Mar-27 DeCal

S1-G-1430 Install Roll up Doors 10 22-Feb-27 05-Mar-27 City

S1-G-1230 Install Final Accessories / Trim / Lockers 5 01-Mar-27 05-Mar-27 Brainard

S1-G-1420 Interior Glazing 1 01-Mar-27 01-Mar-27 Environmental

S1-G-1260 Construction Clean 5 08-Mar-27 12-Mar-27

S1-G-1270 Gilbane Punch 5 15-Mar-27 19-Mar-27

S1-G-1280 Architect / Owner Produce Punchlist 1 22-Mar-27 22-Mar-27

S1-G-1290 GRC Remedy Punchlist Items 20 23-Mar-27 19-Apr-27

S1-G-1300 Final Clean 5 13-Apr-27 19-Apr-27

S1-G-1310 Architect / Owner Sign-off Punch List 5 20-Apr-27 26-Apr-27

S1-G-1240 Relocate Kitchen Equipment 30 01-Jul-27 12-Aug-27

Sequence 1 - Area ESequence 1 - Area E 181 08-Sep-26 A 25-May-27

Rough InRough In 80 08-Sep-26 A 04-Jan-27

S1-E-1000 Interior Framing - E 15 08-Sep-26 A 28-Sep-26 City

S1-E-2050 Overhead Duct Rough 20 29-Sep-26 26-Oct-26 Quality

S1-E-2010 Overhead Mechanical Piping Rough 15 20-Oct-26 09-Nov-26 Quality

S1-E-1020 In Wall and Overhead Plumbing Rough 15 10-Nov-26 03-Dec-26 Danboise

S1-E-1010 In Wall and Overhead Electrical Rough (Electrical / LV / FA) 20 04-Dec-26 04-Jan-27 DeCal

S1-E-2030 Overhead Fire Protection Rough 5 04-Dec-26 10-Dec-26 Elite

S1-E-1240 Insulate MEP 10 04-Dec-26 17-Dec-26 Quality

S1-E-1050 In Wall Inspections 5 18-Dec-26 28-Dec-26

S1-E-1250 Install Cable Tray 5 28-Dec-26 04-Jan-27 DeCal

FinishesFinishes 106 28-Dec-26 25-May-27

S1-E-1060 Hang Drywall 10 28-Dec-26 11-Jan-27 City

S1-G-1450 Pull low voltage wiring 40 05-Jan-27 01-Mar-27

S1-E-1070 Tape and Finish Drywall 10 12-Jan-27 25-Jan-27 City

S1-E-1080 Prime and 1st Coat 10 26-Jan-27 08-Feb-27 Classic

S1-E-1260 Polished Concrete 1 26-Jan-27 26-Jan-27 Syncon

S1-E-1100 Ceiling Grid 10 09-Feb-27 22-Feb-27 City

S1-E-1140 Carpet Flooring 20 09-Feb-27 08-Mar-27 Shock

S3-BC-1380 Signage 5 09-Feb-27 15-Feb-27

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecJan Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1

2027 2028

Stainless Steel Sinks

Rough In to Cooler / Freezer

Set Kitchen Equipment

Flooring Cafeteria

Polished Concrete

Sealed Concrete

Signage

Kitchen Equipment - Plumbing and Mechanical Connections

Kitchen Equipment - Electrical Connections

Final Above Ceiling Inspections

Millwork / Casework

Drop Ceiling Tile

Install Doors and Hardware

Electrical / LV / FA Grid Trim

Install Roll up Doors

Install Final Accessories / Trim / Lockers

Interior Glazing

Construction Clean

Gilbane Punch

Architect / Owner Produce Punchlist

GRC Remedy Punchlist Items

Final Clean

Architect / Owner Sign-off Punch List

Relocate Kitchen Equipment

Interior Framing - E

Overhead Duct Rough

Overhead Mechanical Piping Rough

In Wall and Overhead Plumbing Rough

In Wall and Overhead Electrical Rough (Electrical / LV / FA)

Overhead Fire Protection Rough

Insulate MEP

In Wall Inspections

Install Cable Tray

Hang Drywall

Pull low voltage wiring

Tape and Finish Drywall

Prime and 1st Coat

Polished Concrete

Ceiling Grid

Carpet Flooring

Signage

Finish Date: 05-Nov-27

Data Date: 16-Sep-26

Run Date: 22-Sep-26 15:05

Pershing-1

Remaining Level of Effort

Actual Level of Effort

Project Baseline Bar

Actual Work

Remaining Work

Critical Remaining Work

Summary Milestones

Critical Milestones

Baseline Milestone

Start Finish Subcontractor

S1-E-1230 Electrical / LV / FA Grid Trim 10 23-Feb-27 08-Mar-27 DeCal

S1-E-1270 Install Light Fixtures 20 23-Feb-27 22-Mar-27 DeCal

S1-E-1280 Install Wood Slat Ceiling 10 23-Feb-27 08-Mar-27 City

S1-E-1160 Final Paint 10 02-Mar-27 15-Mar-27 Classic

S1-E-1120 Final Above Ceiling Inspections 1 09-Mar-27 09-Mar-27

S1-E-1130 Install Doors and Hardware 20 16-Mar-27 12-Apr-27 City

S1-E-1110 Casework and MEP Trim 20 16-Mar-27 12-Apr-27 Trend

S1-E-1150 Drop Ceiling Tile 10 23-Mar-27 05-Apr-27 City

S1-E-1290 Interior Glazing 5 23-Mar-27 29-Mar-27 Environmental

S1-E-1170 Construction Clean 4 06-Apr-27 09-Apr-27

S1-E-1180 Gilbane Punch 5 13-Apr-27 19-Apr-27

S1-E-1190 Architect / Owner Produce Punchlist 1 20-Apr-27 20-Apr-27

S1-E-1200 GRC Remedy Punchlist Items 20 21-Apr-27 18-May-27

S1-E-1210 Final Clean 5 12-May-27 18-May-27

S1-E-1220 Architect / Owner Sign-off Punch List 5 19-May-27 25-May-27

Sequence 2 - Area H, Area F, and Area DSequence 2 - Area H, Area F, and Area D 206 08-Sep-26 A 30-Jun-27

Rough InRough In 110 08-Sep-26 A 15-Feb-27

S2-HFD-1280 In Wall MEP Rough In (Area H) 7 08-Sep-26 A 25-Sep-26 Quality

S2-HFD-1270 Hang, Tape, and Finish Drywall (Area H) 8 28-Sep-26 07-Oct-26 City

S2-HFD-1290 Overhead Duct Rough 20 27-Oct-26 24-Nov-26 Quality

S2-HFD-1000 Overhead Mechanical Piping Rough 15 18-Nov-26 10-Dec-26 Quality

S2-HFD-1310 Overhead Plumbing Rough 15 04-Dec-26 24-Dec-26 Danboise

S2-HFD-1020 Overhead Fire Protection Rough 10 18-Dec-26 04-Jan-27 Elite

S2-HFD-1030 Insulate MEP's 10 18-Dec-26 04-Jan-27 Quality

S2-HFD-1010 Overhead Electrical Rough 20 05-Jan-27 01-Feb-27 DeCal

S2-HFD-1320 Cable Tray 5 26-Jan-27 01-Feb-27 DeCal

S2-HFD-1100 Final Above Ceiling Inspections 10 02-Feb-27 15-Feb-27

S2-HFD-1300 Frame Ceilings and Soffits/ Drywall and Finish 10 02-Feb-27 15-Feb-27 City

FinishesFinishes 116 19-Jan-27 30-Jun-27

S1-G-1460 Pull low voltage wiring 40 19-Jan-27 15-Mar-27

S2-HFD-1140 Polished Concrete 10 09-Feb-27 22-Feb-27 Syncon

S2-HFD-1060 Ceiling Grid 20 16-Feb-27 15-Mar-27 City

S2-HFD-1330 Light Fixtures 20 09-Mar-27 05-Apr-27 DeCal

S2-HFD-1150 Install Lockers 15 16-Mar-27 05-Apr-27 Brainard

S2-HFD-1350 Flooring 35 16-Mar-27 03-May-27 Shock

S3-BC-1390 Signage 5 16-Mar-27 22-Mar-27

S2-HFD-1160 Drop Ceiling Tile 11 06-Apr-27 20-Apr-27 City

S2-HFD-1180 Final Paint 10 06-Apr-27 19-Apr-27 Classic

S2-HFD-1120 Install Lab Casework and MEP Trim 20 06-Apr-27 03-May-27 NEIS

S2-HFD-1340 Install Casework 20 06-Apr-27 03-May-27 Trend

S2-HFD-1110 Install Doors and Hardware 15 20-Apr-27 10-May-27 City

S2-HFD-1190 Construction Clean 4 11-May-27 14-May-27

S2-HFD-1200 Gilbane Punch List 10 17-May-27 28-May-27

S2-HFD-1210 Architect / Owner Produce Punchlist 7 01-Jun-27 09-Jun-27

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecJan Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1

2027 2028

Electrical / LV / FA Grid Trim

Install Light Fixtures

Install Wood Slat Ceiling

Final Paint

Final Above Ceiling Inspections

Install Doors and Hardware

Casework and MEP Trim

Drop Ceiling Tile

Interior Glazing

Construction Clean

Gilbane Punch

Architect / Owner Produce Punchlist

GRC Remedy Punchlist Items

Final Clean

Architect / Owner Sign-off Punch List

In Wall MEP Rough In (Area H)

Hang, Tape, and Finish Drywall (Area H)

Overhead Duct Rough

Overhead Mechanical Piping Rough

Overhead Plumbing Rough

Overhead Fire Protection Rough

Insulate MEP's

Overhead Electrical Rough

Cable Tray

Final Above Ceiling Inspections

Frame Ceilings and Soffits/ Drywall and Finish

Pull low voltage wiring

Polished Concrete

Ceiling Grid

Light Fixtures

Install Lockers

Flooring

Signage

Drop Ceiling Tile

Final Paint

Install Lab Casework and MEP Trim

Install Casework

Install Doors and Hardware

Construction Clean

Gilbane Punch List

Architect / Owner Produce Punchlist

Finish Date: 05-Nov-27

Data Date: 16-Sep-26

Run Date: 22-Sep-26 15:05

Pershing-1

Remaining Level of Effort

Actual Level of Effort

Project Baseline Bar

Actual Work

Remaining Work

Critical Remaining Work

Summary Milestones

Critical Milestones

Baseline Milestone

Start Finish Subcontractor

S2-HFD-1220 GRC Remedy Punchlist Items 10 10-Jun-27 23-Jun-27

S2-HFD-1230 Final Clean 5 17-Jun-27 23-Jun-27

S2-HFD-1240 Architect / Owner Sign-off Punch List 5 24-Jun-27 30-Jun-27

Sequence 3 - Area B / Area CSequence 3 - Area B / Area C 190 28-Sep-26 28-Jun-27

Rough InRough In 60 27-Oct-26 25-Jan-27

S3-BC-1290 Overhead Duct Rough 20 27-Oct-26 24-Nov-26 Quality

S3-BC-1000 Overhead Mechanical Piping 15 18-Nov-26 10-Dec-26 Quality

S3-BC-1300 Overhead Plumbing Rough 15 04-Dec-26 24-Dec-26 Danboise

S3-BC-1030 Insulate MEP's 10 11-Dec-26 24-Dec-26 Quality

S3-BC-1010 Overhead Electrical Rough 20 18-Dec-26 18-Jan-27 DeCal

S3-BC-1020 Overhead Fire Protection Rough 10 12-Jan-27 25-Jan-27 Elite

S3-BC-1050 Cable Tray 5 12-Jan-27 18-Jan-27 DeCal

FinishesFinishes 190 28-Sep-26 28-Jun-27

S3-BC-1040 Prime and 1st Coat 10 28-Sep-26 09-Oct-26 Classic

S3-BC-1310 Top of Wall Stud/Drywall/Finish 15 28-Dec-26 18-Jan-27 City

S3-BC-1140 Polished Concrete 10 19-Jan-27 01-Feb-27 Syncon

S3-BC-1330 Frame Ceilings and Soffits/ Drywall and Finish 10 26-Jan-27 08-Feb-27 City

S3-BC-1180 Install Lockers 10 02-Feb-27 15-Feb-27 Brainard

S3-BC-1060 Ceiling Grid 5 09-Feb-27 15-Feb-27 City

S3-BC-1320 Paint Ceiling 10 09-Feb-27 22-Feb-27 Classic

S3-BC-1070 Fire Protection Trim 18 16-Feb-27 11-Mar-27 Elite

S3-BC-1200 Install Final Accessories / Trim / Interior Glazing 5 16-Feb-27 22-Feb-27

S3-BC-1210 Final Paint 10 23-Feb-27 08-Mar-27 Classic

S3-BC-1090 Install Light Fixtures 20 23-Feb-27 22-Mar-27 DeCal

S3-BC-1340 Theater Lighting 10 23-Feb-27 08-Mar-27 Tobins

S3-BC-1130 Install Theater Flooring 35 09-Mar-27 26-Apr-27 Shock

S3-BC-1120 Casework and MEP Trim 20 09-Mar-27 05-Apr-27 Trend

S3-BC-1100 Final Above Ceiling Inspections 5 12-Mar-27 18-Mar-27

S3-BC-1190 Drop Ceiling Tile 2 23-Mar-27 24-Mar-27 City

S3-BC-1350 Concession Casework 10 23-Mar-27 05-Apr-27 Neis

S3-BC-1110 Install Doors and Hardware 15 25-Mar-27 14-Apr-27 City

S3-BC-1160 Theater Equipment 15 27-Apr-27 17-May-27 Tobins

S3-BC-1170 Flooring 10 27-Apr-27 10-May-27 Shock

S3-BC-1360 Signage 5 27-Apr-27 03-May-27

S3-BC-1220 Construction Clean 4 11-May-27 14-May-27

S3-BC-1230 Gilbane Punch 14 17-May-27 04-Jun-27

S3-BC-1240 Architect / Owner Produce Punchlist 1 07-Jun-27 07-Jun-27

S3-BC-1250 GRC Remedy Punchlist Items 10 08-Jun-27 21-Jun-27

S3-BC-1260 Final Clean 5 15-Jun-27 21-Jun-27

S3-BC-1270 Architect / Owner Sign-off Punch List 5 22-Jun-27 28-Jun-27

Sequence 4 - Area ASequence 4 - Area A 175 12-Oct-26 21-Jun-27

Rough In - GymRough In - Gym 17 18-Nov-26 14-Dec-26

S4-A-1000 Overhead Duct Rough 10 18-Nov-26 03-Dec-26 Quality

S4-A-1010 Overhead Electrical Rough 10 30-Nov-26 11-Dec-26 DeCal

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecJan Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1

2027 2028

GRC Remedy Punchlist Items

Final Clean

Architect / Owner Sign-off Punch List

Overhead Duct Rough

Overhead Mechanical Piping

Overhead Plumbing Rough

Insulate MEP's

Overhead Electrical Rough

Overhead Fire Protection Rough

Cable Tray

Prime and 1st Coat

Top of Wall Stud/Drywall/Finish

Polished Concrete

Frame Ceilings and Soffits/ Drywall and Finish

Install Lockers

Ceiling Grid

Paint Ceiling

Fire Protection Trim

Install Final Accessories / Trim / Interior Glazing

Final Paint

Install Light Fixtures

Theater Lighting

Install Theater Flooring

Casework and MEP Trim

Final Above Ceiling Inspections

Drop Ceiling Tile

Concession Casework

Install Doors and Hardware

Theater Equipment

Flooring

Signage

Construction Clean

Gilbane Punch

Architect / Owner Produce Punchlist

GRC Remedy Punchlist Items

Final Clean

Architect / Owner Sign-off Punch List

Overhead Duct Rough

Overhead Electrical Rough

Finish Date: 05-Nov-27

Data Date: 16-Sep-26

Run Date: 22-Sep-26 15:05

Pershing-1

Remaining Level of Effort

Actual Level of Effort

Project Baseline Bar

Actual Work

Remaining Work

Critical Remaining Work

Summary Milestones

Critical Milestones

Baseline Milestone

Start Finish Subcontractor

S4-A-1020 Overhead Fire Protection Rough 10 30-Nov-26 11-Dec-26 Elite

S4-A-1310 Overhead Mechanical Rough 5 04-Dec-26 10-Dec-26 Quality

S4-A-1040 Cable Tray 5 07-Dec-26 11-Dec-26

S4-A-1320 Overhead Plumbing Rough 1 11-Dec-26 11-Dec-26 Danboise

S4-A-1290 Insulate MEP's 1 14-Dec-26 14-Dec-26 Quality

Rough In - Locker RoomRough In - Locker Room 35 04-Dec-26 25-Jan-27

S4-A-1390 Overhead Duct Rough 10 04-Dec-26 17-Dec-26 Quality

S4-A-1400 Overhead Mechanical Rough 10 11-Dec-26 24-Dec-26 Quality

S4-A-1410 Overhead Plumbing Rough 15 28-Dec-26 18-Jan-27 Danboise

S4-A-1420 Overhead Electrical Rough 10 05-Jan-27 18-Jan-27 DeCal

S4-A-1430 Overhead Fire Protection Rough 5 05-Jan-27 11-Jan-27 Elite

S4-A-1440 Insulate MEP's 5 19-Jan-27 25-Jan-27 Quality

Finishes - GymFinishes - Gym 175 12-Oct-26 21-Jun-27

S4-A-1070 Prime and 1st coat 10 12-Oct-26 23-Oct-26 Classic

S1-G-1470 Pull low voltage wiring 20 14-Dec-26 12-Jan-27

S4-A-1140 Final Above Ceiling Inspections 5 13-Jan-27 19-Jan-27

S4-A-1060 Paint Gym Ceiling 10 20-Jan-27 02-Feb-27 Classic

S4-A-1090 Install Gym Overhead Equipment (Hoops/Track) 10 03-Feb-27 16-Feb-27 C&M

S4-A-1350 Final Paint - Gym 5 03-Feb-27 09-Feb-27 Classic

S4-A-1370 Light Fixtures - Gym 10 17-Feb-27 02-Mar-27 DeCal

S4-A-1180 Gym Flooring 30 03-Mar-27 13-Apr-27 Kuhn

S4-A-1200 Install Bleachers and Remaining Gym Equipment 15 14-Apr-27 04-May-27 Interkal

S4-A-1330 Signage 5 14-Apr-27 20-Apr-27

S4-A-1230 Construction Clean 4 05-May-27 10-May-27

S4-A-1240 Gilbane Punch 5 11-May-27 17-May-27

S4-A-1250 Architect / Owner Produce Punchlist 7 18-May-27 26-May-27

S4-A-1260 GRC Remedy Punchlist Items 10 27-May-27 10-Jun-27

S4-A-1270 Final Clean 9 28-May-27 10-Jun-27

S4-A-1280 Architect / Owner Sign-off Punch List 7 11-Jun-27 21-Jun-27

Finishes - Locker RoomFinishes - Locker Room 95 14-Dec-26 27-Apr-27

S1-G-1480 Pull low voltage wiring 40 14-Dec-26 09-Feb-27

S4-A-1470 Final Above Ceiling Inspections 5 26-Jan-27 01-Feb-27

S4-A-1460 Top of Wall Stud/Drywall/Finish 15 02-Feb-27 22-Feb-27 City

S4-A-1500 Frame/Drywall/Finish Hard Ceilings 15 10-Feb-27 02-Mar-27 City

S4-A-1450 Prime and 1st coat 10 03-Mar-27 16-Mar-27 Classic

S4-A-1530 Final Paint - Locker Rooms 10 03-Mar-27 16-Mar-27 Classic

S4-A-1550 Fire Protection Trim 5 17-Mar-27 23-Mar-27 Elite

S4-A-1480 Sealed Concrete 5 17-Mar-27 23-Mar-27 Syncon

S4-A-1560 Epoxy Flooring - Locker Room 10 17-Mar-27 30-Mar-27 Syncon

S4-A-1570 Light Fixtures - Locker Room 10 17-Mar-27 30-Mar-27 DeCal

S4-A-1590 Lockers 15 31-Mar-27 20-Apr-27 Brainard

S4-A-1610 Signage 5 31-Mar-27 06-Apr-27

S4-A-1600 Install Doors and Hardware 5 21-Apr-27 27-Apr-27 City

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecJan Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1

2027 2028

Overhead Fire Protection Rough

Overhead Mechanical Rough

Cable Tray

Overhead Plumbing Rough

Insulate MEP's

Overhead Duct Rough

Overhead Mechanical Rough

Overhead Plumbing Rough

Overhead Electrical Rough

Overhead Fire Protection Rough

Insulate MEP's

Prime and 1st coat

Pull low voltage wiring

Final Above Ceiling Inspections

Paint Gym Ceiling

Install Gym Overhead Equipment (Hoops/Track)

Final Paint - Gym

Light Fixtures - Gym

Gym Flooring

Install Bleachers and Remaining Gym Equipment

Signage

Construction Clean

Gilbane Punch

Architect / Owner Produce Punchlist

GRC Remedy Punchlist Items

Final Clean

Architect / Owner Sign-off Punch List

Pull low voltage wiring

Final Above Ceiling Inspections

Top of Wall Stud/Drywall/Finish

Frame/Drywall/Finish Hard Ceilings

Prime and 1st coat

Final Paint - Locker Rooms

Fire Protection Trim

Sealed Concrete

Epoxy Flooring - Locker Room

Light Fixtures - Locker Room

Lockers

Signage

Install Doors and Hardware

Finish Date: 05-Nov-27

Data Date: 16-Sep-26

Run Date: 22-Sep-26 15:05

Pershing-1

Remaining Level of Effort

Actual Level of Effort

Project Baseline Bar

Actual Work

Remaining Work

Critical Remaining Work

Summary Milestones

Critical Milestones

Baseline Milestone

Start Finish Subcontractor

Mechanical EquipmentMechanical Equipment 107 29-Jun-26 A 01-Dec-26

RTURTU 30 29-Jun-26 A 30-Sep-26

A2250 RTU - MEP Connections 30 29-Jun-26 A 30-Sep-26

A2320 ERU - MEP Connections 30 29-Jun-26 A 30-Sep-26

BoilerBoiler 30 31-Aug-26 A 12-Oct-26

A2270 Boiler - MEP Connections 30 31-Aug-26 A 12-Oct-26

A2260 Set Boiler 0 23-Sep-26*

Exhaust FansExhaust Fans 30 31-Aug-26 A 12-Oct-26

A2290 Exhaust Fans - MEP Connections 30 31-Aug-26 A 12-Oct-26

A2370 Set Exhaust Fans 0 23-Sep-26

Electrical EquipmentElectrical Equipment 53 15-Sep-26 A 01-Dec-26

A2710 Equipment Pads 1 15-Sep-26 A 18-Sep-26

A2480 Set Electrical Equipment 10 21-Sep-26 02-Oct-26 DeCal

A2610 Pull Cable - Primary to medium volt transformet 2 05-Oct-26 06-Oct-26 DeCal

A2620 Pull Cable - Medium Volt to Main Switch Panel 3 07-Oct-26 09-Oct-26 DeCal

A2630 Start Up and Test Equipment 2 12-Oct-26 13-Oct-26 DeCal

A2360 Set Generator 0 15-Oct-26 DeCal

A2280 Generator - MEP Connections 30 16-Oct-26 01-Dec-26 DeCal

A2640 Set Power Pole - DTE 1 26-Oct-26* 26-Oct-26 DeCal

A2650 Pull Cable - Power Pole to Primary switch 2 27-Oct-26 28-Oct-26 DeCal

Hardscape and LandscapesHardscape and Landscapes 311 16-Mar-26 A 04-Jun-27

A1900 Stone and Compact 5 16-Mar-26 A 25-Sep-26 Eastedge

A1980 Base Course 5 05-Oct-26 09-Oct-26 Nagle

A1950 Asphalt Paving - Wearing Course 5 07-May-27 13-May-27 Nagle

A1960 Striping 2 14-May-27 17-May-27 Nagle

A1970 Install Accessories (Light Poles, Bike Racks, Benches, Flag Poles) 7 18-May-27 26-May-27 DeCal

SouthSouth 168 28-Aug-26 A 28-Apr-27

A2540 South - Grading Parking Lot 10 28-Aug-26 A 18-Sep-26 Eastedge

A1920 Curbs and Gutters (Teachers Lot) 5 21-Sep-26 25-Sep-26 DSP

A2000 South - Site Grading 10 28-Sep-26 09-Oct-26 Eastedge

A2660 South - Site Concrete 10 12-Oct-26 23-Oct-26 DSP

A2570 South - Top Soil 5 26-Oct-26 30-Oct-26 PGA

A2580 South - Trees 15 02-Nov-26 23-Nov-26 PGA

A2550 South - Site Screening / Fencing 7 15-Apr-27 23-Apr-27 Industrial Fence

A2590 South - Plantings / Mulch 5 15-Apr-27* 21-Apr-27 PGA

A2560 South - Site Furnishings 5 22-Apr-27 28-Apr-27 PGA

A2600 South - Seeding 3 22-Apr-27 26-Apr-27 PGA

NorthNorth 178 21-Sep-26 03-Jun-27

A2460 North - Grading Parking Lot 5 21-Sep-26 25-Sep-26 Eastedge

A1990 Curbs and Gutters (Main Lot) 5 28-Sep-26 02-Oct-26 DSP

A2300 North - Site Grading 10 05-Oct-26 16-Oct-26 Eastedge

A2500 North - Top Soil 5 19-Oct-26 23-Oct-26 PGA

A2860 North - Site Concrete 10 26-Oct-26 06-Nov-26 DSP

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecJan Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1

2027 2028

RTU - MEP Connections

ERU - MEP Connections

Boiler - MEP Connections

Set Boiler

Exhaust Fans - MEP Connections

Set Exhaust Fans

Equipment Pads

Set Electrical Equipment

Pull Cable - Primary to medium volt transformet

Pull Cable - Medium Volt to Main Switch Panel

Start Up and Test Equipment

Set Generator

Generator - MEP Connections

Set Power Pole - DTE

Pull Cable - Power Pole to Primary switch

Stone and Compact

Base Course

Asphalt Paving - Wearing Course

Striping

Install Accessories (Light Poles, Bike Racks, Benches, Flag Poles)

South - Grading Parking Lot

Curbs and Gutters (Teachers Lot)

South - Site Grading

South - Site Concrete

South - Top Soil

South - Trees

South - Site Screening / Fencing

South - Plantings / Mulch

South - Site Furnishings

South - Seeding

North - Grading Parking Lot

Curbs and Gutters (Main Lot)

North - Site Grading

North - Top Soil

North - Site Concrete

Finish Date: 05-Nov-27

Data Date: 16-Sep-26

Run Date: 22-Sep-26 15:05

Pershing-1

Remaining Level of Effort

Actual Level of Effort

Project Baseline Bar

Actual Work

Remaining Work

Critical Remaining Work

Summary Milestones

Critical Milestones

Baseline Milestone

Start Finish Subcontractor

A2510 North - Trees 15 09-Nov-26 02-Dec-26 PGA

A2520 North - Plantings / Mulch 5 22-Apr-27 28-Apr-27 PGA

A2470 North - Site Screening / Fencing 3 26-Apr-27 28-Apr-27 Industrial Fence

A2490 North - Site Furnishings 5 29-Apr-27 05-May-27 PGA

A2530 North - Seeding 3 29-Apr-27 03-May-27 PGA

A2690 North - Brick Unit Paving 10 20-May-27 03-Jun-27 PGA

CourtyardCourtyard 159 19-Oct-26 04-Jun-27

A2410 Courtyard - Grading 5 19-Oct-26 23-Oct-26 Eastedge

A2680 Courtyard - Site Concrete 15 26-Oct-26 16-Nov-26 DSP

A2700 Courtyard - Trees 10 26-Oct-26 06-Nov-26 PGA

A2440 Courtyard - Plantings / Mulch 5 29-Apr-27 05-May-27 PGA

A2420 Courtyard - Brick Unit Paving 10 06-May-27 19-May-27 PGA

A2450 Courtyard - Seeding 1 06-May-27 06-May-27 PGA

A2010 Exterior Punchlist and Corrections 6 27-May-27 04-Jun-27

Close OutClose Out 212 11-Jan-27 05-Nov-27

A1860 Commissioning 40 11-Jan-27 05-Mar-27

A2140 Health Department Inspection 5 08-Feb-27 12-Feb-27

A2020 Test and Balance 10 11-May-27 24-May-27

A1680 Final Inspections 10 25-May-27 08-Jun-27

A2090 Final Plumbing Inspection 5 25-May-27 01-Jun-27

A2100 Final Electrical Inspection 5 25-May-27 01-Jun-27

A2110 Final Mechanical Inspection 5 25-May-27 01-Jun-27

A2130 Final Low Voltage Inspection (By Owner) 5 25-May-27 01-Jun-27

A2120 Life Safety Inspection 5 04-Jun-27 10-Jun-27

A2230 Owner Training 20 09-Jun-27 07-Jul-27

A1690 Project Close out 60 13-Aug-27 05-Nov-27

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecJan Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1

2027 2028

North - Trees

North - Plantings / Mulch

North - Site Screening / Fencing

North - Site Furnishings

North - Seeding

North - Brick Unit Paving

Courtyard - Grading

Courtyard - Site Concrete

Courtyard - Trees

Courtyard - Plantings / Mulch

Courtyard - Brick Unit Paving

Courtyard - Seeding

Exterior Punchlist and Corrections

Commissioning

Health Department Inspection

Test and Balance

Final Inspections

Final Plumbing Inspection

Final Electrical Inspection

Final Mechanical Inspection

Final Low Voltage Inspection (By Owner)

Life Safety Inspection

Owner Training

Project Close out

Finish Date: 05-Nov-27

Data Date: 16-Sep-26

Run Date: 22-Sep-26 15:05

Pershing-1

Remaining Level of Effort

Actual Level of Effort

Project Baseline Bar

Actual Work

Remaining Work

Critical Remaining Work

Summary Milestones

Critical Milestones

Baseline Milestone

File details come from the government source that posted it. Updated .