ATTACHMENT D - San Diego Progress Report-Full Schedule_VA_ March 2021.pdf

PDF 1 MB Posted

Attached to
Q702--San Diego Kearny Mesa CBOC Activation RFQ
Solicitation number
36C77621Q0296
Issued by

About this file

This pre-solicitation notice announces the Department of Veterans Affairs' intent to solicit quotes for non-personal initial outfitting, transition, and activation services in support of the San Diego Kearny Mesa Outpatient Clinic in San Diego, California. The existing 43,473 square foot clinic will expand to 99,986 square feet to support audiology, mental health, laboratory and pathology, tele-medicine, optometry, podiatry, and primary care services. This will be a firm-fixed-price contract set aside 100% for service-disabled veteran-owned small businesses, with a period of performance of five months. The solicitation is anticipated to be posted on Contract Opportunities on or about May 25, 2021, with a closing date of June 15, 2021. Any questions must be submitted via email to the points of contact listed by the specified deadlines.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bui�di�g C �structi E�gi�eeri�g C �structi

Civi� E�gi�eeri�g

CA State �ice�se 207287 Lusardi Builds…

C rp rate �ffice� 1570 �i�da Vista Drive� Sa� �arc�s� Ca�if�r�ia 92078 (760) 744"3133 FAX (760) 744$9064 �usardi&c�'

1 | P a g e

Clint Fowler Protea Properties 3262 Holiday Court, Suite 100 La Jolla, CA 92037 Date: March 31, 2021

Re: March 2021 Progress Update VA San Diego SFO No. VA-101-15-R-0162 Lease No. 36C10F18L3196

Dear Mr. Fowler, Design Schedule:

1. Core & Shell: City permit issued on 4/6/20.

2. T.I.: Full plan set with slip sheeted bulletins issued to the VA on 7/24/20. Notice of permit approval received on 7/29/2020.

3. Parking Garage: City permit issued 5/15/20.

4. Engineering Civil-Site: Onsite permit issued. Offsite permit issued on 6/23/20.

5. Sewer & Water: Permit issued on 6/23/20.

6. Fire Water: Permit issued on 6/23/20.

7. Fully executed NTP Lease Amendment was executed by VA on 9/28/20.

8. Cost Schedule Bulletin #4 Updated Pricing Lease Amendment was fully executed on 1/27/2021.

Design & Construction Changes Introduced:

1. RFP’s 001 thru 026 and RFP 028 have been issued by the VA. Lessor’s team working through submitting RFP responses and addressing VA comments.

2. RFP’s 001, 003, 004, 005, 007,008, 009, 011, 012, 013, 014, 015, 016, 017, 020, 023, 024, 025, 026, and 028 have been approved by the VA.

3. RFP 002, 006, 018, 019, 022 have been canceled by the VA.

4. RFP 027 and 029 have been voided by the VA.

5. CR’s 01 thru 49 have been issued by the VA. Lessor’s team working through submitting

CR responses.

6. CR’s 01-03, 05-13, 16-21, 24-26, 28-29, 33, 36, 38-39, 41, 44, and 47-48 have been approved by the VA.

7. CR 14 has been canceled by the VA.

On Site Work Completed:

1. Main Building:

a. Level-1: Curtain wall complete, Lobby work in progress, Installation of handrails and bumper guards throughout, Installation of Wall Coverings and Wall-Protection finishes, Installation of corner guards, Millwork and countertop installations in progress, Police suite drywall complete, Stair-4 installed, stair-3 Installed, stair 2 Installed, stair-1 installed, Wall protection finishes in progress, Installation of wood doors, Vinyl tile flooring in progress. Tile-flooring and Wall-Tile installation in progress, Tile waterproofing membrane in-progress. Installation of T-Bar ceiling In-progress, painting throughout in progress.

b. Level-2: Installation of speakers, and Fire Alarm devices, Installation of handrails and bumper guards throughout, Installation of Wall Coverings and Wall-Protection

E�gi�eeri�g C �structi rate �ffice� 1570 �i�da Vista Drive� Sa� �arc�s� Ca�if�r�ia 92078 (760) 744"3133 FAX (760) 744$9064 �usardi&c�'

2 | P a g e finishes, Installation corner guards, Millwork and countertop installations in progress, Installation of handrails and bumper guards, Wall protection finishes in progress, Vinyl tile flooring in progress. Tile-flooring and Wall-Tile installation in progress, Tile waterproofing membrane in-progress. Installation of T-Bar ceiling In-progress,

c. Roof: Main Lobby roofing installation complete.

d. Exterior: Exterior High-roof metal canopy substantially complete. Porte Cochere framing and roofing substrate in progress, stone veneer substantially complete.

2. Building Addition-West:

a. Level-1: Audiology wall paint In-Progress. Interior wall taping and jointing In-progress. Insulation complete. Metal stud framing in progress at audiology booths, Vinyl tile flooring in progress, low voltage work in progress.

b. Roof: Complete.

c. Exterior: Installation of Aluminum Composite Metal panel complete.

3. Building Addition-North:

a. Level-1: Wood door installation In-Progress, Primer coat and 1st paint coat throughout in progress, T-grid installation in progress, low voltage work in progress.

b. Roof: Complete.

c. Exterior: Stone veneer substantially complete. Plaster complete.

4. Site Work: Curbs at south-side of main building complete, median concrete curbs at Aero

Drive complete, Trash Enclosure steel in progress, concrete islands nearing completion, site fencing installations in progress.

5. Parking structure: Facade screen installed and complete. Plaster complete, Painting of parking structure interior and exterior complete.

Expected Completion and Occupancy Date:

1. Per the above mentioned executed NTP Lease Amendment, the contractual project completion and occupancy date is 12/9/2021, however, the Lessor team is tracking substantial project completion and VA building acceptance tentatively as 8/2/2021.

Construction Schedule:

1. Attached is the CPM schedule from March 2021.

2. No schedule risks have been identified at this time.

Construction Look Ahead:

1. Main Building: Interior doors In-progress, resilient flooring In-progress, acoustical ceiling tile In-Progress, low-voltage work in progress, Interior Paint In-progress, acoustical ceiling work in-progress,

2. West Building Addition: Interior wall painting in progress, resilient flooring in progress, drywall finishes in audiology lobby in progress, acoustical ceiling in progress, and low voltage work in progress.

3. North Building Addition: West Building Addition: Interior wall painting in progress, resilient flooring in progress, drywall finishes in audiology lobby in progress, acoustical ceiling in progress, low-voltage work in progress.

4. Site Work: Flat work at Main entry, trash enclosure slab and structural steel.

Final AC paving lift to be installed closer towards project completion.

W

E�gi�eeri�g C �structi rate �ffice� 1570 �i�da Vista Drive� Sa� �arc�s� Ca�if�r�ia 92078 (760) 744"3133 FAX (760) 744$9064 �usardi&c�'

3 | P a g e

5. Parking Garage: Construction will continue through the month of April.

Safety:

1. No injuries were recorded for the month of March. See attached Safety Log.

Certified Payroll:

1. In process for the month of March.

General Remarks:

1. We are tracking COVID-19 impacts to construction as it relates to manpower and material procurement.

Construction Progress Photos:

1. See the construction progress photos attached at the end of this report.

Respectfully Submitted, Anthony Santana

Assistant Field Manager Lusardi Construction Company

Month

Year

City State

Describe The Case

(B1) (B2) (B3) (C) (D) (F)

Construction and Facilities Management

Identify the person

Project Title

Using these categories, check ONLY the most

Classify the case

CFM Office Overseeing Work

Contractor Name LUSARDI CONSTRUCTION

PROTEA VA OUTPATIENT CLINIC

VA-101-15-R-0162Project Number

SAN DIEGO CALIFORNIA

Monthly Record of Work-Related Injuries/Illnesses and Exposure

In accordance with the provisions of your contract, you (the Prime Contractor) shall provide a monthly record of all work hours in the form of Certified Payroll (referred to here as exposure hours) and accident experience incidental to the work (this includes exposure and accident experience of the Prime Contractor and its sub-contractor(s). As a minimum , these records shall include work hours and a record of occupational injuries and illnesses that include the data elements listed below. Definitional criteria for each data element is found in 29 CFR Part 1904. The maintenance of an OSHA 300 Log is required by

OSHA. Most of this information can be obtained from those logs. If data on log provided below is revised after it is submitted to CFM, the Prime Contractor shall provide a revised report to the Resident

Engineer. You must complete a VA Form 2162, Report of Accident Report for all recordable accidents. If you're not sure whether a case is recordable, call the Safety and Occupational Health Program

Manager at (202) 632-5410 for assistance.

CFM PRIME CONTRACTOR

(A) (E) Check the "injury" column or

March

Enter the number of days the injured or ill

(G) (H) (I) (J) (K) (L) (1) (2) (3) (4) (5) (6)

Type of Contract (Choose One):

Construction X

Opn & Main. VHA Construction

Eng. Services Lease Construction X

Cemetary Construction

Other

Date of injury or onset of illness On job transfer or restriction

(days)

In ju ryOther record-able cases

Using these categories, check ONLY the most serious result for each case:

(mo./day)

Describe injury or illness, parts of body affected, and object/substance that directly injured or made person ill (e.g. Second degree burns on right forearm from acetylene torch)

Year to Date

Month

Days away from work

Signature

232270

Certification of Record

Name of Person

Submit. Record

A ll o th e r

Il ln e s s e s

Date

Exposure Hours (Man Hours)

P ri m e o r

S u b

P o r S

Company Name

A g e

G e n d e r Where the event occurred (e.g. Loading dock north end)Date

Employee

Began

Work on

Job

Covered by

Contract

Job Title

(e.g., Welder)

S k in

D is o rd e r

R e s p ir a to ry o n d it io n

P o is o n in g

H e a ri n g

L o s s

(M)

Check the "injury" column or choose one type of illness:

Away from work

(days)

_1_ of _1_

3/31/2021

Anthony Santana

Page days the injured or ill worker was:

Death

Job transfer or restriction

Remained at work

22058

TYPE OF WORK ACTIVITY (Choose One):

Description

Main Lobby - High Ceiling

Taken Date Uploaded By

2021/03/31 11:39:16 Anthony Santana

Upload Date File Name

2021/03/31 12:05:08 D9220539-B2BC-439C-93C9-EED…

Description

Teamlet-5 #2600

Taken Date Uploaded By

2021/03/31 11:30:14 Anthony Santana

Upload Date File Name

2021/03/31 12:05:07 64F8A30F-77B0-45DF-BAF9-47BC…

Description

Taken Date Uploaded By

2021/03/31 07:09:32 Dave Olsen

Upload Date File Name

2021/03/31 13:36:02 20210331_070932.jpg

Description

Taken Date Uploaded By

2021/03/30 13:26:22 Dave Olsen

Upload Date File Name

2021/03/30 14:05:39 20210330_132622.jpg

Lusardi Construction

Printed on Wed Mar 31, 2021 at 06:07 pm PDT

Job #: 3533 VA Clinic - Aero Drive 8875 Aero Drive

San Diego, California 92123 https://storage.procore.com/v4/d/us-east-1/pro-core.com/prostore/20210331190508_production_2755073857.jpeg?sig=7d0faa2daa03a5dae574ef187eea0588562800b0f31b7dce0935cf27b4e3fdcf https://storage.procore.com/v4/d/us-east-1/pro-core.com/prostore/20210331190506_production_2755073753.jpeg?sig=443fc69a78a90c946b300c73857ed8695876aa9896c93c53f9eb2a0192da49ee https://storage.procore.com/v4/d/us-east-1/pro-core.com/companies/6833/01F24ZZZGAJA94R95F0AVQQ4RG?sig=512296cc0805a4871beed63ae184ea8e7a23adde93aee37df81c859fba2e7d89 https://storage.procore.com/v4/d/us-east-1/pro-core.com/companies/6833/01F22F7HJ70JNPWPQT2K93392W?sig=4fb941f0d1c33b034e2605c32f1cbf95d64ba1ddf9e039c24a68c87be99946ec

Taken Date Uploaded By

2021/03/30 13:25:48 Dave Olsen

Upload Date File Name

2021/03/30 14:05:33 20210330_132547.jpg

Description

Taken Date Uploaded By

2021/03/30 11:05:55 Dave Olsen

Upload Date File Name

2021/03/30 14:05:42 20210330_110555.jpg

Description

Taken Date Uploaded By

2021/03/29 14:12:28 Anthony Santana

Upload Date File Name

2021/03/30 07:31:56 DE343401-D81C-48B9-B4BD-579…

Description

Taken Date Uploaded By

2021/03/29 10:59:32 Anthony Santana

Upload Date File Name

2021/03/30 07:32:15 2D91E01E-6DD7-47C1-B527-409…

Lusardi Construction

Printed on Wed Mar 31, 2021 at 06:07 pm PDT

Job #: 3533 VA Clinic - Aero Drive 8875 Aero Drive

San Diego, California 92123 https://storage.procore.com/v4/d/us-east-1/pro-core.com/companies/6833/01F22F7HD92GYXFN8DWFX4RF18?sig=23eb3a2a10f44adf0b76fa62615adc6f4cfa8f28ac78e78a65d86d751f21ecec https://storage.procore.com/v4/d/us-east-1/pro-core.com/companies/6833/01F22F7HSCCF6WMH6G9FV5CQ8W?sig=577a35163a184b9be6e2d32c2826bf383df6912f8dc6574d1922b0bc0c19f8bd https://storage.procore.com/v4/d/us-east-1/pro-core.com/prostore/20210330143156_production_2752204649.jpeg?sig=a69d8c5ff11c6040bf2cd238531c2c91f7d50f94b57a34ab031809328e89ee2a https://storage.procore.com/v4/d/us-east-1/pro-core.com/prostore/20210330143215_production_2752205375.jpeg?sig=7f6a613125cab5dfa0d522bae6574d47fba1966e83f30077f0ea2697d5b2883c

2021/03/29 10:58:19 Anthony Santana

Upload Date File Name

2021/03/30 07:32:33 F6BB3B6F-A8EB-458F-A4E3-7271…

Description

Taken Date Uploaded By

2021/03/29 10:03:42 Dave Olsen

Upload Date File Name

2021/03/30 14:04:43 20210329_100342.jpg

Description

Taken Date Uploaded By

Dave Olsen

Upload Date File Name

2021/03/26 14:40:36 IMG_0964.jpg

Description

Taken Date Uploaded By

2021/03/25 11:13:51 Dave Olsen

Upload Date File Name

2021/03/25 12:08:38 20210325_111350.jpg

Lusardi Construction

Printed on Wed Mar 31, 2021 at 06:07 pm PDT

Job #: 3533 VA Clinic - Aero Drive 8875 Aero Drive

San Diego, California 92123 https://storage.procore.com/v4/d/us-east-1/pro-core.com/prostore/20210330143233_production_2752206437.jpeg?sig=f465964a4ea0d8b212fa98e330aadbbb4586cebecec760f40aa22a8305be8020 https://storage.procore.com/v4/d/us-east-1/pro-core.com/companies/6833/01F22F7GC2W955QP2Z20YGE5JX?sig=b2951be0d23bd9e4ec0213a2c76effea6fa63d10073492431da0ab502bfeebe3 https://storage.procore.com/v4/d/us-east-1/pro-core.com/companies/6833/01F1R7PNJV9JNFEJ7T7XWKKDK9?sig=97075565841306ec8a8a18869616d7d22678d00a92feb00047d10f65d5038f45 https://storage.procore.com/v4/d/us-east-1/pro-core.com/companies/6833/01F1NCKM35XVPMB9T331K38A9G?sig=a7dbc8d013569513dfd156e1415266629ba24bd3df831c5a5913645a54fd47a3

Trash enclosure

Taken Date Uploaded By

2021/03/24 12:17:52 Thomas McLaughlin

Upload Date File Name

2021/03/24 12:17:55 F63F2D07-A294-4791-9B56-F59F…

Description

Taken Date Uploaded By

2021/03/24 12:09:10 Anthony Santana

Upload Date File Name

2021/03/24 12:09:54 7E68766B-6645-4749-A48A-6719…

Description

Light fixtures at waiting 2022

Taken Date Uploaded By

2021/03/24 12:07:56 Anthony Santana

Upload Date File Name

2021/03/24 12:08:52 39DDAC41-697F-465F-967F-C16…

Description

Taken Date Uploaded By

2021/03/22 07:41:50 Anthony Santana

Upload Date File Name

2021/03/23 08:12:54 37245662-B243-4A47-8EA9-1B83…

Lusardi Construction

Printed on Wed Mar 31, 2021 at 06:07 pm PDT

Job #: 3533 VA Clinic - Aero Drive 8875 Aero Drive

San Diego, California 92123 https://storage.procore.com/v4/d/us-east-1/pro-core.com/prostore/20210324191755_production_2744469534.jpeg?sig=25a9b060765bbaabbb893eb7d7a531fe3a9dd980699ff00cb2988b847ce52bf0 https://storage.procore.com/v4/d/us-east-1/pro-core.com/prostore/20210324190953_production_2744444096.jpeg?sig=0a3f27e52b878706f0e636928a139aaf54caf0a2d4e4d1aa40f8bd1a388e23f3 https://storage.procore.com/v4/d/us-east-1/pro-core.com/prostore/20210324190851_production_2744440880.jpeg?sig=3ec1173ad04517e7b584139394e1cfef394baac5a4e6e9f4cd65824f73c59ee4 https://storage.procore.com/v4/d/us-east-1/pro-core.com/prostore/20210323151254_production_2741696863.jpeg?sig=76f470ded9497996fd6a677798629d828e27064938282ca13189af2ab022a898

2021/03/16 12:49:18 Dave Olsen

Upload Date File Name

2021/03/16 14:38:42 20210316_124918.jpg

Description

Taken Date Uploaded By

2021/03/16 09:25:30 Dave Olsen

Upload Date File Name

2021/03/16 14:38:36 20210316_092530.jpg

Description

Curtain wall west main lobby

Taken Date Uploaded By

2021/03/02 08:38:50 Josh Baroni

Upload Date File Name

2021/03/02 08:38:54 A5C9D9E0-432A-4554-95D1-E04…

Description

Dance floor scaffold main lobby

Taken Date Uploaded By

2021/03/02 08:38:20 Josh Baroni

Upload Date File Name

2021/03/02 08:38:23 723110E7-2578-4E8B-88C7-5575…

Lusardi Construction

Printed on Wed Mar 31, 2021 at 06:07 pm PDT

Job #: 3533 VA Clinic - Aero Drive 8875 Aero Drive

San Diego, California 92123 https://storage.procore.com/v4/d/us-east-1/pro-core.com/companies/6833/01F0YFK7FQJFTKJ0QWNKYMR8F2?sig=d85a0cd036d9a669954a4c3307bfb3ec1852a61ee4b4470bdb51480dd8d2ba75 https://storage.procore.com/v4/d/us-east-1/pro-core.com/companies/6833/01F0YFK7FJES0MSJS4PA88BH3M?sig=d2279cd4f838606be02f0147a0465184ea46c03c9e588cf8ca2ccb10196efe8f https://storage.procore.com/v4/d/us-east-1/pro-core.com/prostore/20210302163854_production_2709309706.jpeg?sig=0a2c2d9946f98fa16a9288aeb1dda5802a9b8b1d38d75e03b2e54514efcb34b4 https://storage.procore.com/v4/d/us-east-1/pro-core.com/prostore/20210302163823_production_2709307658.jpeg?sig=9cd530e4444a9c047a6ca94cd7da4474fcb5d551f4b6bd5556565a56a72d021a

2021/03/01 07:53:58 Anthony Santana

Upload Date File Name

2021/03/01 07:56:48 0DED400A-BDE7-4D73-A309-016…

Lusardi Construction

Printed on Wed Mar 31, 2021 at 06:07 pm PDT

Job #: 3533 VA Clinic - Aero Drive 8875 Aero Drive

San Diego, California 92123 https://storage.procore.com/v4/d/us-east-1/pro-core.com/prostore/20210301155648_production_2706961926.jpeg?sig=f60dacde97c6177ebf48352857f11401757cf5aaf6f3fa5d217e996589320400

ID Task Name Duration Start Finish

2 VA Project ‐ San Diego 405 days Mon 2/10/20 Fri 8/27/21

3 Construction Schedule 405 days Mon 2/10/20 Fri 8/27/21

4 Site Improvements 239 days Mon 2/10/20 Thu 1/7/21

85 Site Work, Landscape & Final Asphalt Paving, 81 days Wed 10/21/20 Wed 2/10/21

86 Site Work Around Building 81 days Wed 10/21/20 Wed 2/10/21

101 Trash Enclosure 65 days Wed 2/17/21 Tue 5/18/21

102 Pro Structures Trash Encl. Walls 2 days Wed 2/17/21 Thu 2/18/21

103 Minshew ‐ Trash Enclosure Gates and Posts 5 days Mon 4/12/21 Fri 4/16/21

104 Buxcon Trash Enclosure Roof 2 days Mon 4/19/21 Tue 4/20/21

105 Main Entry Area ‐ Site and Landscaping 37 days Mon 3/29/21 Tue 5/18/21

106 CCI Layout 2 days Mon 3/29/21 Tue 3/30/21

107 CCI Fine Grade ‐ Form Work 9 days Tue 3/30/21 Fri 4/9/21

108 PD Play Flagpole Sleeve 1 day Fri 4/2/21 Fri 4/2/21

109 Scott ‐ Gate Installations 5 days Mon 3/29/21 Fri 4/2/21

110 Concrete Benches 5 days Tue 4/13/21 Mon 4/19/21

111 CCI ‐ Concrete Pours 5 days Tue 4/20/21 Mon 4/26/21

112 PD Play Flagpole, Bike Rack, Furnishings 5 days Tue 4/27/21 Mon 5/3/21

113 Dura Bike Lockers 5 days Tue 4/20/21 Mon 4/26/21

114 PWL ‐ Landscape Soil Prep & Irrigation Parking Islands 10 days Mon 3/29/21 Fri 4/9/21

115 PWL ‐ Landscape Soil Prep 10 days Mon 4/12/21 Fri 4/23/21

116 PWL ‐ Landscape Irrigation 10 days Mon 4/19/21 Fri 4/30/21

117 PWL ‐ Landscape Planting 10 days Mon 4/19/21 Fri 4/30/21

118 RAP Final lift of Paving 2 days Mon 5/3/21 Tue 5/4/21

119 Adair ‐ Site Striping & Signage 5 days Mon 5/10/21 Fri 5/14/21

120 Mcgrath ‐ Sculpture 2 days Mon 5/17/21 Tue 5/18/21

121 Offsite Improvements ‐ New Islands 38 days Mon 3/15/21 Wed 5/5/21

122 Safe‐T‐Lite Traffic Control 1 day Mon 3/15/21 Mon 3/15/21

123 Cement Cutting ‐ Demolition 1 day Tue 3/16/21 Tue 3/16/21

124 LCC & CCI ‐ Grading and UG Sleeves 1 day Wed 3/17/21 Wed 3/17/21

125 CCI ‐ Set up and Pour Curbs and Median 4 days Thu 3/18/21 Tue 3/23/21

126 Trinity ‐ Adjust Utilities to Grade 1 day Wed 3/24/21 Wed 3/24/21

127 RAP ‐ Patch Asphalt 2 days Thu 3/25/21 Fri 3/26/21

128 PWL ‐ Cobble at Median 3 days Mon 3/29/21 Wed 3/31/21

129 Lekos ‐ New Traffic Signals 18 days Mon 4/12/21 Wed 5/5/21

130 Footings 5 days Mon 4/12/21 Fri 4/16/21

131 Conduit, Loops and Wiring 5 days Mon 4/19/21 Fri 4/23/21

132 Install Traffic Signals 5 days Mon 4/26/21 Fri 4/30/21

Pro Structures Trash Encl. Walls 2/18

Minshew - Trash Enclosure Gates and Posts 4/16

Buxcon Trash Enclosure Roof 4/20

CCI Layout 3/30

CCI Fine Grade - Form Work 4/9

PD Play Flagpole Sleeve 4/2

Scott - Gate Installations 4/2

Concrete Benches 4/19

CCI - Concrete Pours 4/26

PD Play Flagpole, Bike Rack, Furnishings 5/3

Dura Bike Lockers 4/26

PWL - Landscape Soil Prep & Irrigation Parking Islands 4/9

PWL - Landscape Soil Prep 4/23

PWL - Landscape Irrigation 4/30

PWL - Landscape Planting 4/30

RAP Final lift of Paving 5/4

Adair - Site Striping & Signage 5/14

Mcgrath - Sculpture 5/18

Safe-T-Lite Traffic Control 3/15

Cement Cutting - Demolition 3/16

LCC & CCI - Grading and UG Sleeves 3/17

CCI - Set up and Pour Curbs and Median 3/23

Trinity - Adjust Utilities to Grade 3/24

RAP - Patch Asphalt 3/26

PWL - Cobble at Median 3/31

Footings 4/16

Conduit, Loops and Wiring 4/23

Install Traffic Signals 4/30

1/26 2/2 2/9 2/162/23 3/1 3/8 3/153/223/29 4/5 4/124/194/26 5/3 5/105/175/245/31 6/7 6/146/216/28 7/5 7/127/197/26 8/2 8/9 8/168/238/30 9/6 9/139/209/2710/410/1110/1810/2511/111/811/1511/2211/2912/612/1312/2012/271/3 1/101/171/241/31 2/7 2/142/212/28 3/7 3/143/213/28 4/4 4/114/184/25 5/2 5/9 5/165/235/30 6/6 6/136/206/27 7/4 7/117/187/25 8/1 8/8 8/158/228/29 9/5 9/129/199/2610/310/1010/1710/2410/3111/711/1411/2111/2812/512/121 February March April May June July August September October November December January February March April May June July August September October November December

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

VA Outpatient Clinic, San Diego Construction Schedule

Page 1 10/1/20

133 Precision ‐ New Striping & Signage 3 days Mon 5/3/21 Wed 5/5/21

134 Parking Garage/ Site Construction 276 days Fri 3/20/20 Fri 4/9/21

266 Core & Shell Improvements 269 days Fri 4/17/20 Wed 4/28/21

267 Demo & Steel at New Openings 52 days Fri 4/17/20 Mon 6/29/20

286 Building CFRP Seismic Upgrades / Retrofit 80 days Fri 4/17/20 Thu 8/6/20

294 Exterior Wall Furring and Plaster 104 days Fri 6/12/20 Wed 11/4/20

308 New 2nd Floor ‐ New 2nd Floor ‐ Grid 2 + 3 16 days Mon 6/22/20 Mon 7/13/20

317 New 2nd Floor ‐ Old Vault Area + Between Grid 4 & 5 28 days Thu 7/2/20 Mon 8/10/20

333 TKE Freight Elevators 120 days Thu 5/28/20 Wed 11/11/20

345 Existing Main Roof ‐ Equipment & Roofing 70 days Fri 7/31/20 Thu 11/5/20

353 New Building Expansion ‐ West 231 days Fri 4/17/20 Fri 3/5/21

409 New Building Expansion ‐ North 172 days Tue 6/9/20 Wed 2/3/21

457 Lobby Structural Steel ‐ 2nd Floor and Roof 105 days Tue 10/13/20 Mon 3/8/21

479 Glass & Metal Panel ‐ Storefront Curtainwall 62 days Tue 2/2/21 Wed 4/28/21

480 Buxcon ‐ Flashings for Curtain Wall 3 days Tue 2/2/21 Thu 2/4/21

481 Buxcon ‐ Wrap Entry Cols before Curtain Wall 3 days Fri 2/5/21 Tue 2/9/21

482 Long ‐ Curtain Wall Storefront 14 days Tue 2/16/21 Fri 3/5/21

483 Long ‐ Installation of Storefront Doors 5 days Mon 3/8/21 Fri 3/12/21

484 Long ‐ Misc. Glass Installations 5 days Mon 3/15/21 Fri 3/19/21

485 BUXCON ‐ Custom Metal Panels 19 days Tue 3/9/21 Fri 4/2/21

486 Buxcon Flashings ‐ Pota‐cochere roofing 2 days Mon 4/5/21 Tue 4/6/21

487 Lusardi Plywood ‐ Pota‐cochere roofing 2 days Tue 4/6/21 Wed 4/7/21

488 Systems WP ‐ Pota‐cochere Roofing System 15 days Thu 4/8/21 Wed 4/28/21

489 Tenant Improvement Construction 319 days Wed 3/25/20 Mon 6/14/21

490 1st Floor ‐ Section "A" 288 days Wed 3/25/20 Fri 4/30/21

491 Framing and Rough‐ins 93 days Wed 3/25/20 Fri 7/31/20

510 Drywall 1A 52 days Mon 7/27/20 Tue 10/6/20

518 Grid, Tile, Millwork, TP/TA 91 days Mon 10/12/20 Mon 2/15/21

533 Finishes In Area 1A 46 days Fri 2/26/21 Fri 4/30/21

534 ECLR Install Carpets & Rubber Flooring 5 days Mon 4/12/21 Fri 4/16/21

535 Spooners Wall Protection Rails 3 days Fri 2/26/21 Tue 3/2/21

536 Heartland Install Ceiling Tile 5 days Mon 4/19/21 Fri 4/23/21

537 MCP ‐ Finish Coat Paint and Wall‐coverings 5 days Mon 4/26/21 Fri 4/30/21

538 1st Floor ‐ Section "B" 286 days Fri 4/3/20 Fri 5/7/21

539 Framing and Rough‐ins 110 days Fri 4/3/20 Thu 9/3/20

557 Drywall ‐ Paint ‐ T‐Grid "1B" 129 days Mon 8/31/20 Thu 2/25/21

578 Finishes in Area "1B" 49 days Tue 3/2/21 Fri 5/7/21

579 VBI Install Barn Doors at Teamlet 5 days Thu 3/11/21 Wed 3/17/21

Precision - New Striping & Signage 5/5

Buxcon - Flashings for Curtain Wall 2/4

Buxcon - Wrap Entry Cols before Curtain Wall 2/9

Long - Curtain Wall Storefront 3/5

Long - Installation of Storefront Doors 3/12

Long - Misc. Glass Installations 3/19

BUXCON - Custom Metal Panels 4/2

Buxcon Flashings - Pota-cochere roofing 4/6

Lusardi Plywood - Pota-cochere roofing 4/7

Systems WP - Pota-cochere Roofing System 4/28

ECLR Install Carpets & Rubber Flooring 4/16

Spooners Wall Protection Rails 3/2

Heartland Install Ceiling Tile 4/23

MCP - Finish Coat Paint and Wall-coverings 4/30

VBI Install Barn Doors at Teamlet 3/17

1/26 2/2 2/9 2/162/23 3/1 3/8 3/153/223/29 4/5 4/124/194/26 5/3 5/105/175/245/31 6/7 6/146/216/28 7/5 7/127/197/26 8/2 8/9 8/168/238/30 9/6 9/139/209/2710/410/1110/1810/2511/111/811/1511/2211/2912/612/1312/2012/271/3 1/101/171/241/31 2/7 2/142/212/28 3/7 3/143/213/28 4/4 4/114/184/25 5/2 5/9 5/165/235/30 6/6 6/136/206/27 7/4 7/117/187/25 8/1 8/8 8/158/228/29 9/5 9/129/199/2610/310/1010/1710/2410/3111/711/1411/2111/2812/512/121 February March April May June July August September October November December January February March April May June July August September October November December

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2 10/1/20

580 Spooners Wall Protection Rails 3 days Tue 3/2/21 Thu 3/4/21

581 ECLR Install Carpets 5 days Mon 4/19/21 Fri 4/23/21

582 Heartland Install Ceiling Tile 5 days Mon 4/19/21 Fri 4/23/21

583 MCP ‐ Finish Coat Paint and Wall‐coverings 10 days Mon 4/26/21 Fri 5/7/21

584 1st Floor ‐ Section "C" (Skip Lobby) 274 days Thu 4/23/20 Tue 5/11/21

585 Framing & Rough‐ins 139 days Thu 4/23/20 Tue 11/3/20

601 Drywall ‐ Paint ‐ T‐Grid "1C" 109 days Thu 9/24/20 Tue 2/23/21

619 Finishes in Area 1C 65 days Wed 2/10/21 Tue 5/11/21

620 TekWorks ‐ Audio Speaker Systems 4 days Wed 2/10/21 Mon 2/15/21

621 TekWorks ‐ Fiber & Wireless 3 days Mon 2/15/21 Wed 2/17/21

622 Spooners Wall Protection Rails 3 days Fri 3/5/21 Tue 3/9/21

623 L2 ‐ Operable Wall Track Installations 2 days Tue 2/16/21 Wed 2/17/21

624 ECLR Install Carpets 5 days Mon 4/26/21 Fri 4/30/21

625 Heartland Install Ceiling Tile 5 days Mon 4/26/21 Fri 4/30/21

626 MCP ‐ Finish Coat Paint & Wall‐coverings 2 days Mon 5/10/21 Tue 5/11/21

627 L2 ‐ Operable Wall Installations 2 days Mon 4/12/21 Tue 4/13/21

628 1st Floor ‐ Section "D" 223 days Fri 7/10/20 Tue 5/18/21

629 Framing & Rough‐ins 69 days Fri 7/10/20 Wed 10/14/20

639 Drywall ‐ Paint ‐ T‐Grid "1D" 88 days Wed 10/14/20 Fri 2/12/21

655 Finishes in Area "1D" 66 days Tue 2/16/21 Tue 5/18/21

656 TekWorks ‐ Audio Speaker Systems 2 days Tue 2/16/21 Wed 2/17/21

657 TekWorks ‐ Fiber & Wireless 2 days Tue 2/16/21 Wed 2/17/21

658 VBI ‐ Install Doors area 1D 3 days Wed 2/17/21 Fri 2/19/21

659 VBI ‐ Install Door Hardware 3 days Wed 2/24/21 Fri 2/26/21

660 MC Paint ‐ Wall Protection Board 2 days Mon 3/1/21 Tue 3/2/21

661 Spooners Wall Protection Rails 2 days Wed 3/10/21 Thu 3/11/21

662 ECLR Install Carpets 5 days Mon 5/3/21 Fri 5/7/21

663 Heartland ‐ Install Ceiling Tile 5 days Mon 5/3/21 Fri 5/7/21

664 MCP ‐ Finish Coat Paint & Wall‐coverings 5 days Wed 5/12/21 Tue 5/18/21

665 2nd Floor ‐ Section "A" 208 days Fri 8/7/20 Tue 5/25/21

666 Framing & Rough‐ins 66 days Fri 8/7/20 Fri 11/6/20

678 Drywall ‐ Paint ‐ T‐Grid "2A" 83 days Mon 11/2/20 Wed 2/24/21

692 Finishes in Area "2A" 80 days Wed 2/3/21 Tue 5/25/21

693 Spooners Wall Protection Rails 3 days Wed 2/3/21 Fri 2/5/21

694 TekWorks ‐ Audio Speaker Systems 4 days Thu 2/18/21 Tue 2/23/21

695 TekWorks ‐ Fiber & Wireless 4 days Thu 2/18/21 Tue 2/23/21

696 TekWorks ‐ Security Installations 7 days Thu 2/25/21 Fri 3/5/21

697 VBI ‐ Install Doors area 2A 5 days Mon 2/22/21 Fri 2/26/21

Spooners Wall Protection Rails 3/4

ECLR Install Carpets 4/23

Heartland Install Ceiling Tile 4/23

MCP - Finish Coat Paint and Wall-coverings 5/7

TekWorks - Audio Speaker Systems 2/15

TekWorks - Fiber & Wireless 2/17

Spooners Wall Protection Rails 3/9

L2 - Operable Wall Track Installations 2/17

ECLR Install Carpets 4/30

Heartland Install Ceiling Tile 4/30

MCP - Finish Coat Paint & Wall-coverings 5/11

L2 - Operable Wall Installations 4/13

TekWorks - Audio Speaker Systems 2/17

TekWorks - Fiber & Wireless 2/17

VBI - Install Doors area 1D 2/19

VBI - Install Door Hardware 2/26

MC Paint - Wall Protection Board 3/2

Spooners Wall Protection Rails 3/11

ECLR Install Carpets 5/7

Heartland - Install Ceiling Tile 5/7

MCP - Finish Coat Paint & Wall-coverings 5/18

Spooners Wall Protection Rails 2/5

TekWorks - Audio Speaker Systems 2/23

TekWorks - Fiber & Wireless 2/23

TekWorks - Security Installations 3/5

VBI - Install Doors area 2A 2/26

1/26 2/2 2/9 2/162/23 3/1 3/8 3/153/223/29 4/5 4/124/194/26 5/3 5/105/175/245/31 6/7 6/146/216/28 7/5 7/127/197/26 8/2 8/9 8/168/238/30 9/6 9/139/209/2710/410/1110/1810/2511/111/811/1511/2211/2912/612/1312/2012/271/3 1/101/171/241/31 2/7 2/142/212/28 3/7 3/143/213/28 4/4 4/114/184/25 5/2 5/9 5/165/235/30 6/6 6/136/206/27 7/4 7/117/187/25 8/1 8/8 8/158/228/29 9/5 9/129/199/2610/310/1010/1710/2410/3111/711/1411/2111/2812/512/121 February March April May June July August September October November December January February March April May June July August September October November December

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 3 10/1/20

698 VBI ‐ Install Door Hardware 5 days Mon 3/1/21 Fri 3/5/21

699 MC Paint ‐ Wall Protection Board 5 days Mon 3/1/21 Fri 3/5/21

700 VBI Install Barn Doors 5 days Thu 3/18/21 Wed 3/24/21

701 Saddleback ‐ Toilet Partitions & Accessories 2 days Thu 3/25/21 Fri 3/26/21

702 ECLR Install Carpets 5 days Mon 5/10/21 Fri 5/14/21

703 Heartland ‐ Install Ceiling Tile 5 days Mon 5/10/21 Fri 5/14/21

704 MCP ‐ Finish Coat Paint & Wall‐coverings 5 days Wed 5/19/21 Tue 5/25/21

705 2nd Floor ‐ Section "D" 199 days Fri 8/28/20 Wed 6/2/21

706 Framing & Rough‐ins 61 days Fri 8/28/20 Fri 11/20/20

718 Drywall ‐ Paint ‐ T‐Grid "2D" 60 days Mon 11/30/20 Fri 2/19/21

731 Finishes in Area "2D" 81 days Wed 2/10/21 Wed 6/2/21

732 Spooners Wall Protection Rails 3 days Wed 2/10/21 Fri 2/12/21

733 Advance ‐ Restroom Plumbing Fixtures 8 days Thu 2/25/21 Mon 3/8/21

734 TekWorks ‐ Audio Speaker Systems 3 days Wed 2/24/21 Fri 2/26/21

735 TekWorks ‐ Fiber & Wireless 4 days Wed 2/24/21 Mon 3/1/21

736 TekWorks ‐ Security Installations 7 days Mon 3/8/21 Tue 3/16/21

737 VBI ‐ Install Doors area 2D 5 days Mon 3/1/21 Fri 3/5/21

738 VBI ‐ Install Door Hardware 5 days Mon 3/8/21 Fri 3/12/21

739 MC Paint ‐ Wall Protection Board 5 days Mon 3/8/21 Fri 3/12/21

740 Saddleback ‐ Toilet Partitions & Accessories 2 days Mon 3/29/21 Tue 3/30/21

741 Installation of Dental Equipment 15 days Mon 4/12/21 Fri 4/30/21

747 ECLR Install Carpets 5 days Thu 5/20/21 Wed 5/26/21

748 Heartland ‐ Install Ceiling Tile 4 days Mon 5/17/21 Thu 5/20/21

749 MCP ‐ Finish Coat Paint & Wall‐coverings 5 days Thu 5/27/21 Wed 6/2/21

750 2nd Floor ‐ Section "B" 193 days Tue 9/8/20 Thu 6/3/21

751 Framing & Rough‐ins 78 days Tue 9/8/20 Thu 12/24/20

764 Drywall ‐ Paint ‐ T‐Grid "2B" 59 days Tue 12/15/20 Fri 3/5/21

776 Finishes in Area "2B" 82 days Wed 2/10/21 Thu 6/3/21

777 Cabinets and Millwork 8 days Wed 2/10/21 Fri 2/19/21

778 Countertops 8 days Mon 2/15/21 Wed 2/24/21

779 Spooners Wall Protection Rails 4 days Mon 2/15/21 Thu 2/18/21

780 Advance ‐ Restroom Plumbing Fixtures 9 days Mon 3/8/21 Thu 3/18/21

781 MC Paint ‐ Wall Protection Board 8 days Mon 3/15/21 Wed 3/24/21

782 TekWorks ‐ Audio Speaker Systems 3 days Mon 3/1/21 Wed 3/3/21

783 TekWorks ‐ Fiber & Wireless 4 days Mon 3/1/21 Thu 3/4/21

784 TekWorks ‐ Security Installations 10 days Wed 3/17/21 Tue 3/30/21

785 VBI ‐ Install Doors area 2B 10 days Mon 3/8/21 Fri 3/19/21

786 VBI ‐ Install Door Hardware 10 days Mon 3/15/21 Fri 3/26/21

VBI - Install Door Hardware 3/5

MC Paint - Wall Protection Board 3/5

VBI Install Barn Doors 3/24

Saddleback - Toilet Partitions & Accessories 3/26

ECLR Install Carpets 5/14

Heartland - Install Ceiling Tile 5/14

MCP - Finish Coat Paint & Wall-coverings 5/25

Spooners Wall Protection Rails 2/12

Advance - Restroom Plumbing Fixtures 3/8

TekWorks - Audio Speaker Systems 2/26

TekWorks - Fiber & Wireless 3/1

TekWorks - Security Installations 3/16

VBI - Install Doors area 2D 3/5

VBI - Install Door Hardware 3/12

MC Paint - Wall Protection Board 3/12

Saddleback - Toilet Partitions & Accessories 3/30

ECLR Install Carpets 5/26

Heartland - Install Ceiling Tile 5/20

MCP - Finish Coat Paint & Wall-coverings 6/2

Cabinets and Millwork 2/19

Countertops 2/24

Spooners Wall Protection Rails 2/18

Advance - Restroom Plumbing Fixtures 3/18

MC Paint - Wall Protection Board 3/24

TekWorks - Audio Speaker Systems 3/3

TekWorks - Fiber & Wireless 3/4

TekWorks - Security Installations 3/30

VBI - Install Doors area 2B 3/19

VBI - Install Door Hardware 3/26

1/26 2/2 2/9 2/162/23 3/1 3/8 3/153/223/29 4/5 4/124/194/26 5/3 5/105/175/245/31 6/7 6/146/216/28 7/5 7/127/197/26 8/2 8/9 8/168/238/30 9/6 9/139/209/2710/410/1110/1810/2511/111/811/1511/2211/2912/612/1312/2012/271/3 1/101/171/241/31 2/7 2/142/212/28 3/7 3/143/213/28 4/4 4/114/184/25 5/2 5/9 5/165/235/30 6/6 6/136/206/27 7/4 7/117/187/25 8/1 8/8 8/158/228/29 9/5 9/129/199/2610/310/1010/1710/2410/3111/711/1411/2111/2812/512/121 February March April May June July August September October November December January February March April May June July August September October November December

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 4 10/1/20

787 VBI Install Barn Doors 10 days Thu 3/25/21 Wed 4/7/21

788 Saddleback ‐ Toilet Partitions & Accessories 2 days Wed 3/31/21 Thu 4/1/21

789 Heartland ‐ Install Ceiling Tile 5 days Fri 5/21/21 Thu 5/27/21

790 ECLR Install Carpets 5 days Fri 5/21/21 Thu 5/27/21

791 L2 ‐ Operable Wall Installations 2 days Wed 4/14/21 Thu 4/15/21

792 MCP ‐ Finish Coat Paint & Wall‐coverings 5 days Fri 5/28/21 Thu 6/3/21

793 2nd Floor ‐ Section "C" 191 days Fri 9/11/20 Fri 6/4/21

794 Framing & Rough‐ins 80 days Fri 9/11/20 Thu 12/31/20

807 Drywall ‐ Paint ‐ T‐Grid "2C" 42 days Thu 12/31/20 Fri 2/26/21

814 Finishes in Area "2C" 76 days Fri 2/19/21 Fri 6/4/21

815 Install M‐P‐E‐FS Finishes in Grid 8 days Mon 2/22/21 Wed 3/3/21

816 Christian Bros. Tile Installations 8 days Mon 3/8/21 Wed 3/17/21

817 Lusardi Exam Room Rails 4 days Mon 3/1/21 Thu 3/4/21

818 Cabinets and Millwork 7 days Mon 2/22/21 Tue 3/2/21

819 Countertops 7 days Thu 2/25/21 Fri 3/5/21

820 Spooners Wall Protection Rails 4 days Fri 2/19/21 Wed 2/24/21

821 ECLR LVT & Sheet Vinyl Flooring 9 days Mon 3/8/21 Thu 3/18/21

822 Advance ‐ Restroom Plumbing Fixtures 8 days Fri 3/19/21 Tue 3/30/21

823 MC Paint ‐ Wall Protection Board 3 days Thu 3/25/21 Mon 3/29/21

824 TekWorks ‐ Audio Speaker Systems 3 days Thu 3/4/21 Mon 3/8/21

825 TekWorks ‐ Fiber & Wireless 3 days Thu 3/4/21 Mon 3/8/21

826 TekWorks ‐ Security Installations 7 days Wed 3/31/21 Thu 4/8/21

827 VBI ‐ Install Doors area 2C 5 days Mon 3/22/21 Fri 3/26/21

828 VBI ‐ Install Door Hardware 5 days Mon 3/29/21 Fri 4/2/21

829 Saddleback ‐ Toilet Partitions & Accessories 2 days Fri 4/2/21 Mon 4/5/21

830 Heartland ‐ Install Ceiling Tile 3 days Fri 5/28/21 Tue 6/1/21

831 ECLR Install Carpets 3 days Fri 5/28/21 Tue 6/1/21

832 MCP ‐ Finish Coat Paint & Wall‐coverings 3 days Wed 6/2/21 Fri 6/4/21

833 West Wing Interior Construction 178 days Mon 10/5/20 Wed 6/9/21

834 Framing & Rough‐ins 70 days Mon 10/5/20 Fri 1/8/21

845 Drywall ‐ Paint ‐ T‐Grid West Wing 29 days Tue 1/19/21 Fri 2/26/21

851 Finishes in the West Wing 75 days Thu 2/25/21 Wed 6/9/21

852 Install Acoustical Ceiling Grid 10 days Thu 2/25/21 Wed 3/10/21

853 Install M‐P‐E‐FS Finishes in Grid 10 days Thu 3/4/21 Wed 3/17/21

854 Christian Bros. ‐ No R/R West ‐ move to North 0 days Wed 3/17/21 Wed 3/17/21

855 Cabinets and Millwork 5 days Wed 3/3/21 Tue 3/9/21

856 Countertops 5 days Mon 3/8/21 Fri 3/12/21

857 Spooners Wall Protection Rails 2 days Thu 2/25/21 Fri 2/26/21

VBI Install Barn Doors 4/7

Saddleback - Toilet Partitions & Accessories 4/1

Heartland - Install Ceiling Tile 5/27

ECLR Install Carpets 5/27

L2 - Operable Wall Installations 4/15

MCP - Finish Coat Paint & Wall-coverings 6/3

Install M-P-E-FS Finishes in Grid 3/3

Christian Bros. Tile Installations 3/17

Lusardi Exam Room Rails 3/4

Cabinets and Millwork 3/2

Countertops 3/5

Spooners Wall Protection Rails 2/24

ECLR LVT & Sheet Vinyl Flooring 3/18

Advance - Restroom Plumbing Fixtures 3/30

MC Paint - Wall Protection Board 3/29

TekWorks - Audio Speaker Systems 3/8

TekWorks - Fiber & Wireless 3/8

TekWorks - Security Installations 4/8

VBI - Install Doors area 2C 3/26

VBI - Install Door Hardware 4/2

Saddleback - Toilet Partitions & Accessories 4/5

Heartland - Install Ceiling Tile 6/1

ECLR Install Carpets 6/1

MCP - Finish Coat Paint & Wall-coverings 6/4

Install Acoustical Ceiling Grid 3/10

Install M-P-E-FS Finishes in Grid 3/17

3/17

Cabinets and Millwork 3/9

Countertops 3/12

Spooners Wall Protection Rails 2/26

1/26 2/2 2/9 2/162/23 3/1 3/8 3/153/223/29 4/5 4/124/194/26 5/3 5/105/175/245/31 6/7 6/146/216/28 7/5 7/127/197/26 8/2 8/9 8/168/238/30 9/6 9/139/209/2710/410/1110/1810/2511/111/811/1511/2211/2912/612/1312/2012/271/3 1/101/171/241/31 2/7 2/142/212/28 3/7 3/143/213/28 4/4 4/114/184/25 5/2 5/9 5/165/235/30 6/6 6/136/206/27 7/4 7/117/187/25 8/1 8/8 8/158/228/29 9/5 9/129/199/2610/310/1010/1710/2410/3111/711/1411/2111/2812/512/121 February March April May June July August September October November December January February March April May June July August September October November December

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 5 10/1/20

858 ECLR LVT & Sheet Vinyl Flooring 3 days Fri 3/19/21 Tue 3/23/21

859 Advance ‐ Restroom Plumbing Fixtures 5 days Wed 3/31/21 Tue 4/6/21

860 Installation of Audiology Booths 20 days Mon 3/1/21 Fri 3/26/21

861 TekWorks ‐ Audio Speaker Systems 3 days Tue 3/9/21 Thu 3/11/21

862 TekWorks ‐ Fiber & Wireless 3 days Tue 3/9/21 Thu 3/11/21

863 TekWorks ‐ Security Installations 5 days Mon 3/29/21 Fri 4/2/21

864 VBI ‐ Install Doors West Wing TI 5 days Mon 3/29/21 Fri 4/2/21

865 VBI ‐ Install Door Hardware 5 days Mon 4/5/21 Fri 4/9/21

866 Heartland ‐ Install Ceiling Tile 3 days Wed 6/2/21 Fri 6/4/21

867 ECLR Install Carpets 3 days Wed 6/2/21 Fri 6/4/21

868 MCP ‐ Finish Coat Paint & Wall‐coverings 3 days Mon 6/7/21 Wed 6/9/21

869 North Wing + Police Interior Construction 173 days Thu 10/15/20 Mon 6/14/21

870 Framing & Rough‐ins 83 days Thu 10/15/20 Mon 2/8/21

879 Drywall ‐ Paint ‐ T‐Grid at North + Police 28 days Wed 2/3/21 Fri 3/12/21

885 Finishes in North Wing 76 days Mon 3/1/21 Mon 6/14/21

886 Paint Primer Coat + Check Walls + 1st Coat Paint 10 days Wed 3/10/21 Tue 3/23/21

887 Install Acoustical Ceiling Grid 10 days Thu 3/11/21 Wed 3/24/21

888 Install M‐P‐E‐FS Finishes in Grid 10 days Thu 3/18/21 Wed 3/31/21

889 Christian Bros Restroom Tile 10 days Thu 3/18/21 Wed 3/31/21

890 Cabinets and Millwork 6 days Wed 3/10/21 Wed 3/17/21

891 Countertops 6 days Mon 3/15/21 Mon 3/22/21

892 Spooners Wall Protection Rails 3 days Mon 3/1/21 Wed 3/3/21

893 ECLR LVT & Sheet Vinyl Flooring 10 days Wed 3/24/21 Tue 4/6/21

894 TekWorks ‐ Audio Speaker Systems 3 days Fri 3/12/21 Tue 3/16/21

895 TekWorks ‐ Fiber & Wireless 4 days Fri 3/12/21 Wed 3/17/21

896 TekWorks ‐ Security Installations 7 days Mon 4/5/21 Tue 4/13/21

897 VBI ‐ Install Doors North Wing TI 5 days Mon 4/5/21 Fri 4/9/21

898 VBI ‐ Install Door Hardware 5 days Mon 4/5/21 Fri 4/9/21

899 Saddleback ‐ Toilet Partitions & Accessories 3 days Tue 4/6/21 Thu 4/8/21

900 Advance ‐ Restroom Plumbing Fixtures 7 days Thu 4/1/21 Fri 4/9/21

901 L2 ‐ Operable Wall Installations 2 days Fri 4/16/21 Mon 4/19/21

902 Heartland ‐ Install Ceiling Tile 3 days Mon 6/7/21 Wed 6/9/21

903 ECLR Install Carpets 3 days Mon 6/7/21 Wed 6/9/21

904 MCP ‐ Finish Coat Paint & Wall‐coverings 3 days Thu 6/10/21 Mon 6/14/21

905 1st Floor ‐ Radiology Rooms & Main Corridor 100 days Mon 1/25/21 Fri 6/11/21

906 Framing & Rough‐ins 24 days Mon 1/25/21 Thu 2/25/21

912 Drywall ‐ Paint ‐ T‐Grid in the Radiology 15 days Mon 3/15/21 Fri 4/2/21

913 Drywall ‐ One Side Radiology and Corridor 5 days Tue 3/16/21 Mon 3/22/21

ECLR LVT & Sheet Vinyl Flooring 3/23

Advance - Restroom Plumbing Fixtures 4/6

Installation of Audiology Booths 3/26

TekWorks - Audio Speaker Systems 3/11

TekWorks - Fiber & Wireless 3/11

TekWorks - Security Installations 4/2

VBI - Install Doors West Wing TI 4/2

VBI - Install Door Hardware 4/9

Heartland - Install Ceiling Tile 6/4

ECLR Install Carpets 6/4

MCP - Finish Coat Paint & Wall-coverings 6/9

Paint Primer Coat + Check Walls + 1st Coat Paint 3/23

Install Acoustical Ceiling Grid 3/24

Install M-P-E-FS Finishes in Grid 3/31

Christian Bros Restroom Tile 3/31

Cabinets and Millwork 3/17

Countertops 3/22

Spooners Wall Protection Rails 3/3

ECLR LVT & Sheet Vinyl Flooring 4/6

TekWorks - Audio Speaker Systems 3/16

TekWorks - Fiber & Wireless 3/17

TekWorks - Security Installations 4/13

VBI - Install Doors North Wing TI 4/9

VBI - Install Door Hardware 4/9

Saddleback - Toilet Partitions & Accessories 4/8

Advance - Restroom Plumbing Fixtures 4/9

L2 - Operable Wall Installations 4/19

Heartland - Install Ceiling Tile 6/9

ECLR Install Carpets 6/9

MCP - Finish Coat Paint & Wall-coverings 6/14

Drywall - One Side Radiology and Corridor 3/22

1/26 2/2 2/9 2/162/23 3/1 3/8 3/153/223/29 4/5 4/124/194/26 5/3 5/105/175/245/31 6/7 6/146/216/28 7/5 7/127/197/26 8/2 8/9 8/168/238/30 9/6 9/139/209/2710/410/1110/1810/2511/111/811/1511/2211/2912/612/1312/2012/271/3 1/101/171/241/31 2/7 2/142/212/28 3/7 3/143/213/28 4/4 4/114/184/25 5/2 5/9 5/165/235/30 6/6 6/136/206/27 7/4 7/117/187/25 8/1 8/8 8/158/228/29 9/5 9/129/199/2610/310/1010/1710/2410/3111/711/1411/2111/2812/512/121 February March April May June July August September October November December January February March April May June July August September October November December

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 6 10/1/20

914 Insulation 2 days Tue 3/23/21 Wed 3/24/21

915 Drywall ‐ 2nd Side 5 days Thu 3/25/21 Wed 3/31/21

916 Tape and Texture Walls 7 days Mon 3/15/21 Tue 3/23/21

917 Paint Primer Coat + Check Walls + 1st Coat Paint 5 days Wed 3/24/21 Tue 3/30/21

918 Install Acoustical Ceiling Grid 3 days Wed 3/31/21 Fri 4/2/21

919 Finishes in the Radiology 72 days Thu 3/4/21 Fri 6/11/21

920 Install M‐P‐E‐FS Finishes in Grid 5 days Fri 4/2/21 Thu 4/8/21

921 Christian Bros ‐ Tile 5 days Thu 4/1/21 Wed 4/7/21

922 Cabinets 3 days Wed 3/31/21 Fri 4/2/21

923 Countertops 3 days Thu 4/1/21 Mon 4/5/21

924 Spooners Wall Protection Rails 3 days Thu 3/4/21 Mon 3/8/21

925 Heartland ‐ Install Ceiling Tile 1 day Thu 6/10/21 Thu 6/10/21

926 MCP ‐ Finish Coat Paint & Wall‐coverings 2 days Thu 6/10/21 Fri 6/11/21

927 1st Floor ‐ Main Lobby 95 days Thu 12/31/20 Wed 5/12/21

928 Elevator Installations 37 days Thu 12/31/20 Fri 2/19/21

933 Framing & Rough‐ins 10 days Mon 3/1/21 Fri 3/12/21

934 UBG ‐ Scaffold in Lobby 2 days Mon 3/1/21 Tue 3/2/21

935 Frame Walls & Ceilings 6 days Wed 3/3/21 Wed 3/10/21

936 M‐P‐E Rough‐ins Walls/Ceiling 2 days Thu 3/11/21 Fri 3/12/21

937 Install HM Door & Window Frames 2 days Thu 3/11/21 Fri 3/12/21

938 UBG ‐ Plywood for 3‐Form Reglet 2 days Thu 3/11/21 Fri 3/12/21

939 Drywall ‐ Paint ‐ T‐Grid in the Lobby 27 days Wed 3/24/21 Thu 4/29/21

940 Drywall ‐ One Side and Ceiling in Lobby 10 days Thu 4/1/21 Wed 4/14/21

941 Insulation 2 days Wed 4/14/21 Thu 4/15/21

942 Drywall ‐ 2nd Side 10 days Fri 4/16/21 Thu 4/29/21

943 Tape and Texture Walls 10 days Wed 3/24/21 Tue 4/6/21

944 Paint Primer Coat + Check Walls + 1st Coat Paint 7 days Wed 4/7/21 Thu 4/15/21

945 UBG ‐ Remove Scaffolding 2 days Fri 4/16/21 Mon 4/19/21

946 Frame Lobby Planter 5 days Tue 4/20/21 Mon 4/26/21

947 Install Acoustical Ceiling Grid 5 days Fri 4/16/21 Thu 4/22/21

948 Finishes in the Lobby 18 days Mon 4/19/21 Wed 5/12/21

949 Long ‐ Install 3 Interior Storefont Assemblies 7 days Mon 4/19/21 Tue 4/27/21

950 Install Custom Lighting in Lobby 2 days Tue 4/20/21 Wed 4/21/21

951 Install M‐P‐E‐FS Finishes in Grid 3 days Tue 4/20/21 Thu 4/22/21

952 Spooners ‐ Cabinets and Lobby Planter 3 days Wed 4/21/21 Fri 4/23/21

953 Christian Bros ‐ Lobby Floor Tile 5 days Mon 4/26/21 Fri 4/30/21

954 Countertops 2 days Mon 5/3/21 Tue 5/4/21

955 Heartland ‐ Install Ceiling Tile 1 day Wed 5/5/21 Wed 5/5/21

Insulation 3/24

Drywall - 2nd Side 3/31

Tape and Texture Walls 3/23

Paint Primer Coat + Check Walls + 1st Coat Paint 3/30

Install Acoustical Ceiling Grid 4/2

Install M-P-E-FS Finishes in Grid 4/8

Christian Bros - Tile 4/7

Cabinets 4/2

Countertops 4/5

Spooners Wall Protection Rails 3/8

Heartland - Install Ceiling Tile 6/10

MCP - Finish Coat Paint & Wall-coverings 6/11

UBG - Scaffold in Lobby 3/2

Frame Walls & Ceilings 3/10

M-P-E Rough-ins Walls/Ceiling 3/12

Install HM Door & Window Frames 3/12

UBG - Plywood for 3-Form Reglet 3/12

Drywall - One Side and Ceiling in Lobby 4/14

Insulation 4/15

Drywall - 2nd Side 4/29

Tape and Texture Walls 4/6

Paint Primer Coat + Check Walls + 1st Coat Paint 4/15

UBG - Remove Scaffolding 4/19

Frame Lobby Planter 4/26

Install Acoustical Ceiling Grid 4/22

Long - Install 3 Interior Storefont Assemblies 4/27

Install Custom Lighting in Lobby 4/21

Install M-P-E-FS Finishes in Grid 4/22

Spooners - Cabinets and Lobby Planter 4/23

Christian Bros - Lobby Floor Tile 4/30

Countertops 5/4

Heartland - Install Ceiling Tile 5/5

1/26 2/2 2/9 2/162/23 3/1 3/8 3/153/223/29 4/5 4/124/194/26 5/3 5/105/175/245/31 6/7 6/146/216/28 7/5 7/127/197/26 8/2 8/9 8/168/238/30 9/6 9/139/209/2710/410/1110/1810/2511/111/811/1511/2211/2912/612/1312/2012/271/3 1/101/171/241/31 2/7 2/142/212/28 3/7 3/143/213/28 4/4 4/114/184/25 5/2 5/9 5/165/235/30 6/6 6/136/206/27 7/4 7/117/187/25 8/1 8/8 8/158/228/29 9/5 9/129/199/2610/310/1010/1710/2410/3111/711/1411/2111/2812/512/121 February March April May June July August September October November December January February March April May June July August September October November December

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 7 10/1/20

956 MCP ‐ Finish Coat Paint & Wall‐coverings 5 days Thu 5/6/21 Wed 5/12/21

957 Commissioning and Finals 201 days Mon 10/26/20 Mon 8/2/21

958 Start up and Test All Electrical & Data Equipment 113 days Mon 10/26/20 Wed 3/31/21

959 Complete Main Electrical Room 30 days Mon 10/26/20 Fri 12/4/20

960 Complete All Sub‐Electrical Rooms 45 days Mon 10/26/20 Fri 12/25/20

961 Delivery of New House Panel 1 day Mon 12/21/20 Mon 12/21/20

962 Install SDG&E Transformer (Temp Power) 1 day Mon 12/21/20 Mon 12/21/20

963 Complete all Switch Gear installations 30 days Mon 12/21/20 Fri 1/29/21

964 Pull Home Runs and Test all Breakers 10 days Mon 2/1/21 Fri 2/12/21

965 Delivery of Bus Duct 1 day Mon 2/15/21 Mon 2/15/21

966 Delivery of Bus Duct ‐ DELAY 14 days Tue 2/16/21 Fri 3/5/21

967 Neal Electric Bus Duct Installation 12 days Mon 3/8/21 Tue 3/23/21

968 City Inspection for Meter release 1 day Wed 3/24/21 Wed 3/24/21

969 SDG&E Pull Secondary Wire 4 days Thu 3/25/21 Tue 3/30/21

970 SDG&E ‐ Electrical Meter Set 1 day Wed 3/31/21 Wed 3/31/21

971 Electrical Commissioning 37 days Mon 3/29/21 Tue 5/18/21

972 Neal's Title 24 Programing 10 days Mon 3/29/21 Fri 4/9/21

973 Electrical Lighting Commissioning 25 days Mon 4/12/21 Fri 5/14/21

974 Fire Alarm Programming 10 days Mon 4/12/21 Fri 4/23/21

975 Fire Alarm Commissioning ‐ FD Inspection 10 days Mon 4/26/21 Fri 5/7/21

976 Security Systems Testing 5 days Mon 5/10/21 Fri 5/14/21

977 Speakers and Paging Systems Commissioning 5 days Mon 5/10/21 Fri 5/14/21

978 Nurse Call Commissioning 2 days Mon 5/17/21 Tue 5/18/21

979 Start up and Test All Mechanical Equipment 86 days Mon 4/5/21 Mon 8/2/21

980 Climatec Controls (Neal Electric Power to Each Item) 40 days Mon 4/5/21 Fri 5/28/21

981 AHUS 8 days Mon 4/5/21 Wed 4/14/21

982 VAVs 7 days Thu 4/15/21 Fri 4/23/21

983 Room Pressure 7 days Mon 4/26/21 Tue 5/4/21

984 FCUs 6 days Wed 5/5/21 Wed 5/12/21

985 DHWS 2 days Thu 5/13/21 Fri 5/14/21

986 HHWS 1 day Mon 5/17/21 Mon 5/17/21

987 ERV 1 day Tue 5/18/21 Tue 5/18/21

988 Exhaust Fan VFDs 6 days Wed 5/19/21 Wed 5/26/21

989 Exhaust Fans 2 days Thu 5/27/21 Fri 5/28/21

990 BCM Startup & Commissioning 40 days Fri 4/16/21 Thu 6/10/21

991 AHUS 5 days Fri 4/16/21 Thu 4/22/21

992 FCUs 10 days Fri 4/23/21 Thu 5/6/21

993 HHWS 5 days Fri 5/7/21 Thu 5/13/21

MCP - Finish Coat Paint & Wall-coverings 5/12

Complete Main Electrical Room 12/4

Complete All Sub-Electrical Rooms 12/25

Delivery of New House Panel 12/21

Install SDG&E Transformer (Temp Power) 12/21

Complete all Switch Gear installations 1/29

Pull Home Runs and Test all Breakers 2/12

Delivery of Bus Duct 2/15

Neal Electric Bus Duct Installation 3/23

City Inspection for Meter release 3/24

SDG&E Pull Secondary Wire 3/30

SDG&E - Electrical Meter Set 3/31

Neal's Title 24 Programing 4/9

Electrical Lighting Commissioning 5/14

Fire Alarm Programming 4/23

Fire Alarm Commissioning - FD Inspection 5/7

Security Systems Testing 5/14

Speakers and Paging Systems Commissioning 5/14

Nurse Call Commissioning 5/18

AHUS 4/14

VAVs 4/23

Room Pressure 5/4

FCUs 5/12

DHWS 5/14

HHWS 5/17

ERV 5/18

Exhaust Fan VFDs 5/26

Exhaust Fans 5/28

AHUS 4/22

FCUs 5/6

HHWS 5/13

1/26 2/2 2/9 2/162/23 3/1 3/8 3/153/223/29 4/5 4/124/194/26 5/3 5/105/175/245/31 6/7 6/146/216/28 7/5 7/127/197/26 8/2 8/9 8/168/238/30 9/6 9/139/209/2710/410/1110/1810/2511/111/811/1511/2211/2912/612/1312/2012/271/3 1/101/171/241/31 2/7 2/142/212/28 3/7 3/143/213/28 4/4 4/114/184/25 5/2 5/9 5/165/235/30 6/6 6/136/206/27 7/4 7/117/187/25 8/1 8/8 8/158/228/29 9/5 9/129/199/2610/310/1010/1710/2410/3111/711/1411/2111/2812/512/121 February March April May June July August September October November December January February March April May June July August September October November December

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 8 10/1/20

994 ERV 2 days Fri 5/14/21 Mon 5/17/21

995 VFDs 9 days Tue 5/18/21 Fri 5/28/21

996 Exhaust Fans 9 days Mon 5/31/21 Thu 6/10/21

997 Test & Balance 40 days Tue 5/4/21 Mon 6/28/21

998 HVAC Commissioning ‐ Functional Testing 30 days Tue 6/22/21 Mon 8/2/21

999 Plumbing Systems Commissioning 20 days Mon 4/12/21 Fri 5/7/21

1000 Hot Water Systems and Water Softener 20 days Mon 4/12/21 Fri 5/7/21

1001 Punch List Walk & Work 45 days Mon 4/26/21 Fri 6/25/21

1002 Completion of Principal Categories of Work 0 days Mon 6/28/21 Mon 6/28/21

1003 Commissioning/Functional Testing 20 days Tue 6/22/21 Mon 7/19/21

1004 Building Systems Certification 0 days Mon 7/19/21 Mon 7/19/21

1005 Final…