ATTACHMENT D MATERIAL PRICE ADJUSTMENT SHEET AND EXAMPLE (2).pdf

PDF 2 MB Posted

Attached to
1941-26-R-IFBD-00035
Solicitation number
3160007998
Issued by
Jefferson County, Mississippi

About this file

This is a Material Price Adjustment Worksheet form issued by the Mississippi Department of Transportation (MDOT) for tracking and calculating price adjustments on contract materials. The document serves as a tool for site managers to document and manually correct fuel and material price adjustments when data entry errors occur during contract performance. The form is designed for use on specific projects, such as the example provided for project HISP-0022-00(023) in Jasper County, which involved hot mix asphalt materials. The worksheet captures project identification information, contract base prices, estimated performance periods, and itemized material descriptions with associated quantities and units.

The example demonstrates a contract involving asphalt materials with a base price of $3.1258 per unit during the initial period (July 1, 2017 to July 28, 2017), adjusted to $3.3253 for the current period, reflecting a price differential of $0.1995 per unit. The calculation worksheet accounts for two line items: 10,000 tons of 12.5mm Hot Mix asphalt (Item 403-B) at $0.055 per unit totaling $550, and 15,000 tons of 19mm Hot Mix asphalt (Item 401-C) at $0.048 per unit totaling $720, resulting in a total material adjustment of $1,270. This form is utilized exclusively for corrective adjustments and does not replace the automated fuel and material adjustment systems typically employed during contract execution.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AT,T TD

MATERIAL PRICE ADJUSTMENT

SHEETAND EXAMPLE

CSD-881 MISSISSIPPI DEPARTMENT OF TRANSPORTATION

Rev' 6-17

Jackson, Mississippi

WORKSHEET FOR MATERIAL PRICE ADJUSTMENT

PROJECT NUMBER

COUNW

MATERIAL

CONTRACT BASE PRICE

ESTIMATED PERIOD

BASE PRICE FOR CURRENT PERIOD

PRICE DIFFERENTIALS

ADJUSTMENTS = TOTAL MATERIAL X PRICE DIFFERENTIALS

ADJUSTMENT FOR FUEL AND OTHER MATERIALS

TOTAL ADJUSTMENT

NOTE: SITE MANAGER PERFORMS ALL REQUIRED FUEL AND MATERIAL

ADJUSTMENTS. THIS FORM IS ONLY USED TO CORRECT THE FUEL

ADJUSTMENT MANUALLY IF DATA ENTRY ERRORS WERE MADE.

TO

ITEM NO ITEM DESCRIPTION QUANTITY UNIT

MATERIAL PER

UNIT

TOTAL MATERIAL

PER ITEM

TOTAL MATERIAL 0

CSD-881 MISSISSIPPI DEPARTMENT OF TRANSPORTATION

Rev' 5-17

Jackson, Mississippi

WORKSHEET FOR MATERIAL PRICE ADJUSTMENT

PROJECT NUMBER HrSP-0022-00(023) 301301-100

COUNTY Jasper

MATERIAL AC-30

CONTRACT BASE PRICE 3.1258

ESTTMATED PERTOD 7lLl20L7 TO 7/2s/20L7

BASE PRICE FOR CURRENT PERIOD

PRICE DIFFERENTIALS

ADJUSTMENTS = TOTAL MATERIAL X PRICE DIFFERENTIALS

ADJUSTMENT FOR FUEL AND OTHER MATERIALS

TOTAL ADJUSTMENT

NOTE: SITE MANAGER PERFORMS ALL REQUIRED FUEL AND MATERIAL

ADJUSTMENTS. THIS FORM IS ONLY USED TO CORRECT THE FUEL

ADJUSTMENT MANUALLY IF DATA ENTRY ERRORS WERE MADE.

3.3253

0.1995 s 2s3.37

5 2s3.37

ITEM NO ITEM DESCRIPTION QUANTITY UNIT

MATERIAL PER

UNIT

TOTAL MATERIAL

PER ITEM

403-B Hot Mix 12.5mm MT 10,000.00 Ton 0.055 5s0

401-C Hot Mix 19mm MT 15,000.00 Ton 0.048 720

TOTAL MATERIAL L270