The provided document is the "Attachment C Plans and Drawings to Basewide PAVEMENT REPAIR 8-1-23.pdf" for the PANG Basewide Pavement Repair contract opportunity located in Multnomah County and the City of Portland, Oregon. The project involves fog sealing 5,000 square feet, pavement patching and repair of 5,000 square feet, and crack sealing of 10,000 linear feet of pavement at the Portland Air National Guard Base. The contractor will be required to thoroughly clean the cracks and any areas to be patched or repaired using compressed air, dispose of all debris off-base, and install sealants conforming to ASTM D6690 standards. The contractor must also provide a test section, coordinate with the government for access and escort, and complete the work within the approved project schedule.

The document provides details on the sealant material requirements, crack preparation and sealing procedures, and general project notes. It does not contain information on pricing, set-asides, incumbents, funding sources, or contract term and renewal options.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BASEWIDE PAVEMENT REPAIR

Date: AUGUST 2023 SHEET:

DRAWING:

BASEWIDE PAVEMENT REPAIR

Portland Air National Guard Base, Oregon

G-100

Sheet Index

G-001 COVER SHEET

G-002 DETAILS

D-101 SITE PLAN

D-102 LEVEL OF IMPORTANCE

1 of 3COVER SHEET https://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwjVhK2qie7fAhUP3Z8KHSeACb8QjRx6BAgBEAU&url=https://twitter.com/142ndfw&psig=AOvVaw32y30V2CqXruITh-xp-403&ust=1547582792340035

DRAWING:

G-101

GENERAL SITE NOTES:

1. CONTRACTOR TO THROUGHLY DRY AND CLEAN THE CRACKS

AND ANY AREA TO BE PATCHED OR REPAIR, WITH

COMPRESSED AIR (100CFM OR GREATER) TO REMOVE

OXIDEZED PAVEMENT, LOOSE AGGREGATE AND FOREIGN

DEBRIS.

2. ALL DEBRIS TO BE DISPOSED OFF BASE. WASTE TICKETS TO

BE SUBMITTED TO PANG ENVIRONMENTAL DEPARTMENT.

3. SEALANTS TO CONFORM WITH ASTMD6690, TYPE II OR ASTM

D6690, TYPE I. PREFERRED BRAND: COLJOINT 6690 TYPE I

AND II OR APPROVED EQUAL.

4. BACKER ROD MATERIAL- WHEN REQUIRED, USE BACKER ROD

MATERIAL IN ALL CRACKS THAT OTHERWISE WOULD

REQUIRE EXCESSIVE SEALANT. PLACE THE BACKER ROD SO

THAT THE TOP OF THE BACKER ROD IS AT LEAST 3/4 INCH

BELOW THE TOP OF THE PAVEMENT. ENSURE THAT THE

BACKER ROD MATERIAL IS PLACED AT THE SPECIFIED DEPTH

AND IS NOT STRETCHED OR TWISTED DURING INSTALLATION.

5. RATE OF PROGRESS OF CRACK PREPARATION - LIMIT THE

STAGES OF CRACK PREPARATION, WHICH INCLUDE AIR

PRESSURE CLEANING AND PLACING OF THE BACKER ROD

MATERIAL, TO ONLY THAT LINEAR FOOTAGE THAT CAN BE

SEALED DURING THE SAME DAY.

6. PREPARATION OF SEALANT- DO NOT HEAT HOT-POURED

SEALANTS IN EXCESS OF THE SAFE HEATING TEMPERATURE

RECOMMENDED BY THE MANUFACTURER, AS SHOWN ON THE

SEALANT CONTAINERS. WITHDRAW AND WASTE SEALANT

THAT HAS BEEN OVERHEATED OR SUBJECTED TO

APPLICATION TEMPERATURES FOR OVER 4 HOURS OR THAT

HAS REMAINED IN THE APPLICATOR AT THE END OF THE

DAY'S OPERATION.

7. SUBMIT MANUFACTURER'S INSTRUCTIONS 3 DAYS PRIOR TO

THE USE OF THE MATERIAL ON THE PROJECT. INSTALLATION

OF THE MATERIAL WILL NOT BE ALLOWED UNTIL THE

INSTRUCTIONS ARE RECEIVED.

8. TIME OF APPLICATION - SEAL CRACKS IMMEDIATELY

FOLLOWING FINAL CLEANING AND DRYING OF THE CRACK

WALLS AND FOLLOWING THE PLACEMENT OF THE BACKER

ROD MATERIAL (WHEN REQUIRED). PLACE SEALANT ONLY

WHEN CRACKS ARE DRY. RECLEAN CRACKS THAT CANNOT BE

SEALED UNDER THE CONDITIONS SPECIFIED, OR WHEN RAIN

INTERRUPTS SEALING OPERATIONS, AND ALLOW TO DRY OR

DRY BY MECHANICAL MEANS PRIOR TO INSTALLING THE

SEALANT

9. SEALING THE CRACK - IMMEDIATELY PRECEDING, BUT NOT

MORE THAN 50 FEET AHEAD OF THE CRACK SEALING

OPERATIONS, PERFORM A FINAL CLEANING AND DRYING WITH

COMPRESSED AIR. CRACKS SHOULD BE FILLED NO HIGHER

THAN 1/8 INCH ABOVE THE PAVEMENT. REMOVE EXCESS OR

SPILLED SEALANT FROM THE PAVEMENT BY APPROVED

METHODS AND DISCARD IT. INSTALL THE SEALANT IN A

MANNER WHICH PREVENTS THE FORMATION OF VOIDS AND

ENTRAPPED AIR. SEVERAL PASSES WITH THE APPLICATOR

WAND MAY BE NECESSARY TO OBTAIN THE SPECIFIED

SEALANT DEPTH FROM THE PAVEMENT SURFACE. DO NOT

USE GRAVITY METHODS OR POURING POTS TO INSTALL THE

SEALANT MATERIAL. DO NOT PERMIT TRAFFIC OVER NEWLY

SEALED PAVEMENT UNTIL THE SEALANT HAS CURED. CHECK

CRACKS FREQUENTLY TO ENSURE THAT THE NEWLY

INSTALLED SEALANT IS CURED TO A TACK-FREE CONDITION

WITHIN 3 HOURS.

10. CRACK SEALANT INSTALLATION - TEST SECTION PRIOR TO THE

CLEANING AND SEALING OF THE CRACKS FOR THE ENTIRE

PROJECT, CONSTRUCT A TEST SECTION AT LEAST 200 FEET

LONG USING THE SPECIFIED MATERIALS AND APPROVED

EQUIPMENT TO DEMONSTRATE THE PROPOSED SEALING OF

ALL CRACKS OF THE PROJECT. FOLLOWING THE COMPLETION

OF THE TEST SECTION AND BEFORE ANY OTHER CRACK IS

SEALED, INSPECT THE TEST SECTION TO DETERMINE THAT

THE MATERIALS AND INSTALLATION MEET THE

REQUIREMENTS SPECIFIED. IF MATERIALS OR INSTALLATION

DO NOT MEET REQUIREMENTS, REMOVE THE MATERIALS AND

RE-CLEAN AND RESEAL THE CRACKS AT NO COST TO THE

GOVERNMENT.

11. CLEANUP - DAILY, REMOVE UNUSED MATERIALS FROM THE

SITE AND LEAVE THE PAVEMENT IN A CLEAN CONDITION.

GENERAL SITE NOTES

GENERAL PROJECT NOTES:

1. CONTRACTOR SHALL VERIFY EXISTING CONDITIONS AND

ADJUST WORK PLAN ACCORDINGLY, PRIOR TO

BEGINNING CONSTRUCTION.

2. WORK TO BE COMPLETED IN RESTRICTED AREA.

GOVERNEMTN ESCORT REQUIRED FOR THE DURATION

OF THE PROJECT.

3. PROJECT SCHEDULE (DAYS AND TIMES) MUST BE

APPROVED 72 HOURS PRIOR TO START OF WORK, TO

SCHEDULE GOVERNMENT ESCORT.

4. THE CONTRACTOR SHALL BE RESPONSIBLE FOR

COORDINATING WITH 142 SFS/RESOURCE PROTECTION

OFFICE FOR ACCESS TO PANG BASE (SEE ITB/CONTRACT

FOR DETAILS).

5. FOD TRAINING IS REQUIRED FOR ALL CONTRACTORS

WORKING PAST THE FLIGHTLINE. PANG WILL PROVIDE

FOD TRAINING.

6. CONTRACTOR TO PROVIDE SANITARY STATION.

7. CONTRACTOR TO PROVIDE WATER FOR PROJECT. NO

TRUCK OR EQUIPMENT WASHING IS APPROVED ON

BASE.

REFERENCES:

1. Provide sealants conforming to ASTM D6690, Type II or ASTM D6690, Type I. Preferred Brand: ColJoint 6690 Type I and II or approved equal.

https://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwjVhK2qie7fAhUP3Z8KHSeACb8QjRx6BAgBEAU&url=https://twitter.com/142ndfw&psig=AOvVaw32y30V2CqXruITh-xp-403&ust=1547582792340035

DRAWING:

D-100

SITE PLAN

LEGEND

FOG SEAL (5,000 SQFT)

PATCH/REPAIR (5,000 SQFT)

CRACK SEAL (10,000 LNFT)

N

NOT TO SCALE

https://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwjVhK2qie7fAhUP3Z8KHSeACb8QjRx6BAgBEAU&url=https://twitter.com/142ndfw&psig=AOvVaw32y30V2CqXruITh-xp-403&ust=1547582792340035

Slide Number 1
Slide Number 2
Slide Number 3

File details come from the government source that posted it. Updated .