About this file
This document is a Mass Grading Package of technical drawings for the Pitkin County Solid Waste Center project located at 32046 Jack Gredig Lane in Aspen, Colorado. The drawings, prepared by HDR engineering firm, detail a comprehensive mass grading plan covering 10 sheets that include site surveys, existing and proposed conditions, erosion control plans, and cut/fill earthwork quantities. The project involves extensive site preparation, including removing existing infrastructure like groundwater monitoring wells, leachate piping, drainage culverts, and guardrails. The mass grading plans show significant earthwork, with a total cut volume of 109,830.86 cubic yards and a fill volume of 49,615.30 cubic yards, resulting in a net cut of 60,215.56 cubic yards.
The technical drawings indicate complex site grading with varying slope ratios ranging from 1.4:1 to 8.90%, and propose future site improvements including a scalehouse, household hazardous waste area, retaining wall (115 linear feet, maximum height of 16 feet), stormwater management features, and new roadways and access points. The project involves careful erosion and sediment control measures, including construction fencing, silt fences, check dams, and vehicle tracking controls. The drawings are marked "Preliminary - Not for Construction" and dated April 25, 2025, suggesting this is a planning and design phase document preparing for future construction of the Pitkin County Solid Waste Center civil improvements.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment D - Leachate Impoundment Bid Tab.pdf | ||
| Attachment E - Leachate Impoundment CQA Plan.pdf | ||
| Attachment A - Mass Grading Package Bid Tab.pdf | ||
| RFP 069.25 - SWC Grading and Civil Improvements.pdf | ||
| Attachment B - Mass Grading Package Project Manual.pdf | ||
| Attachment F - Leachate Impoundment Drawings.pdf | ||
| Attachment G - Sample Construction Contract.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ROARING FORK RIVER
HIGHWAY 82
PROJECT AREA
NOT FOR CONSTRUCTION
PRELIM
INARY
PITKIN COUNTY
SOLID WASTE
CENTER
MASS GRADING
32046 Jack Gredig Lane, Aspen, CO 81611
10406338
ISSUE DATE DESCRIPTION
Project Number
Sheet Number
Sheet Name
1670 Broadway, Suite 3400 Denver, CO 80202 303-764-1520
Project Status
Project Manager Project Architect Landscape Architect Civil Engineer Structural Engineer Mechanical Engineer Electrical Engineer
Fire & Life Safety
Sheet Designer
Scale
AUTHOR
M. ROHR
R. MCKINLEY
A. SHAHID
N. ANDERSON
C. MULDERICK
K. PRINDS
B. JOHNSON
R. GONZALES
Plumbing Engineer
0 1/2" 1" 2"
K. PRINDS
Series Name
1 04/11/25 DRAFT MASS GRADING
2 04/25/25 MASS GRADING PACKAGE
COVER SHEET
1" = 50'
MGP01
PREPARED FOR
PITKIN COUNTY SOLID WASTE CENTER
32046 JACK GREDIG LANE
ASPEN, CO 81611
TYLER CARVELL - 970.429.3364
CIVIL ENGINEER
HDR ENGINEERING, INC
1670 BROADWAY. SUITE 3400
DENVER, CO 80202
NEAL ANDERSON, PE - 303.318.6343
CIVIL ENGINEER
WEAVER CONSULTANTS GROUP
7340 EAST CALEY AVENUE. SUITE 110
CENTENNIAL, CO 80111
JACOB MIDKIFF, PE - 720.529.0132
ARCHITECT
HDR ARCHITECTURE, INC
1670 BROADWAY. SUITE 3400
DENVER, CO 80202
JAMES BRAAM, AIA, NCARB, LEED AP - 303.524.8445
LANDSCAPE ARCHITECT
HDR ARCHITECTURE, INC
1670 BROADWAY. SUITE 3400
DENVER, CO 80202
KENT FREED, PLA, LEED AP - 303.323.9561
PITKIN COUNTY SOLID WASTE CENTER
MASS GRADING PLAN
32046 JACK GREDIG LANE, ASPEN CO 81611
A TRACT OF LAND SITUATED IN
SECTION 7 & 8, TOWNSHIP 9 SOUTH, RANGE 85 WEST OF THE 6TH P.M.
COUNTY OF PITKIN, STATE OF COLORADO
1" = 1000'
VICINITY MAP
SHEET INDEX
MGP01 MASS GRADING PLAN COVER SHEET
MGP02 GENERAL NOTES
MGP03 SURVEY/EXISTING CONDITIONS
MGP04 FUTURE SITE PLAN
MGP05 MASS GRADING PLAN - NORTH
MGP06 MASS GRADING PLAN - SOUTH
MGP07 EROSION CONTROL - NORTH
MGP08 EROSION CONTROL - SOUTH
MGP09 EROSION CONTROL DETAILS
MGP10 CUT/FILL EARTHWORK QUANTITIES
NOT FOR CONSTRUCTION
PRELIM
INARY
PITKIN COUNTY
SOLID WASTE
CENTER
MASS GRADING
32046 Jack Gredig Lane, Aspen, CO 81611
10406338
ISSUE DATE DESCRIPTION
Project Number
Sheet Number
Sheet Name
1670 Broadway, Suite 3400 Denver, CO 80202 303-764-1520
Project Status
Project Manager Project Architect Landscape Architect Civil Engineer Structural Engineer Mechanical Engineer Electrical Engineer
Fire & Life Safety
Sheet Designer
Scale
AUTHOR
M. ROHR
R. MCKINLEY
A. SHAHID
N. ANDERSON
C. MULDERICK
K. PRINDS
B. JOHNSON
R. GONZALES
Plumbing Engineer
0 1/2" 1" 2"
K. PRINDS
Series Name
1 04/11/25 DRAFT MASS GRADING
2 04/25/25 MASS GRADING PACKAGE
GENERAL NOTES
1" = 50'
MGP02
1. PRIOR TO COMMENCEMENT OF CONSTRUCTION, A LICENSED SURVEYOR SHALL STAKE THE PROPERTY BOUNDARIES, AS WELL AS ANY PROTECTED AREAS OF THE SITE. THE CONTRACTOR SHALL NOTIFY THE
ENGINEER IMMEDIATELY OF ANY DISCREPANCIES FROM THE CONSTRUCTION DOCUMENTS.
2. ALL SITE IMPROVEMENTS SHALL BE CONSTRUCTED IN STRICT COMPLIANCE WITH SPECIFICATIONS AND
CONSTRUCTION DOCUMENTS.
3. ALL STRAIGHT-LINE DIMENSIONS SHOWN ARE AT 90 DEGREES UNLESS OTHERWISE NOTED.
4. ALL DIMENSIONS ARE TO THE OUTSIDE FACE OF BUILDINGS, TO CENTERLINES, AND TO THE FACE OF CURB, UNLESS OTHERWISE NOTED.
5. THE MAXIMUM DISTANCE BETWEEN JOINTS IN WALKWAYS SHALL BE EQUAL TO THE WIDTH OF THE WALKWAY
OR EVERY 10 FEET, WHICHEVER IS LESS, UNLESS OTHERWISE NOTED.
6. 6. REFER TO THE ARCHITECTURAL AND/OR STRUCTURAL PLANS FOR INFORMATION ON ALL PROPOSED
BUILDINGS, BUILDING APPURTENANCES, OR OTHER STRUCTURES.
7. THE CONTRACTOR SHALL COORDINATE ALL PAVEMENT OPENINGS WHICH IMPACT PEDESTRIAN ACCESS AND/OR CREATE VEHICULAR INTERRUPTIONS WITH TYLER CARVELL, PITKIN COUNTY, AND THE COLORADO
DEPARTMENT OF TRANSPORTATION AT LEAST 72 HOURS PRIOR TO BEGINNING WORK.
8. FIRE TRUCK AND EMERGENCY ACCESS LANES SHALL BE MARKED IN ACCORDANCE WITH THE INTERNATIONAL
FIRE CODE AND THE REQUIREMENTS OF THE LOCAL FIRE DEPARTMENT.
9. ALL SIGNAGE AND STRIPING SHALL BE IN ACCORDANCE WITH THE FEDERAL HIGHWAY ADMINISTRATION’S
“MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES” UNLESS OTHERWISE NOTED.
10. ALL SIGNAGE LOCATIONS INTERNAL TO THE SITE SHALL BE COORDINATED WITH THE OWNER AT THE TIME OF INSTALLATION. SIGNAGE LEADING ONTO PUBLIC THOROUGHFARE SHALL BE INSTALLED AS SHOWN IN THE CONTRACT DOCUMENTS AND IN ACCORDANCE WITH THE PITKIN COUNTY AND COLORADO DEPARTMENT OF
TRANSPORTATION STANDARDS.
11. THIS SITE LIES WITHIN FEMA ZONE ‘X’ AND IS NOT AFFECTED BY THE 100-YEAR FLOODPLAIN AS SHOWN ON MAP
08097C0116E, EFFECTIVE 08.15.2019.
1. THE AREA OF DISTURBANCE IS 11.6 ACRES.
2. EROSION AND SEDIMENT CONTROL MEASURES SHALL BE IMPLEMENTED PRIOR TO ANY SOIL-DISTURBING
ACTIVITIES.
3. THE EROSION AND SEDIMENT CONTROL PLAN HAS BEEN PREPARED IN ACCORDANCE WITH THE MILE HIGH FLOOD DISTRICT FOR AUTHORIZATION TO DISCHARGE UNDER THE NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES), STORM WATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY FOR
STAND ALONE CONSTRUCTION PROJECTS.
4. THE CONTRACTOR SHALL IMPLEMENT THE STORMWATER MANAGEMENT PLAN (SWMP) AND MAINTAIN A COPY ON-SITE AT ALL TIMES IN ACCORDANCE WITH STATE AND LOCAL GUIDELINES. THE CONTRACTOR SHALL BE ENTIRELY RESPONSIBLE FOR THE IMPLEMENTATION AND MAINTENANCE OF EROSION AND SEDIMENT CONTROL MEASURES. THE APPROVED EROSION AND SEDIMENT CONTROL PLAN SHALL GOVERN THE OVERALL EROSION CONTROL EFFORT, BUT THE CONTRACTOR IS RESPONSIBLE FOR ADJUSTING, MODIFYING, OR ADDING CONTROLS AS NEEDED THROUGHOUT CONSTRUCTION TO ENSURE COMPLIANCE WITH NPDES AND/OR LOCAL
GRADING PERMIT REGULATIONS.
5. GOOD HOUSEKEEPING MEASURES FOR MATERIALS STORAGE AND HANDLING, VEHICLE FUELING AND MAINTENANCE, SPILL RESPONSE AND CLEANUP, AND WASTE MANAGEMENT MUST BE FOLLOWED TO ENSURE
THAT RUNOFF FROM THE SITE IS FREE OF CONTAMINANTS.
6. ALL INSPECTION REPORTS SHALL BE AVAILABLE ON THE CONSTRUCTION SITE AT ALL TIMES AND SHALL BE
PRESENTED FOR REVIEW UPON REQUEST.
7. EROSION AND SEDIMENT CONTROL MEASURES SHALL BE MAINTAINED AT ALL TIMES AND MUST CONTINUE
UNTIL THE SITE IS PERMANENTLY STABILIZED IN ACCORDANCE WITH PERMIT REQUIREMENTS.
8. ANY DISTURBED AREA LEFT EXPOSED FOR A PERIOD OF GREATER THAN 14 DAYS SHALL BE STABILIZED WITH TEMPORARY SEEDING. DISTURBED AREAS THAT REMAIN IDLE AFTER 30 DAYS SHALL BE STABILIZED WITH
PERMANENT VEGETATION.
9. ALL SITE SOILS EXPOSED DURING DEMOLITION AND CONSTRUCTION, INCLUDING SOIL THAT IS STOCKPILED ON SITE, MUST BE PROTECTED FROM WIND AND RAIN EROSION THROUGH THE USE OF APPROPRIATE TEMPORARY
MEASURES.
10. WASTE CONTAINERS MUST BE CLOSED AND SECURED WHEN NOT IN USE AND AT THE END OF EACH WORKDAY.
THE CONTRACTOR IS RESPONSIBLE FOR PROPER CONTAINMENT OF ALL MATERIALS, INCLUDING TRASH, ON
THE SITE.
11. THE CONTRACTOR SHALL TAKE ALL NECESSARY PRECAUTIONS DURING DEWATERING OPERATIONS TO MINIMIZE SEDIMENT TRANSFER. DISCHARGING UNFILTERED WATER FROM AN EXCAVATION IS NOT
ACCEPTABLE.
12. THE CONTRACTOR IS RESPONSIBLE FOR MINIMIZING THE TRACKING OF MUD, SOIL, AND ROCK FROM CONSTRUCTION AREAS ONTO ROADWAYS. SEDIMENT TRACKED ONTO A ROADWAY MUST BE REMOVED DAILY.
13. BOTH STAGING AND STOCKPILE AREAS SHALL BE CLEARLY IDENTIFIED ON THE SITE AND SHALL BE BOUNDED ON THE DOWN-SLOPE SIDE BY SILT FENCE TO PROTECT AGAINST THE RELEASE OF ANY SEDIMENT. SUCH
AREAS SHALL BE LOCATED AWAY FROM STREAMS, PONDS, SWALES, AND CATCH BASINS.
14. THE CONTRACTOR SHALL TAKE ALL REASONABLE MEANS TO ELIMINATE THE TRANSPORT OF DUST FROM THE PROJECT SITE. SPECIAL MEASURES, SUCH AS PERIODICALLY APPLYING WATER TO THE WORK SITE, SHALL BE
INCORPORATED INTO THE CONTRACTOR’S WORK PLAN.
15. AFTER FINAL STABILIZATION IS ACHIEVED AND APPROVED BY THE CDPHE, ALL TEMPORARY EROSION AND
SEDIMENT CONTROL MEASURES SHALL BE REMOVED FROM THE SITE WITHIN 30 DAYS.
16. SITE INSPECTIONS SHALL BE CARRIED OUT BY A QUALIFIED STORMWATER MANAGER (QSM). THE QSM’S
CONTACT INFORMATION SHALL BE NOTED IN THE ON-SITE EROSION AND SEDIMENT CONTROL
DOCUMENTATION.
1. AFTER THE REMOVAL OF VEGETATION, TOPSOIL SHALL BE STRIPPED FROM THE SITE TO A DEPTH OF [3] INCHES AND SHALL BE STOCKPILED FOR SPREADING UPON THE FINAL GRADING OF SLOPES AND SWALES.
2. ALL SLOPES [4:1] (H:V) AND STEEPER SHALL BE STABILIZED IN ACCORDANCE WITH THE EROSION AND SEDIMENT CONTROL PLANS AND DETAILS. INSTALL THESE MEASURES PER THE SPECIFICATIONS AND THE
MANUFACTURER’S INSTRUCTIONS.
3. PROPOSED CONTOURS ARE APPROXIMATE AND ARE SHOWN TO DEMONSTRATE DESIGN INTENT. SPOT ELEVATIONS AND SLOPES SHALL BE USED FOR GRADING LAYOUT AND TO CONFIRM DESIGN COMPLIANCE.
4. NO WORK SHALL OCCUR WITHIN THE RIGHT-OF-WAY OR ON ADJACENT PROPERTY WITHOUT PRIOR APPROVAL
AND COORDINATION WITH THE RESPECTIVE OWNER.
5. ALL PROPOSED SPOT ELEVATIONS REPRESENT FINISHED GRADE, UNLESS OTHERWISE NOTED.
1. THE CONTRACTOR IS RESPONSIBLE FOR THE COORDINATION AND SEQUENCING OF DEMOLITION AS DESCRIBED BY THESE DOCUMENTS AND SPECIFICATIONS. THE CONTRACTOR SHALL OBTAIN ALL REQUIRED
PERMITS PRIOR TO COMMENCING DEMOLITION.
2. ALL EROSION AND SEDIMENT CONTROL DEVICES SHALL BE IN PLACE PRIOR TO THE START OF
SOIL-DISTURBING ACTIVITIES.
3. THE CONTRACTOR SHALL VERIFY THE LOCATIONS OF ALL EXISTING UTILITIES IN THE PROJECT AREA PRIOR TO STARTING CONSTRUCTION. THE CONTRACTOR SHALL CONTACT 811 A MINIMUM OF BUSINESS 3 DAYS PRIOR
TO EXCAVATION.
4. THE CONTRACTOR IS RESPONSIBLE FOR COORDINATION WITH ANY IMPACTED PRIVATE UTILITY (GAS, POWER, CABLE, ETC.). NOTIFY THE ENGINEER IMMEDIATELY OF ANY POTENTIAL CONFLICT WITH THE PROPOSED
DESIGN.
5. THERE MAY BE EXISTING UNMARKED UTILITIES PRESENT. THE CONTRACTOR IS RESPONSIBLE FOR VERIFYING LOCATIONS AND DETERMINING THE STATUS (I.E. ACTIVE OR INACTIVE) OF THESE UTILITIES TO THE MAXIMUM EXTENT POSSIBLE. SHOULD ANY UNMARKED UTILITIES BE DISCOVERED, THE CONTRACTOR SHALL
IMMEDIATELY NOTIFY BOTH THE ENGINEER AND UTILITY OWNER.
6. ALL MATERIAL GENERATED BY DEMOLITION SHALL BE HAULED FROM THE SITE AND LEGALLY DISPOSED OF AT AN APPROVED DISPOSAL FACILITY. IF ENVIRONMENTAL CONTAMINANTS ARE ENCOUNTERED DURING CONSTRUCTION, THE SOIL SHALL BE TESTED PRIOR TO DISPOSAL IN ACCORDANCE WITH ALL LOCAL, STATE, AND FEDERAL REGULATIONS. REFUSE MUST NOT BE LEFT ON THE PROJECT SITE, ON ADJACENT PROPERTIES, OR BURIED IN EXCAVATIONS.
7. ASPHALT AND CONCRETE DEMOLITION LIMITS THAT ARE ADJACENT TO EXISTING HARDSCAPE SHALL BE
DEFINED WITH A SAW CUT TO OBTAIN A CLEAN EDGE.
8. FENCING SHALL BE INSTALLED TO PREVENT UNAUTHORIZED INTERACTION WITH THE WORK AREA. ACCESS TO THE WORK AREA SHALL BE CLEARLY MARKED AS A CONSTRUCTION ENTRANCE AND SHALL BE LOCKED
OUTSIDE OF WORKING HOURS.
9. THE CONTRACTOR IS RESPONSIBLE FOR ALL NECESSARY TRAFFIC CONTROL AND RELATED PERMITTING
DURING CONSTRUCTION, PER LOCAL AND STATE STANDARDS.
10. THE CONTRACTOR IS RESPONSIBLE FOR REPAIRING OR REPLACING ANY ADJACENT CONCRETE, ASPHALT, FENCING, LANDSCAPING, OR OTHER EXISTING IMPROVEMENTS DAMAGED DURING CONSTRUCTION, WHICH HAVE NOT BEEN IDENTIFIED FOR DEMOLITION OR REMOVAL. THIS INCLUDES REPAIR OF ANY DAMAGE DUE TO CONSTRUCTION TRAFFIC. THE REPAIR SHALL LEAVE THE IMPROVEMENT IN A CONDITION THAT IS EQUAL TO
OR BETTER THAN THE CONDITION DOCUMENTED AT THE START OF THE PROJECT.
11. THE CONTRACTOR SHALL COORDINATE WITH THE OWNER ON ANY ITEMS NOTED TO BE SALVAGED.
12. THE CONTRACTOR SHALL FLAG OVERHEAD UTILITIES PRIOR TO MOBILIZATION IN ACCORDANCE WITH THE
UTILITY PROVIDER’S REQUIREMENTS.
13. THE CONTRACTOR SHALL STAKE ALL EXISTING ENVIRONMENTAL BUFFERS AND SETBACKS, AS NOTED ON THE
PLANS, PRIOR TO THE START OF WORK.
14. THE CONTRACTOR SHALL COORDINATE ALL RIGHT-OF-WAY IMPACTS WITH THE LOCAL JURISDICTION. THESE INCLUDE, BUT ARE NOT LIMITED TO, REDUCTION IN STREET LIGHTING, SIDEWALK ACCESS, AND LANE CLOSURES. THE CONTRACTOR SHALL OBTAIN ANY NECESSARY PERMITS IN ADVANCE OF THE IMPACT.
15. REFER TO THE GEOTECHNICAL REPORT PREPARED FOR THIS SITE BY HDR ENGINEERING, INC. DATED
03/14/2025 FOR SPECIFIC SITE DATA AND RECOMMENDATIONS.
SITE PLAN NOTES
GRADING AND DRAINAGE NOTESEROSION AND SEDIMENT CONTROL NOTES
DEMOLITION NOTESCONSTRUCTION SEQUENCE
1. OBTAIN ALL REQUIRED LAND DEVELOPMENT AND EROSION AND SEDIMENT CONTROL PERMITS FROM PITKIN COUNTY AND THE COLORADO DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT BEFORE ANY LAND DISTURBING ACTIVITIES OCCUR. ALL PERMITS SHALL BE MAINTAINED ON-SITE THROUGHOUT CONSTRUCTION.
2. SCHEDULE AND HOLD A PRE-CONSTRUCTION MEETING TO DISCUSS THE PROJECT AND THE EROSION AND SEDIMENT CONTROL MEASURES THAT WILL BE UTILIZED THROUGHOUT CONSTRUCTION. ATTENDEES SHALL
INCLUDE REPRESENTATIVES FROM THE CONTRACTOR, OWNER, AND ENGINEER. IF APPLICABLE,
REPRESENTATIVES FROM THE PITKIN COUNTY SHALL BE INVITED TO ATTEND AS WELL.
3. INSTALL ALL PERIMETER EROSION AND SEDIMENT CONTROL MEASURES PRIOR TO ANY SOIL-DISTURBING
ACTIVITIES.
4. SITE WORK SHALL BE SEQUENCED TO LIMIT SITE DISTURBANCE TO THE SMALLEST AREA POSSIBLE.
5. BEGIN ROUGH GRADING OF THE SITE. STABILIZE DISTURBED AREAS AS DESCRIBED IN THE EROSION AND
SEDIMENT CONTROL NOTES.
6. INSTALL CONCRETE WASHOUT PRIOR TO BEGINNING CONCRETE INSTALLATION.
7. INSTALL SITE IMPROVEMENTS. MAINTAIN APPROPRIATE EROSION AND SEDIMENT CONTROL MEASURES AT ALL
TIMES. PROVIDE INLET PROTECTION FOR EACH STRUCTURE AT THE TIME OF INSTALLATION.
8. INSPECT EROSION AND SEDIMENT CONTROL MEASURES AT LEAST WEEKLY AND WITHIN 24 HOURS AFTER EACH WEATHER EVENT EXCEEDING ½ INCH OF TOTAL PRECIPITATION. ANY ACCUMULATED SEDIMENT SHALL BE REMOVED AND PLACED IN DESIGNATED DISPOSAL AREAS THAT ARE APPROVED BY BOTH THE CLIENT AND
PITKIN COUNTY. REPAIR OR REPLACE ANY MEASURES AS NECESSARY.
9. AS AREAS ARE BROUGHT TO FINAL GRADE, IMMEDIATELY APPLY PERMANENT SEEDING TO ESTABLISH COVER AND ADD MULCH AS APPLICABLE TO PROTECT THE SEED. APPLY EROSION CONTROL MATTING TO SLOPES AS
SPECIFIED IN THE CONTRACT DOCUMENTS.
10. ONCE CONSTRUCTION IS COMPLETE, VEGETATION HAS BEEN ESTABLISHED, AND THE SITE IS FULLY STABILIZED IN ACCORDANCE WITH NPDES AND/OR GRADING PERMIT REQUIREMENTS, ALL TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES SHALL BE REMOVED FROM THE SITE UPON APPROVAL OF PITKIN COUNTY. ANY DISTURBANCE THAT OCCURS DURING REMOVAL OF THE MEASURES SHALL BE
IMMEDIATELY STABILIZED WITH PERMANENT SEEDING AND MULCH.
73207320
735073607370
EXISTING GROUNDWATER MONITORING
WELL TO BE REMOVED BY OTHERS
PRIOR TO MASS GRADING ACTIVITIES.
EXISTING STOCKPILES TO BE
RELOCATED BY OTHERS PRIOR
TO MASS GRADING ACTIVITIES.
EXISTING LEACHATE TANK TO BE
REMOVED BY OTHERS PRIOR TO
MASS GRADING ACTIVITIES
EXISTING LEACHATE PIPING TO BE
REMOVED BY OTHERS PRIOR TO
MASS GRADING ACTIVITIES.
CLEAR AND GRUB AREA TO
BE DISTURBED BY MASS
GRADING ACTIVITIES
EXISTING DRAINAGE
CULVERT TO BE REMOVED
EXISTING GUARDRAIL TO BE REMOVED
EXISTING ACCESS ROAD TO
REMAIN AND BE PROTECTED
EXISTING GUARDRAIL TO
REMAIN AND BE PROTECTED
EXISTING BUILDING TO
REMAIN AND BE PROTECTED
EXISTING STAGING AND
STORAGE AREA TO REMAIN
AND BE PROTECTED
NOT FOR CONSTRUCTION
PRELIM
INARY
PITKIN COUNTY
SOLID WASTE
CENTER
MASS GRADING
32046 Jack Gredig Lane, Aspen, CO 81611
10406338
ISSUE DATE DESCRIPTION
Project Number
Sheet Number
Sheet Name
1670 Broadway, Suite 3400 Denver, CO 80202 303-764-1520
Project Status
Project Manager Project Architect Landscape Architect Civil Engineer Structural Engineer Mechanical Engineer Electrical Engineer
Fire & Life Safety
Sheet Designer
Scale
AUTHOR
M. ROHR
R. MCKINLEY
A. SHAHID
N. ANDERSON
C. MULDERICK
K. PRINDS
B. JOHNSON
R. GONZALES
Plumbing Engineer
0 1/2" 1" 2"
K. PRINDS
Series Name
1 04/11/25 DRAFT MASS GRADING
2 04/25/25 MASS GRADING PACKAGE
SURVEY/EXISTING
CONDITIONS
1" = 50'
MGP03
LEGEND
EXISTING PROPOSED
PROPERTY LINE
GUARDRAIL
1. SITE PLAN IS FOR REFERENCE ONLY AND PROPOSED SITE IMPROVEMENTS MAY BE REVISED
FOR FUTURE CONSTRUCTION DOCUMENTS
2. PRIOR TO COMMENCEMENT OF CONSTRUCTION, A LICENSED SURVEYOR SHALL STAKE THE
PROPERTY BOUNDARIES, AS WELL AS ANY PROTECTED AREAS OF THE SITE. THE
CONTRACTOR SHALL NOTIFY THE ENGINEER IMMEDIATELY OF ANY DISCREPANCIES FROM
THESE DOCUMENTS.
3. ALL SITE IMPROVEMENTS SHALL BE CONSTRUCTED IN STRICT COMPLIANCE WITH
SPECIFICATIONS AND CONSTRUCTION DOCUMENTS.
4. ALL STRAIGHT-LINE DIMENSIONS SHOWN ARE AT 90 DEGREES UNLESS OTHERWISE NOTED.
5. ALL DIMENSIONS ARE TO THE OUTSIDE FACE OF BUILDINGS, TO CENTERLINES, AND TO THE
EDGE OF PAVEMENT, UNLESS OTHERWISE NOTED.
6. THE MAXIMUM DISTANCE BETWEEN JOINTS IN WALKWAYS SHALL BE EQUAL TO THE WIDTH OF
THE WALKWAY OR EVERY 10 FEET, WHICHEVER IS LESS, UNLESS OTHERWISE NOTED.
SITE NOTES
PROPOSED FUTURE LIMITS OF
STORM-WATER MANAGEMENT FEATURE
EXISTING LEACHATE PIPE TO
BE REMOVED BY OTHERS
EXISTING EXTENTS OF WASTE
SURVEY CONTROL POINT
ASPHALT PAVEMENT TO BE REMOVED.
COORDINATE EXTENTS OF REMOVAL WITH LIMITS OF
DISTURBANCE FOR EARTHWORK ACTIVITIES.
DN
MOTHERLODE MERCANTILE
SCALEHOUSE
HOUSEHOLD
HAZARDOUS
WASTE
RECYCLING
CAMPUS
PROPOSED RETAINING WALL
LENGTH: 115 LF
AREA: +-920 SF
MAX HEIGHT: 16'
PROPOSED 8' "Z"
WALL
PROPOSED
GUARD RAIL
12'
12'
PROPOSED LIMITS OF
FUTURE STORMWATER
MANAGEMENT FEATURE
EXISTING EXTENTS OF
WASTE
EXISTING OVERHEAD
ELECTRICAL LINE TO
REMAIN
EXISTING UTILITY POLE
TO REMAIN
RETURN LANE
PROPERTY BOUNDARY
PROPOSED PATIO AREA
PROPOSED LANDSCAPE
AREA
LANDSCAPE AREA
EXISTING ROADWAY
TO REMAIN
LANDSCAPE AREA
LOADING DOCK
PAVEMENT
STRIPING
CONCRETE WALK
LANDSCAPE AREA
PAVEMENT STRIPING (TYP)
34'
.5'
25'
.5'
45'
40'
R50'
R30'
R5'
R50'
R15'
R25'
R15'
.71
'76'
R9 5'
PROPOSED WATER
STORAGE TANKS
.8'
40'
SWALE
18' 18'
20'
9'
EXISTING MAINTENANCE BUILDING
"YIELD TO TRUCKS"
SIGNAGE
R15'
R49'
R10'
NOT FOR CONSTRUCTION
PRELIM
INARY
PITKIN COUNTY
SOLID WASTE
CENTER
100% MASS GRADING PACKAGE
32046 Jack Gredig Lane, Aspen, CO 81611
10406338
ISSUE DATE DESCRIPTION
Project Number
Sheet Number
Sheet Name
1670 Broadway, Suite 3400 Denver, CO 80202 303-764-1520
Project Status
Project Manager Project Architect Landscape Architect Civil Engineer Structural Engineer Mechanical Engineer Electrical Engineer
Fire & Life Safety
Sheet Designer
Scale
AUTHOR
M. ROHR
R. MCKINLEY
A. SHAHID
N. ANDERSON
C. MULDERICK
K. PRINDS
B. JOHNSON
R. GONZALES
Plumbing Engineer
0 1/2" 1" 2"
K. PRINDS
Series Name
FUTURE SITE PLAN
(FOR REFERENCE)
1" = 50'
MGP04
LEGEND
EXISTING PROPOSED
PROPERTY LINE
GUARDRAIL
1. SITE PLAN IS FOR REFERENCE ONLY AND PROPOSED SITE IMPROVEMENTS MAY BE REVISED
FOR FUTURE CONSTRUCTION DOCUMENTS
2. PRIOR TO COMMENCEMENT OF CONSTRUCTION, A LICENSED SURVEYOR SHALL STAKE THE
PROPERTY BOUNDARIES, AS WELL AS ANY PROTECTED AREAS OF THE SITE. THE
CONTRACTOR SHALL NOTIFY THE ENGINEER IMMEDIATELY OF ANY DISCREPANCIES FROM
THESE DOCUMENTS.
3. ALL SITE IMPROVEMENTS SHALL BE CONSTRUCTED IN STRICT COMPLIANCE WITH
SPECIFICATIONS AND CONSTRUCTION DOCUMENTS.
4. ALL STRAIGHT-LINE DIMENSIONS SHOWN ARE AT 90 DEGREES UNLESS OTHERWISE NOTED.
5. ALL DIMENSIONS ARE TO THE OUTSIDE FACE OF BUILDINGS, TO CENTERLINES, AND TO THE
EDGE OF PAVEMENT, UNLESS OTHERWISE NOTED.
6. THE MAXIMUM DISTANCE BETWEEN JOINTS IN WALKWAYS SHALL BE EQUAL TO THE WIDTH OF
THE WALKWAY OR EVERY 10 FEET, WHICHEVER IS LESS, UNLESS OTHERWISE NOTED.
SITE NOTES
EXISTING EXTENTS OF WASTE
PROPOSED FUTURE LIMITS OF
STORM-WATER MANAGEMENT FEATURE
PROPOSED ASPHALT PAVING
7360736573707375738073857390739574007405741074157420742574307435744074457450
746074
90749
FFE 7485.00
FFE 7467.00
FFE 7465.50
FFE 7485.00 3.40%
3.4 6%
1.35%
1.7 1%
2.9 6%
1.7 7%
1.71% 3.7:1
2.5:1
2.5:1
2.2 :1
3.2:1
3.0 :1
4.6 :1
4.7:1
2.0 :1
2.5:1
2.0 :1
2.0 :1
2.0 :1
8.9 0%
8.90%
8.90%
8.41%
8.90%
8.90%
4.8 4%
5.01%
3.1 4%
3.9 4%
1.98%
9.3 3%
10.21%
7.3:1
5.5 :1
8.9 4%
2.75%
2.5 :1 2.1:1
EL 7484.82
EL 7477.73
EL 7477.21
EL 7476.49
EL 7476.00
TW 7485.00
1.4:1
1.6:1
2.2 :1
4.2 2%
8.5 8%
4.1 4%
9.46%
2.0:1
2.0 :1
2.0:1
A
A
EL 7464.24
EL 7464.43
EL 7465.61
EL 7477.00
EL 7479.65
EL 7483.02EL 7483.98
EL 7484.18
EL 7483.61
EL 7502.00
EL 7502.00
EL 7488.51EL 7488.51
EL 7486.77EL 7486.77
EL 7476.08
EL 7474.19
EL 7476.40
EL 7474.87
EL 7471.73
EL 7468.43
EL 7467.34
EL 7468.38
EL 7476.85
EL 7478.88 7325733073357340734573507355736073657370737573807385739073957400
743074
742074
7485749074957500
2.5 :1
10+00
11+00
+0
13+00
14+00
15+00
+0
17+00
18+00
19+00
19+56.48
7468 7467
PROPOSED ROADWAY
EXISTING GRADE
10+00 10+50 11+00 11+50 12+00 12+50 13+00 13+50 14+00 14+50 15+00 15+50 16+00 16+50 17+00 17+50 18+00 18+50 19+00 19+50 19+75
-8.90%
-8.90%
-8.90%
ACCESS ROADWAY CENTERLINE PROFILE
H: 1"=50 V:1"=50
0+00 0+50 1+00
.05
.05
7.5
2'
50'
11'
2'
1'
VARIES
-1.78%
TYPICAL ACCESS ROADWAY CROSS SECTION
H: 1"=50 V:1"=50
NOT FOR CONSTRUCTION
PRELIM
INARY
PITKIN COUNTY
SOLID WASTE
CENTER
MASS GRADING
32046 Jack Gredig Lane, Aspen, CO 81611
10406338
ISSUE DATE DESCRIPTION
Project Number
Sheet Number
Sheet Name
1670 Broadway, Suite 3400 Denver, CO 80202 303-764-1520
Project Status
Project Manager Project Architect Landscape Architect Civil Engineer Structural Engineer Mechanical Engineer Electrical Engineer
Fire & Life Safety
Sheet Designer
Scale
AUTHOR
M. ROHR
R. MCKINLEY
A. SHAHID
N. ANDERSON
C. MULDERICK
K. PRINDS
B. JOHNSON
R. GONZALES
Plumbing Engineer
0 1/2" 1" 2"
K. PRINDS
Series Name
1 04/11/25 DRAFT MASS GRADING
2 04/25/25 MASS GRADING PACKAGE
1" = 50'
MGP05
MASS GRADING
PLAN - NORTH
SLOPE ARROW0.40%X.XX%X.XX%
EXISTING CONTOUR W/ELEVATION (MAJOR)
EXISTING CONTOUR (MINOR)
NEW CONTOUR (MAJOR)
NEW CONTOUR (MINOR)
SWALE
1. CONTRACTOR TO FIELD VERIFY ANY EXISTING UTILITIES PRIOR TO CONSTRUCTION
ACTIVITIES.
GRADING NOTES
LEGEND
EXISTING PROPOSED
PROPERTY LINE
GUARDRAIL
EXISTING EXTENTS OF WASTE
PROPOSED FUTURE LIMITS OF
SEE SHEET MGP06 FOR CONTINUATION
SEE SHEET MGP02 FOR CONTINUATION
NOT FOR CONSTRUCTION
PRELIM
INARY
PITKIN COUNTY
SOLID WASTE
CENTER
MASS GRADING
32046 Jack Gredig Lane, Aspen, CO 81611
10406338
ISSUE DATE DESCRIPTION
Project Number
Sheet Number
Sheet Name
Project Status
Sheet Designer
Scale
AUTHOR
Series Name
1 04/11/25 DRAFT MASS GRADING
Weaver Consultants Group 7340 E. Caley Avenue, Suite 110 Centennial, CO 80111
2 04/25/25 MASS GRADING PACKAGE
Project Manager Project Architect Landscape Architect Civil Engineer Structural Engineer Mechanical Engineer Electrical Engineer
Fire & Life Safety
M. ROHR
R. MCKINLEY
A. SHAHID
J. MIDKIFF
C. MULDERICK
K. PRINDS
B. JOHNSON
R. GONZALES
Plumbing Engineer K. PRINDS
MASS GRADING
PLAN - SOUTH
MGP06
1" = 50'
7360736573707375738073857390739574007405741074157420742574307435744074457450
72857320
746074
90749
PROPERTY BOUNDARY
CF
CF
CD
VTC
VTC
LOD
LOD
LOD
LOD
LOD
LOD
CD
CD
CD
CD
CF
CF
CD
CD
SCR
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LO
D
LO
D
LO
D LOD LOD LOD
LOD
LO
D
LO
D
LOD
LOD
LOD
LO
D
LOD
LOD
LO
D
LO
D
LO
D
LO
D
LOD
LOD
LOD
LOD
LO
D
LOD
LOD
LO
D
LO
D
LOD
LOD
LODLOD
LO
D
LOD
LOD
LOD
LOD
LOD
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LOD
LO
D
LO
D
LO
D
LOD
CF
CF
C
F C
F C
F C
F
CF
CF
CF
CF
CF
CF
73307335734073457350735573607365737073757380
73907395
35 743574
NOT FOR CONSTRUCTION
PRELIM
INARY
PITKIN COUNTY
SOLID WASTE
CENTER
MASS GRADING
32046 Jack Gredig Lane, Aspen, CO 81611
10406338
ISSUE DATE DESCRIPTION
Project Number
Sheet Number
Sheet Name
1670 Broadway, Suite 3400 Denver, CO 80202 303-764-1520
Project Status
Project Manager Project Architect Landscape Architect Civil Engineer Structural Engineer Mechanical Engineer Electrical Engineer
Fire & Life Safety
Sheet Designer
Scale
AUTHOR
M. ROHR
R. MCKINLEY
A. SHAHID
N. ANDERSON
C. MULDERICK
K. PRINDS
B. JOHNSON
R. GONZALES
Plumbing Engineer
0 1/2" 1" 2"
K. PRINDS
Series Name
1 04/11/25 DRAFT MASS GRADING
2 04/25/25 MASS GRADING PACKAGE
1" = 50'
MGP07
EROSION AND
SEDIMENTATION
CONTROL PLAN - NORTH
EXISTING CONTOUR W/ELEVATION (MAJOR)
EXISTING CONTOUR (MINOR)
NEW CONTOUR (MAJOR)
NEW CONTOUR (MINOR)
SWALE
1. CONTRACTOR TO FIELD VERIFY ANY EXISTING UTILITIES PRIOR TO CONSTRUCTION
ACTIVITIES.
GRADING NOTES
LEGEND
EXISTING PROPOSED
PROPERTY LINE
GUARDRAIL
EXISTING EXTENTS OF WASTE
PROPOSED FUTURE LIMITS OF
STORM-WATER MANAGEMENT FEATURE
CONTROL MEASURE (CM) LEGEND
CD CHECK DAM
LOD LOD LIMITS OF DISTURBANCE
CF CF CONSTRUCTION FENCE
VTC VEHICLE TRACKING CONTROL
SF SF SILT FENCE
SCR STABILIZED CONSTRUCTION ROAD
SEE SHEET MGP08 FOR CONTINUATION
CF
LOD
CD
CD
SCR
LO
D
LO
D
LO
D
LO
D
LOD
LOD
LOD
LO
D
LO
D
LO
D
LOD
LOD
LOD
LO
D
LO
D
LO
D
LO
D
LO
D
LOD
LO
D
LO
D
LOD
LO
D
LO
DLOD
CF
C F
C F
CF
C F
CF
CF
C F
C F
CF
CF
CF
CF
CF
C F
CF
CF
CF
CF
CF
C F
CF
CF
SEE SHEET MGP03 FOR CONTINUATION
VTC
SCR
CD
CD
CD
CD
CF
LOD
NOT FOR CONSTRUCTION
PRELIM
INARY
PITKIN COUNTY
SOLID WASTE
CENTER
MASS GRADING
32046 Jack Gredig Lane, Aspen, CO 81611
10406338
ISSUE DATE DESCRIPTION
Project Number
Sheet Number
Sheet Name
Project Status
Sheet Designer
Scale
AUTHOR
Series Name
1 04/11/25 DRAFT MASS GRADING
Weaver Consultants Group 7340 E. Caley Avenue, Suite 110 Centennial, CO 80111
2 04/25/25 MASS GRADING PACKAGE
Project Manager Project Architect Landscape Architect Civil Engineer Structural Engineer Mechanical Engineer Electrical Engineer
Fire & Life Safety
M. ROHR
R. MCKINLEY
A. SHAHID
J. MIDKIFF
C. MULDERICK
K. PRINDS
B. JOHNSON
R. GONZALES
Plumbing Engineer K. PRINDS
EROSION AND
SEDIMENTATION
CONTROL PLAN - SOUTH
MGP08
1" = 50'
CONTROL MEASURE (CM) LEGEND
CD
LOD LOD
CF CF
VTC
SF SF SF
SCR
SILT FENCE
NTS
MGP04
CONSTRUCTION FENCE
NTS
MGP04
VEHICLE TRACKING CONTROL
NTS
MGP04
CHECK DAM
NTS
MGP04
STABILIZED CONSTRUCTION ROADWAY
NTS
MGP04
NOT FOR CONSTRUCTION
PRELIM
INARY
PITKIN COUNTY
SOLID WASTE
CENTER
MASS GRADING
32046 Jack Gredig Lane, Aspen, CO 81611
10406338
ISSUE DATE DESCRIPTION
Project Number
Sheet Number
Sheet Name
1670 Broadway, Suite 3400 Denver, CO 80202 303-764-1520
Project Status
Project Manager Project Architect Landscape Architect Civil Engineer Structural Engineer Mechanical Engineer Electrical Engineer
Fire & Life Safety
Sheet Designer
Scale
AUTHOR
M. ROHR
R. MCKINLEY
A. SHAHID
N. ANDERSON
C. MULDERICK
K. PRINDS
B. JOHNSON
R. GONZALES
Plumbing Engineer
0 1/2" 1" 2"
K. PRINDS
Series Name
1 04/11/25 DRAFT MASS GRADING
2 04/25/25 MASS GRADING PACKAGE
1" = 50'
MGP09
EROSION AND
SEDIMENTATION
CONTROL DETAILS
746074
-5
-4
-3
-2
-6
-10
-12
-7
-4
-1
-1
-17
-24
-13
-7
-6
-2
-1
-12
-17
-18
-20
-6
-9
-2
-1
-6
-16
-17
-23
-22
-21
-16
-2
-27
-20
-24
-19
-13
-17
-13
-7
-2
-4
-13
-15
-10
-14
-16
-12
-9
-4
-11
-18
-15
-11
-7
-18
-16
-13
-8
-4
-2
-11
-11
-9
-5
-11
-11
-12
-8
-3
-11
-3
-12
-9
-5
-1
-13
-13
-1
-6
-2
-13
-11
-6
-2
-1
-22
-4
-8
-21
-17
-8
-5
-10
-16
-23
-23
-16
-12
-2
-10
-13
-17
-13
-9
-8
-4
-5
-8
-7
-4
-1
Cut/Fill Summary Name
Earthwork
Totals
Cut Factor
1.000
Fill Factor
1.000
2d Area
486854.47 Sq. Ft.
486854.47 Sq. Ft.
Cut
109830.86 Cu. Yd.
109830.86 Cu. Yd.
Fill
49615.30 Cu. Yd.
49615.30 Cu. Yd.
Net
60215.56 Cu. Yd.<Cut>
60215.56 Cu. Yd.<Cut>
NOT FOR CONSTRUCTION
PRELIM
INARY
PITKIN COUNTY
SOLID WASTE
CENTER
MASS GRADING
32046 Jack Gredig Lane, Aspen, CO 81611
10406338
ISSUE DATE DESCRIPTION
Project Number
Sheet Number
Sheet Name
1670 Broadway, Suite 3400 Denver, CO 80202 303-764-1520
Project Status
Project Manager Project Architect Landscape Architect Civil Engineer Structural Engineer Mechanical Engineer Electrical Engineer
Fire & Life Safety
Sheet Designer
Scale
AUTHOR
M. ROHR
R. MCKINLEY
A. SHAHID
N. ANDERSON
C. MULDERICK
K. PRINDS
B. JOHNSON
R. GONZALES
Plumbing Engineer
0 1/2" 1" 2"
K. PRINDS
Series Name
1 04/11/25 DRAFT MASS GRADING
1" = 50'
MGP08
CUT / FILL
EARTHWORK
QUANTITIES
EXISTING CONTOUR W/ELEVATION (MAJOR)
EXISTING CONTOUR (MINOR)
NEW CONTOUR (MAJOR)
NEW CONTOUR (MINOR)
1. CONTRACTOR TO FIELD VERIFY ANY EXISTING UTILITIES PRIOR TO CONSTRUCTION
ACTIVITIES.
GRADING NOTES
LEGEND
EXISTING PROPOSED
PROPERTY LINE
GUARDRAIL
EXISTING EXTENTS OF WASTE
PROPOSED FUTURE LIMITS OF
MGP10
| MGP01 - COVER SHEET |
| MGP02 - GENERAL NOTES |
| MGP03 - SURVEY/EXISTING CONDITIONS |
| MGP04 - FUTURE SITE PLAN (FOR REFERENCE) |
| MGP05 - MASS GRADING PLAN - NORTH |
| MGP06 - MASS GRADING PLAN - SOUTH |
| MGP07 - EROSION AND SEDIMENTATION CONTROL PLAN - NORTH |
| MGP08 - EROSION AND SEDIMENTATION CONTROL PLAN - SOUTH |
| MGP09 - EROSION AND SEDIMENTATION CONTROL DETAILS |
| MGP10 - CUT / FILL EARTHWORK QUANTITIES |
File details come from the government source that posted it. Updated .