This document is a Specification Section for the Masonry Restoration and Cleaning of the Governor Coles Monument Structure Repairs. The work includes tuckpointing mortar joints, removing and replacing existing mortar joints, cleaning all stone surfaces of the monument, removing and replacing all joint sealants, and resetting a stairway rail stone. The work must be performed by a firm with at least 3 years of successful experience in comparable masonry restoration projects. Contractors must submit product data, samples, and comply with delivery, storage, and handling requirements. The work can only be performed when air temperatures are between 40°F and 80°F and must follow a specific sequencing process. The specification outlines the required masonry materials, cleaning materials and equipment, and mortar mix requirements. Cleaning methods, joint raking, and joint pointing procedures are detailed, along with curing and final cleaning requirements.

The document does not provide pricing terms, set asides, information about incumbents, funding requirements and sources, or renewal options. It solely focuses on the technical specifications and requirements for the masonry restoration and cleaning work.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

045000 - 1 MASONRY RESTORATION AND

CLEANING Governor Coles Monument Structure Repairs

06/14/2023

SECTION 04500 - MASONRY RESTORATION AND CLEANING

PART 1 GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, photos and general provisions of Contract, including General and Supplementary Conditions and Division-1 Specification sections, apply to work of this section.

1.2 DESCRIPTION OF WORK

A. Extent of masonry restoration work is indicated on photos.

B. Masonry restoration work includes the following:

C.

1.3 QUALIT AY SSURANCE

A. Restoration Specialist: Work must be performed by a firm having not less than 3 years successful experience in comparable masonry restoration projects and employing personnel skilled in the restoration processes and operations indicated.

B. Repointing: Prepare sample area of approximately 2 feet high by 2 feet wide for each type of repointing required to demonstrate methods and quality of workmanship expected in pointing mortar joints and new brick installation. The intent of the new pointing work is to match cleaned existing mortar. Newly pointed areas shall be consistent with existing adjacent mortar joints for color and texture.

1.4 SUBMITTALS

A. Product Data: Submit manufacturer's technical data for each product indicated including recommendations for their application and use. Include test reports and certifications substantiating that products comply with requirements.

B. Samples: Submit, for verification purposes, samples of the following:

1. Each new exposed masonry mortar to be used for replacing existing materials. Include in each set of samples the full range of colors and textures to be expected in completed work.

2. Each type of chemical cleaning material data.

3. Each type of chemical clear sealer provide manufacturers data.

4. Stone masonry patching materials product data and application instructions

1.5 DELIVERY, STORAGE AND HANDLING

A. Deliver materials to site in manufacturer's original and unopened containers and packaging, bearing labels as to type and names of products and manufacturers.

B. Protect masonry restoration materials during storage and construction from wetting by rain, snow or ground water, and from staining or intermixture with earth or other types of materials.

C. Protect grout, mortar and other materials from deterioration by moisture and temperature. Store in a dry location or in waterproof containers. Keep containers tightly closed and away from open flames.

Protect liquid components from freezing. Comply with manufacturer's recommendations for minimum and maximum temperature requirements for storage.

1. Tuckponting mortar joints

2. Removal all existing mortar joints

3. Clean all stone surfaces of monument

4. Remove and replace all joint sealant-mach the color of adjacent masonry surfaces

5. Re-set stairway rail stone

045000 - 2 MASONRY RESTORATION AND

Structure Repairs

06/15/2023

1.6 PROJECT CONDITIONS

A. Do not repoint mortar joints or repair masonry unless air temperatures are between 40 deg.F (4 deg.C) and 80 deg.F (27 deg.C) and will remain so for at least 48 hours after completion of work.

B. Prevent grout or mortar used in repointing and repair work from staining face of surrounding masonry and other surfaces. Remove immediately grout and mortar in contact with exposed masonry and other surfaces.

C. Protect sills, ledges and projections from mortar droppings.

1.7 SEQUENCING/SCHEDULING

A. Perform masonry restoration work in the following sequence:

1. Clean Stone.

2. Rake-out existing mortar from joints indicated to be repointed.

3. Repoint existing mortar joints of masonry indicated to be restored.

PART 2 PRODUCTS

2.1 MASONRY MATERIALS

A. Mortar materials

1. Hydrated Lime: ASTM C 207, Type N.

2. Colored Mortar Aggregate: Natural or manufactured sand selected to produce mortar color to match adjacent existing mortar color.

3. For pointing mortar provide sand with rounded edges.

4. Match size, texture and gradation of existing mortar as closely as possible.

5. Colored Mortar Pigment: Natural and synthetic iron oxides and chromium oxides, compounded for use in mortar mixes. Use only pigments with record of satisfactory performance in masonry mortars.

6. Water: Clean, free of oils, acids, alkalis and organic matter.

2.2 CLEANING MATERIALS AND EQUIPMENT

A. For Stone Mas onry

1. D/2 Biological Solution Cleaner

B. For spot problem stains where required

1. Product: Subject to compliance with requirements, provide "D/2 Biological Solution Cleaner"

C. Water for Cleaning: Clean, potable, free of oils, acids, alkalis, salts, and organic matter.

1. Warm Water: Heat water to temperature of 140 deg.F-180 deg.F (60 deg.C-82 deg.C).

D. Brushes: Fiber bristle only.

E. Spray Equipment: Provide equipment for controlled spray application of water and chemical cleaners, if any, at rates indicated for pressure, measured at spray tip, and for volume.

045000 - 3 MASONRY RESTORATION AND

Structure Repairs

06/1/2023

1. For spray application of chemical cleaners provide low-pressure tank or chemical pump suitable for chemical cleaner indicated, equipped with cone-shaped spray-tip.

2. For spray application of water provide fan-shaped spray-tip which disperses water at angle of not less than 15 degrees.

2.3 POINT MORTAR MIXES

A. General:

1. Measurement and Mixing: Measure cementitious and aggregate material in a dry condition by volume or equivalent weight. Do not measure by shovel, use known measure. Mix materials in a clean mechanical batch mixer.

2. Mixing Pointing Mortar: Thoroughly mix cementitious and aggregate materials together before adding any water. Then mix again adding only enough water to produce a damp, unworkable mix, which will retain its form when, pressed into a ball. Maintain mortar in this dampened condition for 1-to-2 hours. Add remaining water in small portions until mortar of desired consistency is reached. Use mortar within 30 minutes of final mixing; do not retemper or use partially hardened material.

3. Colored Mortar: Produce mortar of color required by use of selected ingredients. Do not adjust proportions without Architect's approval.

PART 3 EXECUTION

3.1 MASONRY CLEANING

A. PREPARATION

1. General: Comply with recommendations of manufacturers of chemical cleaners for protecting building surfaces against damage from exposure to their products.

2. Protect persons, motor vehicles, surrounding surfaces of building whose masonry surfaces are being restored, building site, mask windows and window frames.

3. Prevent chemical cleaning solutions from coming into contact with pedestrians, motor vehicles, landscaping, buildings and other surfaces, which could be injured by such contact.

4. Do not clean masonry during winds of sufficient force to spread cleaning solutions to unprotected surfaces.

5. Dispose of run-off from cleaning operations by legal means and in manner which prevents soil erosion, undermining of paving and foundations, damage to landscaping, and water penetration into building interiors.

6. Erect temporary protection covers over pedestrian walkways and at points of entrance and exit for persons and vehicles, which must remain in operation during course of masonry restoration work.

7. Protect glass and unpainted metal trim from contact with chemical cleaners by covering them with liquid strippable masking agent or polyethylene film and waterproof masking tape. Apply masking agent to comply with manufacturer's recommendations. Do not apply liquid masking agent to painted or porous surfaces.

8. For removal of lead paint, follow procedures noted in Environmental Drawings and comply with all local, state, and federal environmental regulations.

045000 - 4 MASONRY RESTORATION AND

Structure Repairs

06/14/2023

B. Chemical Cleaner Application Methods:

1.General: Apply chemical cleaners to masonry surfaces to comply with chemical manufacturer's recommendations using brush or spray application methods, at Contractor's option, unless otherwise indicated. Do not allow chemicals to remain on surface for periods longer than that indicated or recommended by manufacturer.

3.2 REPOINTING EXISTING MASONRY

A Joint Raking:

1. Rake out mortar from joints to depths equal to 2-1/2 times their widths but not less than 3/4" nor less than that required to expose sound, unweathered mortar.

2. Remove mortar from masonry surfaces within raked-out joints to provide reveals with square backs and to expose masonry for contact with pointing mortar. Brush, vacuum or flush joints to remove dirt and loose debris.

3. Do not spall edges of masonry units or widen joints. Replace any masonry units, which become damaged.

4. Cut out old mortar by hand with chisel and mallet, unless otherwise indicated.

5. Power operated rotary hand saws and grinders will be permitted but only on specific written approval of Architect based on submission by Contractor of a satisfactory quality control program and demonstrated ability of operators to use tools without damage to masonry. Quality control program shall include provisions for supervising performance and preventing damage due to worker fatigue.

B. Joint Pointing:

1. Rinse masonry joint surfaces with water to remove any dust and mortar particles. Time application of rinsing so that, at time of pointing, excess water has evaporated or run off, and joint surfaces are damp but free of standing water.

2. Apply first layer of pointing mortar to areas where existing mortar was removed to depths greater than surrounding areas. Apply in layers not greater than 3/8" until a uniform depth is formed.

Compact each layer thoroughly and allow to become thumbprint-hard before applying next layer.

3. After joints have been filled to a uniform depth, place remaining pointing mortar in 3 layers with each of first and second layers filling approximately 2/5 of joint depth and third layer the remaining 1/5. Fully compact each layer and allow to become thumbprint hard before applying next layer. Where existing bricks have rounded edges recess tool final layer slightly back from face of brick. Take care not to spread mortar over edges onto exposed masonry surfaces, or to featheredge mortar.

4. When mortar is thumbprint hard, tool joints to match original appearance of joints, unless otherwise indicated. Remove excess mortar from edge of joint by brushing.

5. Cure mortar by maintaining in a damp condition for not less than 72 hours.

6. Where repointing work precedes cleaning of existing masonry allow mortar to harden not less than 30 days before beginning cleaning work.

045000 - 5 MASONRY RESTORATION AND

Structure repairs

06/15/2016

3.3

7. Owner shall have the right to perform periodic tests to verify depth of repointing. Contractor shall repair with like materials area where mortar has been removed to ascertain depth of repointing.

FINAL CLEANING

A. After mortar has fully hardened thoroughly clean exposed masonry surfaces of excess mortar and foreign matter using stiff nylon or bristle brushes and clean water, spray applied at low pressure.

B. Use of metal scrapers or brushes will not be permitted.

C.

3.3

Use of acid or alkali cleaning agents will not be permitted.

END OF SECTION 04500