This is the Santa Monica Recycled Water Master Plan (RWMP), a comprehensive planning document prepared by Kennedy Jenks for the City of Santa Monica's Water Resources Division dated January 19, 2024. The plan establishes a strategic roadmap for the City's recycled water infrastructure development to achieve water self-sufficiency by optimizing local water resources through non-potable reuse (NPR), groundwater replenishment reuse (GRR), and direct potable reuse (DPR). The RWMP identifies project components including transmission and distribution pipelines, customer retrofits, injection wells, monitoring wells, and treatment facilities. The plan evaluates thirteen portfolio concepts combining different combinations of NPR, GRR, and DPR projects, with construction cost estimates ranging from $22.8 million to $84.7 million depending on the portfolio selected. The preferred portfolio (Portfolio 5c) prioritizes development NPR expansion through backbone pipeline extensions, GRR utilizing two injection wells, and DPR implementation, with a total construction cost of $54.0 million when including the San Vicente Median component. Implementation is phased from 2024 through 2033, with NPR pipelines and customer retrofits scheduled for 2025-2030 and 2029-2033, GRR Well SM-11i for 2025-2026, and DPR for 2025-2026.
The preferred portfolio would deliver 1,680 acre-feet per year (AFY) of recycled water comprising 392 AFY for NPR, 626 AFY for GRR, and 662 AFY for DPR, with an annualized unit construction cost of $1,200 per acre-foot and a life cycle unit cost of $3,900 per acre-foot when combined with operation and maintenance costs. The plan projects that both GRR and DPR projects would have positive impacts on potable water rates through avoided treatment costs at the Hyperion Water Reclamation Plant and potential recycled water sales revenues, potentially offsetting costs allocated to the potable water enterprise. The City has identified funding opportunities through grants and loans and is committed to pursuing external funding to minimize impacts on customer rates. Key regulatory milestones include regulatory approval for GRR obtained December 21, 2023, and ongoing coordination with the State Water Resources Control Board Division of Drinking Water regarding DPR final regulations adopted in December 2023. The master plan incorporates the City's adopted 2017 Water Neutrality Ordinance and 2022 Recycled Water Ordinance, which mandates recycled water use for new developments within the established recycled water service area.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Recycled Water Master Plan
19 January 2024
FINAL
SMURRF
SWIP AWTF
35 North Lake Ave, Suite 550 Pasadena, California 91101
(626) 568-4300
FINAL
Santa Monica
Recycled Water Master Plan
(RWMP)
19 January 2024
Prepared for
The City of Santa Monica
KJ Project No. 2244514.00 https://www.google.com/search?q=kennedy+jenks+padadena&rlz=1C1GCEA_enUS972US973&oq=kennedy+jenks+padadena&gs_lcrp=EgZjaHJvbWUyBggAEEUYOTIPCAEQLhgNGK8BGMcBGIAEMg0IAhAAGIYDGIAEGIoFMg0IAxAAGIYDGIAEGIoFMg0IBBAAGIYDGIAEGIoFMgYIBRBFGEDSAQgzNDgxajBqN6gCALACAA&sourceid=chrome&ie=UTF-8
THIS PAGE INTENTIONALLY BLANK
Santa Monica Recycled Water Master Plan (RWMP) - DRAFT | Page - i
\\kjc.local\kjc-root\kj-office\pas\projects\2022\2244514.00_santa monica-rwmp\09-reports\9.09-rwmp\final report\final_sm rwmp_1.19.2024.docx
Table of Contents
Executive Summary ............................................................................................................................... I
ES.1 Background and Overview ................................................................................................ I
ES.2 Water Supply Assessment............................................................................................... IV
ES.3 Water Reuse Opportunities ............................................................................................. V
ES.4 Recycled Water Market Assessment .......................................................................... VI
ES.5 Project Components and Portfolio Development ............................................... VIII
ES.6 Preferred Portfolio ............................................................................................................ XV
ES.7 Hydraulic Model ............................................................................................................... XVI
ES.8 Preferred Portfolio Costs and Implementation ................................................. XVII
ES.9 Pricing and Financing Considerations ...................................................................... XX
Section 1 Introduction .......................................................................................................... 1-1
1.1 Overall Study Goal and Objectives ............................................................................ 1-1
1.2 Relevant Studies ............................................................................................................... 1-2
1.3 RWMP Approach and Organization ......................................................................... 1-3
1.4 Background ........................................................................................................................ 1-4
1.4.1 2014 & 2018 Sustainable Water Master Plan ........................................ 1-4
1.5 Recently Adopted Ordinances and Recycled Water Guidelines ................... 1-6
1.5.1 2017 Water Neutrality Ordinance ............................................................. 1-6
1.5.2 2022 Recycled Water Ordinance and User Guidelines ....................... 1-6
Section 2 Water Supply Assessment ................................................................................ 2-1
2.1 City Water Supplies and Usage .................................................................................. 2-1
2.2 Potable Water Supply .................................................................................................... 2-1
2.2.1 Local Groundwater Basins ........................................................................... 2-1
2.2.2 Imported Water ............................................................................................... 2-3
2.2.3 Water Conservation ....................................................................................... 2-3
2.2.4 Historical and Future Water Use Trends ................................................. 2-4
2.3 City Recycled Water Sources and Supply .............................................................. 2-4
2.4 SMURRF and California Beach Initiative Project ................................................ 2-5
2.5 SWIP AWTF ........................................................................................................................ 2-6
2.6 Other Potential Recycled Water Supplies .............................................................. 2-6
2.6.1 West Basin Municipal Water District ....................................................... 2-8
2.6.2 City of Los Angeles Department of Water and Power .......................... 2-8
Section 3 Water Reuse Opportunities and Regulations ............................................ 3-9
Table of Contents (cont’d)
Santa Monica RWMP - FINAL | Page - ii
3.1 Multi-Barrier Approach to Reuse .............................................................................. 3-9
3.2 Overview of Recycled Water Regulations and Requirements .................... 3-10
3.2.1 Non-Potable Reuse ....................................................................................... 3-11
3.2.1.1 Irrigation Requirements ..................................................... 3-12
3.2.1.2 Non-Irrigation Requirements ........................................... 3-13
3.2.2 Groundwater Replenishment Reuse (GRR) .......................................... 3-13
3.2.3 Direct Potable Reuse (DPR) ....................................................................... 3-14
3.3 City’s Recycled Water Facilities and Sustainable Water
Infrastructure Project .................................................................................................. 3-15
3.3.1 SMURRF ............................................................................................................ 3-17
3.3.2 SWIP AWTF and Stormwater Harvesting Tank ................................... 3-18
3.3.3 Existing Recycled Water Distribution System ..................................... 3-21
3.4 GRRP Facilities ................................................................................................................ 3-22
3.5 DPR Strategy and Proposed Treatment Scheme .............................................. 3-23
3.6 Environmental Compliance ....................................................................................... 3-27
Section 4 Recycled Water Market Assessment ............................................................. 4-1
4.1 Market Assessment Approach .................................................................................... 4-1
4.2 NPR Market Assessment ............................................................................................... 4-1
4.2.1 Summary of Existing NPR Water Customers and Demands .............. 4-1
4.2.2 Potential Non-Potable Customers and Demands .................................. 4-4
4.2.2.1 Potential Demand from Existing Potable Water
Customers ................................................................................... 4-4
4.2.2.2 Potential Demand from Future Customers ................... 4-6
4.2.2.3 Planned Developments .......................................................... 4-8
4.2.2.4 Potential Demands from Users Outside City
Limits ............................................................................................ 4-9
4.2.3 Summary of Potential Non-Potable Demand Evaluation ................... 4-9
4.3 Potable Water Reuse Market Assessment ........................................................... 4-10
4.3.1 GRR Demands ................................................................................................. 4-10
4.3.2 DPR Demands ................................................................................................. 4-10
4.4 Recycled Water Supply and Demand Evaluation ............................................. 4-11
4.5 Recycled Water Market Assessment Summary................................................. 4-12
Section 5 Evaluation and Project Development ........................................................... 5-1
5.1 NPR Expansion Evaluation and Project Components ....................................... 5-1
5.1.1 NPR Expansion Evaluation ........................................................................... 5-1
5.1.1.1 Anchor Customers and Backbone Extensions .............. 5-2
5.1.1.2 NPR Cost-Effectiveness Analysis ....................................... 5-4
5.1.2 NPR Project Components .............................................................................. 5-6
Santa Monica RWMP - FINAL | Page - iii
5.1.2.1 Transmission Pipeline (Backbone Extensions) ........... 5-7
5.1.2.2 Distribution Pipelines ............................................................ 5-7
5.1.2.3 Customer Retrofits .................................................................. 5-8
5.1.2.4 New Dual-Plumbing Facilities ............................................. 5-8
5.2 GRR Project Components ............................................................................................. 5-8
5.2.1 Injection Wells & Monitoring Wells .......................................................... 5-9
5.3 DPR Project Components ........................................................................................... 5-10
5.3.1 DPR Pipeline ................................................................................................... 5-10
5.3.2 DPR Pump Station ......................................................................................... 5-11
5.3.3 Treatment ........................................................................................................ 5-11
5.4 Infrastructure Design Criteria .................................................................................. 5-11
5.5 Project Component Costs ........................................................................................... 5-12
5.5.1 GRR Costs ......................................................................................................... 5-16
5.5.2 DPR Costs ......................................................................................................... 5-16
5.6 Regional Reuse Opportunities .................................................................................. 5-16
Section 6 Portfolio Development and Evaluation ....................................................... 6-1
6.1 Identification of Portfolio Concepts ......................................................................... 6-1
6.2 Portfolio Costs ................................................................................................................... 6-3
Section 7 Preferred Portfolio.............................................................................................. 7-1
7.1 Basis of Selection for Preferred Portfolio .............................................................. 7-1
7.2 Preferred Portfolio Costs .............................................................................................. 7-3
7.3 Implementation Plan ...................................................................................................... 7-7
7.4 10-year Capital Improvement Plan (CIP) .............................................................. 7-9
Section 8 Hydraulic Model ................................................................................................... 8-1
8.1 Model Setup ....................................................................................................................... 8-1
8.1.1 Model Conversion ........................................................................................... 8-1
8.1.2 Model Scenarios .............................................................................................. 8-1
8.1.3 Query Sets .......................................................................................................... 8-2
8.1.4 Demand Sets ..................................................................................................... 8-2
8.1.4.1 Diurnal Curves ........................................................................... 8-3
8.2 Existing Recycled Water System Hydraulic Model ............................................ 8-5
8.2.1 Existing Facilities and Controls .................................................................. 8-5
8.2.1.1 Pipes and Junctions ................................................................. 8-5
8.2.1.2 SMURRF Pump Station ........................................................... 8-6
8.2.1.3 SWIP AWTF Pump Station .................................................... 8-8
8.2.1.4 Pump Controls ........................................................................... 8-9
8.2.2 Summary of Supply and Demand ............................................................. 8-10
Santa Monica RWMP - FINAL | Page - iv
8.3 Preferred Portfolio Hydraulic Model ..................................................................... 8-12
8.3.1 Facilities and Controls ................................................................................. 8-12
8.3.1.1 Pipelines and Junctions ....................................................... 8-12
8.3.1.2 Existing Pump Stations and Controls ............................. 8-13
8.3.1.3 Proposed DPR Pump Station and Controls .................. 8-13
8.3.2 Summary of Supply and Demand ............................................................. 8-14
8.3.2.1 Demand Management .......................................................... 8-15
8.4 Model Outcomes ............................................................................................................ 8-15
8.4.1 Existing Recycled Water System .............................................................. 8-15
8.4.2 Preferred Portfolio System ........................................................................ 8-19
Section 9 Pricing and Financing Considerations ......................................................... 9-1
9.1 Rate Structures and Pricing Methodologies – Other Agencies ..................... 9-1
9.2 Overview of Recycled Water Pricing Methodologies and Practices ........... 9-2
9.2.1 Historical Recycled Water Pricing Practices .......................................... 9-2
9.2.2 Recycled Water Rate Structures and Cost Recovery ............................ 9-3
9.2.3 Recycled Water Pricing Concepts .............................................................. 9-4
9.2.3.1 AWWA Standards ..................................................................... 9-4
9.3 Pricing Considerations for Santa Monica Recycled Water ............................. 9-5
9.4 Determining the Marginal Rate Impacts on Potable Water Rates ................ 9-6
9.5 Costs for Recycled Water Preferred Portfolio ..................................................... 9-7
9.6 Recycled Water Deliveries ........................................................................................... 9-8
9.7 Cost Savings from Less Effluent to Hyperion ....................................................... 9-8
9.8 Recycled Water Sales Revenue .................................................................................. 9-9
9.9 Remaining Costs Allocated to Potable Water .................................................... 9-10
9.10 Marginal Impacts on Potable Water Rates .......................................................... 9-11
9.11 Funding Opportunities ................................................................................................ 9-12
References
Appendices .............................................................................................................................................................................................. i
Santa Monica RWMP - FINAL | Page - v
List of Tables
Table ES-1: Summary of Portfolio Construction Costs .................................................................................. ES-XIV
Table ES-2: Preferred Portfolio Costs ............................................................................................................... ES-XVIII
Table ES-3: Implementation Timeline for the Preferred Portfolio .......................................................... ES-XIX
Table 1-1: Relevance of City’s Studies to this RWMP ........................................................................................... 1-2
Table 2-1: City Recycled Water Facilities and Anticipated Production ......................................................... 2-5
Table 3-1: Recycled Water Quality Guidelines for Irrigation .......................................................................... 3-13
Table 3-2: Planned Recycled Water Extension Projects .................................................................................... 3-22
Table 3-3: Proposed DPR Treatment Mechanisms .............................................................................................. 3-26
Table 3-4: Current Anticipated Log Removal Credits for the Proposed DPR Treatment Scheme ... 3-26
Table 3-5: Anticipated Total Log Removal Credits for the Proposed DPR Treatment Scheme ......... 3-27
Table 3-6: Project Participants, Regulatory Agencies and Roles ................................................................... 3-28
Table 4-1: Existing Recycled Water Customers and Demands ......................................................................... 4-2
Table 4-2: Potential Recycled Water Demand from Existing Potable Water Customers ....................... 4-4
Table 4-3: Summary of Potential Recycled Water Demand from Future Customers .............................. 4-6
Table 4-4: Summary of Non-Potable Demand ......................................................................................................... 4-9
Table 4-5: Potential GRR Demands ............................................................................................................................ 4-10
Table 5-1: Expansion Areas, Backbone Extensions, and Anchor Customers .............................................. 5-4
Table 5-2: Summary of Backbone Extensions ......................................................................................................... 5-7
Table 5-3: Summary of Distribution Pipelines ........................................................................................................ 5-8
Table 5-4: Design Criteria and Assumptions .......................................................................................................... 5-12
Table 6-1: Portfolio Strategies, Facilities and Demands ...................................................................................... 6-2
Table 6-2: Summary of Portfolio Construction Costs ($ Million) .................................................................... 6-6
Table 7-1: Preferred Portfolio Costs ............................................................................................................................ 7-5
Table 7-2: Implementation Timeline ........................................................................................................................... 7-8
Table 7-3: 10-Year CIP Project List ............................................................................................................................ 7-10
Table 8-1: Hydraulic Model Scenarios ........................................................................................................................ 8-2
Table 8-2: Demand Diurnal Curve Summary ........................................................................................................... 8-3
Table 8-3: SMURRF Pump Design Information and Model Components ..................................................... 8-8
Table 8-4: SWIP AWTF Pump Design Information ................................................................................................ 8-8
Table 9-1. Survey of Recycled Water Pricing ........................................................................................................... 9-1
Table 9-2: Calculating the Marginal Impact on Portable Water Rates .......................................................... 9-7
Table 9-3: Project Costs for Preferred Portfolio (not including San Vicente Median) ............................ 9-8
Table 9-4: Recycled Water Deliveries (acre-feet) .................................................................................................. 9-8
Table 9-5: Sewer Costs Avoided .................................................................................................................................... 9-9
Table 9-6: Potential Contribution from Sewer Enterprise ................................................................................. 9-9
Table 9-7: Potential Recycled Water Sales Revenue ........................................................................................... 9-10
Table 9-8: Sum of Avoided Sewer Costs and Recycled Water Sales ............................................................. 9-10
Table 9-9: Remaining Costs Allocated to Potable Water ................................................................................... 9-11
Santa Monica RWMP - FINAL | Page - vi
Table 9-10: Impact on Water Rates ........................................................................................................................... 9-12
List of Figures
Figure ES-1: Master Plan Approach ............................................................................................................................ ES-I
Figure ES-2: Closing the Loop on the City’s One-Water Cycle ........................................................................ ES-II
Figure ES-3: Existing Recycled Water System and Recycled Water Service Area ................................ ES-III
Figure ES-4: Recycled Water Market Survey Map ........................................................................................... ES-VII
Figure ES-5: Average Monthly Recycled Water Supply and Demand ..................................................... ES-VIII
Figure ES-6: Approach to NPR Expansion Evaluation and Project Component Identification ....... ES-IX
Figure ES-7: Potential NPR Backbone Extensions ............................................................................................... ES-X
Figure ES-8: GRRP Project Components ................................................................................................................ ES-XI
Figure ES-9: DPR Concept Project Components ................................................................................................ ES-XII
Figure ES-10: Summary of Portfolio Concepts ................................................................................................. ES-XIII
Figure ES-11: Preferred Portfolio Facilities ......................................................................................................... ES-XV
Figure 1-1: Master Plan Approach ................................................................................................................................ 1-3
Figure 1-2: City of Santa Monica Existing Water Resources Schematic (SWMP 2018) .......................... 1-4
Figure 1-3: Closing the Loop on the City’s One-Water Cycle ............................................................................. 1-6
Figure 1-4: Recycled Water Service Area .................................................................................................................. 1-8
Figure 2-1: Santa Monica Basin and Sub-Basin Boundaries .............................................................................. 2-2
Figure 2-2: City Projected Water Use Trends (2025 – 2040) ............................................................................ 2-4
Figure 2-3: Overview of Existing City Facilities ...................................................................................................... 2-5
Figure 2-4: Existing and Potential Future Regional Potable Reuse Projects .............................................. 2-7
Figure 3-1: Multi-Barrier Approach to Reuse .......................................................................................................... 3-9
Figure 3-2: Progression of California Potable Reuse Regulations and Legislation ................................ 3-15
Figure 3-3: Location of SWIP Facilities ..................................................................................................................... 3-15
Figure 3-4: City SWIP Facilities to Expand Local Reuse .................................................................................... 3-16
Figure 3-5: SMURRF Facility and Process Flow Diagram ................................................................................. 3-18
Figure 3-6: SWIP AWTF Facility and Flow Diagram ........................................................................................... 3-19
Figure 3-7: City’s Existing Recycled Water System and Planned Extensions ........................................... 3-21
Figure 3-8: Olympic AWTF and Arcadia WTP Flow Diagram .......................................................................... 3-24
Figure 3-9: DPR Chemical and Flow Control Strategy ........................................................................................ 3-25
Figure 4-1: City's Existing Recycled Water Customers ........................................................................................ 4-3
Figure 4-2: Potential Recycled Water Customers (Existing Potable Water Customers) ....................... 4-5
Figure 4-3: Potential Future Recycled Water Customers ................................................................................... 4-7
Figure 4-4: Average Monthly Recycled Water Supply and Potential Non-Potable, Indirect, and Direct
Reuse Demand ..................................................................................................................................... 4-12
Figure 4-5: Recycled Water Market Survey Map .................................................................................................. 4-13
Figure 5-1: Approach to NPR Expansion Evaluation and Project Component Identification .............. 5-1
Santa Monica RWMP - FINAL | Page - vii
Figure 5-2: Potential Backbone Extensions .............................................................................................................. 5-3
Figure 5-3: RoCE Equation ............................................................................................................................................... 5-5
Figure 5-4: NPR Cost-Effectiveness Results ............................................................................................................. 5-6
Figure 5-5: GRRP Project Components ....................................................................................................................... 5-9
Figure 5-6: DPR Project Components ........................................................................................................................ 5-10
Figure 5-7: Backbone Concept Construction Cost Summary ........................................................................... 5-14
Figure 5-8: Backbone Concept Annualized Unit Construction Costs ........................................................... 5-15
Figure 5-9: Potential Recycled Water Supplies and Beneficial Reuse Applications .............................. 5-17
Figure 5-10: Potential Future Delivery Locations for Tertiary Recycled Water for NPR .................... 5-18
Figure 6-1: Summary of Portfolio Concepts ............................................................................................................. 6-1
Figure 6-2: Portfolio Construction Cost Summary................................................................................................. 6-4
Figure 6-3: Portfolio Concept Annual Unit Construction Cost Summary ..................................................... 6-5
Figure 7-1: Preferred Portfolio Facilities ................................................................................................................... 7-2
Figure 7-2: Preferred Portfolio Diversified Demands .......................................................................................... 7-3
Figure 7-3: Preferred Portfolio Construction Cost Summary ........................................................................... 7-6
Figure 7-4: Preferred Portfolio Life Cycle Unit Cost Summary ......................................................................... 7-7
Figure 8-1: Hydraulic Model Development ............................................................................................................... 8-1
Figure 8-2: Irrigation Diurnal Curve ............................................................................................................................ 8-4
Figure 8-3: Dual-Plumbing Diurnal Curve ................................................................................................................. 8-4
Figure 8-4: IPR/DPR Diurnal Curve ............................................................................................................................. 8-5
Figure 8-5: Existing Recycled Water Pipe Sizes ...................................................................................................... 8-6
Figure 8-6: Pump Curve for SMURRF Small Pump ................................................................................................ 8-7
Figure 8-7: Pump Curve for SMURRF Big Pump ..................................................................................................... 8-7
Figure 8-8: Pump Curve for SWIP AWTF Pumps .................................................................................................... 8-9
Figure 8-9: SMURRF Pump Controls for Existing System ................................................................................. 8-10
Figure 8-10: SWIP AWTF Pump Controls for Existing System ....................................................................... 8-10
Figure 8-11: Supply vs. Existing Diurnal ADD ....................................................................................................... 8-11
Figure 8-12: Supply vs. Existing Diurnal MDD ...................................................................................................... 8-11
Figure 8-13: Existing & Preferred Portfolio RW System ................................................................................... 8-12
Figure 8-14: Proposed DPR Pump Station and Controls ................................................................................... 8-13
Figure 8-15: Supply vs. Demand Existing & Preferred Portfolio ADD Diurnal Demands .................... 8-14
Figure 8-16: Supply vs. Demand Existing & Preferred Portfolio MDD Diurnal Demands ................... 8-15
Figure 8-17: Existing ADD Pressure Results (Hour 2) ....................................................................................... 8-16
Figure 8-18: Existing ADD Flow Results (Hour 2) ............................................................................................... 8-17
Figure 8-19: Existing MDD Pressure Results (Hour 2) ...................................................................................... 8-18
Figure 8-20: Existing MDD Flow Results (Hour 2) .............................................................................................. 8-19
Figure 8-21: Preferred Portfolio ADD Pressure Results (Hour 2) ................................................................. 8-20
Figure 8-22: Preferred Portfolio ADD Flow Results (Hour 2) ......................................................................... 8-21 file://///KJC.local/KJC-Root/KJ-Office/PAS/Projects/2022/2244514.00_Santa%20Monica-RWMP/09-Reports/9.09-RWMP/Final%20Report/FINAL_SM%20RWMP_1.19.2024.docx%23_Toc156486452 file://///KJC.local/KJC-Root/KJ-Office/PAS/Projects/2022/2244514.00_Santa%20Monica-RWMP/09-Reports/9.09-RWMP/Final%20Report/FINAL_SM%20RWMP_1.19.2024.docx%23_Toc156486455 file://///KJC.local/KJC-Root/KJ-Office/PAS/Projects/2022/2244514.00_Santa%20Monica-RWMP/09-Reports/9.09-RWMP/Final%20Report/FINAL_SM%20RWMP_1.19.2024.docx%23_Toc156486456 file://///KJC.local/KJC-Root/KJ-Office/PAS/Projects/2022/2244514.00_Santa%20Monica-RWMP/09-Reports/9.09-RWMP/Final%20Report/FINAL_SM%20RWMP_1.19.2024.docx%23_Toc156486457 file://///KJC.local/KJC-Root/KJ-Office/PAS/Projects/2022/2244514.00_Santa%20Monica-RWMP/09-Reports/9.09-RWMP/Final%20Report/FINAL_SM%20RWMP_1.19.2024.docx%23_Toc156486458 file://///KJC.local/KJC-Root/KJ-Office/PAS/Projects/2022/2244514.00_Santa%20Monica-RWMP/09-Reports/9.09-RWMP/Final%20Report/FINAL_SM%20RWMP_1.19.2024.docx%23_Toc156486459 file://///KJC.local/KJC-Root/KJ-Office/PAS/Projects/2022/2244514.00_Santa%20Monica-RWMP/09-Reports/9.09-RWMP/Final%20Report/FINAL_SM%20RWMP_1.19.2024.docx%23_Toc156486460
Santa Monica RWMP - FINAL | Page - viii
List of Appendices
Appendix A 2022 Recycled Water Ordinance and Recycled Water Guidelines, Policies, and
Procedures
Appendix B Market Assessment Supporting Information
Appendix C Recycled Water Expansion Supporting Information
Appendix D Estimating Engineers Opinion of Probable Construction Costs
Appendix E Supporting Information for Hydraulic Model
Santa Monica RWMP - FINAL | Page - ix
Acronyms and Abbreviations
$ dollars
% percent
AACE Association for the Advancement of Cost Engineering
ADD average daily demand
AF Acre-feet
AFM Acre-feet per month
AFY Acre-feet per year
AOP Advanced oxidation process
AWTF Advanced Water Treatment Facility
AWWA American Water Works Association
BMP Best Management Practice
Caltrans California Department of Transportation
Carollo Carollo Engineers
CGBSC California Green Building Standards Code
CBI California Beach Initiative
CCR California Code of Regulations
CDPH California Department of Public Health
CEQA California Environmental Quality Act
CF Cartridge Filtration
CIMIS California Irrigation Management Information System
CIP Capital Improvement Plan
City City of Santa Monica
City City of Santa Monica
City of LA City of Los Angeles
CWA Clean Water Act
DAF dissolved air flotation
DDW Division of Drinking Water
DPR Direct potable reuse
ECLWRF Edward’s C. Little Water Reclamation Facility
EPA Environmental Protection Agency
EWMP Enhanced Watershed Management Plan
Ft Feet
FRRO Flow Reversal Reverse Osmosis
GAC Granular activated carbon
GIS geographic information systems gpcd gallons per capita per day
Santa Monica RWMP - FINAL | Page - x gpd Gallons per day
GRR Groundwater Replenishment Reuse
GRRP Groundwater Replenishment Reuse Project
H2O2 hydrogen peroxide
HAA Housing Accountability Act
HCF Hundred cubic feet
HDR HDR, Inc.
HGL Hydraulic Grade Line
HP Horsepower
HWRP Hyperion Water Reclamation Plant
IPR Indirect potable reuse
IS Initial Study
ISTEA Intermodal Surface Transportation Efficiency Act
KJ Kennedy Jenks
LACDPH Los Angeles County Department of Public Health
LADWP Los Angeles Department of Water and Power
LARWQCB Los Angeles Regional Water Quality Control Board
LASAN LA Sanitation and Environment lb(s) pound(s)
LRV Log reduction values
Master Plan Recycled Water Master Plan
MBR Membrane bioreactor
MDD Maximum daily demand
MG Million gallons mg/L Milligrams per liter mgd Million gallons per day mil million
MND Mitigated Negative Declaration
MS4 municipal separate storm sewer system
MWD Metropolitan Water District of Southern California n/a not available
NBS NBS Governance Finance Group
NEPA National Environmental Policy Act
NPDES National Pollutant Discharge Elimination System
NPR Non-Potable Reuse
O&M Operations and maintenance ppd Pounds per day psi pounds per square inch
Santa Monica RWMP - FINAL | Page - xi
PVC Polyvinyl Chloride
RO Reverse osmosis
RoCE Radius of cost-effectiveness
RW Recycled water
RW
Guidelines
Recycled Water Ordinance, Recycled Water Guidelines, Policies, and Procedures
RWMP Recycled Water Master Plan
RWQCB Regional Water Quality Control Board
SBX7-7 Water Conservation Act of 2009
SMGB Santa Monica Groundwater Basin
SMMC Santa Monica Municipal Code
SMURRF Santa Monica Urban Runoff Recycling Facility
SS Suspended Solids
SSI Suitable Site Inventory
SWIP Sustainable Water Infrastructure Project
SWMP Sustainable Water Master Plan
SWRCB State Water Resources Control Board
SYA Sustainable Yield Analysis
TDH Total dynamic head
TDS Total dissolved solids
TM Technical memorandum
TSS Total suspended solids
UF Ultrafiltration
UV Ultraviolet
UWMP Urban Water Management Plan
WCU Water Conservation Unit
WDR Waste Discharge Requirements
West Basin West Basin Municipal Water District
WRR Water Recycling Requirements
WTP Water Treatment Plant
WWC Wastewater Contribution yr year
Santa Monica RWMP - FINAL | Page ES- I
Executive Summary The City of Santa Monica (City) is a community committed to protecting the environment and the beautiful coastline of the Santa Monica Bay. The City’s Public Works Department- Water Resources
Division leads the City’s efforts to achieve its vision for water self-sufficiency, maintain high quality drinking water, and invest in a resilient water supply system and infrastructure.
Historically, the City’s water sources have been a combination of local groundwater and imported
Northern California and Colorado River water purchased from the Metropolitan Water District of
Southern California (MWD). Over the years, the City has implemented an effective water conservation program, an innovative stormwater harvesting and reuse program and most recently a new advanced water recycling facility to bolster local supplies and reduce the City’s reliance on imported water.
The expansion of recycled water use is a critical component in achieving the City’s goal of water self-sufficiency and enhance drought resiliency. The goal of this Santa Monica Recycled
Water Master Plan (RWMP or Master Plan) is to guide the planning of and capital investments in future recycled water infrastructure development for the City.
ES.1 Background and Overview
This Recycled Water Master Plan (RWMP) connects the dots between the City’s existing systems, facilities in construction and new facilities needed to reduce the City’s reliance on imported water supplies. The RWMP establishes a road map to optimize the use of the City’s available recycled water resources for non-potable reuse (e.g., irrigation and dual-plumbing) and future potable reuse, while also exploring regional partnership opportunities. The overall approach for the RWMP is illustrated in Figure ES-1.
Figure ES-1: Master Plan Approach
Santa Monica RWMP - FINAL | Page ES- II
The City’s 2018 Sustainable Water Master Plan (SWMP) outlined the City’s strategy to develop an integrated approach to maximize local water resources in order to achieve long-term water self-sufficiency and drought resilience. The RWMP builds on the projects that have been implemented as part of the three key SWMP components, listed below and illustrated in Figure ES-
2.
• 2018 SWMP Component 1 – Increasing water conservation efforts through an optimal conservation plan that permanently reduces water demand.
• 2018 SWMP Component 2 – Developing sustainable and drought resilient alternative water supplies by increasing recycled water production through the Sustainable Water
Infrastructure Project (SWIP), which includes upgrading the existing Santa Monica Urban
Runoff Recycling Facility (SMURRF) and constructing a new Advanced Water Treatment
Facility (AWTF). The SWIP offsets imported water by recharging local groundwater aquifers in the Olympic Sub-Basin with advanced treated recycled water from SWIP to maintain sustainable yield pumping levels.
• 2018 SWMP Component 3 – Expanding local groundwater production within sustainable yield limits and upgrading the City’s Arcadia Water Treatment Plant (WTP) with flow reversal reverse osmosis (FRRO) to increase water production and further offset imported water purchases.
Figure ES-2: Closing the Loop on the City’s One-Water Cycle
Construction of the SMURRF upgrades and the SWIP AWTF were completed in 2022 and the upgrades at Arcadia WTP are scheduled for completion in Spring 2024. The entire suite of local water supply projects in Component 2 and 3 of the 2018 SWMP will be online in early 2024 and are an integral part of the City’s future recycled water expansion plans.
Santa Monica RWMP - FINAL | Page ES- III
In parallel to infrastructure upgrades, the City has implemented Water Neutrality and Recycled
Water Ordinances, and developed Recycled Water Guidelines, Policies, and Procedures (RW
Guidelines) to support expansion of the City’s recycled water distribution system. The Water
Neutrality Ordinance, adopted in 2017, caps water use for new developments to the average five-year historical use for that individual parcel. The Recycled Water Ordinance, adopted in March
2022, formalizes water recycling requirements, describes the applicability for mandatory recycled water use and allowable exemptions, and establishes a recycled water service area within the City limits, shown in Figure ES-3.
Figure ES-3: Existing Recycled Water System and Recycled Water Service Area
Santa Monica RWMP - FINAL | Page ES- IV
Applicable new developments within the boundary of the recycled water service area are required to install facilities necessary for the delivery of recycled water as a development standard. The recycled water service area was developed to align with the extent of the existing recycled water distribution system, also shown in Figure ES-3, and the City’s objective to implement groundwater replenishment through groundwater injection. It was also developed to align with the current state of planned and future developments in the City, and as such, is intended to be updated regularly.
The RW Guidelines, adopted in April 2022, guide the implementation of recycled water facilities, and describe the procedures for the application and engineering control requirements for recycled water use.
ES.2 Water Supply Assessment
The City supplies potable water through a combination of local groundwater from the Santa
Monica Groundwater Basin (SMGB) and water purchased from the Metropolitan Water District of Southern California (MWD) imported from the Colorado River and/or the State Water
Project. The expansion of the recycled water system will help the City enhance its water service reliability and resiliency to reduce dependencies on imported water supplies.
The City’s local groundwater supply provides, on average, approximately 50-70 percent of the total water supply, and water imported from MWD accounts for the remaining 30-50 percent of the
City’s total water supply. The Charnock, Arcadia, Coastal, and Olympic Sub-basins are the major sources of local groundwater with nine active wells and two new wells undergoing permitting.
Based on the 2020 MWD Urban Water Management Plan (UWMP) analysis, MWD can deliver the
City’s supplemental water demands for a normal water year, single dry-year, and five consecutive drought years. However, given the uncertainties of climate change and recurring droughts, the City is committed to developing additional local, drought-resilient supplies to lessen their dependency on imported water. Once water self-sufficiency is achieved, the City will maintain these imported water connections, for water security, in case of a natural disaster or other emergencies.
The City’s recycled water supply is derived from two facilities: (1) Urban and stormwater runoff and brackish/saline groundwater supply treated at the SMURRF and (2) Local wastewater and stormwater runoff treated at the SWIP AWTF, with an anticipated production of 560 AFY and 1,120
AFY, respectively. The combined 1,680 AFY represents the available locally produced recycled water considered for this Master Plan.
There are established recycled water programs in areas adjacent to the City, at West Basin
Municipal Water District (West Basin) and the City of Los Angeles (City of LA), which could offer opportunities to bring additional recycled water supplies to offset potable demands. The ability of the City to beneficially use regional recycled water supplies depends on the additional infrastructure needed, implementation schedule of regional partners, and the available quantity and quality of the regional supply. In addition, establishing the partnerships and agreements
Santa Monica RWMP - FINAL | Page ES- V necessary to make these types of inter-agency programs a reality would require time and funding and could be considered a long-range strategy for the City.
ES.3 Water Reuse Opportunities
The City’s recycled water begins as local wastewater, urban and stormwater runoff, and brackish groundwater before undergoing a series of treatment steps, using a multi-barrier approach, to remove organic matter and pollutants and produce high-quality, advanced treated recycled water. The production and use of recycled water must adhere to strict regulations stipulating the levels of treatment, allowable types of reuse and water quality requirements.
This RWMP focuses on non-potable and potable reuse, as defined below:
• Non-potable reuse (NPR) for a specific purpose other than drinking. For the City this includes landscape irrigation and dual-plumbing for indoor reuse.
• Groundwater Replenishment Reuse (GRR), also referred to as indirect potable reuse
(IPR), incorporates recycled water into a groundwater aquifer, where it mixes and assimilates with native groundwater, thus providing an environmental buffer prior to extraction and use as a source of domestic water supply. The City is in the process of implementing a Groundwater Replenishment Reuse Project (GRRP) using direct injection into the Olympic sub-basin that would then be extracted via groundwater production wells and treated at the Arcadia WTP to meet drinking water needs. The City obtained regulatory approval for GRR on 21 December 2023.
• Direct potable reuse (DPR) is the purposeful introduction of highly purified recycled water into a drinking water supply, immediately upstream of a drinking water treatment plant (referred to as raw water augmentation) or directly into the potable water supply distribution system downstream of a WTP (referred to as treated water augmentation). The
City’s DPR concept is considered raw water augmentation and would combine advanced treated water from the SMURRF and SWIP AWTF with extracted water from the Olympic
Well Field. The combined flow would be conveyed to a new Olympic AWTF that feeds into the recently upgraded Arcadia WTP prior to distribution to the City’s drinking water customers.
The production, discharge, distribution, and use of recycled water are subject to federal, state, and local regulations, the primary objectives of which are to protect public health. NPR regulations are well established, and the City already has the needed approvals to operate its existing NPR system.
As the system expands, new NPR customers would need to follow applicable regulatory requirements, as described in the RW Guidelines. For the GRRP, the City’s SWIP Title 22 GRRP
Engineering Report (Stantec et. al, 2022) was developed to provide the State Water Resources
Control Board (State Water Board) Division of Drinking Water (DDW) and the Los Angeles Regional
Santa Monica RWMP - FINAL | Page ES- VI
Water Quality Control Board (LARWQCB or RWQCB) with specific project information to obtain the necessary permits for IPR, and the RWQCB approved amendments to the City’s Waste Discharge
Requirements/Water Recycling Requirements to allow IPR in December 2023. The State Water
Board also adopted the DPR regulations in December 2023. The City has been communicating the proposed DPR strategy with the DDW and will continue to work collaboratively with the DDW to demonstrate that the proposed treatment strategies would achieve the log reduction values and other requirements defined in the final regulations.
ES.4 Recycled Water Market Assessment
A recycled water market assessment was conducted to identify types of uses that are currently approved for recycled water applications and those that are anticipated to be approved in the future. The assessment was performed in two parts: (1) to identify existing and potential future
NPR customers and (2) to assess the potential potable reuse opportunities for GRR and DPR.
The non-potable market assessment focused on the geographic distribution of potential customers, relative to the existing recycled water system, which would meet the requirements of the City’s Recycled Water Ordinance. Potential future customers identified for NPR were based on discussions with the City, identification of existing irrigation customers and potential future dual-plumbed developments within the City’s established recycled water service area. The City serves approximately 61 AFY of recycled water to customers already connected to the existing recycled water system. The NPR market assessment identified 176 AFY of potential demand for existing potable water customers (parks, schools, commercial/industrial) that could be converted for NPR and 602 AFY of potential future customers that could be developed for NPR. The timing of these future developments and whether they are within the City’s recycled water service area are critical factors in determining which customers could be most suitable for NPR. Additional recycled water transmission and distribution infrastructure would need to be designed to accommodate serving both new existing potable customers and future developments.
The potable market assessment considered the potential amount of recycled water that could be delivered for GRR and DPR. The GRR demand is based on the injection capacity of injection wellSM-
10i and the completion of two additional injection wells (SM-11i and SM-12i), with injection rates of approximately 200 gallon per minute (gpm) per well (323 AFY) and 97 percent capture rate, for a maximum estimated injection of 969 AFY. The potential DPR demand is based on the ability to achieve a wastewater contribution (WWC ) of 10 percent for chemical control to meet the anticipated treatment train requirements for DPR (DDW, 2021).