About this file

This document contains an in-place equipment list and description of work for a federal contract to replace HVAC equipment at Building 1074. The Naval Sea Systems Command is soliciting proposals to remove an existing roof top air handling unit and install five new ductless split system units at Building 1074 of the NAVSEA NUWC Division in Keyport. The contractor will be responsible for removing the old HVAC equipment, supplying and installing the new ductless split systems, as well as any necessary electrical, plumbing, and core drilling work. An equipment list is provided to track assets removed and installed along with costs. The replacement of the roof top unit and addition of ductless systems will allow for modification of the building's HVAC system.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Installed Equipment

Contract No:
Project Title:
Asset NumberDescriptionLong DescriptionBuilding No.Room No.Asset QtyUOMReplacement CostSupplier/VendorManufactureModel No.Serial No.Manufacture Warranty Expiration DateInstallation DateEquipment Removed
New Asset Number
(Note 4)Description of Equipment or materials Installed
(Note 3)Additional Relevant Information (e.g. size, capacity, limits, etc…)Building #Room Number of installed equipmentQuantity
(Note 1)Standard Unit of Measure for asset installedCost (material and labor to remove (if applicable) and install asset
(Note 2)Name/Address/Email/
Phone NumberManufacturerModel number of installed equipmentSerial number of installed equipmentMM/DD/YYYY
(Where no Manufacture Warranty use Contract Warranty Date)MM/DD/YYYY
Asset Number of removed asset

(if no label present on asset this column is Not Applicable) (Note 3)

Notes:
1. When installing assets with a unit of issue of "EACH", there must be a separate line item for each asset.
2. Costing data is to include the cost (labor and material) of removing the old asset and installing the new asset.
3. Enter equipment installed in column B and equipment removed in column O.
4. This column is not necessary for the final submittal from the contrator. FMS will create asset number when they receive the spreadsheet from the government.

Example

Contract No:NXXXXX-21-C-XXXX
Project Title:Replace Breathing Air Filters and Install Carpet
Asset NumberDescriptionLong DescriptionBuilding No.Room No.Asset QtyUOMReplacement CostSupplier/VendorManufactureModel No.Serial No.Manufacture Warranty Expiration DateInstallation DateEquipment Removed
New Asset Number
(Note 4)Description of Equipment or materials Installed
(Note 3)Additional Relevant Information (e.g. size, capacity, limits, etc…)Building #Room Number of installed equipmentQuantity
(Note 1)Standard Unit of Measure for asset installedCost (material and labor to remove (if applicable) and install asset
(Note 2)Name/Address/Email/
Phone NumberManufacturerModel number of installed equipmentSerial number of installed equipmentMM/DD/YYYY
(Where no Manufacture Warranty use Contract Warranty Date)MM/DD/YYYY
Asset Number of removed asset

(if no label present on asset this column is Not Applicable) (Note 3)

Breathing Air Filterlocated behind cabinet next to AHU-1 op switch50941011EA$2,400.00Atlas - 1234 Street Way, America WA 98383 atlas@msn.com/
360-123-4567Atlas CopcoFTX345BUSTB00043563/12/213/12/175094-0-101-154A-40-1H
Breathing Air Filterlocated behind cabinet next to AHU-1 op switch50941011EA$2,400.00Atlas - 1234 Street Way, America WA 98383 atlas@msn.com/
360-123-4567Atlas CopcoFTX345BUSTB00043573/12/213/12/175094-0-101-154A-40-1J
CARPET5094116, 117, 118300SQFT$4,200.00Carpets - 156 Lumber Way,

Bert WA 98317 carpets@msn.com

360-266-0154MohawkMOHAWH - STRBUN/A3/21/193/12/17N/A
Notes:
1. When installing assets with a unit of issue of "EACH", there must be a separate line item for each asset.
2. Costing data is to include the cost (labor and material) of removing the old asset and installing the new asset.
3. Enter equipment installed in column B and equipment removed in column O.
4. This column is not necessary for the final submittal from the contrator. FMS will create asset number when they receive the spreadsheet from the government.