| File | Type | Posted |
|---|---|---|
| Sol_140P6420R0032.pdf | ||
| Attachment - Technical Questionnaire.docx | DOCX document | |
| Attachment - Wage Determination- 07-10-20.pdf | ||
| Attachment - Statement of Work.pdf | ||
| Attachment - Past Performance Questionnaire.docx | DOCX document | |
| Attachment - Drawings-Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table 1 Bid Schedule Exterior Front Stair Restoration First Ladies National Historic Site August 2020
| Line Item No. | Item | Quantity | Units | Unit Price | Total |
| Miscellaneous Project Preparation | |||||
| 001 | Conduct Field Measurements | HR | |||
| 002 | Prepare Shop Drawings | HR | |||
| 003 | Temporary Stair and Railing- Materials | LS | |||
| 004 | Temporary Stair and Railing- Labor | HR | |||
| 005 | Install Hardened Protection of Building-Materials | LS | |||
| 006 | Install Hardened Protection of Building-Labor | HR | |||
| 007 | Provide temporary public rerouting measures | LS | |||
| Removals | |||||
| 008 | Remove and/or remove and salvage existing stair - Equipment | LS | |||
| 009 | Remove and/or remove and salvage existing stair - Labor | HR | |||
| Improvements | |||||
| 010 | Fabricate new stair and rail |Restore Railing - Materials | LS | |||
| 011 | Fabricate new stair and rail |Restore Railing - Labor | HR | |||
| 012 | Install Stone Stair Treads - Materials | LS | |||
| 013 | Install Stone Stair Treads - Labor | HR | |||
| 014 | Clean and Prepare Street Railing - Materials | LS | |||
| 015 | Clean and Prepare Street Railing - Labor | HR | |||
| 016 | Apply Primer and Paint finish - Materials | LS | |||
| 017 | Apply Primer and Paint finish - Labor | HR | |||
| 018 | Reset new stair in place - Equipment | LS | |||
| 019 | Reset new stair in place - Labor | HR | |||
| 020 | Restore electrical service - Materials | LS | |||
| 021 | Restore electrical service - Labor | HR |
| Subtotals |
| Overhead % |
| Profit % |
| Bond % |
| Total |