Attachment B
Water Distribution System Replacement Campus West Side
ESTIMATED INSTALLED COST OF C900/C905 PVC PIPE Fittings:
MaterialQuantityMaterial CostInstall RateLabor & Equipment CostTotal Installed Cost
#($/#)(Total $)(#/HR)($/HR)(Total $)(Total $)
8 x 8 x 2 Tee (D-D-D) 29412$0.00
8 x 8 x 8 Tee (D-D-D) 11032$0.00
12 x 12 x 4 Tee (D-D-D) 6772$0.00
12 x 12 x 8 Tee (D-D-D) 29512$0.00
4, 45 Bend105$0.00
4, 90 Bend (D) 7035$0.00
8, 45 Bend55$0.00
12, 45 Bend35$0.00
12, 90 Bend (D-D) 15012$0.00
12, Pipe - Ftg, Valve JR (D) 6825$0.00
8, Pipe - Ftg, Valve JR (D) 3065$0.00
4, Pipe - Ftg, Valve JR (D) 1585$0.00
3/4", Pipe - Ftg, Valve155$0.00
Total$0.00Total$0.00Total$0.00
ESTIMATED INSTALLED COST OF C900/C905 PVC PIPE:
Pipe SizeTotal LengthMaterial CostInstall RateLabor & Equipment CostBackfill CostTotal Installed Cost
(IN)(LF)($/LF)(Total $)(LF/HR)($/LF)(Total $)($/LF)(Total $)($/LF)(Total $)
3/4"750200$ 14.97$0.00$ - 0
2175$ 14.97$0.00$ - 0
43,500150$ 14.97$0.00$ - 0
6125$ 17.16$0.00$ - 0
81,750115$ 19.45$0.00$ - 0
10100$ 21.67$0.00$ - 0
122,500100$ 24.00$0.00$ - 0
Total$ - 0Total$ - 0Total$ - 0Total$ - 0
ESTIMATED CONSTRUCTION EQUIPMENT RENTAL AND MISC.
MaterialQuantityUnitMaterial CostInstall RateLabor & Equipment CostTotal Installed Cost
#($/#)(Total $)(HR)($/HR)(Total $)(Total $)
Excavator12080
Track Skid Steer12080
Grass Seed20Bags40
Straw200Bails40
Total$0.00Total$0.00Total$0.00
ESTIMATED RECONSTRUCTION COST OF ASPHALT ROADS AND RETAINING WALL:
MaterialQuantityUnitMaterial CostInstall RateLabor & Equipment CostTotal Installed Cost
#($/#)(Total $)(HR)($/HR)(Total $)(Total $)
Hot mix asphalt and concrete aggregate surfacing3000Sq. Ft.$0.00
Asphaltic Labor, Basic160$0.00
Surface preparation material, sealant3000Sq. Ft.$0.00
Asphaltic Equipment Allowance1Item$0.00
Total$0.00Total$0.00Total$0.00
Project SubTotal$0.00
Project Misc. Supplies, Parts, Fuel and Rentals; 15%$0.00
Project Total$0.00
Locality Adjustment 7%$0.00
Overhead 10%$0.00
Profit 8.5%$0.00
Sub-Total$ - 0
Contingency 25%$ - 0
Total$ - 0

Cost Tables

Pipe Material Cost:Install Rates:
DiameterPVC C900/905Ductile IronPVC C905Ductile IronDiameterPVC C900/905Ductile Iron
DR 18 PipePC 350 PipeDR 25 PipePC 250 Pipe
(IN)($/LF)($/LF)($/LF)($/LF)(IN)(LF/HR)(LF/HR)
4$1.88$9.004150100
6$3.68$14.746125100
8$6.30$18.388115100
10$9.59$23.751010090
12$13.51$30.431210085
14$17.51$40.30$13.44148070
16$24.06$50.17$17.51$43.73166458
18$30.32$62.38$22.08$50.59185650
20$37.42$27.23$58.30205045
24$53.80$39.32$65.93244035
3030
3636
4242
4848
Notes:
1. PVC pipe prices obtained on 2/7/11 and represent JM Eagle Block 45
2. Ductile Iron pipe prices obtained 2/7/11
3. All stated prices are marked up 20% to accomadate distribution margins and market price fluctuations
4. PVC C900 referrs to 4" - 12" diameter pipeBackfill Cost & Scenario:
5. PVC C905 referrs to 14" - 48" diameter pipe3" Bedding Only0.00$/Ton
6. DR 18 PVC pipe rated at 235 psiSpringline of Pipe (1/2 Dia)0Density (LBS/FT^3)
7. DR 25 PVC pipe rated at 165 psiTop of Pipeor
8. Ductile Iron PC 350 pipe is rated at 350 psi6" Above Top of Pipe0.00$/CY
9. Ductile Iron PC 250 pipe is rated at 250 psi12" Above Top of Pipe
0.00
Labor & Equipment Cost:
ItemQty (EA)Unit Cost ($/LF)Extended Cost ($/LF)Diameter (IN)OD (IN)3" Bedding OnlySpringline of Pipe (1/2 Dia)Top of Pipe6" Above Top of Pipe12" Above Top of Pipe
Laborer3$40.42$121.2644.800.020.060.080.120.16
Operator3$54.81$164.4366.900.020.070.090.140.19
Foreman11$62.03$62.0389.050.030.080.110.160.21
CAT 330 Excavator2$120.00$240.001011.100.030.090.130.180.24
CAT 966G Wheel Tire Loader1$71.00$71.001213.200.030.100.150.210.26
Notes:Total ($/HR):$658.721415.300.030.110.170.230.29
1. Foreman rate equals Operator rate plus 15%1617.400.030.130.190.250.32
2. Labor rates based on RS Means: Labor Rate for Construction Industry, 36th Edition1819.500.030.140.210.280.34
3. Equipment rates based on Rental Rate Blue Book for Construction Equipment, Volume 12021.600.040.150.230.300.37
2425.800.040.170.270.350.43
3032.000.040.210.340.430.51
3638.300.050.250.410.510.61
4244.500.050.300.490.600.70
4850.800.060.340.570.690.80