Attachment B Special Provisions.pdf
PDF 378 KB Posted
- Solicitation number
- S-73000-00013286
- Issued by
- Baker County, Oregon
About this file
This document contains Special Provisions for a highway construction project issued by the Oregon Department of Transportation (ODOT) for the I-84: N. Huntington Interchange Bridge Deck and Concrete Pavement Repairs project located in Baker and Malheur Counties along the Old Oregon Trail Highway. The project is scheduled for May 2025 and involves structures, paving, and concrete repairs, specifically focusing on bridge deck repairs, concrete pavement repairs, terminal expansion joint repairs, cold plane pavement removal, asphalt concrete paving, and permanent striping. The work will be performed on Interstate 84 between mile points 345.60 and 346.05, with specific staging and traffic management requirements including lane closures and work zone restrictions from May 19 through August 01.
The project is classified as a State-Buy America Project, utilizing the 2024 edition of the Oregon Standard Specifications for Construction. The contract will use High Early Strength (HES) concrete with specific mix design requirements, and includes provisions for quality control, materials testing, surface preparation, reinforcement placement, and detailed specifications for various construction activities. The contractor will be responsible for managing traffic, protecting existing infrastructure, ensuring proper concrete placement and curing, and meeting specific performance and smoothness standards. Payment will be made on a unit price basis for various line items including concrete pavement repair, spall repair, and longitudinal pavement markings, with 75% of payment withheld until a signed warranty is received.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Required Supplemental Request Form - Public Improvement.dat | — | |
| Invitation.To.Bid~20.docx | DOCX document | |
| Cheese Blended.docx | DOCX document | |
| Attachment A Plans~10.pdf | ||
| Addendum.3~1.docx | DOCX document | |
| Attachment C Bid.Pricing.Form.xlsx | XLSX spreadsheet | |
| 00013826 Preliminary Results.xlsx | XLSX spreadsheet | |
| 00013286 Intent To Award~1.xlsx | XLSX spreadsheet | |
| Addendum.1~4.docx | DOCX document | |
| Addendum.2~2.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL PROVISIONS
FOR HIGHWAY CONSTRUCTION
OREGON DEPARTMENT OF TRANSPORTATION
SALEM, OREGON
STRUCTURES, PAVING & CONCRETE REPAIRS
I-84: N. HUNTINGTON INTCHGE. BRIDGE DECK & CONC. PVMT.
REPAIRS PROJECT
OLD OREGON TRAIL HIGHWAY
BAKER & MALHEUR COUNTIES
MAY 2025
I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs Project
TABLE OF CONTENTS FOR SPECIAL PROVISIONS
WORK TO BE DONE
SECTION 00165 - QUALITY OF MATERIALS
SECTION 00210 - MOBILIZATION
SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC
SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC
CONTROL
SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS
SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES
SECTION 00225 - TEMPORARY PAVEMENT MARKINGS
SECTION 00226 - TEMPORARY ROADSIDE BARRIERS AND IMPACT
ATTENUATORS
SECTION 00237 - AGENCY-PROVIDED STAGING AREAS
SECTION 00253 - TEMPORARY WORK ACCESS AND CONTAINMENT
SECTION 00280 - EROSION AND SEDIMENT CONTROL
SECTION 00290 - ENVIRONMENTAL PROTECTION
SECTION 00331 - SUBGRADE STABILIZATION
SECTION 00501 - BRIDGE REMOVAL
SECTION 00504 - CONCRETE DECK SURFACE PREPARATION
SECTION 00537 - PENETRATING CONCRETE SURFACE TREATMENT
SECTION 00539 - CONCRETE AND CRACK SEALING
SECTION 00584 - ELASTOMERIC CONCRETE NOSING
SECTION 00585 - EXPANSION JOINTS
SECTION 00598- CONCRETE COATING AND SEALING
SECTION 00620 - COLD PLANE PAVEMENT REMOVAL
SECTION 00730 - EMULSIFIED ASPHALT TACK COAT
SECTION 00744 - ASPHALT CONCRETE PAVEMENT
SECTION 00758 - REINFORCED CONCRETE PAVEMENT REPAIR
SECTION 00820 - CONCRETE BARRIER
SECTION 00842 - FACILITY IDENTIFICATION MARKERS
SECTION 00866 - LONGITUDINAL PAVEMENT MARKINGS - HIGH
PERFORMANCE
SECTION 02050 – CURING MATERIALS
SECTION 02510 – REINFORCEMENT
FOR
Structures, Paving & Concrete Repairs I-84: N. Huntington Intchge. Bridge Deck & Conc. Repairs
Old Oregon Trail Highway Baker & Malheur Counties
PROFESSIONAL OF RECORD CERTIFICATION:
Seal w/signature
I certify the Special Provision Section(s) listed below are applicable to the design for the subject project for Bridge design elements. Modified Special Provisions were prepared by me or under my supervision.
Sections 00253, 00501, 00504, 00537, 00539, 00584, 00585, 00598 and 00842
FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST
Date: 2025.03.17 16:40:18-07'00' applicable to the design for the subject project for roadway design elements and temporary traffic control. Modified Special Provisions were prepared by me or under my supervision.
Sections 00165, 00220, 00221, 00222, 00224, 00225, 00226, 00280, 00331, 00620, 00730, 00744, 00758, 00820, 00857, 00866, 02050 and 02510
2025.03.17 15:38:27 -07'00' applicable to the design for the subject project for Agency Provided Staging Areas. Modified Special Provisions were prepared by me or under my supervision.
Section 00237
2025.03.17 15:42:08 -07'00'
I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 1
WORK TO BE DONE
The Work to be done under this Contract consists of the following:
1. Install temporary traffic control.
2. Construct bridge deck seal and joint repairs.
3. Construct continuously reinforced concrete pavement repairs.
4. Construct terminal expansion joint repairs.
5. Construct cold plane pavement removal and asphalt concrete paving.
6. Install permanent striping.
Perform additional and Incidental Work as called for by the Specifications and Plans.
APPLICABLE SPECIFICATIONS
The Specifications that are applicable to the Work on this Project is the 2024 edition of the "Oregon Standard Specifications for Construction", as modified by these Special Provisions.
All number references in these Special Provisions shall be understood to refer to the Sections and subsections of the Standard Specifications bearing like numbers and to Sections and subsections contained in these Special Provisions in their entirety.
CLASS OF PROJECT
This is a State - Buy America Project.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 2
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 3
SECTION 00165 - QUALITY OF MATERIALS
Comply with Section 00165 of the Standard Specifications modified as follows:
00165.35(e) Certificate of Origin of Construction Materials – Replace this subsection, except for the subsection number and title, with the following:
When a certificate of material origin for construction materials is specified, complete the form furnished by the Engineer as required by 00160.20(d) for Federal-aid projects.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 4
SECTION 00210 - MOBILIZATION
Comply with Section 00210 of the Standard Specifications.
SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC
Comply with Section 00220 of the Standard Specifications modified as follows:
00220.02(a) General Requirements - Add the following bullet(s) to the end of the bullet list:
• When an abrupt edge is created by excavation, protect traffic according to the "Excavation Abrupt Edge" and the "Typical Abrupt Edge Delineation" configurations shown on the Standard Drawings.
• Protect traffic by grinding and inlaying existing longitudinal rumble strips before staging traffic across them. Grind and inlay existing rumble strips according to the "Existing Rumble Strip Removal" detail shown on the Standard Drawings. Use Level 2, 1/2 inch ACP, or as directed.
00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:
Traffic Lanes may be closed on the Old Oregon Trail Highway (I-84) when allowed, shown, or directed during the following periods of time except as specified in 00220.40(e)(2):
Single Lane Closures – One Traffic Lane in each direction on the Old Oregon Trail Highway (I-84) may be closed during the following times:
• At all times, for a maximum of 7 consecutive days
• Maintain at least 16 feet of clear lane width, one half hour before sunrise and one half hour after sunset, unless shown or directed otherwise.
• Maintain at least 14 feet of clear lane width during nighttime hours, one half after sunset and one half hour before sunrise.
Succeeding roadway closures will not be allowed until traffic clears from preceding closure.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 5
Add the following subsection:
00220.40(f) Limited Duration Road Closure - The Contractor will be permitted to close all Traffic Lanes per location during bridge work on the Old Oregon Trail Highway (I-84) at the following locations and periods of time except as specified in 00220.40(e)(2):
• May 19 through August 01 o Old Oregon Trail Highway (I-84) Eastbound lanes, mile point 345.67 to mile point 346.05 Stage 1: at any time for a maximum of 10 consecutive Days.
• May 19 through August 01 o Old Oregon Trail Highway (I-84) Westbound lanes, mile point 345.67 to mile point 346.05 Stage 2: at any time for a maximum of 10 consecutive Days.
Do not close the road until all Materials and Equipment are on hand or guaranteed to be delivered so that the Work can be done in an efficient manner with a minimum period of road closure.
The road closure will not be allowed until temporary traffic control devices and signs are installed according to the TCP and the requirements of Section 00221 and Section 00222.
Succeeding roadway closures will not be allowed until traffic clears from preceding closure.
Add the following subsection:
00220.41 Bridge Work - Before starting any grading or Pavement removal at Bridge ends or removal of Pavement from Bridge decks, arrange so that all Equipment, labor, and Materials required to complete the Pavement replacement Work and Bridge deck waterproofing Work are on hand or are guaranteed to be delivered. Once grading and Pavement removal begins, vigorously prosecute and complete this Work. Complete paving and membrane waterproofing Work in the shortest possible time.
Temporarily taper or bevel longitudinal and transverse grade changes or drop-offs resulting from grading and Pavement removal and membrane waterproofing Work with asphalt concrete mixture to provide a smooth and safe transition. Construct tapers according to 00620.40.
Add the following subsection:
00220.45 Load Restrictions on Bridges -
For Structure No. 09123, limit the combined weight of Equipment, vehicles, and supplies placed in a closed Traffic Lane or Shoulder on the Bridge according to 00253.46.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 6
SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL
Comply with Section 00221 of the Standard Specifications modified as follows:
00221.06 Traffic Control Plan - Replace this subsection with the following subsection:
00221.06 Traffic Control Plan and Tourist-Oriented Directional and Business Logo Signs –
(a) Traffic Control Plan - Submit one of the following, 5 Calendar Days before the preconstruction conference:
(1) Agency Traffic Control Plan - If the Contractor intends to use the Agency TCP without modification, a written notification indicating that the Agency TCP will be used without modification.
(2) Contractor-Modified Traffic Control Plan - The Contractor may request to use a Contractor-modified Agency TCP, or a TCP developed by the Contractor. Do not use a modified TCP, or a TCP developed by the Contractor, unless approved by the Engineer. Use the Agency TCP unless a modified TCP, or a TCP developed by the Contractor is accepted.
The Engineer is not obligated to consider any modified Agency TCP or a TCP developed by the Contractor. The Agency will not be liable to the Contractor for failure to accept or act upon any request for a modified Agency TCP or a TCP developed by the Contractor.
To conserve time and funds, the Contractor may first submit a written request for a preliminary review by the Engineer. The request should contain a description of the proposal together with a rough estimate of anticipated dollar and time impacts. The Engineer will, within a reasonable time, respond to the Contractor in writing whether or not the request would be considered by the Agency.
If requesting a Contractor-modified Agency TCP, or a TCP developed by the Contractor, at a minimum the request shall meet all requirements of the Contract documents and comply with the Project transportation management plan (TMP).
Provide the following information:
• Stamped Working Drawings according to 00150.35 that include the proposed TCP showing all TCM and quantities of TCD.
• A TPAR plan that includes:
• Details and features used to provide pedestrian accessibility.
• Pedestrian staging Plans at a scale no smaller than 1 inch = 50 feet.
• Temporary alternate facilities or detour routes for pedestrian traffic.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 7
• Staging sequences and details for Work affecting vehicular, pedestrian, and bicycle traffic.
• Proposed order and duration of the TCM.
• A detailed temporary striping plan.
If the Contractor’s request to use a Contractor-modified Agency TCP, or a TCP developed by the Contractor is approved in whole or in part, acceptance will be made by a Change Order.
The Engineer will establish prices that represent a fair measure of the value of Work to be added, changed, or deleted as a result of any accepted modifications to the Agency TCP or an accepted TCP developed by the Contractor.
Once a TCP has been accepted by the Engineer, any additional modifications must be submitted by the Contractor for Agency review following the procedure described above. The Engineer is not obligated to consider additional modifications to a previously approved TCP.
(b) Tourist-Oriented Directional and Business Logo Signs - Submit one of the following for approval, at least 5 Calendar Days before the preconstruction conference:
(1) No Signs - If there are no tourist-oriented directional (TOD) or business logo signs on the Project, a written notification that no TOD or business logo signs exist within the Project limits or
(2) Signs - Submit one copy of a sketch map of the Project showing all existing TOD and business logo signs and a written narrative describing how these signs will be kept in service and protected throughout all the construction stages. If modifications are necessary, submit updated information to the Engineer for approval at least 21 Calendar Days before the change is needed.
00221.90(b) Temporary Protection and Direction of Traffic – Replace the bullet that begins “Providing, Surfacing, maintain…” with the following bullet:
• Providing, surfacing, maintaining, removing, and restoring the TPAR.
SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS
Comply with Section 00222 of the Standard Specifications modified as follows:
00222.15(b) Portable Changeable Message Signs - Add the following paragraph to the end of this subsection:
For PCMS mounted on rollers, use 2-line PCMS from the QPL.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 8
00222.40(e) Temporary Sign Placement - Add the following to the end of the bullet list:
• Install "ROAD WORK AHEAD" (W20-1-48) signs with a 36 by 24-inch "FINES DOUBLE" (R2-6aP) rider on the Old Oregon Trail Highway, according to the "TCD Spacing Table" shown on the Standard Drawings or as modified by the Plans except do not install the "FINES DOUBLE" rider on concrete barrier mounted signs.
• Install beyond each end of the Project, facing outgoing traffic, an "END ROAD WORK"
(CG20-2A-24) sign a distance of (A ÷ 2) according to the "TCD Spacing Table" shown on the Standard Drawings or as modified by the Plans.
• For paving operations on freeways, place “ABRUPT EDGE” (CW21-9) and “ROAD
WORK XX MPH” (CW20-1a) signs as shown. Use an “XX” value equal to 15 mph below the current posted regulatory speed. If a speed is posted for a temporary regulatory speed reduction, that speed is the current posted regulatory speed.
• Install a 72 by 24-inch "CONSTRUCTION VEHICLE DO NOT FOLLOW" (CW23-14) sign on rigid substrate on the back of all Material or Equipment delivery vehicles.
• During bridge and concrete repair operations on the Old Oregon Trail Highway, install temporary signing and other required TCD as shown. Install temporary speed zone signing according to and as shown in the Temporary Speed Zone Order.
Add the following subsection:
00222.40(f) Temporary Speed Zone Reduction - Install a temporary regulatory speed zone, as directed. Use regulatory signs for all required temporary speed zone signage.
00222.45(c) Radar Speed Trailers - Add the following bullet(s) to the end of the bullet list:
• Place a radar speed trailer approximately 1000 feet beyond the end of the lane closure taper, as shown on Standard Drawing TM880, or as shown or directed
• Install a 30 by 36-inch “SPEED LIMIT YY” (R2-1) sign below the trailer display panel.
The “YY” value is the legal speed limit as determined by a Speed Zone Order signed by the State Traffic Engineer.
• Install a 36 by 36-inch “ROAD WORK YY MPH” (CW20-1a) sign below the trailer display panel. Use a value of 50 for “YY” on the sign
00222.80(a) Area Basis -
Add the following sentence to the end of the paragraph that begins "Temporary signs will…":
No measurement of quantities will be made for “CONSTRUCTION VEHICLE DO NOT FOLLOW” (CW23-14) signs.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 9
Add the following sentence to the end of this subsection:
Temporary signing quantities include temporary regulatory speed zone signage.
00222.90 Payment -
Add the following to the end of this subsection:
Payment will be made for not more than 1 set of Work Area signs. All additional sets of Work Area signs will be at no additional cost to the Agency.
Add the following to the end of this subsection:
No separate or additional payment will be made for furnishing, installing, and maintaining 72 by 24-inch "CONSTRUCTION VEHICLE DO NOT FOLLOW" (CW23-14) signs. Payment will be included in 00221.90(b).
SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES
Comply with Section 00224 of the Standard Specifications.
SECTION 00225 - TEMPORARY PAVEMENT MARKINGS
Comply with Section 00225 of the Standard Specifications modified as follows:
00225.90 Payment – Replace the paragraph that begins “Item (a)…” with the following paragraph:
Item (a) includes installation and removal of temporary pavement markers having either one or two reflective faces.
Replace the paragraph that begins “Item (b)…” with the following paragraph:
Item (b) includes installation of flexible temporary pavement markers and removal of flexible temporary pavement markers and temporary flexible pavement marker covers.
Add the following paragraph after the paragraph that begins “Item (b)…”:
Items (c) and (e) include removal of the temporary tape.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 10
SECTION 00226 - TEMPORARY ROADSIDE BARRIERS AND IMPACT ATTENUATORS
Comply with Section 00226 of the Standard Specifications modified as follows:
00226.43 Truck Mounted Attenuator – Replace the paragraph that begins “When workers or construction Equipment…” with the following paragraphs:
Use a truck mounted impact attenuator (TMA), when workers or construction Equipment are exposed to Public Traffic on a Freeway or Multi-Lane Highway and are not located behind a rigid barrier system, as follows unless otherwise shown or directed:
• Each Shoulder or each lane closure where the preconstruction posted speed is 45 mph or more.
00226.80(b)(2) Temporary Barrier - Add the following to the end this subsection:
The quantities will be limited to those shown in Table 00226-1. The estimated quantity of Temporary Barrier is:
TABLE 00226-1
Stage/Phase Location (MP to MP)
Temporary Barrier (foot)
Temporary Barrier, Minimum Deflection
(foot) Stage 1 345.60 - 346.00 1300 Stage 2 345.60 - 346.00 1125
Total Quantity 2425
00226.90 Payment - Add the following Pay Item(s) to the end of the Pay Item list:
Add the following paragraphs after the paragraph that begins "In items (g) and (h)…":
Payment for items (g) performed beyond the quantity shown in the Contract Schedule of Items will be made at the Contract unit price if the Engineer determines that the Contract unit price does not exceed the value of the Work as determined according to Section 00197. If the Engineer determines that the Contract unit price exceeds the value of the Work, payment for the Additional Work will be made according to 00195.20.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 11
SECTION 00237 - AGENCY-PROVIDED STAGING AREAS
Section 00237, which is not a Standard Specification, is included in this Project by Special Provision.
Description
00237.00 Scope - This Work consists of utilizing Agency provided prospective or mandatory staging areas as the Contractor elects or as required for the construction of the Contract.
Locate staging area(s) in previously improved area(s) that have been paved or compacted and graveled, unless otherwise shown or approved.
00237.01 Prospective Staging Areas - If the Contractor elects not to utilize the listed prospective staging area(s) or elects to use other or additional staging areas, 00290.10 applies.
(a) Prospective Staging Area, Sand Shed #8403:
• Location – US30 (Hwy #449), MP 3.37
• Access - Adjacent south
• Available Area - 0.5 acres
(b) Prospective Staging Area, Crossover:
• Location - I-84 (Hwy #006), MP 368.248
• Access - Adjacent west in the median
• Available Area - 600 feet long by 50 feet wide (must maintain minimum 30 feet from the edge of Traveled Way.
00237.05 Pre-Work Meeting - Before occupying a staging area, attend a pre-work meeting at the staging area with the Engineer and the following owners or representatives:
Subsection Source
Name Contact Names and phone numbers
00237.01(a) Sand Shed #8403
ODOT Maintenance: Steve Roberton (541) 889-6618 or
(541) 881-7879
00237.01(b) Crossover ODOT Maintenance: Steve Roberton (541) 889-6618 or
(541) 881-7879
00237.40 General - All vehicles and Equipment, prior to entering the site for the first time, and each subsequent time if the vehicle has left the Roadway outside the construction Project limits, shall be steam cleaned of all debris (soil, dirt, plant parts, and vegetative matter) before being brought back to the site. Notify the Engineer before moving each vehicle onto the site.
Certify, in writing, that the Equipment has been steam cleaned.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 12
00237.41 Restrictions and Protection of Resources - Comply with the following for all operations within the staging area operations:
• Protect cultural resources according to 00290.50.
• Protect migratory birds according to 00290.36(a).
00237.44 Staging Area Operations - The following apply during staging area operations:
• Provide, operate, and maintain wildland firefighting equipment appropriate for the current fire levels on-site at all times during all staging operations.
• To control dust, apply water to staging area access road(s) and staging operations.
• For staging area Sand Shed #8403 (00237.01(a)), maintain the gates into the site at all times.
00237.47 Staging Area Vacating - Before vacating the staging area(s) the following apply:
• Remove all structures, construction debris and trash, and equipment from the staging area.
• Remove solid waste and hazardous material from the site and dispose of properly.
Provide documentary evidence of proper disposal and verify the amount of material removed.
• If a spill or dumping has occurred or if a spill or dumping is suspected to have occurred, 00290.20(3)(g) applies.
• Level the ground to pre-existing condition
• Attend a post-work meeting at each staging area to evaluate staging area rehabilitation work with the Engineer.
Measurement
00237.80 Measurement - No measurement of quantities will be made for Work performed under this Section.
Payment
00237.90 Payment - No separate or additional payment will be made for Work performed under this Section.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 13
SECTION 00253 - TEMPORARY WORK ACCESS AND CONTAINMENT
Comply with Section 00253 of the Standard Specifications modified as follows:
00253.00 Scope - Add the following paragraph to the end of this subsection:
On Structure No. 09123, provide temporary work access and containment system(s) for Bridge Rail Silane Sealing on spans 1 through 3.
00253.07 Work Bridge Structural Design Requirements - Replace this subsection, except for the subsection number and title, with the following:
Unless otherwise specified in Section 00252, design work Bridges according to AASHTO Guide Design Specifications for Bridge Temporary Works. Provide materials for temporary work Bridges meeting the requirements of the applicable Sections of Part 00500. Comply with all requirements of applicable permitting agencies according to Section 00290.
00253.40 General - Add the following paragraph to the end of this subsection:
Containment and work platforms do not extend more than 0 feet below bottom of existing Structure.
The combined effect of all loads in the closed area(s) will be limited to the lesser of:
• Bending moment and maximum shear produced by one lane of HS20 on each span of the Structure;
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 14
SECTION 00280 - EROSION AND SEDIMENT CONTROL
Comply with Section 00280 of the Standard Specifications modified as follows:
00280.00 Scope - Replace the paragraph that begins "This Work also consists of providing temporary …" with the following paragraph:
This Work also consists of providing temporary erosion and sediment control (ESC) measures and furnishing, installing, moving, operating, maintaining, inspecting, and removing ESC throughout the Project area according to the Standard Drawings, the erosion and sediment control plan (ESCP), the Specifications, or as directed, until the site is permanently stabilized. Included also is the monitoring of weather, of stormwater and receiving waters, the reporting of monitoring observations, the reporting of corrective actions (when necessary) and the updates and revisions of the ESCP, including ESCP cover sheet, necessary to keep it representative of current site conditions and compliant with the 1200- CA permit if applicable.
Delete the paragraph that begins “When contaminants, pollutants or hazardous materials…”.
Add the following paragraph to the end of this subsection:
The Agency's NPDES 1200-CA permit is not applicable to the Project. Before beginning Work on the Project, obtain a NPDES 1200-CA permit from the applicable local jurisdiction or a NPDES 1200-C permit that is applicable to the Project.
Add the following paragraph to the end of this subsection:
The Agency’s NPDES 1200-CA permit is not applicable to this Project. Comply with all applicable conditions of this Section.
00280.04 Erosion and Sediment Control Plan on Agency Controlled Lands - Replace the bullet that begins “Information required under 1200-CA…” with the following bullet:
• Information required under 1200-CA permit, if applicable.
00280.06 Erosion and Sediment Control Manager - Delete this subsection.
00280.41(f) Hauling Material – Replace this subsection, except for the subsection number and title, with the following:
Cover loads carrying soil or sediment which may generate dust. Haul saturated loads in water tight beds or drain saturated loads prior to leaving the Project Site.
00280.41(g) Underground Injection Controls (UIC) – Replace this subsection, except for the subsection number and title, with the following:
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 15
Do not allow storm water from work area to enter Underground Injection Control (UIC) inlets, UIC catch basins or UIC wells.
00280.62 Inspecting and Monitoring – Delete the paragraph that begins “Inspect the Project Site…”.
00280.62(a) Inspection - Replace the paragraph that begins "Perform site inspection, complete…" with the following paragraph:
Inspect the Project Site and all ESC devices for Effective Function and potential erosion or sediment movement and complete all applicable parts of the ODOT Erosion Control Monitoring Form, and submit the form to the Agency as follows:
00280.64(a) Corrective Action Timelines – Delete the bullet that begins “If completion of corrective action is not feasible…”
Delete the bullet that begins “Provide a schedule for clean-up and corrective actions…”
Delete the bullet that begins “Provide all corrective action documentation and photographs…”
SECTION 00290 - ENVIRONMENTAL PROTECTION
Comply with Section 00290 of the Standard Specifications modified as follows:
00290.10 Staging and Disposal Sites – Replace the paragraph that begins “Locate staging areas…” with the following paragraph:
Locate staging areas and disposal sites in previously improved or disturbed sites, including existing Roadways, pullouts, turnouts, parking lots, and storage yards that have been compacted, and graveled or paved, unless otherwise specified in Section 00237 or approved, in writing, by the Engineer.
00290.90 Payment - Add the following paragraph(s) to the end of this subsection:
No separate or additional payment will be made for work zone fencing.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 16
SECTION 00331 - SUBGRADE STABILIZATION
Comply with Section 00331 of the Standard Specifications.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 17
SECTION 00501 - BRIDGE REMOVAL
Comply with Section 00501 of the Standard Specifications modified as follows:
00501.00 Scope - Add the following paragraph(s) to the end of this subsection:
Remove portions of the existing bridge 09123_ as shown.
Add the following subsection:
00501.02 Plans - Plans of the existing Structure are available from the Engineer. Prints of these plans are available upon request.
Add the following subsection:
00501.03 Submittals - Submit unstamped bridge removal plans according to 00150.35 7 Calendar Days before beginning removal work.
Include the following information in the submittal:
• Removal sequence, including contractor staging and traffic staging.
• Detailed schedule of bridge removal work.
• Type of equipment that will be used, including size and capacity.
• Equipment location during removal operations.
Do not begin bridge removal work until the bridge removal plans have been approved.
SECTION 00504 - CONCRETE DECK SURFACE PREPARATION
Comply with Section 00504 of the Standard Specifications modified as follows:
00504.01 Definitions: Replace this subsection with the following subsection:
00504.01 Definitions and Acronym:
(a) Definitions:
Bonded Membrane - A polymer or spray-on waterproofing membrane system that is fully or partially bonded to the concrete deck.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 18
Class 1 Preparation - Deck surface preparation for a membrane or overlay system on an existing bridge deck, where the existing concrete is sound, and minimal concrete removal is required to reach sound concrete.
Class 2 Preparation - Deck surface preparation in areas that are determined by the Engineer to have Unsound Concrete that requires concrete removal beyond the limits of Class 1 Preparation.
Class 3 Preparation - Deck surface preparation in areas where concrete removal extends through the full thickness of the deck.
Fabric Membrane - A rolled or sheet waterproofing membrane system that is installed below or between layers of asphalt Pavement.
Unsound Concrete - Delaminated or otherwise deteriorated concrete identified by a deck delamination survey or during surface preparation operations.
(b) Acronym:
ICRI - International Concrete Repair Institute
00504.21(b) Scarifying Equipment – Replace the paragraph that begins “Furnish power-operated diamond grinding…” with the following paragraph:
Furnish power-operated diamond grinding, micro-milling, or shot blasting scarifying Equipment capable of uniformly removing the existing surface to depths required.
00504.21(b)(3) Shot-blasting - Replace this subsection, except for the subsection number and title, with the following:
Furnish mono-directional or bi-directional shot blast machines with single or multiple blast wheels that conform to EPA air pollution requirements by containing dust and steel abrasive media and that can prepare concrete surfaces according to ICRI Technical Guideline No. 310.2R, to the project specific Concrete Surface Profiles (CSP) profile. Furnish shot type S-330 or larger diameter. If the Equipment is not equipped for simultaneous bi-directional blasting, make separate passes in opposite directions to ensure equal cleaning on all sides of the exposed aggregate.
00504.21(b)(4) Hydroblasting – Delete this subsection.
00504.40(f) Structural Overlay Removal - Replace the paragraph that begins “Remove the existing Structural Overlay to the parent …” with the following paragraph:
Remove the existing Structural Overlay to the parent deck surface. Use Equipment that can sufficiently remove the overlay without exceeding 1/2 inch of parent deck removal.
00504.41(b) Class 1 Preparation – Replace this subsection, except for the subsection number and title, with the following:
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 19
• Roughen the existing concrete surface to an exposed aggregate surface texture meeting the following volumetric profiles and ICRI CSP:
• Polymer overlays (MPCO’s and PPC’s) and membranes require minimum profile depth of 1/16 inch and CSP 5.
• Structural cementitious overlays (SCO’s and HESC’s) require a minimum profile depth of 1/8 inch and CSP 7.
• Determine profile depth according to ASTM E965 (standard volumetric test). Perform four tests per 500 square yards of concrete surface prepared, with a minimum of four tests per Day. Visually verify CSP profile with ICRI CSP chips.
• Protect visible reinforcing steel and reinforcing steel where the Plans show it to be within 1/2 inch of the surface.
• When not in conflict with this Specification, follow surface preparation requirements in ICRI Technical Guideline No. 310.2R.
00504.42(a) PPC, MPCO, and Membrane Installations – Replace this subsection with the following:
00504.42(a) PPC, MPCO, Deck Seal, and Membrane Installations - Prepare all surfaces that are to be in contact with the membrane, deck seal or overlay, including vertical contact areas, as follows:
• Clean the entire surface by shot-blasting within 24 hours of placing the membrane or overlay.
• Sweep the area magnetically to remove metal residue.
• Blow clean the surfaces with compressed air.
• Immediately after surface preparation is complete cover the prepared deck with clear plastic, overlapping it to prevent contaminants from construction vehicles or other sources from contacting the deck. Maintain the covering until PPC, MPCO, deck seal or membrane installation.
• If the prepared surface becomes contaminated by spills, rain, or other contaminant before placing the membrane or overlay, prepare the surface again according to this Subsection.
00504.42(b) SCO Overlays – Replace the bullet that begins “Clean the entire surface by shot-blasting…” with the following bullet:
• Clean the entire surface by shot-blasting. Shot-blasting is not required on final surfaces that were prepared by chipping or jack hammering.
SECTION 00537 - PENETRATING CONCRETE SURFACE TREATMENT
Section 00537, which is not a Standard Specification, is included in this Project by Special
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 20
Description
00537.00 Scope - This Work consists of furnishing and placing penetrating sealers on concrete Bridge decks, concrete overlays, and other concrete surfaces as shown.
00537.04 Submittals - Submit the following at least 7 Calendar Days before the pre-placement meeting for each sealer proposed for use:
• Penetrating sealer, including: Brand name, manufacture’s name, and a copy of the manufacturer’s unabridged application procedures.
• A detailed work plan for the deck sealer preparation, application, and cleanup. Include estimated dates and detailed timelines (sealer installation and opening the Bridge to traffic).
• Plan to shield storm drains, traffic and pedestrians from penetrating sealer application, including overspray.
• Number and size of sample lots for cores. Include a map or drawing of core locations.
Do not proceed with the Work until the proposed work plan has been approved by the Engineer.
00537.05 Pre-Placement Meeting - Hold a pre-placement meeting with the Engineer at least 10 Calendar Days before applying the sealer. Do not proceed with the Work until the proposed work plan has been approved by the Engineer.
Materials
00537.10 Materials:
(a) Silane Sealer - Furnish a water based silane sealer meeting the requirements of 02060.30.
(b) Dye - Furnish a fugitive dye to make the solution visible on the treated concrete surface for at least 5 hours. Ensure the dye is not conspicuous longer than 7 Days after application when exposed to direct sunlight.
Equipment
00537.20 General - Remove all Equipment that leaks oil or other contaminants from the Project Site until they are repaired.
00537.21 Application Equipment - Furnish truck mounted or trailer mounted low pressure airless application Equipment with an application pressure from 15 psi to 40 psi and multiple adjustable nozzles. Prevent overspray or misting. Provide heavy nap rollers or other manufacturer recommended Equipment, as approved by the Engineer. Hand pump sprayers are not permitted.
Labor
00537.30 Personnel Qualifications – Provide a technical representative from the sealer manufacturer must be present during the first application of each approved sealer on the
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 21
Project. The need for manufacturer’s representative may be waived if the Contractor provides evidence and reference contacts for work involving at least 5 Bridges treated with the same products within the last two years.
Construction
00537.40 General - Do not begin sealing Work until all Materials and Equipment necessary to perform the Work are at the job site.
(a) Application Conditions - Apply the sealer when the following conditions exist:
• The ambient and deck surface temperature are between 45 °F and 100 °F.
• The deck surface:
• Has been dry for at least 72 hours.
• Has a surface temperature at least 5 °F above the dew point.
• There is no forecasted precipitation during application and less than 12 hours after completion of application. If precipitation occurs during application or 12 hour window, stop work and re-apply sealer at no additional cost to the Agency.
• Wind speeds are 15 mph or less.
(b) Handling Materials - Store sealer at temperatures recommended by the manufacturer. Use penetrating sealer treatment solution from original unopened manufacturers containers with seal(s) intact and the manufacturer's label visible. Do not use Materials that have exceeded their expiration date.
00537.41 Surface Preparation - Prepare all deck surfaces according to Section 00504 modified as follows:
• Perform Class 1 Preparation according to 00504.41(b) with a surface texture depth profile of at least 1/16 inch.
• Perform final surface preparation according to 00504.42(a).
• Block out interior Bridge joints and drains with rigid polyethylene foam or other approved Material to prevent leaking of sealer. Clean the surfaces of dirt, dust, curing compounds, laitance, debris, oil, grease, and foreign matter that would prevent sealer penetration, adhesion, or drying.
• Ensure all foreign Materials are removed from the concrete surfaces.
• Approved solvents and hand tools can be used to remove bonded Materials detrimental to concrete surface treatment.
00537.42 Application:
(a) General - Apply sealer according to the following:
• Use the same sealer for the entire Structure.
• No thinning or alteration of the sealer, with exception of the fugitive dye, is permitted.
• Apply sealer within the same shift as final surface preparation.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 22
• Apply the sealer by brushing, rolling or spraying a flood coat onto concrete surfaces with approved Equipment.
• Avoid sealer running or pooling. Spread treatment from ponded areas to dry areas.
• On sloping and vertical concrete surfaces, apply sealer from bottom to top.
• When possible, apply subsequent coats perpendicular to the previous application.
• Sweep the entire deck surface after the sealer has cured and remove all loose material.
(b) Pre-production Trial Application - Perform a test application on each Structure in the presence of the Engineer. Perform the test with a minimum of 1/2 gallon of sealer. Use the approved Equipment and apply the sealer within the project limits on the surface to be treated. Verify coating application methods and yield rates.
(c) Application of Sealer:
(1) Number of Coats and Yield Rate - Apply a minimum of two coats. Apply at the yield rate verified by the pre-production trial application, or at a minimum rate of 140 square feet per gallon.
(2) Coating Thickness and Coverage Requirements - Coating thickness measurements will not be made. A visual inspection for complete coverage will be made by the Engineer after each coat. If coating coverage of any single coat is incomplete, apply an additional coat at no additional cost to the Agency.
(3) Protection - Protect Public Traffic, pedestrians, exposed metal, and non-concrete appurtenances from overspray using physical barriers or other approved methods.
00537.43 Inspection - The Engineer will inspect Materials and each phase of preparation and coating. Do not proceed with succeeding phases until approved. Provide the Engineer with timely, safe access to areas where Work is being performed. Allow adequate time for inspection at each hold point. Provide hold points at the following times:
• Before cleaning operations begin.
• After cleaning operations are completed and before application of any coating
Materials.
• After Pre-production trial application.
• After each full coat.
00537.44 Sampling and Testing of Bridge Decks - For each Structure, determine the number of core locations by dividing the surface area of the Bridge deck by 10,000 square feet. Round to the nearest whole number. A minimum of 2 cores are required per Structure.
Take cores a minimum of 7 Days after silane application. Prior to coring, locate rebar in the Bridge deck to avoid rebar. Make cores 3 inch in diameter by 4 inch in depth. Core the concrete in the Engineer’s presence and submit the cores to the Engineer for verification testing.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 23
Repair core locations using Material from 02015.20 of the QPL. Perform core hole repairs the same Day the cores are taken.
Sampling and testing is for informational purposes only. Acceptance will be visual and based off application rates.
00537.80 Measurement - The quantities of penetrating concrete sealing will be measured on the area basis, and will be the sealed surface area, excluding curb and rail faces, and will be limited to the Neat Lines and dimensions shown or directed. Field measurement of the area will not be made. The area will be determined by calculating the area from the dimensions shown.
00537.90 Payment - The accepted quantities of penetrating concrete sealing will be paid for at the Contract unit price, per square foot, for the item "Penetrating Concrete Sealing".
Payment will be payment in full for furnishing and placing all Materials, and for furnishing all Equipment, labor, and Incidentals necessary to complete the Work as specified.
SECTION 00539 - CONCRETE AND CRACK SEALING
Section 00539, which is not a Standard Specification, is included in this Project by Special
00539.00 Scope - This Work consists of furnishing and placing concrete and crack sealer on concrete Bridge decks, concrete overlays, and other concrete sections as shown.
00539.10 Materials - Furnish a High Modulus concrete and crack sealer meeting the requirements of Section 02060.
Furnish a PCC repair material meeting the requirements of Section 02015 that is compatible with the sealer.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 24
Construction
00539.40 General - Begin sealing work when all materials and equipment necessary to perform the work are at the job site and all required repairs are made.
(a) Placement Conditions - Apply the sealer when:
• The ambient temperature, surface temperature, and relative humidity (RH) meet the requirements on the manufacturer's written data sheet.
• The concrete substrate is dry, and has been dry for at least 24 hrs.
• During the hours of darkness, work areas are illuminated. Submit an illumination plan for approval at the pre-placement conference.
(b) Handling Materials - Store sealer at temperatures recommended by the manufacturer.
(c) Pre-Placement Meeting - Hold a pre-placement meeting with the Engineer at least 10 Calendar Days before applying the sealer. Submit for the Engineer's approval a manufacturer approved procedure for preparing the concrete surface, applying the sealer, and broadcasting the Sand. Include in the procedure the number of persons required, Equipment, installation sequence, sealer application rate, sealer dwell time, sealer gel time, broadcast Sand application rate, traffic control, and the estimated time schedule for installing the sealer and opening the Bridge to traffic. Do not proceed with the Work until the proposed procedure has been approved by the Engineer.
• Area of Application - Apply the sealer full width of the deck and roadway or as directed.
• Protect adjacent surfaces not to be covered with the sealer from spatter or coating.
• Applicator Qualifications - Provide a manufacturer authorized applicator. Re-certify the manufacturer authorized applicators yearly.
00539.42 Preparing Bridge Decks:
(a) Surface Removal - Remove the existing asphalt concrete wearing surface from the bridge decks, according to Section 00503.
(b) Surface Preparation - Prepare all surfaces that are to receive a deck seal according to Section 00504.
00539.45 Installation - Install sealer according to the following:
• Roll, squeegee, or broom the sealer at application rates and procedures recommended by the manufacturer.
• Allow sealer to dwell on the surface for the time recommended by the manufacturer.
• Remove all excess sealer from the surface with a squeegee, broom, or by other methods and within the time limitations recommended by the manufacturer before broadcasting the Sand.
• Before the sealer gels, broadcast the Sand at the rate recommended by the manufacturer or as required to reach refusal.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 25
• Sweep the entire deck surface after the sealer has cured and remove all loose Material.
00539.80 Measurement - The quantities of concrete and crack sealer will be measured on the area basis, and will be the sealed surface area, excluding curb and rail faces, and will be limited to the Neat Lines and dimensions shown or directed.
00539.90 Payment - The accepted quantities of concrete and crack sealer will be paid for at the Contract unit price, per square foot, for the item "Concrete and Crack Sealer".
Payment will be payment in full for furnishing and placing all Materials, and for furnishing all Equipment, labor, and Incidentals necessary to complete the Work as specified.
SECTION 00584 - ELASTOMERIC CONCRETE NOSING
Comply with Section 00584 of the Standard Specifications modified as follows:
00584.00 Scope - Add the following paragraph to the end of this subsection:
This Work also includes the replacement of existing elastomeric concrete nosing as shown and specified.
00584.80 Measurement - Replace this subsection, except for the subsection number and title, with the following:
The quantities of Work performed under this Section will be measured according to the following:
(a) Elastomeric Concrete Nosing Material - Elastomeric concrete nosing Material will be measured on the volume basis for Material placed in the nosing. When using a mobile mixer, the quantities will be determined by converting the weight identified on the mixer’s automatic metering device to volume, using the manufacturer’s published unit weight and yield factor. When hand batching, the quantities will be determined based on volumes calculated by batch weights and published unit weights of the Material. If placed monolithically with a premixed polymer concrete overlay, the volume will be calculated by multiplying the average depth of the nosing by the measured area.
(b) Constructing Elastomeric Concrete Nosing - Constructing elastomeric concrete nosing will be measured on the area basis. The length will be determined by measuring from face of curb to face of curb along the centerline of the joint. The width will be determined by measuring to the outer limits of the installed Material perpendicular to the joint. Subtract the area of the joint opening from the area calculation.
Joint seal Material will be measured according to 00585.80.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 26
00584.90 Payment – Replace this subsection, except for the subsection number and title, with the following:
The accepted quantities of Work performed under this Section will be paid for at the Contract unit price, per unit of measurement, for the following items:
Pay Item Unit of Measurement
(a) Elastomeric Concrete Nosing Material .................................. Cubic Foot
(b) Constructing Elastomeric Concrete Nosing ......................... Square Foot
Payment will be payment in full for furnishing and placing all Materials, and for furnishing all Equipment, labor, and Incidentals necessary to complete the Work as specified.
Joint seal Material will be paid for according to 00585.90.
No separate or additional payment will be made for providing the manufacturer's representative.
SECTION 00585 - EXPANSION JOINTS
Comply with Section 00585 of the Standard Specifications modified as follows:
00585.43 Armored Corners – Replace the title of this subsection with “Armored Corners and Edgebeam”
Replace the paragraph that begins "Provide joint corner armoring …" with the following paragraph:
Provide joint corner armoring or edgebeam with anchors as shown or specified, and according to the following:
00585.43(a) Tolerance - Replace the paragraph that begins "Install armored corners that are straight…" with the following paragraph:
Install armored corners or edgebeams that are straight and do not deviate from a true line by more than 1/4 inch horizontal and 1/8 inch vertical over the length of the joint, nor more than 1/16 inch in either direction from a 12-foot straightedge.
00585.43(b) Installation - Replace the paragraph that begins "Furnish armored corners in the longest …" with the following paragraph:
Furnish armored corners or edgebeams in the longest practical length as controlled by transportation and installation.
SPS_M25002, I-84: N. Huntington Intchge. Bridge Deck & Conc. Pvmt. Repairs, Contract, May 2025 27
Replace the paragraph that begins "For new construction, install armored …" with the following paragraph:
For new construction, install armored corners or edgebeams with anchors in preformed blockouts at least 14 Days after the deck is cast with the joint opening as shown. Support the armored corners or edgebeams securely in position before placing concrete in the joint blockout.