This document is a pricing schedule for federal contract FNWZ 25-0166 for South Apron Blast Shields construction work. The pricing schedule contains two line items: a base bid and one optional bid, each priced as a lump sum (LS) for construction services funded under appropriation 529 FUNDS. Both line items encompass all survey, design, layout, plant, labor, supplies, equipment, materials, supervision, and incidentals required to complete work in compliance with the Statement of Work and contract terms and conditions.

The base bid carries a performance period of 60 days from the Notice to Proceed (NTP), while Option 1 has an accelerated performance period of 14 days from NTP. Performance time includes mobilization, submittal approval, material delivery, construction work execution, closeout documentation, and submission of DD Form 1354 information upon work completion. Contractors are required to submit pricing for both the base bid and optional line item, with a total contract price line provided for summary.

View the file

Other files

File Type Posted
FA466126R0008_Amendment0001_13Oct2026.pdf PDF
Wage Determination (Heavy).pdf PDF
FNWZ 25-0166 South Apron Blast Shields_SoW_Redacted.pdf PDF
Q and A Sheet.docx DOCX document
FA466126R0008 solicitation_Redacted.pdf PDF
Attachment C - AF Form 3065.pdf PDF
Attachment C - AF Form 3064.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment B South Apron Blast Shields

PRICING SCHEDULE FNWZ 25-0166

Attachment C – Pricing Schedule - Page 1 of 1

0001 Base Bid – South Apron Blast Shields (Construction) 529 FUNDS This item includes all survey, design, layout, plant, labor, supplies, equipment, materials, supervision and incidentals required to complete all work in compliance with the Statement of Work and terms & conditions of the contract for South Apron Blast Shields

LS $

0001 Option 1 – South Apron Blast Shields (Construction) 529 FUNDS This item includes all survey, design, layout, plant, labor, supplies, equipment, materials, supervision and incidentals required to complete all work in compliance with the Statement of Work and terms & conditions of the contract for South Apron Blast Shields.

LS $

TOTAL $

CONTRACT PERFORMANCE TIME:

1. Period of Performance

a. Base Bid - The period of performance shall be 60 days from the Notice to Proceed (NTP).

b. Option 1 – The period of performance shall be 14 days from the Notice to Proceed (NTP).

2. Performance time includes mobilization, submittal approval, delivery of materials, actual construction work, close out documents, and submitted DD Form 1354 information when work is completed.

File details come from the government source that posted it. Updated .