About this file

This memorandum outlines updated procedures for selecting task orders on Architect-Engineer indefinite delivery contracts. Key details include:

  • Procedures apply to all USACE headquarters, divisions, districts, centers, laboratories and field activities for A-E Brooks Act selections under IDCs.

  • Selection boards must comply with composition requirements for different task order value thresholds. Task order notices must include selection criteria and allow firms to submit supplemental information. Evaluations and selection memorandums document the most highly qualified firms.

  • The solicitation seeks an IDIQ multiple task order award contract for general engineering and design services from multiple locations within the Corps' North Atlantic Division boundaries. A minimum of three contracts will be awarded to share a $24 million MATOC pool over five years. Task orders will be firm-fixed-price and selected following the procedures in the memorandum.

View the file

Other files for this federal contract opportunity

Other files attached to Small Business General Design A-E IDIQ, newest first.
File Type Posted
Attachment C Joint Venture Agreement Rev.pdf PDF
Attachment B Blank PPQ.pdf PDF
Combined Synopsis and Solicitation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE ARMY

U.S. ARMY CORPS OF ENGINEERS

441 G STREET, NW

WASHINGTON, D.C. 20314-1000

CECT-ZA (415-17b-1) 14 April 2021

MEMORANDUM FOR Acquisition Community

SUBJECT: Updated Procedures for the Selection of Task Orders on Architect-Engineer Indefinite Delivery Contracts (IDCs)

1. References:

a. 40 United States Code, Chapter 11, Selection of Architects and Engineers (Brooks Act). (https://uscode.house.gov/browse.xhtml)

b. Federal Acquisition Regulation (FAR) Subpart 16.5, Indefinite-Delivery Contracts.

(https://www.acquisition.gov/)

c. FAR Subpart 36.6, Architect-Engineer Services. (https://www.acquisition.gov/)

d. Engineer Pamphlet (EP) 715-1-7, Architect-Engineer Contracting in USACE, 29 February 2012. (https://www.publications.usace.army.mil/)

2. Purpose:

a. The Directors’ Policy Memorandum 2020-02 published 3 March 2020, subject:

Procedures for the Selection of Task Orders on Architect-Engineer Indefinite Delivery Contracts (IDC), is rescinded and replaced with the issuance of this memorandum.

b. The purpose of this memorandum is to reinforce requirements and specify procedures for the selection of an Architect-Engineer (A-E) contractor under a multiple-award task order contract (MATOC). This memorandum is being issued to ensure compliance with the Brooks Act and FAR requirements.

c. This information supplements task order selection processes in the current EP 715-1-7 (2012 edition) (“the EP”) until such time that the EP is updated. To the extent that any interpretation of this memorandum conflicts with the EP, this memorandum will take precedence. To the extent that any interpretation of this memorandum conflicts with the Brooks Act and/or the FAR, the Brooks Act and/or the FAR will take precedence.

CECT-ZA

3. Applicability:

This memorandum is applicable to all Headquarters USACE elements, Divisions, Districts, Centers, Laboratories and Field Operating Activities for all A-E Brooks Act selections under IDCs.

4. Definitions:

a. Indefinite Delivery Contract (IDC) (also known as an Indefinite Delivery/Indefinite Quantity Contract) – Provides for an indefinite quantity, with stated limits, of supplies or services during a fixed period. The government places orders for individual requirements. See FAR Subpart 16.5.

b. Single Award Task Order Contract (SATOC) – A single base contract with a specific scope that is awarded to a single A-E firm under which task orders are issued.

c. Multiple Award Task Order Contract (MATOC) – A base contract awarded to a pool of a minimum of three A-E firms issued from a single solicitation. An individual firm is selected from the pool and awarded a task order for each requirement that arises within scope of the base contract. Capacity of the contract is shared among the pool of A-E firms awarded the base contract.

5. Implementation:

Procedures specified herein shall apply to all new multiple-award A-E base contracts (and task order selections made under those base contracts) awarded after 3 March 2020. Existing IDCs and those IDCs that have already gone through the selection phase are not affected unless otherwise noted herein. Nevertheless, it is strongly recommended that procedures that would not require a contractual change to existing IDCs be implemented immediately.

6. Base Contracts:

a. SATOCs. Districts or Centers may award SATOCs without having to justify why multiple awards are not appropriate (FAR 16.500(d)). As a result, when an A-E SATOC has been properly awarded and no other SATOC awarded by the District or Center includes the same or similar (i.e., overlapping) scope of work, Districts and Centers need not comply with the procedures required for Multiple Award IDCs as outlined below. The selection and award of SATOCs are qualifications-based per the Brooks Act (EP 715-1-7, para 2-8.e).

b. MATOCs. The selection and award of task orders under A-E MATOCs must be executed as qualifications-based contract actions, per the Brooks Act (EP 715-1-7, para 2-8.e), following the requirements of FAR 16.500(d) and Subpart 36.6.

c. Districts or Centers shall not award multiple A-E SATOCs that have the same or overlapping scopes of work from either a single or multiple synopses. This means that the breadth of each SATOC synopsis scope should be narrowed, both substantively and geographically, to ensure that only one contractor is evaluated as the most highly qualified firm to perform the entire scope of services under the awarded SATOC.

d. Selection of at Least Three Firms. When awarding MATOCs, it is necessary to select and award to at least three firms to comply with FAR 16.500(d) and Subpart 36.6.

However, going forward, in applying this guidance, in the event that three firms are not part of the MATOC ordering pool, making it non-compliant with the Brooks Act and the procedure in FAR Subpart 36.6, the MATOC (base contract) will require justification and approval in accordance with FAR Subpart 6.3.

e. Avoiding Overly Broad Scopes. It is important that the scopes of work for an A-E IDC not be overly broad (e.g., all manner of A-E work that could potentially be performed within a District, or work that extends beyond a Division boundary not specific to a defined program). The use of such broad scopes makes it extremely difficult to comply with the Brooks Act and implementing regulations.

f. Annual Updates for SF 330s. As most A-E IDCs have extended performance periods of five (5) years or longer, the information contained in the SF 330 on file used for selection can become outdated over the term of the IDC. Per the Brooks Act, firms are encouraged to update their qualifications information on an annual basis. A-E firms will be encouraged to amend their SF 330s to showcase relevant recently completed projects, to update the resumes, and to provide an updated SF 330 (Part II) for their team. Any changes in key personnel and subcontractors from what was approved in the SF 330 on file shall be reviewed for formal approval by the Contracting Officer as soon as practical per the procedures specified in the EP, FAR 44.204(b), and FAR 52.244-4.

7. Task Order Selection Procedures:

The following selection criteria and procedures shall be used for task order selection among all future A-E MATOCs. After the requirement is received and validated, the technical lead will provide input to the Contracting Officer regarding which specific A-E contract(s) have scopes that include the specific requirement. Because it is the Contracting Officer’s legal obligation to ensure that any task order issued under an IDC is within the scope of that IDC, the Contracting Officer will approve which contract or suite of contracts encompasses the required scope of services.

a. Selection Board Composition. The chairperson and any board members shall have the same qualifications as stated in paragraph 3-6.b. of EP 715-1-7. The composition of the selection board should be tailored to the task order requirement, subject to the following limitations:

(1) For task order projects with an estimated value greater than $5.5 million, the chairperson and evaluation board members shall have the same makeup as stated in paragraph 3-6.b. of EP 715-1-7.

(2) For task order projects with an estimated value between the Simplified Acquisition Threshold (SAT) (currently $250K) and $5.5 million, the selection board may consist of as few as two evaluators, including the chairperson.

(3) For task order projects with an estimated value below the SAT, the selection board may consist of a single evaluator in accordance with FAR 36.602-5(b).

b. Task Order Requirement Notice (TORN). If a task order is to be awarded under a MATOC, the Contracting Officer shall notify all A-E firms within the MATOC pool of the task order requirement. The TORN shall include a short summary of the scope of work and selection criteria, and, if appropriate, a Request for Supplemental Information tailored to the specific task order requirement. Enclosure A is a sample TORN with the supplemental information request.

(1) Task order specific selection criteria shall be listed in order of importance and relative weight, and must include, at a minimum, the criteria required by FAR 36.602-1.

(2) A Request for Supplemental Information in the TORN is intended to supplement existing information and as such should focus on information required to evaluate each firm relative to the specific task order requirement. For example, the TORN might indicate that each firm should submit only three relevant projects demonstrating their specialized experience to perform the task order requirement or information on personnel to be used for the project and, if not already identified in the existing SF 330, their qualifications. The expectation is that, in most cases, the information provided by the A-E firm should be brief (three pages or less) and require minimal effort on the A-E firm’s part. The set of questions or request for information sent to each firm must be identical. Submission of a new SF 330 is not required for each task order unless requested by the TORN.

(3) An Alternate TORN process may be used when the Contracting Officer and the evaluators believe that the government already has sufficient information in the existing SF 330 to determine the most highly qualified firm without the need to request supplemental information. See Enclosure B.

(4) The Contracting Officer should give each firm sufficient time as is necessary under the circumstances to respond to the TORN. Typically, given the focused nature of the request, most information should be able to be provided within five days. A firm may choose not to respond or to indicate that the information on file is adequate (see paragraph 7.c. below). A firm may also request that they not be considered for the specific task order requirement (and would subsequently not be among those firms evaluated). If fewer than three firms respond to the TORN, then justification and approval under FAR Subpart 6.3 may not be required to allow the selection.

c. Evaluation and Discussions (Interviews). Using the selection criteria specified in the TORN, the selection board will evaluate the SF 330s on file and any responses to the TORN to determine the three most highly qualified firms for the specific task order requirement. To ensure that the government meets its obligation to conduct discussions for each task order requirement, all firms must be given an opportunity to respond with specific information relevant to the task order requirement regardless of whether the government uses a TORN with a request for supplemental information or the Alternate TORN process. See Enclosure C for a flow chart depicting the TORN process.

d. Selection Memorandum. Following the evaluation, the selection board shall prepare a selection memorandum recommending, in order of preference, at least three firms that are considered the most highly qualified to perform the work called for under the task order.

(1) The selection memorandum must indicate the rationale for the ranking of the most highly qualified firms by the selection board against the selection criteria in sufficient detail to allow the selection authority to understand the basis for the recommendations. A detailed selection report using formal language is not necessary, but as with any procurement document, it must be sufficiently detailed to rationally support the decision.

(2) The selection report documentation need not be extensive, but it must clearly reflect a) what information was used to evaluate; and b) the results of the evaluation and any discussions against the selection criteria used for the task order.

e. Selection Decision. The task order selection authority making the selection decision shall be designated in accordance with AFARS 5136.602-4 and 5136.602-5 and USACE implementation guidance. It is recommended that the selection authority for task orders greater than $5.5M be the Chief of the District or Center Engineering Division. The task order selection authority will review the recommendations prepared by the evaluation board and make the final selection decision. FAR 36.602-4 provides guidance if the selection authority does not agree with the recommendations of the selection board.

f. Notification and Debriefings. All firms that were sent a TORN will be promptly notified upon a selection decision. Unsuccessful offerors for task orders greater than $5.5M will be given the opportunity for a debriefing in accordance with EP 715-1-7, para 3-12. Debriefings are not required for any task order award estimated to be below $5.5M, however they will be provided upon request.

Indefinite Delivery Contracts (IDCs)

8. Update: Engineer Pamphlet (EP) 715-1-7 and the USACE Acquisition Instruction (UAI) will be updated to reflect these procedures.

9. Points of Contact: The points of contact for this memorandum are Mr. John Jacobson at (202) 761-8817 or john.a.jacobson@usace.army.mil, CECT, and Mr.

Kenneth Simmons at (202) 761-7234 or Kenneth.C.Simmons@usace.army.mil, CECW.

CHRISTINE T. ALTENDORF, SES

Director of Military Programs

DAVID W. PITTMAN, P.E., Ph D., SES Director of Research and Development

DAVID R. COOPER, SES

Chief Counsel

3 Encls

1. Enclosure A – Sample TORN (with request for supplemental information)

2. Enclosure B – Alternate TORN Process (no request for supplemental information)

3. Enclosure C – A-E TORN Process Flow Chart

ALVIN B. LEE, SES

Director of Civil Works

JILL E. STIGLICH, SES

Director of Contracting mailto:john.a.jacobson@usace.army.mil mailto:Kenneth.C.Simmons@usace.army.mil

ENCLOSURE A

Sample TORN (with request for supplemental information)

In accordance with paragraph 7.b.(2) of this memorandum, this sample Task Order Requirement Notice (TORN) may be used when the Contracting Officer and the evaluators believe that the government requires supplemental information to determine the most highly qualified firm for a specific task order requirement. The selection board will determine specifically what additional information is necessary. Bullets below are examples only.

TASK ORDER REQUIREMENT NOTICE

Architectural-Engineering services are required to: [insert description of task order requirement]

This serves as notice of an upcoming task order under the subject IDC. You may submit a maximum three pages in total of supplemental information to support the selection of your firm as the most highly qualified contractor for this task order. Covers, tabs and graphics are not needed.

You are requested to provide the following supplemental information for use in conjunction with your SF 330 on file and past performance information available to the government.

1) Key Staffing: What are the qualifications of the personnel who will be working on this task order?

2) Relevant Experience and Past Performance: Provide a brief description of the qualifications and experience, to include specific projects, your firm has conducted relevant to the scope of this task order. Relevant information from CPARS also will be reviewed.

3) Technical: Provide a brief description of your proposed technical approach to this specific task order.

Responses must be returned by XX:XX on XX. [Typically, this will be five days, but may vary based on the size and complexity of the requirement.]

The government will review the technical capabilities, as reflected in the responses to the request for supplemental information above, and information in the current SF 330s on file, to determine the most highly qualified firm for this task order requirement.

Additional discussions may occur once the information has been reviewed; however, the intent is to make the selection decision based on the information provided.

Selection of the most highly qualified firm will use the criteria in FAR 36.602-1.

This request for supplemental information allows you to provide information not in your SF 330 on file, which may be relevant to this task order requirement. Please submit your information in PDF format via email.

FEE PROPOSALS ARE NOT DUE AT THIS TIME. A REQUEST FOR PROPOSAL

WILL BE ISSUED TO THE FIRM FOUND MOST HIGHLY QUALIFIED FOR THE

SPECIFIC TASK ORDER.

ENCLOSURE B

Alternate TORN Process (no request for supplemental information)

In accordance with paragraph 7.b.(3) of this memorandum, an Alternate TORN process may be used when the Contracting Officer and the evaluators believe that the government already has sufficient information in an existing SF 330 to determine the most highly qualified firm for a specific task order requirement without the need to request supplemental information. When using the Alternate TORN process, the following procedures apply:

1. First, evaluators must analyze and evaluate each MATOC awardee’s existing SF 330 already on file. The evaluators must apply each of the required FAR 36.602-1 criteria to the information in the firms’ SF 330s. Following this initial evaluation, the selection board and the Contracting Officer may determine that additional supplemental information is not necessary. The evaluation of each firm’s qualifications and the basis for the determination that additional supplemental information is not necessary should be supported in writing by citing the specific information identified in the SF 330s, which is responsive to each of the evaluation criteria mandated by the FAR.

2. Next, after making a reasonable determination that no additional supplemental information is necessary, the Alternate TORN is issued to notify all MATOC awardees of the requirement and to allow firms the opportunity to submit additional qualifications information, if they so choose, in response to the specific task order requirement.

3. Finally, following receipt of any additional qualifications information, the evaluators must incorporate and evaluate this new information along with the existing information in the SF 330s prior to drafting the selection memorandum in accordance with paragraph 7.d. of this memorandum.

ENCLOSURE C

A-E TORN

Process Flow

Chart

1. References:
a. 40 United States Code, Chapter 11, Selection of Architects and Engineers
(Brooks Act). (https://uscode.house.gov/browse.xhtml)
b. Federal Acquisition Regulation (FAR) Subpart 16.5, Indefinite-Delivery Contracts.
c. FAR Subpart 36.6, Architect-Engineer Services. (https://www.acquisition.gov/)
d. Engineer Pamphlet (EP) 715-1-7, Architect-Engineer Contracting in USACE, 29 February 2012. (https://www.publications.usace.army.mil/)
2. Purpose:
a. The Directors’ Policy Memorandum 2020-02 published 3 March 2020, subject: Procedures for the Selection of Task Orders on Architect-Engineer Indefinite Delivery Contracts (IDC), is rescinded and replaced with the issuance of this memorandum.
b. The purpose of this memorandum is to reinforce requirements and specify procedures for the selection of an Architect-Engineer (A-E) contractor under a multiple-award task order contract (MATOC). This memorandum is being issued to ensure compliance...
c. This information supplements task order selection processes in the current EP 715-1-7 (2012 edition) (“the EP”) until such time that the EP is updated. To the extent that any interpretation of this memorandum conflicts with the EP, this memorandum...
3. Applicability:
This memorandum is applicable to all Headquarters USACE elements, Divisions, Districts, Centers, Laboratories and Field Operating Activities for all A-E Brooks Act selections under IDCs.
4. Definitions:
a. Indefinite Delivery Contract (IDC) (also known as an Indefinite Delivery/Indefinite Quantity Contract) – Provides for an indefinite quantity, with stated limits, of supplies or services during a fixed period. The government places orders for indiv...
b. Single Award Task Order Contract (SATOC) – A single base contract with a specific scope that is awarded to a single A-E firm under which task orders are issued.
c. Multiple Award Task Order Contract (MATOC) – A base contract awarded to a pool of a minimum of three A-E firms issued from a single solicitation. An individual firm is selected from the pool and awarded a task order for each requirement that arise...
5. Implementation:
6. Base Contracts:
a. SATOCs. Districts or Centers may award SATOCs without having to justify why multiple awards are not appropriate (FAR 16.500(d)). As a result, when an A-E SATOC has been properly awarded and no other SATOC awarded by the District or Center includes...
b. MATOCs. The selection and award of task orders under A-E MATOCs must be executed as qualifications-based contract actions, per the Brooks Act (EP 715-1-7, para 2-8.e), following the requirements of FAR 16.500(d) and Subpart 36.6.
c. Districts or Centers shall not award multiple A-E SATOCs that have the same or overlapping scopes of work from either a single or multiple synopses. This means that the breadth of each SATOC synopsis scope should be narrowed, both substantively an...
d. Selection of at Least Three Firms. When awarding MATOCs, it is necessary to select and award to at least three firms to comply with FAR 16.500(d) and Subpart 36.6. However, going forward, in applying this guidance, in the event that three firms ar...
e. Avoiding Overly Broad Scopes. It is important that the scopes of work for an A-E IDC not be overly broad (e.g., all manner of A-E work that could potentially be performed within a District, or work that extends beyond a Division boundary not specif...
f. Annual Updates for SF 330s. As most A-E IDCs have extended performance periods of five (5) years or longer, the information contained in the SF 330 on file used for selection can become outdated over the term of the IDC. Per the Brooks Act, firms ...
7. Task Order Selection Procedures:
The following selection criteria and procedures shall be used for task order selection among all future A-E MATOCs. After the requirement is received and validated, the technical lead will provide input to the Contracting Officer regarding which speci...
a. Selection Board Composition. The chairperson and any board members shall have the same qualifications as stated in paragraph 3-6.b. of EP 715-1-7. The composition of the selection board should be tailored to the task order requirement, subject to...
b. Task Order Requirement Notice (TORN). If a task order is to be awarded under a MATOC, the Contracting Officer shall notify all A-E firms within the MATOC pool of the task order requirement. The TORN shall include a short summary of the scope of w...
c. Evaluation and Discussions (Interviews). Using the selection criteria specified in the TORN, the selection board will evaluate the SF 330s on file and any responses to the TORN to determine the three most highly qualified firms for the specific ta...
d. Selection Memorandum. Following the evaluation, the selection board shall prepare a selection memorandum recommending, in order of preference, at least three firms that are considered the most highly qualified to perform the work called for under ...
e. Selection Decision. The task order selection authority making the selection decision shall be designated in accordance with AFARS 5136.602-4 and 5136.602-5 and USACE implementation guidance. It is recommended that the selection authority for task...
f. Notification and Debriefings. All firms that were sent a TORN will be promptly notified upon a selection decision. Unsuccessful offerors for task orders greater than $5.5M will be given the opportunity for a debriefing in accordance with EP 715-1-...
8. Update: Engineer Pamphlet (EP) 715-1-7 and the USACE Acquisition Instruction (UAI) will be updated to reflect these procedures.
9. Points of Contact: The points of contact for this memorandum are Mr. John Jacobson at (202) 761-8817 or john.a.jacobson@usace.army.mil, CECT, and Mr. Kenneth Simmons at (202) 761-7234 or Kenneth.C.Simmons@usace.army.mil, CECW.
ENCLOSURE A
ENCLOSURE B
Alternate TORN Process (no request for supplemental information)
2021-04-15T11:18:23-0400
ALTENDORF.CHRISTINE.T.1230956029
2021-04-16T16:10:52-0400
LEE.ALVIN.BRYAN.1066429764
2021-04-16T20:36:44-0500
PITTMAN.DAVID.W.1230771789
2021-04-14T20:22:57-0400
STIGLICH.JILL.E.1093489817
2021-04-21T11:15:43-0400
COOPER.DAVID.R.1295877355

File details come from the government source that posted it. Updated .