FXI and ISR Mirror Bender Upgrade Package Statement of Work and Technical Specifications Summary
This Statement of Work (SOW) dated March 26, 2026, establishes the requirements for designing, manufacturing, installing, and testing mirror bender upgrades for two beamlines at the National Synchrotron Light Source II (NSLS-II) located at Brookhaven National Laboratory (BNL). The contractor shall deliver one Collimating Mirror (CM) Bender System and one Toroidal Mirror (TM) Bender System for the FXI beamline, plus one Horizontal Focusing Mirror (HFM) Bender with in-vacuum double piping cooling lines and one Vertical Focusing Mirror (VFM) Bender for the ISR beamline. These systems will replace existing piezo-based bender systems with stepper-motor-controlled designs while maintaining identical motion performance in travel range, resolution, accuracy, and repeatability. All components must operate in ultra-high-vacuum (UHV) environments with base pressure below 10⁻⁸ mbar, be radiation resistant, comply with ASME B31.3 piping standards, and meet NFPA70 electrical standards with certification by a Nationally Recognized Testing Laboratory (NRTL).
The contractor is responsible for final design review deliverables at 8 weeks post-award, equipment delivery at 32 weeks, and complete installation and testing at BNL by 38 weeks. All in-UHV assemblies must be cleaned and baked prior to delivery, with baking temperatures of 150°C without encoders or 120°C with encoders. Specific technical requirements include vibrational stability below 1.0 microradians in the 4-100 Hz range for FXI mirrors, bend radius ranges from infinity to 5 kilometers with actuator resolution of 0.2 percent, and HFM cooling systems designed for leak and over-pressure testing. The contractor must provide comprehensive factory acceptance testing and site acceptance testing, supply one spare motor and encoder of each type used, provide a two-year warranty against failure and defects, follow BNL Quality Assurance requirements per form BNL-QA-101, obtain Job Hazard Analysis approval prior to work commencement, and furnish all necessary tools, equipment, and supplies.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NSLS-II Page 1 of 8 26MAR2026
FXI and ISR Mirror Bender Upgrade Package
Statement of Work and Technical Specifications
March 26, 2026
1. BACKGROUND:
NSLS-II is a synchrotron light source that has a highly optimized 3 GeV electron storage ring, full-energy injector, experimental beamlines and optics, and appropriate support equipment. The FXI and ISR mirror bender upgrades described in this document (referred to as “The Equipment”) comprise of new
Collimating Mirror (CM) and Toroidal Mirror (TM) benders for the FXI beamline, and new Horizontal
Focusing Mirror (HFM) and Vertical Focusing Mirror (VFM) benders for the ISR beamline.
2. STATEMENT OF WORK:
This Statement of Work (SOW) is the basis for the procurement of the upgrading of the mirror benders for the FXI and ISR Beamlines at the National Synchrotron Light Source II (NSLS-II) at Brookhaven
National Laboratory (BNL). This SOW outlines the Contractor’s responsibilities and obligations necessary for completing the requirements as set forth herein.
2.1 In accordance with the Specification document and all referenced documents, the Contractor shall design, engineer, manufacture, and assemble the Equipment. The Contractor shall test the
Equipment at the Contractor’s facility, then deliver, install, and test the Equipment at BNL. It is the
Contractor’s responsibility to ensure that the Equipment complies with all specification requirements.
2.2 The Contractor shall be responsible for providing a final design review (FDR) report that reflects the state of the developed design of the Equipment in accordance with the specifications identified herein. A final design review meeting shall be held via video conference to review the FDR report between BSA and the Contractor. The Contractor shall be responsible for maintaining and submitting minutes of the FDR and shall also incorporate any agreed-to changes into the final FDR
Report
2.3 Controls interface requirements are documented in BSA document NSLSII-CRL-RSI-001, Experimental Facilities Requirements, Specifications and Interfaces for the Controls and Data
Acquisition System. Motor interfacing standards are found in BSA document NSLSII-CRL-STD-
001, Beamline Systems Instrumentation Interfacing Standard. The vacuum criteria are described in
BSA document LT-ENG-RSI-SR-VA-002, Requirements for Design and Fabrication of
Components for NSLS-II UHV Systems.
2.4 All electrical equipment must be in accordance with U.S. standards, must comply with NFPA70, and shall be certified, listed or labeled by a Nationally Recognized Testing Laboratory (NRTL) or the BSA Authority Having Jurisdiction as specified in BNL-QA-101 document, clause 3.10.
Note that the CE Mark is not a recognized NRTL Certification Mark.
2.5 For process piping requirements, the contractor shall use ASME B31.3 or equivalent approved by BSA in writing. The cooling water lines shall be designed to ASME B31.3 requirements. In all cases, 100% proof testing shall be completed on each component to 150% of the maximum
NSLS-II Page 2 of 8 26MAR2026 working pressure for hydrostatic tests, or 110% of the maximum working pressure for pneumatic tests.
2.6 The Contractor shall install the equipment at BNL.
2.7 The Contractor shall provide a Job Hazard Analysis (JHA), identifying hazards and required controls associated with performing the upgrade, to BSA for acceptance prior to the start of work.
2.8 The Contractor shall be responsible for providing PPE based off their equipment, repair, and supplier’s operator’s manual and the JHA.
2.9 No after hours or weekend work shall be performed unless approved by BSA Work Control
Coordinator, 1 day prior to work.
2.10 The Contractor shall provide their own tools, equipment, and any necessary supplies to complete the job.
2.11 The Contractor shall follow the Quality Assurance requirements as set forth in BSA Form BNL-
QA-101, “Brookhaven National Laboratory Supplier Quality Assurance Requirements,” specifically sections: 3.2-3.22, 4.4, 4.6, 4.7, 4.7.1, 4.7.2, 4.7.3, 4.10, 4.10.1, 4.10.2, 4.10.3, 4.10.4, 4.14, 4.15, 4.16, 4.19, 4.21, 4.30, 4.31, 4.34, and 4.39.
2.12 The Contractor shall provide one (1) spare motor and one (1) spare encoder and readout of each type used on the Equipment.
2.13 The Contractor shall provide a warranty for the Equipment, against failure and defects for a period of two (2) years from final acceptance at BNL.
NSLS-II Page 3 of 8 26MAR2026
3. TECHNICAL SPECIFICATIONS:
3.1 Scope of Supply:
This section describes the requirements for the mirror benders upgrade.
The scope of supply includes:
• One (1) FXI Collimating Mirror (CM) Bender System
• One (1) FXI Toroidal Mirror Bender (TM) System
• One (1) ISR Horizontal Focusing Mirror (HFM) Bender and in-vacuum, double piping, metal cooling lines for existing mirror substrate
• One (1) ISR Vertical Focusing Mirror (VFM) Bender
• Cables in ultra-high-vacuum and high X-ray radiation environment from component to feedthroughs
The scope of supply excludes:
• Mirror substrates
• Mirror tanks
• Standard NSLS-II motion controller for stepper motors
The mirror benders shall be designed to fit into existing mirror systems already installed at BNL. The overall mirror dimensions are provided in the specific bender specifications. Interfacing details to the mirror systems will be provided by BNL to the Contractor one (1) week after the contract is awarded.
The Contractor shall design, manufacture, install, and test stepper-motors to control the tangential bending of the CM/TM mirror units at the FXI Beamline and HFM/VFM mirror units at ISR Beamline, replacing the currently used piezo-based bender systems. The new configuration shall not alter any motion performance in terms of travel range, resolution, accuracy, and repeatability; also, it shall provide a locking position functionality when the motor is de-energized, setting it at the last/closest full step position. The mirror bender design shall include provisions for ensuring the mirror is not damaged during bending actuation.
The motors shall be shielded from radiation with a 2 mm stainless steel plate . Cables from the motors and feedthroughs shall be provided for the in-vacuum section, as well as the feedthroughs themselves. Cables shall be radiation resistant or shielded from radiation. An additional double TC Type K feedthrough shall be provided (for the motors’ temperature) and the connection in UHV shall be prepared. All in-UHV assemblies shall be UHV-conditioned (UHV cleaned and baked) before delivery.
In-air cables for motors, encoders, and limit switches shall be prepared for wiring up to the pre-existing breakout box.
One or two additional interface boxes, replacing the pre-existing one(s), shall be prepared for accepting inputs from the respective motor and limit switches, and for outputs from the BNL standard connectors
(see NSLSII-CRL-RSI-001).
During the motor installation process at NSLS-II, functional testing of the bender stages shall be performed to ensure the proper functioning of both mechanisms and compliance with specifications.
NSLS-II Page 4 of 8 26MAR2026
3.2 Vacuum Requirements:
All components of the mirror benders shall be capable of operating in UHV conditions and shall comply with the criteria described in BSA document LT-ENG-RSI-SR-VA-002, “Requirements for Design and
Fabrication of Components for NSLS-II UHV Systems”. The benders shall not contaminate the UHV condition in the mirror vessels and shall be designed to avoid carbon contamination. All in-UHV assemblies shall be UHV-conditioned (UHV cleaned and baked) before delivery. The new components shall be resistant to high X-ray radiation environment in mirror vessels.
Specific UHV requirements are shown in Table 1.
Table 1: UHV System Requirements
Item Requirement
Baking Temperature without encoders 150°C
Baking Temperature with encoders 120°C
Base Pressure < 10-8mbar
The flanges with feedthroughs shall comply with the specifications described in BSA document LT-ENG-
RSI-SR-VA-002.
3.3 FXI Collimating Mirror Bender
Table 2: FXI Collimating Mirror Bender
Parameter/Description Specification
Mirror temperature (no beam) 20-35°C
Vibrational stability of reflected beam < 1.0 µrad in the 4-100 Hz range
Nominal tangential radius 13.4 km ± 2%
Bend radius range Infinity (flat) to 5 km (collimating)
Bender actuator resolution [2] 0.2% of desired bend radius
Bender actuator repeatability [2] 0.5% of desired bend radius
Bender actuator encoder Yes
Bender actuator encoder resolution 0.2% change in bend radius.
3.4 FXI Toroidal Mirror Bender
Table 3: FXI Toroidal Mirror Bender
Mirror Bender Specification
Mirror temperature 20-25°C
Vibrational stability of reflected beam < 1 µrad in the 4-100 Hz range
Mirror nominal tangential radius 10.8 km ± 2%
Bend radius range Infinity (flat) to 5 km (collimating)
Bender actuator resolution [1] 0.2% of desired bend radius
Bender actuator repeatability [1] 0.5% of desired bend radius
Bender encoder Yes
Bender actuator encoder resolution 0.2% change in bend radius.
NSLS-II Page 5 of 8 26MAR2026
3.5 ISR Horizontal Focusing Mirror Bender
The ISR HFM parameters and dimensions are provided in Table 4 for reference:
Table 4: ISR HFM Parameters and Dimensions
Parameter Specification/Description
Substrate Material Monolithic Block, Optical Grade Silicon Single-Crystal
Active Area 800 mm long x 20 mm wide
Orientation Horizontally-deflecting, inboard
Shape Cylindrical about Y-axis
Bender Yes
Radius Range of Bender 7 km to ∞
Bender Resolution 2.5% of the radius, for radius of 7.5–14 km
3.6 ISR Vertical Focusing Mirror Bender
The ISR VFM specifications are provided in Table 5:
Table 5: ISR VFM Specifications
Parameter Specification/Description
Substrate Material Monolithic Block of Optical Grade Single-Crystal Silicon
Active Area 600 mm long x 20 mm wide
Orientation Vertically-deflecting, upward
Shape Cylindrical about X-axis
Bender Yes
Radius Range of Bender 5 km to ∞
Bender Resolution 2% of the radius, for radius of 5.5–12 km
3.7 Testing
3.7.1 Factory Acceptance Testing
3.7.1.1 Dimensions: Verify that all components are fabricated to the specified dimensions and fit together correctly.
3.7.1.2 Vacuum readiness: Verify that all vacuum components are baked as specified and that the vacuum criteria are met, as described in BSA document LT-ENG-RSI-SR-VA-002, “Requirements for
Design and Fabrication of Components for NSLS-II UHV Systems.”
3.7.1.3 Wiring and connections: Verify that all wiring and connections are made according to specifications.
3.7.1.4 Sensors: Verify that sensors are connected properly and show proper readings.
3.7.1.5 HFM cooling lines: Perform leak tests and over-pressure tests.
3.7.1.6 Motion system: Verify that all motions are implemented with the specified motion direction, range, resolution, repeatability, and stability.
NSLS-II Page 6 of 8 26MAR2026
3.7.1.7 Verify that the limits and encoders are implemented as specified.
3.7.1.8 Verify that all motors are running smoothly and are properly tuned.
3.7.1.9 The precision of these tests is limited to the capability of the Contractor’s measurement instruments and the ambient environments.
3.7.2 Site Acceptance Testing
Repeat the above tests and perform the following tests:
3.7.2.1 Verification of installation: verify that all components are installed to their nominal locations, in respective mirror tanks, following the surveying procedures, and that all components are installed as specified.
3.7.2.2 Motion and calibration: test the motion direction, resolution, repeatability, and stability of motorized motions using BSA equipment. Check calibration of all motions.
3.7.2.3 Equipment protection: verify EPS functional performance, including the limit switches.
3.7.2.4 Vacuum: verify that the vacuum meets the vacuum specifications.
3.7.2.5 Cooling: verify that HFM cooling lines are connected to the utilities as specified. Verify that water is flowing at its nominal flow rate or pressure range. Verify that vacuum levels are meeting specifications with cooling.
3.7.2.6 Angular stability of HFM: measure the angular stability of the mirror, both with and without the closed-loop cooling system turned on.
3.7.2.7 Performance: Carry out performance tests on all beamline components to verify that the measured performance meets the specifications described.
4. MILESTONES AND DELIVERABLES:
Table 6: Milestones and Deliverables
Item Deliverable Due Date (weeks after contract award)
1 Final design review report 8 weeks
2 Equipment delivery 32 weeks
3 Installation and testing 38 weeks
4 Receipt of end item documentation package With equipment delivery
NSLS-II Page 7 of 8 26MAR2026
5. ACRONYMS
ASME American Society of Mechanical Engineers
BNL Brookhaven National Laboratory
BSA Brookhaven Science Associates
CM Collimating Mirror
DSSI Data Science & System Integration (group)
ESH Environment, Safety & Health
FDR Final Design Review
FXI Full X-ray Imaging
HFM Horizontal Focusing Mirror
ISR Integrated In situ and Resonant
JHA Job Hazard Analysis
NRTL Nationally Recognized Testing Laboratory
PPE Personal Protection Equipment
SOW Statement of Work
SPC Technical Specification
TC Thermocouple
TM Toroidal Mirror
VFM Vertical Focusing Mirror