Attachment A Specifications.pdf

PDF 753 KB Posted

Attached to
RCM Road Striping, Olympic National Park
Solicitation number
140P8321Q0037
Issued by

View the file

Other files

File Type Posted
Attachment D Forms to Include with Quote.docx DOCX document
Sol_140P8321Q0037.pdf PDF
Attachment C DOL Wage Determination.pdf PDF
Attachment B - MAPS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specifications

Road Striping Mora, Sol Duc and Barnes Point

PMIS 237892

FY2021

Developed By

Olympic National Park Facility Management 600 East Park Ave Port Angeles, WA

FY21 Road Striping 00 20 00-1 Table of Contents

TABLE OF CONTENTS

Number Title .......................................................................................... Number of Pages

00 20 00 Table of Contents

DIVISION 1 - GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 27 00 Definition of Contract Line Items 01 31 00 Project Meetings 01 33 23 Submittal Procedures 01 35 23 Accident Prevention 01 51 13 Temporary Services 01 56 00 Temporary Controls 01 59 00 Field Offices and Sheds 01 60 00 Material and Equipment 01 70 00 Project Closeout

DIVISION 32 – Pavement Specialties 32 17 23 Pavement Markings

FY21 Road Striping 01 11 00-1 Summary of Work

SECTION 01 11 00 SUMMARY OF WORK

PART 1: GENERAL

1.1 DESCRIPTION:

1. The Work of this contract consists of the preparation and re-painting of approximately 347,000 linear feet of solid white fog line and approximately 347,000 linear feet of yellow centerline at three areas within Olympic National Park. Pavement marking material shall be Type B Waterborne traffic paint with Type 1 glass beads.

Work shall include:

A. Approximately 49,000 LNFT of solid white fog line and 49,000 LNFT solid yellow centerline on Mora Road.

B. Approximately 290,700 LNFT of solid white fog line and 290,700 LNFT solid yellow centerline on Sol Duc Valley Road.

C. Approximately 7,200 LNFT of solid white fog line and 7,200 LNFT solid yellow centerline on Lake Crescent Road.

D. Appropriate Traffic Control to complete the above work.

1.2 LOCATION:

A. Mora Road in Forks, WA 98331

B. Sol Duc Valley Road in Port Angeles, WA 98363

C. Lake Crescent Road in Port Angeles, WA 98362

1.3 CONTRACTOR'S USE OF PREMISES:

1. Construction Camp: Establishment of a camp within the Park and at this location will not be permitted.

2. Work Hours: Work hours are from 7:00am to 7:00pm Monday through Friday. Weekend work will normally not be allowed. Special requests may be made through the Contracting Officer.

3. Confine storage of materials to the area as indicated during the pre-construction meeting as part of this contract. Coordinate deliveries so that deliveries fit available storage area.

4. The following conditions shall be followed during the Contractor's work while in the Park:

A. To prevent unnatural attractants to bears, no foods, garbage, drinks, trash, or food and drink containers shall be placed outside trailers or buildings, except during actual use. Any mishandling of garbage, trash, foods, and other potential bear attractants described above will result in the responsible person or Contractor receiving a citation subject to a fine or court appearance before the U.S. Magistrate. Repetition of mishandling or any case of deliberate feeding will result in loss of in-Park operation privileges

B. Pets are prohibited.

C. Feeding of any wildlife is prohibited.

5. Preservation of Natural Features: Confine all operations to work limits of the project. Prevent damage to natural su

6. Vehicles/Heavy Equipment: Vehicles / Heavy Equipment:

FY21 Road Striping 01 11 00-2 Summary of Work

A. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits. Failure to comply with traffic regulations will result in a citation being issued to the driver.

B. Vehicle Parking: The contractor shall park vehicles and heavy equipment in designated areas as shown on the Site Location Map or as established at the preconstruction meeting.

C. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles at all times.

D. Vehicle Exhaust: All vehicles will be properly maintained to ensure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.

E. Spills: The Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. The Contractor must immediately notify the Contracting Officer of spills.

F. DOT Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to driver with appropriate license class, medical examiner card as appropriate with license class, carrying three (3) triangles or three (3) flares, mounted fire extinguisher, and valid DOT safety sticker.

1.4 FIELD VERIFICATION: Field verify all new and existing dimensions and utilities affecting the work of this Contract before ordering products.

1.5 CONTRACTOR-FURNISHED ITEMS: All materials shall be Contractor-furnished from outside the Park.

PART 2: PRODUCTS Not used.

PART 3: EXECUTION Not used.

END OF SECTION 01 11 00

FY21 Road Striping 01 27 00-1 CONTRACT LINE ITEMS

SECTION 01 27 00 DEFINITION OF CONTRACT LINE ITEMS

PART 1 GENERAL

1.1 DESCRIPTION

1. The work of this bid item consists of the preparation and re-painting of approximately 346,900 LNFT of white fog line in three areas of Olympic National Park and 346,900 LNFT of yellow centerline, including Type 1 glass beads applied to top coat . Include all costs necessary to complete the work including labor, equipment, tools, materials, supplies, mobilization, traffic control, overhead, profit and bond.

2. If no bid item exists for a portion of the work, include the costs in a related line item.

3. Quantities are estimates only. Vendor will invoice for actual amounts of LNFT painted.

Description Quantity Unit Price Amount Sol Duc Road Pavement Marking:

(Type B – White+Yellow) 581,400 LNFT $ $

Mora Road Pavement Marking:

(Type B – White+Yellow) 98,000 LNFT $ $

Lake Crescent Rd Pavement Marking:

(Type B – White+Yellow) 14,400 LNFT $ $

FY21 Road Striping 01 27 00-2 CONTRACT LINE ITEMS

END OF SECTION 01 27 00

FY21 Road Striping 01 31 00-1 Project Meetings

SECTION 01 31 00 PROJECT MEETINGS

PART 1: GENERAL

1.1 PRE-CONSTRUCTION CONFERENCE: Before start of construction, Contracting Officer will arrange a meeting at Headquarters and an onsite meeting with Contractor. The meeting agenda will include the following as a minimum:

Correspondence procedures

Designation of responsible personnel

Labor standards provisions

Payroll reports

Changes

Payments to Contractor

Subcontractors

Park rules and regulations

Accident prevention program (including name of responsible supervisor)

Accident reporting

Documents required under the contract

Recycling program

Saturday, Sunday, holiday and night work

Safety program (compliance with the "Accident Prevention “clause of the General Provisions)

Tentative construction schedule

Submittal of shop drawings, project data, and samples

Relationship of Division 1 to other divisions

1.2 SITE MEETING: At the conclusion of the preconstruction meeting, a site meeting will be held to review conditions at the site. Some of the issues to be discussed follow:

Materials staging area

Office Trailer location

Other contracted work in the area

END OF SECTION 01 31 00

FY21 Road Striping 01 33 23-1 Submittals

SECTION 01 33 23 SUBMITTAL PROCEDURES

PART 1: GENERAL

1.1 DESCRIPTION: The work of this section consists of submittal requirements before and during construction.

1.2 RELATED REQUIREMENTS: Closeout submittals - Section 01700.

1.3 PRODUCT DATA, AND SAMPLES:

1. General Procedures:

A. Coordinate all submittals and review them for legibility, accuracy, completeness, and compliance with contract requirements. Forward submittals that are related to or affect one another as a package to facilitate coordinated review.

B. List submittals on National Park Service form CM-16. Identify the front of each sheet or item with the submittal and item number.

C. Submittals will not be accepted for review if identification is missing an incorrect number of submittals are submitted, the transmittal form is incorrectly filled out, submittals are not coordinated, or submittals do not show evidence of Contractor's approval.

D. Contracting Officer reserves the right to require submittals in addition to those called for in individual sections.

2. Specific Procedures:

A. Samples: Samples shall be large enough to clearly illustrate the functional characteristics and full range of color, texture, or pattern.

B. Manufacturers' Literature: Submit only pertinent pages; mark each copy of standard printed data to identify products referenced in specification section.

3. Contracting Officer's Review:

A. After approving submittals, Contracting Officer will return one copy to the Contractor.

B. If submittals are not approved, Contracting Officer will return one copy to Contractor with reasons for rejection. Resubmit, identifying changes.

C. Any work done before approval shall be at Contractor's own risk.

1.6 SIMILAR PRODUCTS OR APPROVED EQUAL:

1. For each item proposed as a "similar product or approved equal," submit items required in each section and additional supporting data, including:

A. Drawings and samples as appropriate.

B. Comparison of the qualities of the proposed item with that specified.

C. Changes required in other elements of the work because of the substitution.

D. Name, address, and telephone number of vendor plus Manufacturer's literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.

2. No pre-bid approvals will be made. Any submittal of a "similar product" constitutes a representation that the Contractor:

A. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.

B. Will provide the same warranties for the proposed item as for the item specified.

FY21 Road Striping 01 33 23-2 Submittals

C. Has determined that the proposed item is compatible with interfacing items.

D. Will coordinate the installation of such item and make all changes required in other elements of the work because of such item.

E. Waives all claims for additional expenses that may be incurred as a result of the use of a "similar product".

3. New Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials.

END OF SECTION 01 33 23

TRANSMITTAL - NATIONAL PARK SERVICE Transmittal No.:

Sheet: 1 of:

Park:

Project:

Contract No.:

Pkg. No.:

Date:

Contractor:

Subcontractor/Supplier:

NPS ACTION

Specification Section No.

Description of Item (Size, Type, Name, Manufacturer, Use, Etc.)

Contractor Signature

Recommended by

Title, Date

Title

Date

I hereby certify that this submittal has been reviewed for accuracy, completeness, and compliance with contract requirements (FAR 52.236-21)

Review Comments

Action By

Date

Contracting Officer’s Representative

Approval of this submittal is subject to the provisions of the contract drawings and specifications. This action is for general concurrence only and the Government is not responsible for errors or omission.

SUBMITTAL LOG DATES: From contractor [__________], To reviewer [__________], From reviewer [__________], To Contractor [__________] Distribution: ( ) Contractor ( ) DSC File ( ) COR ( ) A/E ( ) DSC Interim ( ) COR Interim ( ) Contractor Interim CM-16Rev. 4/00 (Formerly DSC-1(CS)

TRANSMITTAL CONTINUATION - NATIONAL PARK SERVICE Transmittal No.:

Sheet: 1 of:

Park:

Project:

Contract No.:

Pkg. No.:

Date:

Contractor:

Subcontractor/Supplier:

NPS ACTION

Specification Section No.

Description of Item (Size, Type, Name, Manufacturer, Use, Etc.)

Review Comments

CM-16 Rev. 4/00 (Formerly DSC-1(CS)

FY21 Road Striping 01 35 23-1 Accident Prevention

Section 01 35 23 ACCIDENT PREVENTION

1.1 DESCRIPTION: The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.

1.2 SUBMITTALS:

1. Accident Prevention Program: Before on-site work begins, submit for approval an accident prevention program. The Contracting Officer will review the proposed program for compliance with OSHA and project requirements. If the program requires any revisions or corrections, the Contractor shall resubmit the program within 10 days. No progress payments will be processed until the program is approved. The program shall include:

A. Name of responsible supervisor to carry out the program.

B. Weekly and monthly safety meetings.

C. First aid procedures.

D. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.

E. Training, both initial and continuing.

F. Planning for possible emergency situations, such as floods, fires, cave-ins, slides, explosions, power outages, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.

G. Housekeeping: Section 01 56 00.

H. Fire Protection: Section 01 51 13.

2. Traffic Control Plan: Before on-site work begins, submit for approval a traffic control plan. The Contracting Officer will review the proposed program for compliance with OSHA and project requirements.

If the program requires any revisions or corrections, the Contractor shall resubmit the program within 10 days. No progress payments will be processed until the program is approved.

3. Submit a report of safety meetings and of inspections.

4. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.

1.3 QUALITY ASSURANCE:

1. Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the General Provisions.

In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project site. Failure to comply with the requirements of this section and related sections may result in suspension of work.

2. Qualifications of Employees:

A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.

B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

C. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment.

FY21 Road Striping 01 35 23-2 Accident Prevention

Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.

1.4 ACCIDENT REPORTING:

1. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Within 7 days of a reportable accident, fill out and forward to the Contracting Officer a DI-134 form, which may be obtained from Contracting Officer.

2. All Other Accidents: The Contractor shall report all other accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.

PART 2: PRODUCTS

2.1 FIRST AID FACILITIES: Provide adequate facilities for the number of employees and the type of construction at the site.

2.2 PERSONNEL PROTECTIVE EQUIPMENT: Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.

2.3 BARRIERS: Section 01 53 00.

PART 3: EXECUTION

3.1 EMERGENCY INSTRUCTIONS: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

3.2 ESCAPE ROUTES: Provide and maintain adequate escape routes at all times in accordance with the Life Safety Code (NFPA 101-91). No corridor, aisle, stairway, door, or exit shall be obstructed or used in a manner that interferes with escape routes.

3.3 PROTECTIVE EQUIPMENT:

1. Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.

2. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.

3.4 SAFETY MEETINGS:

1. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.

2. Conduct monthly safety meetings for all levels of supervision. Notify the Contracting Officer so that he may attend. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the accident prevention program. The Contracting Officer will enter the results of the meetings into his daily log.

3.5 HARD HATS AND PROTECTIVE EQUIPMENT AREAS:

1. A hard hat area will be designated by the Contracting Officer. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.

2. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times.

FY21 Road Striping 01 35 23-3 Accident Prevention

3.6 TRAINING:

1. First Aid: Provide adequate training to ensure prompt and efficient first aid.

2. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.

END OF SECTION 01 35 23

FY21 Road Striping 01 51 13-1 Temporary Services

SECTION 01 51 13 TEMPORARY SERVICES

1.1 DESCRIPTION: The work of this section consists of providing temporary services required for Contractor's performance of the work of this Contract.

PART 2: PRODUCTS

2.1 GENERAL: Temporary materials may be new or used but must be adequate in capacity for the required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.

2.2 FIRE PROTECTION EQUIPMENT: UL Class 2A, 2-1/2-gallon water type, stored-pressure extinguisher and UL Class 10, Type I, 15-pound B:C carbon dioxide extinguisher.

PART 3: EXECUTION

3.1 TELEPHONE:

1. No telephone service is available onsite for Contractor's use. The project sites does have cellular phone coverage.

3.2 WATER:

1. Potable water is not available at the site.

3.3 SANITARY FACILITIES:

1. Contractor shall provide temporary restroom facilities.

3.4 FIRE PREVENTION AND PROTECTION:

1. A capable and qualified person shall be placed in charge of fire protection. The responsibilities shall include locating and maintaining fire protective equipment and establishing and maintaining safe torch cutting and welding procedures.

2.Hazard Control: Take all necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids in buildings. Provide adequate ventilation during use of volatile or noxious substances.

3. Spark Arresters: Equip all gasoline or diesel-powered equipment used in potential forest or grass fire locations with spark arresters.

4. Locate internal combustion equipment so that exhausts discharge well away from combustible materials.

5. Locate service areas a minimum of 25 feet from buildings. Shut down equipment before refueling.

6. Smoking: Smoking on the construction site is prohibited.

3.5 PROTECTION EQUIPMENT REQUIRED:

1. Vehicles and Equipment: Provide one extinguisher on each vehicle or piece of equipment.

END OF SECTION 01 51 13

FY21 Road Striping 01 56 00-1 Temporary Controls

SECTION 01 56 00 TEMPORARY CONTROLS

PART 1: GENERAL

1.1 DESCRIPTION: The work of this section consists of providing temporary controls.

PART 2: PRODUCTS Not Used.

PART 3: EXECUTION

3.1 HOUSEKEEPING:

1. Keep project neat, orderly, and in a safe condition at all times.

2. Provide enough containers for collecting construction debris and construction materials to be recycled. Food storage and disposal must meet Park regulations.

3. The Contractor is encouraged to provide individually marked containers for recycling personal items, such as aluminum cans, newspapers, plastic, corrugated cardboard. These items may be recycled by the Contractor or turned over to the Park recycling committee. Demolished roof material shall be taken to local metal recycling.

4. Keep volatile wastes in covered containers.

5. Routine magnetic sweeps of the jobsite are encouraged, to minimize hazard to humans, animals and vehicles.

3.2 DISPOSAL:

1. Immediately remove hazardous rubbish from project site. Place other construction debris in refuse containers at least daily. Dispose of refuse at least weekly, in a legal manner, at public or private dumping areas outside the Park. Do not burn or bury refuse inside the Park.

3.3 AIR AND WATER POLLUTION CONTROL:

1. Take all necessary reasonable measures to reduce air and water pollution by any material or equipment used during construction.

2. Do not dispose of volatile wastes or oils in storm or sanitary drains.

3. Do not allow waste materials to be washed into streams or bodies of water.

END OF SECTION 01 56 00

FY21 Road Striping 01 59 00-1 Field Offices

SECTION 01 59 00 FIELD OFFICES AND SHEDS

PART 1: GENERAL

1.1 DESCRIPTION: The requirements of this section consist of furnishing, locating, and removing temporary structures, equipment, and furnishings.

1.2 RELATED REQUIREMENTS: Temporary services - Section 01 51 0.

PART 2: PRODUCTS

2.1 CONTRACTOR'S FIELD OFFICE: Contractor may provide an office for his own use. Size, location and construction shall be subject to approval of the Contracting Officer. The location for these temporary facilities will be decided at the site meeting.

PART 3: EXECUTION

3.1 STRUCTURES: Locate where directed by Contracting Officer, a minimum of 20 feet from permanent structures.

3.2 REMOVAL: Remove structures, equipment, and furnishings, and terminate services after punch list is 100 percent completed or when directed by Contracting Officer.

END OF SECTION 01 59 00

FY21 Road Striping 01 60 00-1 Materials and Equipment

SECTION 01 60 00 MATERIAL AND EQUIPMENT

PART 1: GENERAL

1.1 DESCRIPTION: The work of this section consists of the general procedures for handling, storing, and protecting material and equipment.

1.2 TRANSPORTATION AND HANDLING: Arrange deliveries of materials in accordance with construction schedules; coordinate to avoid conflict with work and conditions at the site. Deliver materials in undamaged condition, in manufacturer's original containers or packaging, with identifying labels intact and legible. Contractor is encouraged to obtain materials in biodegradable or recyclable/ reusable packaging which uses the minimum amount of packaging possible.

1.3 LOCATION: Materials and equipment to be used must be stored within the contract limit line, unless specifically approved by the Contracting Officer.

1.4 STORAGE AND PROTECTION: Store materials in accordance with manufacturer's instructions, with seals and labels accessible for inspection. Conform to specific requirements in individual sections in addition to those listed below.

1. Interior Storage: Maintain temperature and humidity within the ranges required by manufacturer's instructions.

2. Exterior Storage:

A. Store products subject to damage by the elements in weather tight enclosures.

B. Store fabricated products above the ground, on blocking or skids; prevent soiling or staining. Cover products subject to damage or deterioration with impervious sheet coverings; provide adequate ventilation to avoid condensation.

C. Store loose granular materials in a well-drained area on solid surfaces to prevent mixing with foreign matter.

3. Protection After Installation: Provide adequate coverings as necessary to protect installed materials from damage resulting from natural elements, traffic, and subsequent construction.

END OF SECTION 01 60 00

FY21 Road Striping 01 70 00-1 Project Closeout

SECTION 01 70 00 PROJECT CLOSEOUT

1.1 DESCRIPTION: The work of this section consists of final cleanup, closeout submittals, and final inspection procedures.

PART 2: PRODUCTS

2.1 CLEANING MATERIALS: As recommended by the manufacturer of surface to be cleaned.

PART 3: EXECUTION

3.1 CLEANING: Remove all tools, equipment, surplus materials, and rubbish. Restore or refinish surfaces of existing facilities that are marred, scratched, or damaged due to the work of this contract to match original condition. Remove grease, dirt, stains, foreign materials, and labels from interior and exterior finished surfaces. Sweep paved areas, rake grounds. At time of final inspection, project shall be thoroughly clean and ready for use.

3.2 CLOSEOUT SUBMITTALS: Submit before final inspection request.

1. Guarantees and Bonds: As specified in individual sections.

2. Spare Parts and Materials: As specified in individual sections.

3.3 SUBSTANTIAL COMPLETION AND FINAL INSPECTION: Submit written certification that project, or designated portion of project, is substantially complete, and request in writing a final inspection.

Contracting Officer will inspect within 10 days of receipt of request.

1. When Contracting Officer determines that Work is substantially complete, he will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion.

2. If Contracting Officer determines that the Work is not substantially complete, he will immediately notify Contractor in writing, stating reasons. After completing Work, Contractor shall resubmit certification and request a new final inspection.

3.4 ACCEPTANCE OF THE WORK: After all deficiencies have been corrected, a Letter of Acceptance will be issued.

3.5 POST-CONSTRUCTION INSPECTION: Before expiration of warranty period, Contracting Officer will inspect project and notify Contractor in writing of all deficiencies.

END OF SECTION 01 70 00

DIVISION 32

SITE WORK

FY21 Road Striping 32 17 23.13-1 Painted Pavement Markings

32 17 23.13 Pavement Markings (Painted)

1.1 DESCRIPTION: The requirements of this section consist of painted markings applied to pavement.

1.2 REFERENCES:

1. Whenever the words "Standard Specifications" are referred to, the reference is to the U.S.

Department of Transportation Federal Highway Administration Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-14).

2. Refer to FP-14 standard specifications, section 634 for pavement markings and section 718 for paint an d g lass bea d specifications.

3. Signing and striping to meet the requirements in the latest edition of the Manual on Uniform Traffic Control Devices (MUTCD).

PART 2: PRODUCTS

2.1 PAINT:

1. Pavement markings are Type B (Waterborne traffic paint with Type 1 Glass Beads).

2. Paint colors shall comply with the specifications listed in section 718.10 of the FHWA standard specifications (ASTM D1729).

3. Paint reflectance for both White and Yellow traffic paint shall adhere to ASTM E1347.

2.2 GLASS BEADS:

1. Conform to AASHTO M 247 for Type 1 Glass Beads. Treat glass beads with an adherence coating as recommended by the manufacturer.

2.3 PROHIBITED MATERIALS: Traffic paint shall not contain mercury, lead, chromium, diarylide pigments, toluene, chlorinated solvents, hydrolysable chlorine derivatives, ethylene-based glycol ethers and their acetates, nor any other EPA hazardous waste material over the regulatory levels per CFR 40 Part 261.24.

PART 3: EXECUTION

3.1 STRIPING AND MARKINGS

1. Painted pavement markings shall comply with FP-14 section 634.05

A. Apply paint when pavement and air temperatures at 50oF and rising. Refer to and follow manufacturer’s guidelines for application in other weather conditions, including high wind and relative humidity.

B. Do not heat paint above 120oF. Spray paint at a 15mil minimum wet film thickness or at a rate of 102 square feet per gallon.

C. Apply Type 1 glass beads on the paint at a rate of 6 to 8 pounds per gallon, per each coat of paint.

D. Apply two coats.

END OF SECTION 32 17 23.13

PART 1: GENERAL
1.1 DESCRIPTION:
1. The Work of this contract consists of the preparation and re-painting of approximately 347,000 linear feet of solid white fog line and approximately 347,000 linear feet of yellow centerline at three areas within Olympic National Park. Pavement m...
Work shall include:
A. Approximately 49,000 LNFT of solid white fog line and 49,000 LNFT solid yellow centerline on Mora Road.
B. Approximately 290,700 LNFT of solid white fog line and 290,700 LNFT solid yellow centerline on Sol Duc Valley Road.
C. Approximately 7,200 LNFT of solid white fog line and 7,200 LNFT solid yellow centerline on Lake Crescent Road.
D. Appropriate Traffic Control to complete the above work.
1.2 LOCATION:
A. Mora Road in Forks, WA 98331
B. Sol Duc Valley Road in Port Angeles, WA 98363
C. Lake Crescent Road in Port Angeles, WA 98362
1.3 CONTRACTOR'S USE OF PREMISES:
1. Construction Camp: Establishment of a camp within the Park and at this location will not be permitted.
2. Work Hours: Work hours are from 7:00am to 7:00pm Monday through Friday. Weekend work will normally not be allowed. Special requests may be made through the Contracting Officer.
3. Confine storage of materials to the area as indicated during the pre-construction meeting as part of this contract. Coordinate deliveries so that deliveries fit available storage area.
4. The following conditions shall be followed during the Contractor's work while in the Park:
A. To prevent unnatural attractants to bears, no foods, garbage, drinks, trash, or food and drink containers shall be placed outside trailers or buildings, except during actual use. Any mishandling of garbage, trash, foods, and other potential bear ...
B. Pets are prohibited.
C. Feeding of any wildlife is prohibited.
5. Preservation of Natural Features: Confine all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas, repair or replace damaged trees and plants (per direction by NPS arborists and horticulturis...
6. Vehicles/Heavy Equipment: Vehicles / Heavy Equipment:
A. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits. Failure to comply with traffic regulations will result in a citation being issued to the driver.
B. Vehicle Parking: The contractor shall park vehicles and heavy equipment in designated areas as shown on the Site Location Map or as established at the preconstruction meeting.
C. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles at all times.
D. Vehicle Exhaust: All vehicles will be properly maintained to ensure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as tho...
E. Spills: The Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. The Contractor must immed...
F. DOT Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to driver with appropriate license class, medical examiner card as appropriate with license class, carrying three (3) triangles or three (3) flar...
1.4 FIELD VERIFICATION: Field verify all new and existing dimensions and utilities affecting the work of this Contract before ordering products.
1.5 CONTRACTOR-FURNISHED ITEMS: All materials shall be Contractor-furnished from outside the Park.
PART 2: PRODUCTS Not used.
PART 3: EXECUTION Not used.
PART 1 GENERAL
1.1 DESCRIPTION
1. The work of this bid item consists of the preparation and re-painting of approximately 346,900 LNFT of white fog line in three areas of Olympic National Park and 346,900 LNFT of yellow centerline, including Type 1 glass beads applied to top coat . ...
2. If no bid item exists for a portion of the work, include the costs in a related line item.
3. Quantities are estimates only. Vendor will invoice for actual amounts of LNFT painted.
PART 2: PRODUCTS Not used.
PART 3: EXECUTION Not used.
PART 1: GENERAL
1.1 PRE-CONSTRUCTION CONFERENCE: Before start of construction, Contracting Officer will arrange a meeting at Headquarters and an onsite meeting with Contractor. The meeting agenda will include the following as a minimum:
1.2 SITE MEETING: At the conclusion of the preconstruction meeting, a site meeting will be held to review conditions at the site. Some of the issues to be discussed follow:
PART 2: PRODUCTS Not used.
PART 3: EXECUTION Not used.
PART 1: GENERAL
1.1 DESCRIPTION: The work of this section consists of submittal requirements before and during construction.
1.2 RELATED REQUIREMENTS: Closeout submittals - Section 01700.
1.3 PRODUCT DATA, AND SAMPLES:
1. General Procedures:
A. Coordinate all submittals and review them for legibility, accuracy, completeness, and compliance with contract requirements. Forward submittals that are related to or affect one another as a package to facilitate coordinated review.
B. List submittals on National Park Service form CM-16. Identify the front of each sheet or item with the submittal and item number.
C. Submittals will not be accepted for review if identification is missing an incorrect number of submittals are submitted, the transmittal form is incorrectly filled out, submittals are not coordinated, or submittals do not show evidence of Cont...
D. Contracting Officer reserves the right to require submittals in addition to those called for in individual sections.
2. Specific Procedures:
A. Samples: Samples shall be large enough to clearly illustrate the functional characteristics and full range of color, texture, or pattern.
B. Manufacturers' Literature: Submit only pertinent pages; mark each copy of standard printed data to identify products referenced in specification section.
3. Contracting Officer's Review:
A. After approving submittals, Contracting Officer will return one copy to the Contractor.
B. If submittals are not approved, Contracting Officer will return one copy to Contractor with reasons for rejection. Resubmit, identifying changes.
C. Any work done before approval shall be at Contractor's own risk.
1.6 SIMILAR PRODUCTS OR APPROVED EQUAL:
1. For each item proposed as a "similar product or approved equal," submit items required in each section and additional supporting data, including:
A. Drawings and samples as appropriate.
B. Comparison of the qualities of the proposed item with that specified.
C. Changes required in other elements of the work because of the substitution.
D. Name, address, and telephone number of vendor plus Manufacturer's literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.
2. No pre-bid approvals will be made. Any submittal of a "similar product" constitutes a representation that the Contractor:
A. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
B. Will provide the same warranties for the proposed item as for the item specified.
C. Has determined that the proposed item is compatible with interfacing items.
D. Will coordinate the installation of such item and make all changes required in other elements of the work because of such item.
E. Waives all claims for additional expenses that may be incurred as a result of the use of a "similar product".
3. New Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials.
PART 2: PRODUCTS Not used.
PART 3: EXECUTION Not used.
PART 1: GENERAL
1.1 DESCRIPTION: The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.
1.2 SUBMITTALS:
1. Accident Prevention Program: Before on-site work begins, submit for approval an accident prevention program. The Contracting Officer will review the proposed program for compliance with OSHA and project requirements. If the program requires any ...
A. Name of responsible supervisor to carry out the program.
B. Weekly and monthly safety meetings.
C. First aid procedures.
D. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work incl...
E. Training, both initial and continuing.
F. Planning for possible emergency situations, such as floods, fires, cave-ins, slides, explosions, power outages, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of pe...
G. Housekeeping: Section 01 56 00.
H. Fire Protection: Section 01 51 13.
2. Traffic Control Plan: Before on-site work begins, submit for approval a traffic control plan. The Contracting Officer will review the proposed program for compliance with OSHA and project requirements. If the program requires any revisions or cor...
3. Submit a report of safety meetings and of inspections.
4. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.
1.3 QUALITY ASSURANCE:
1. Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the General Provisions. In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not mee...
2. Qualifications of Employees:
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
C. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all...
1.4 ACCIDENT REPORTING:
1. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Within 7 days of a reportable accident, fill out and forw...
2. All Other Accidents: The Contractor shall report all other accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
PART 2: PRODUCTS
2.1 FIRST AID FACILITIES: Provide adequate facilities for the number of employees and the type of construction at the site.
2.2 PERSONNEL PROTECTIVE EQUIPMENT: Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.
2.3 BARRIERS: Section 01 53 00.
PART 3: EXECUTION
3.1 EMERGENCY INSTRUCTIONS: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
3.2 ESCAPE ROUTES: Provide and maintain adequate escape routes at all times in accordance with the Life Safety Code (NFPA 101-91). No corridor, aisle, stairway, door, or exit shall be obstructed or used in a manner that interferes with escape routes.
3.3 PROTECTIVE EQUIPMENT:
1. Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
2. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
3.4 SAFETY MEETINGS:
1. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.
2. Conduct monthly safety meetings for all levels of supervision. Notify the Contracting Officer so that he may attend. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety ...
3.5 HARD HATS AND PROTECTIVE EQUIPMENT AREAS:
1. A hard hat area will be designated by the Contracting Officer. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
2. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times.
3.6 TRAINING:
1. First Aid: Provide adequate training to ensure prompt and efficient first aid.
2. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or othe...
PART 1: GENERAL
1.1 DESCRIPTION: The work of this section consists of providing temporary services required for Contractor's performance of the work of this Contract.
PART 2: PRODUCTS
2.1 GENERAL: Temporary materials may be new or used but must be adequate in capacity for the required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.
2.2 FIRE PROTECTION EQUIPMENT: UL Class 2A, 2-1/2-gallon water type, stored-pressure extinguisher and UL Class 10, Type I, 15-pound B:C carbon dioxide extinguisher.
PART 3: EXECUTION
3.1 TELEPHONE:
1. No telephone service is available onsite for Contractor's use. The project sites does have cellular phone coverage.
3.2 WATER:
1. Potable water is not available at the site.
3.3 SANITARY FACILITIES:
1. Contractor shall provide temporary restroom facilities.
3.4 FIRE PREVENTION AND PROTECTION:
1. A capable and qualified person shall be placed in charge of fire protection. The responsibilities shall include locating and maintaining fire protective equipment and establishing and maintaining safe torch cutting and welding procedures.
2. Hazard Control: Take all necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids in buildings. Provide adequate ventilation during use of volatile or noxious substances.
3. Spark Arresters: Equip all gasoline or diesel-powered equipment used in potential forest or grass fire locations with spark arresters.
4. Locate internal combustion equipment so that exhausts discharge well away from combustible materials.
5. Locate service areas a minimum of 25 feet from buildings. Shut down equipment before refueling.
6. Smoking: Smoking on the construction site is prohibited.
3.5 PROTECTION EQUIPMENT REQUIRED:
1. Vehicles and Equipment: Provide one extinguisher on each vehicle or piece of equipment.
PART 1: GENERAL
1.1 DESCRIPTION: The work of this section consists of providing temporary controls.
PART 2: PRODUCTS Not Used.
PART 3: EXECUTION
3.1 HOUSEKEEPING:
1. Keep project neat, orderly, and in a safe condition at all times.
2. Provide enough containers for collecting construction debris and construction materials to be recycled. Food storage and disposal must meet Park regulations.
3. The Contractor is encouraged to provide individually marked containers for recycling personal items, such as aluminum cans, newspapers, plastic, corrugated cardboard. These items may be recycled by the Contractor or turned over to the Park recycli...
4. Keep volatile wastes in covered containers.
5. Routine magnetic sweeps of the jobsite are encouraged, to minimize hazard to humans, animals and vehicles.
3.2 DISPOSAL:
1. Immediately remove hazardous rubbish from project site. Place other construction debris in refuse containers at least daily. Dispose of refuse at least weekly, in a legal manner, at public or private dumping areas outside the Park. Do not burn o...
3.3 AIR AND WATER POLLUTION CONTROL:
1. Take all necessary reasonable measures to reduce air and water pollution by any material or equipment used during construction.
2. Do not dispose of volatile wastes or oils in storm or sanitary drains.
3. Do not allow waste materials to be washed into streams or bodies of water.
PART 1: GENERAL
1.1 DESCRIPTION: The requirements of this section consist of furnishing, locating, and removing temporary structures, equipment, and furnishings.
1.2 RELATED REQUIREMENTS: Temporary services - Section 01 51 0.
PART 2: PRODUCTS
2.1 CONTRACTOR'S FIELD OFFICE: Contractor may provide an office for his own use. Size, location and construction shall be subject to approval of the Contracting Officer. The location for these temporary facilities will be decided at the site meeting.
PART 3: EXECUTION
3.1 STRUCTURES: Locate where directed by Contracting Officer, a minimum of 20 feet from permanent structures.
3.2 REMOVAL: Remove structures, equipment, and furnishings, and terminate services after punch list is 100 percent completed or when directed by Contracting Officer.
PART 1: GENERAL
1.1 DESCRIPTION: The work of this section consists of the general procedures for handling, storing, and protecting material and equipment.
1.2 TRANSPORTATION AND HANDLING: Arrange deliveries of materials in accordance with construction schedules; coordinate to avoid conflict with work and conditions at the site. Deliver materials in undamaged condition, in manufacturer's original cont...
1.3 LOCATION: Materials and equipment to be used must be stored within the contract limit line, unless specifically approved by the Contracting Officer.
1.4 STORAGE AND PROTECTION: Store materials in accordance with manufacturer's instructions, with seals and labels accessible for inspection. Conform to specific requirements in individual sections in addition to those listed below.
1. Interior Storage: Maintain temperature and humidity within the ranges required by manufacturer's instructions.
2. Exterior Storage:
A. Store products subject to damage by the elements in weather tight enclosures.
B. Store fabricated products above the ground, on blocking or skids; prevent soiling or staining. Cover products subject to damage or deterioration with impervious sheet coverings; provide adequate ventilation to avoid condensation.
C. Store loose granular materials in a well-drained area on solid surfaces to prevent mixing with foreign matter.
3. Protection After Installation: Provide adequate coverings as necessary to protect installed materials from damage resulting from natural elements, traffic, and subsequent construction.
PART 2: PRODUCTS Not used.
PART 3: EXECUTION Not used.
PART 1: GENERAL
1.1 DESCRIPTION: The work of this section consists of final cleanup, closeout submittals, and final inspection procedures.
PART 2: PRODUCTS
2.1 CLEANING MATERIALS: As recommended by the manufacturer of surface to be cleaned.
PART 3: EXECUTION
3.1 CLEANING: Remove all tools, equipment, surplus materials, and rubbish. Restore or refinish surfaces of existing facilities that are marred, scratched, or damaged due to the work of this contract to match original condition. Remove grease, dirt...
3.2 CLOSEOUT SUBMITTALS: Submit before final inspection request.
1. Guarantees and Bonds: As specified in individual sections.
2. Spare Parts and Materials: As specified in individual sections.
3.3 SUBSTANTIAL COMPLETION AND FINAL INSPECTION: Submit written certification that project, or designated portion of project, is substantially complete, and request in writing a final inspection. Contracting Officer will inspect within 10 days of r...
1. When Contracting Officer determines that Work is substantially complete, he will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion.
2. If Contracting Officer determines that the Work is not substantially complete, he will immediately notify Contractor in writing, stating reasons. After completing Work, Contractor shall resubmit certification and request a new final inspection.
3.4 ACCEPTANCE OF THE WORK: After all deficiencies have been corrected, a Letter of Acceptance will be issued.
3.5 POST-CONSTRUCTION INSPECTION: Before expiration of warranty period, Contracting Officer will inspect project and notify Contractor in writing of all deficiencies.
32 17 23.13 Pavement Markings (Painted)
PART 1: GENERAL
1.1 DESCRIPTION: The requirements of this section consist of painted markings applied to pavement.
PART 2: PRODUCTS
2.1 PAINT:
1. Pavement markings are Type B (Waterborne traffic paint with Type 1 Glass Beads).
2. Paint colors shall comply with the specifications listed in section 718.10 of the FHWA standard specifications (ASTM D1729).
3. Paint reflectance for both White and Yellow traffic paint shall adhere to ASTM E1347.
2.2 GLASS BEADS:
1. Conform to AASHTO M 247 for Type 1 Glass Beads. Treat glass beads with an adherence coating as recommended by the manufacturer.

2.3 PROHIBITED MATERIALS: Traffic paint shall not contain mercury, lead, chromium, diarylide pigments, toluene, chlorinated solvents, hydrolysable chlorine derivatives, ethylene-based glycol ethers and their acetates, nor any other EPA hazardous was...

PART 3: EXECUTION
1. Painted pavement markings shall comply with FP-14 section 634.05