This is a Description/Specifications/Statement of Work for the Sawtooth National Recreation Area Admin Site Window & Door Replacements Project. The project involves replacing existing windows, exterior entry doors, sliding glass patio doors, and overhead garage doors on various housing units and a warehouse building at two administrative sites: the North Fork Administrative site north of Ketchum, Idaho, and the Stanley Ranger Station Administrative site south of Stanley, Idaho. New windows and sliding glass patio doors must be fiberglass-framed, exterior entry doors must be fiberglass, and overhead garage doors must be steel. The estimated price range is $150,000 to $250,000 with an anticipated end date of September 30, 2026. Work is limited to 7:00 a.m. to 7:00 p.m. Monday through Saturday. The contractor must submit a site plan for staging areas, field offices, parking, and storage for approval at least 15 days prior to construction and must limit disturbance to one building at a time, ensuring buildings are not left exposed to weather for more than one day.
The contractor is responsible for maintaining occupied housing units with minimal public inconvenience, providing adequate safety signage and barricades, managing parking to preserve tenant access, and providing port-a-potties for all construction personnel while keeping restroom facilities off-limits. Electrical service and water via exterior hose bibbs are available for construction use. The contractor must establish and maintain waste disposal containers, picking up debris daily and emptying containers weekly. Overnight camping onsite is prohibited, and burning or burying construction waste is not permitted. Specifications include sections on measurement and payment, submittal procedures, quality control, selective demolition, waste material disposal, rough carpentry, interior finish carpentry, joint sealants, fiberglass sliding doors, fiberglass entry doors, sectional doors, and fiberglass windows. The document was issued in January 2026.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
Sawtooth National Recreation Area Admin Site Window & Door Replacements Project
Project Description:
This project will replace existing windows, exterior entry doors, sliding glass patio doors, and overhead garage doors on various housing units and a warehouse building, as identified on the Plans. New windows and sliding glass patio doors shall be fiberglass-framed, exterior entry doors shall be fiberglass, and overhead garage doors shall be steel.
Project Location:
This project will occur on two administrative sites, one being the North Fork Administrative site located just north of Ketchum, Idaho, and the other being the Stanley Ranger Station Administrative site located just south of Stanley, Idaho. Northing and Easting coordinate locations are provided for reference on the Plans for the Sawtooth National Recreation Area Headquarters building and for the Stanley Ranger Station building.
Field Offices, Work Camps, Staging and Storage Areas:
Contractor shall submit a site plan showing proposed staging areas, access and parking locations, locations for field offices (if needed), staging of work trailers, and storage areas for review and approval by the CO a minimum of 15 days prior to construction.
Overnight camping onsite will not be allowed.
Site Information and Limitations:
The work shall be completed so that disturbance is limited to one building at a time or sequenced so that buildings are not left exposed to the weather for more than a day. Contractor shall take all necessary precautions to protect building elements and finishes from damage from precipitation during work.
Housing units will be occupied by tenants during the project construction. Contractor shall at all times conduct operations to ensure the least inconvenience to the public.
Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Contractor shall minimize disturbance of all undisturbed areas.
Contractor shall also use care to only park in locations as approved by the CO to ensure tenant parking is maintained throughout the project.
Electrical service exists for each housing unit. Contractors may use existing electrical service during construction if it doesn’t interfere with tenant use of the facility. Contractor shall provide connections and extensions of services as required for construction operations. Water service is also available for use at each building site via exterior hose bibbs. Restroom and sink facilities are off limits to the Contractor’s personnel. Contractor shall provide port-a-potties for use by all construction personnel.
Allowable Construction Hours – 7:00 a.m. to 7:00 p.m. Monday through Saturday for all work activities.
Waste Management and Disposal:
Contractor shall provide and maintain appropriate waste disposal containers or bins at the project site for the duration of the project construction. Waste material and debris shall be picked up and deposited in the waste disposal bins daily. Containers must be emptied on a weekly basis unless more frequent emptying is needed. Burning or burying of construction waste material on site will not be permitted.
Anticipated End Date:
September 30, 2026
Estimated Price Range:
$150,000 - $250,000
Specifications:
The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to or are included in payment for other pay items in this contract. These items are considered incidental, and no additional compensation will be made.
Section 011250 – Measurement and Payment Section 013300 – Submittal Procedures Section 014100 – Quality Control Section 017320 – Selective Demolition Section 024100 – Waste Material Disposal Section 061000 – Rough Carpentry Section 062023 – Interior Finish Carpentry Section 079200 – Joint Sealants Section 081816 – Fiberglass Sliding Doors Section 081423 – Fiberglass Entry Doors Section 083613 – Sectional Doors Section 085413 – Fiberglass Windows
END OF SECTION C
January 2026
| Electrical service exists for each housing unit. Contractors may use existing electrical service during construction if it doesn’t interfere with tenant use of the facility. Contractor shall provide connections and extensions of services as required... |
| Allowable Construction Hours – 7:00 a.m. to 7:00 p.m. Monday through Saturday for all work activities. |