Attachment A SOW.pdf
PDF 2 MB Posted
- Attached to
- Windsor Township EWP - USDA-NRCS-Ohio Federal contract opportunity
- Solicitation number
- 12FPC325B0004
About this file
This document is a set of construction specifications for a federal contract opportunity with the USDA Natural Resources Conservation Service (NRCS) for an Emergency Watershed Protection (EWP) project in Windsor Township, Morgan County, Ohio. The specifications cover multiple construction activities including pollution control, seeding and mulching, mobilization and demobilization, traffic control, water removal, excavation, earthfill, drainfill, rock riprap installation, and gabion basket placement.
The project requires detailed quality control, with specifications for material sourcing, placement techniques, and testing. Key materials include limestone rock riprap (Type C), woven wire gabion baskets, and crushed limestone drainfill. The contractor must follow strict guidelines for material preparation, placement, compaction, and testing, with specific requirements for rock size, gradation, and durability. Measurement and payment will be made based on various methods including unit prices and lump sum pricing, with most subsidiary items included in the mobilization and demobilization bid item.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_12FPC325B0004 -rev1.pdf | ||
| Windsor Twp ECP Site Showing Notes 7-17-25.pdf | ||
| Windsor Sign In - Site Showing Attendees.pdf | ||
| Sol_12FPC325B0004.pdf | ||
| Sol_12FPC325B0004.pdf | ||
| Attachment C - maps-charts.pdf | ||
| Attachment B -WD 2015-4765.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INDEX OF CONSTRUCTION AND MATERIAL SPECIFICATIONS
SPEC
NO.
CONSTRUCTION
SPECIFICATION
SPEC
NO.
MATERIAL
SPECIFICATION
521 Aggregates for Drainfill and Filters
6 Seeding, Sprigging and Mulching 523 Rock for Riprap
8 Mobilization and Demobilization
9 Traffic Control
11 Removal of Water
21 Excavation
23 Earthfill
24 Drainfill
61 Rock Riprap
94 Contractor Quality Control
Gabions and Gabion Mattresses
NRCS-10/2024
OH-EWP-WINDSOR TOWNSHIP
Pollution Control
This page intentionally left blank
210 H 642 CS 5 (June 2024) 1
Construction Specification 5 — Pollution Control Title 210 – Engineering Part 642 – Specifications for Construction Contracts Subpart B – National Construction Specifications June 2024
A. Scope
1. The work consists of installing measures or performing work to control erosion and minimize the production of sediment and other pollutants to water and air from construction activities.
2. The following BioPreferred® product categories are applicable to this specification:
a. Mulch and compost materials
b. Erosion control materials
c. Fertilizers
d. Dust suppressants
e. Agricultural spray adjuvants
B. Material
1. Silt fence conform to the requirement of Materials Specification 592, Geotextile.
All other material furnished meet the requirements of the material specifications listed in Section G of this specification.
2. Erosion and Sediment Control Measures and Works. The measures and works includes, but are not limited to, the following:
a. Staging of Earthwork Activities. Scheduling the excavation and moving of soil materials to minimize the size of areas disturbed and unprotected from erosion for the shortest reasonable time.
b. Seeding. Seeding to protect disturbed areas occur as soon as reasonably possible following completion of that earthwork activity.
c. Mulching. Mulching to provide temporary protection of the soil surface from erosion.
d. Diversions. Diversions to divert water from work areas and to collect water from work areas for treatment and safe disposition. These are temporary and must be removed and the area restored to its near-original condition when the diversions are no longer required or when permanent measures are installed.
e. Stream Crossings. Culverts or bridges where equipment must cross streams.
These are temporary must and be removed and the area restored to its near-original condition when the crossings are no longer required or when permanent measures are installed.
f. Sediment Basins. Sediment basins for collecting, settling, and eliminating sediment from eroding areas that impact properties and streams below the
210 H 642 CS 5 (June 2024) 2 construction sites. These basins are temporary and must be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
g. Sediment Filters. Straw bale filters or geotextile sediment fences for trapping sediment from areas with limited runoff. Sediment filters must be properly anchored to prevent erosion under or around them. Silt fences must be installed and maintained in accordance with ASTM D6462. These filters are temporary and must be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
h. Waterways. Waterways for the safe disposal of runoff from fields, diversions, and other structures or measures. These works are temporary and must be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
i. Other. Additional protection measures as specified in Section G of this specification or required by the federal, state, or local government.
C. Chemical Pollution
1. The contractor must provide watertight tanks or barrels or construct a sump sealed with plastic sheets to collect and temporarily contain chemical pollutants, such as drained lubricating or transmission fluids, grease, soaps, concrete mixer wash water, or asphalt, produced as a by-product from the construction activities.
Dispose of pollutants in accordance with appropriate state and federal regulations.
At the completion of the construction work, remove tanks, barrels, and sumps and restore the area to its original condition as specified in Section H of this specification. Sump removal must be conducted without causing pollution.
2. Sanitary facilities, such as chemical toilets, and septic tanks must not be located next to live streams, wells, or springs. They must be located at a distance sufficient to prevent contamination of any water source. At the completion of construction activities, facilities must be disposed of without causing pollution as specified in Section H of this specification.
D. Air Pollution
1. The burning of brush or slash and the disposal of other materials must adhere to state and local regulations.
2. Fire prevention measures must be taken to prevent the start or spreading of wildfires that may result from project activities. Firebreaks or guards must be constructed and maintained at locations shown on the drawings.
3. All public access or haul roads used by the contractor during construction of the project must be sprinkled or otherwise treated to fully suppress dust. All dust control methods must ensure safe construction operations at all times. If chemical dust suppressants are applied, the material must be a commercially available product specifically designed for dust suppression, and the application must follow the manufacturer’s requirements and recommendations. A copy of the product data sheet and manufacturer’s recommended application procedures must be provided to the engineer 5 working days before the first application.
210 H 642 CS 5 (June 2024) 3
E. Maintenance, Removal, and Restoration
1. All pollution-control measures and temporary works must be adequately maintained in a functional condition for the duration of the construction period.
Remove all temporary measures and restore the site to near-original condition.
F. Measurement and Payment
1. Method 1. For items of work for which specific unit prices are established in the contract, each item is measured to the nearest unit applicable. Payment for each item is made at the contract unit price for that item. For water or chemical suppressant items used for dust control for which items of work are established in Section H of this specification, measurement for payment will not include water or chemical suppressants that are used inappropriately or excessively. Such payment will constitute full compensation for the completion of the work.
2. Method 2. For items of work for which lump-sum prices are established in the contract, payment is made as the work proceeds and is supported by invoices presented by the contractor that reflect actual costs. If the total of all progress payments is less than the lump-sum contract price for this item, the balance remaining for this item will be included in the final contract payment. Payment of the lump-sum contract price will constitute full compensation for completion of the work.
3. Method 3. For items of work for which lump-sum prices are established in the contract, payment will be prorated and provided in equal amounts on each monthly progress payment estimate. The number of months used for prorating must be the number estimated to complete the work as outlined in the contractor’s approved construction schedule. The final month’s prorate amount will be provided with the final contract payment. Payment as described will constitute full compensation for completion of the work.
4. All Methods. The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items, and the items to which they are made subsidiary, are identified in Section H of this specification.
G. Items of Work and Construction Details Items of work to be performed in conformance with this specification and the construction details therefore are:
Subsidiary Item - Pollution Control
1. The Contractor is required to provide the Contracting Officer's Representative with a written Pollution Control Plan of Operations for this project.
2. The Contractor shall perform the work of this project in a manner consistent and in conformance with Federal, State, or Local Government regulations, to protect the site and downstream areas from degradation.
3. Method of Payment Section F Measurement and Payment does not apply. No separate payment will be made for Pollution Control. Compensation for this item will be included in the payment for Bid Item 1 - Mobilization and Demobilization.
NRCS-10/2024
210 H 642 CS 6 (June 2024) 1
Construction Specification 6 — Seeding, Sprigging, and Mulching
Title 210 - Engineering Part 642 – Specifications for Construction Contracts Subpart B – National Construction Specifications June 2024
A. Scope
1. The work consists of preparing the area for treatment; furnishing and placing seed, sprigs, mulch, fertilizer, inoculant, lime, and other soil amendments; and anchoring mulch in designated areas as specified.
2. The following BioPreferred® product categories are applicable to this specification:
a. Mulch and compost materials
b. Erosion control materials
c. Fertilizers
d. Agricultural spray adjuvants
B. Material
1. Seed.
a. All seed must conform to the current rules and regulations of the state where it is being used and must be from the latest crop available. It must meet or exceed the standard for purity and germination listed in Section G.
b. Seed must be labeled in accordance with the state laws and the U.S.
Department of Agriculture rules and regulations under the Federal Seed Act in effect on the date of invitations for bids. Bag tag figures are evidence of purity and germination. No seed will be accepted with a test date of more than 9 months before the delivery date to the site.
c. Seed that has become wet, moldy, or otherwise damaged in transit or storage will not be accepted. The percent of noxious weed seed allowable must be as defined in the current state laws relating to agricultural seeds. Each type of seed must be delivered in separate sealed containers and fully tagged unless an exception is granted in writing by the contracting officer.
2. Fertilizer. Unless otherwise specified, the fertilizer must be a commercial-grade fertilizer. It must meet the standard for grade and quality specified by state law.
Where fertilizer is furnished from bulk storage, the contractor must furnish a supplier’s certification of analysis and weight. When required by the contract, a representative sample of the fertilizer must be furnished to the contracting officer for chemical analysis.
210 H 642 CS 6 (June 2024) 2
3. Inoculants. The inoculant for treating legume seeds must be a pure culture of nitrogen-fixing bacteria prepared specifically for the species and must not be used later than the date indicated on the container or as otherwise specified. A mixing medium, as recommended by the manufacturer, must be used to bond the inoculant to the seed. Two times the amount of the inoculant recommended by the manufacturer must be used (unless seed is applied using a hydraulic seeder; then four times the amount must be used). Seed must be sown within 24 hours of treatment and must not remain in the hydraulic seeder longer than 4 hours.
4. Lime and Other Soil Amendments. Lime must consist of standard ground agriculture limestone or approved equivalent. Standard ground agriculture limestone is defined as ground limestone meeting current requirements of the state’s Department of Agriculture. Other soil amendments must meet quality criteria and application requirements specified in Section G.
5. Mulch Tackifiers. Asphalt emulsion tackifiers must conform to the requirements of ASTM D977, Specification for Emulsified Asphalt. The emulsified asphalt may be rapid setting, medium setting, or slow setting. Non-asphaltic tackifiers required because of environmental considerations must be as specified in Section G.
6. Straw Mulch Material. Straw mulch must consist of wheat, barley, oat or rye straw, hay, grass cut from native grasses, or other plants as specified in Section G.
The mulch material must be air-dried reasonably light in color and must not be musty, moldy, caked, or otherwise of low quality. The use of mulch that contains noxious weeds is not permitted. The contractor must provide a method satisfactory to the contracting officer for determining weight of mulch furnished.
7. Other Mulch Materials. Mulching materials, such as wood cellulose fiber mulch, mulch tackifiers, synthetic fiber mulch, netting, and mesh may be required for specialized locations and conditions. These materials, when specified, must be accompanied by the manufacturer’s recommendations for methods of application.
C. Seeding Mixtures, Sod, Sprigs, and Dates of Planting
1. The application rate per acre for seed mixtures, sprigs, or sod and the date of seeding or planting must be as shown on the plans or as specified in Section G.
D. Seedbed Preparation and Treatment
1. Dress areas to be treated to a smooth, firm surface. On sites where equipment can operate on slopes safely, adequately loosen and smooth the seedbed (4 to 6 inches deep). Depending on soil and moisture conditions, disking, cultipacking, or both, may be necessary to properly prepare a seedbed. Where equipment cannot operate safely, prepare the seedbed by methods like scarifying, providing a roughened soil surface by hand so that broadcast seed will remain in place.
2. If seeding is to be accomplished immediately following construction operations, seedbed preparation may not be required except on a compacted, polished, or freshly cut soil surface.
210 H 642 CS 6 (June 2024) 3
3. Rocks larger than 6 inches in diameter, trash, weeds, and other debris that will interfere with seeding or maintenance operations must be removed or disposed of as specified in Section G.
4. Discontinue seedbed preparation when soil moisture conditions are not suitable for the preparation of a satisfactory seedbed as determined by the responsible engineer.
E. Seeding, Sprigging, Fertilizing, Mulching, and Stabilizing
1. Perform all seeding or sprigging operations in such a manner that the seed or sprigs are applied in the specified quantities uniformly in the designated areas.
The method and rate of seed application must be as specified in Section G. Unless otherwise specified, seeding or sprigging must be accomplished within 2 days after final grading is completed and approved.
2. Apply fertilizer, lime, and other soil amendments as specified in Section G. When specified, the fertilizer and soil amendments must be thoroughly incorporated into the soil immediately following surface application.
3. The rate, amount, and kind of mulching or mesh must be as specified in Section G. Apply mulches uniformly to the designated areas. They must be applied to areas seeded not later than 2 working days after seeding has been performed.
Stabilize straw mulch material within 24 hours of application using a mulch crimper or equivalent anchoring tool or by a suitable tackifier. When the mulch crimper or equivalent anchoring tool is used, it must have straight blades and be the type manufactured expressly for and capable of firmly punching the mulch into the soil. Where the equipment can be safely operated, it must be operated on the contour. Use hand methods where equipment cannot safely operate to perform the work required.
4. Apply the tackifier uniformly over the mulch material at the specified rate or inject it into the mulch material as it is being applied. Stabilizing materials like mesh or netting must be applied smoothly but loosely on the designated areas.
The edges of these materials must be buried or securely anchored using spikes or staples as specified in Section G.
5. The contractor must maintain the mesh or netting areas until all work under the contract has been completed and accepted. Maintenance must consist of the repair of areas damaged by water erosion, wind, fire, or other causes. Such areas must be repaired to reestablish the intended condition and to the design lines and grades required by the contract. The areas must be re-fertilized, reseeded, and re-mulched before the new application of the mesh or netting.
F. Measurement and Payment
1. Method 1. For items of work for which specific unit prices are established in the contract, each area treated is measured as specified in Section G and area is calculated to the nearest 0.1 acre. Payment for treatment is made at the contract unit price for the designated treatment, which will constitute full compensation for completion of the work.
210 H 642 CS 6 (June 2024) 4
a. When specified as an item of work, mesh or netting is measured to the nearest square yard of surface area covered and accepted. Payment is made at the contract unit price and will constitute full compensation for completion of the work.
2. Method 2. For items of work for which specific lump-sum prices are established in the contract, the quantity of work will not be measured for payment. Payment for this item is made at the contract lump-sum price for the item and will constitute full compensation for the completion of the work.
3. Method 3. For items of work for which lump-sum prices are established in the contract, payment is made as the work proceeds. Progress payments will be determined as specified in Section G. Payment of the lump-sum contract price will constitute full compensation for completion of the work.
4. All Methods. The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in Section G.
Items of work to be performed in conformance with this specification and the construction details therefore are:
Subsidiary Item – Seeding, Sprigging and Mulching This item shall include seeding and mulching of all disturbed areas within the construction limits as shown and described in the drawings.
1. Fertilizer All areas shall have fertilizer uniformly applied at the following rates:
• Nitrogen (N) - 150 pounds per acre
• Phosphorus P2O5 - 150 pounds per acre
• Potassium K2O - 150 pounds per acre
This specification can be met by applying fertilizer having an analysis of 15-15-15 at the rate of 1000 pounds per acre or 23 pounds per thousand square feet.
2. Seed All seed shall be labeled, tagged or marked in accordance with Section 907.03 of the Revised Code of Ohio. Seed tags showing germination and purity shall be attached to all bags. No pre-mixed seed shall be used unless the following conditions are met:
a. The weight, purity, and germination for each kind of seed is specified on the tag for each lot of seed. Seeding rates shall be adjusted for Pure Live Seed (PLS) at the time of seeding. Pure Seed (PLS) = percent germination. Seed shall have the equivalent of a minimum of 80% pure live seed.
When the percent purity multiplied by the percent germination gives a percentage less than 80, the rate of seeding will be increased to provide a minimum PLS of 80.
b. Seeding mixtures and rates per acre:
All areas -
Kentucky 31 Tall Fescue -60 lbs per acre or 1.5 lbs per 1000 square ft.
Annual Ryegrass -10 lbs per acre or 0.25 lbs per 1000 square ft.
3. Seedbed Preparation Seedbed preparation shall be completed within 48 hours after application of fertilizer. All areas accessible to equipment shall be disked to incorporate fertilizer and to prepare a seedbed a minimum of three inches deep. The final seedbed preparation operation shall be performed across the slope and immediately prior to seeding. Suitable equipment shall be used to smooth the seedbed prior to seeding.
On areas inaccessible to a disk, a one-inch minimum seedbed will be prepared using suitable tillage tools or hand tools. All rocks greater than 3 inches in size shall be removed.
4. Sowing the Seed Seeding shall be completed as soon as practical after final grading. Broadcast the seed and cover approximately 1/4-inch deep with a light harrow, culti-packer, or other suitable equipment, operated across the slope. On areas too steep or otherwise inaccessible to equipment, the seed shall be covered with a hand rake, or other suitable equipment.
5. Mulch and Method of Anchoring Mulch shall consist of (wheat, rye, or barley) straw and shall be applied uniformly at 2 air-dried tons per acre or 100 lbs. per 1000 square feet. Mulch shall be applied within 48 hours after application of seeding. All bailing wire and twine shall be removed from the seeded and mulched areas. No anchoring is required.
6. Method of Payment Section F Measurement and Payment does not apply. No separate payment will be made for Seeding, Sprigging, and Mulching. Compensation for this item will be included in the payment for Bid Item 1 – Mobilization and Demobilization.
210 H 642 CS 8 (June 2024) 1
Construction Specification 8 — Mobilization and Demobilization
Title 210 – Engineering Part 642 – Specifications for Construction Contracts
1. The work consists of the mobilization and demobilization of the contractor’s forces and equipment necessary for performing the work required under the contract. It does not include mobilization and demobilization for specific items of work for which payment is provided elsewhere in the contract. Mobilization will not be considered as work in fulfilling the contract requirements for commencement of work.
B. Equipment and Material
1. Mobilization includes all activities and associated costs for transportation of contractor’s personnel, equipment, and operating supplies to the site;
establishment of offices, buildings, and other necessary general facilities for the contractor’s operations at the site; premiums paid for performance and payment bonds including coinsurance and reinsurance agreements as applicable; and other items specified in Section D of this specification.
2. Demobilization includes all activities and costs for transportation of personnel, equipment, and supplies not required or included in the contract from the site, including the disassembly, removal, and site cleanup of offices, buildings, and other facilities assembled on the site specifically for this contract.
3. This work includes mobilization and demobilization required by the contract at the time of award. If additional mobilization and demobilization activities and costs are required during the performance of the contract as a result of changed, deleted, or added items of work for which the contractor is entitled to an adjustment in contract price, compensation for such costs will be included in the price adjustment for the item or items of work changed or added.
C. Payment
1. Payment will be made as the work proceeds after presentation of paid invoices or documentation of direct costs by the contractor showing specific mobilization and demobilization costs and supporting evidence of the charges of suppliers, subcontractors, and others. When the total of such payments is less than the lump-sum contract price, the balance remaining will be included in the final contract payment. Payment of the lump sum contract price for mobilization and demobilization will constitute full compensation for completion of the work.
210 H 642 CS 8 (June 2024) 2
2. Payment will not be made under this item for the purchase costs of materials having a residual value, the purchase costs of materials to be incorporated in the project, or the purchase costs of operating supplies.
D. Items of Work and Construction Details Items of work to be performed in conformance with this specification and the construction details therefore are:
Bid Item 1 - Mobilization and Demobilization
1. This item shall consist of mobilizing and demobilizing all forces, equipment, and materials necessary for performing the work required under this contract.
2. Any ingress/egress or storage/lay-down areas within the Work Limits must be returned to the condition existing prior to construction. Any storage/lay-down areas outside the Work Limits shall be coordinated between the Contractor and Landowner.
3. A portable toilet and toilet maintenance services shall be supplied at the site by a commercial vendor for the duration of the contract.
4. A written and detailed construction schedule will be required prior to beginning work.
5. Items subsidiary to this bid item are:
a. Pollution Control – Construction Specification 5
b. Seeding, Sprigging, and Mulching – Construction Specification 6
c. Traffic Control – Construction Specification 9
d. Contractor Quality Control – Construction Specification 94
210 H 642 CS 9 (June 2024) 1
Construction Specification 9 — Traffic Control
Title 210 – Engineering Part 642 – Specifications
1. The work consists of establishing traffic control and maintaining safe, convenient use of public roads and right of way.
B. Traffic and Access
1. The contractor’s operations must cause no unnecessary inconvenience to the public. Maintain the public right of way at all times unless interruption is authorized by proper local authority. Contractor’s authorized closing or detour plans must be provided to the engineer for approval.
2. Provide and maintain safe and adequate access to all public protection devices and to all critical utility-control locations. Facility access must be continuous and unobstructed unless otherwise approved.
C. Storage of Equipment and Material in Public Streets
1. Construction materials and equipment must not be stored or parked on public streets, roads, or highways. During any material or equipment loading or unloading activities that may temporarily interfere with traffic, an acceptable detour must be provided for the duration of the activity. Any associated expense for this activity is the responsibility of the contractor.
2. Excavated material, including suitable material that is intended for adjacent trench backfill or other earth backfill as specified in Section E of this specification, must not be stored on public streets, roads, or highways that remain in service for the public. Any waiver of this requirement must be obtained from the proper local authority and approved by the engineer. All excess and unsuitable material must be removed from the site as soon as possible. Remove any spillage from roadways before they are used by the public.
D. Street Closures, Detours, and Barricades
1. The contractor must comply with the requirements of all applicable, responsible units of government for closure of any street, road, or highway. The contractor must provide the required barriers, guards, lights, signs, temporary bridges, and flaggers and inform the public of any detours and construction hazards by the most suitable means available, such as local newspapers or radio stations. The contractor is also responsible for compliance with additional public safety requirements that may arise during construction. The contractor must furnish, 210 H 642 CS 9 (June 2024) 2 install, and, upon completion of the work, promptly remove all signs, warning devices, and other materials used in the performance of this work.
2. Unless otherwise specified, the contractor must notify, in writing, the fire chief, police chief, county sheriff, state patrol, schools that operate school buses, or any other government official as appropriate no less than 7 days before closing, partly closing, or reopening any street, road, or highway.
3. Unless otherwise specified, the contractor must furnish to the engineer a written plan showing the proposed method of signing, barricading for traffic control, and safety for street detours and closures.
4. All temporary detours will be maintained to ensure use of public rights of way is provided in a safe manner. This may include dust control, grading, and graveling as required in Section G of this specification.
E. General and Specific References
1. All signs, signals, barricades, use of flaggers, and other traffic control and public safety devices must conform to the general requirements set forth in the Manual of Uniform Traffic Control Devices (MUTCD) and the latest edition of Standard Highway Signs and Standard Alphabets for Highway Signs and OSHA Construction Industry Standards (29 CFR Part 1926), Subpart G, Signs, Signals, and Barricades, unless otherwise specified in Section G of this specification.
F. Measurement and Payment
1. For items of work for which specific lump-sum prices are established in the contract, payment for the work is made at the contract lump-sum price. Progress payments will be made based upon the percentage of estimated total time that traffic control will be required unless otherwise specified in Section G of this specification. Payment will constitute full compensation for all flaggers, labor, materials, equipment, and other items necessary and incidental to completion of the work.
2. Compensation for any item of work described in the contract but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and items to which they are made subsidiary are identified in Section G of this specification.
Items of work to be performed in conformance with this specification and the construction details therefore are:
Subsidiary Item – Traffic Control
1. The roadways shall remain open to two-way traffic during the period of construction. The Contractor shall coordinate maintenance of traffic activities with the Windsor Township Trustee's Office by contacting Cynthia Schaad at the following phone number: (740) 651 – 8611.
The Contractor shall coordinate with the Township Trustee's at least 7 working days prior to the start of work. A construction schedule shall also be provided to the Township Trustees.
2. Traffic Control shall be in accordance with ODOT Construction and Material Specifications Item 614 and other applicable portions of the specifications, as well as the Ohio Manual of Uniform Traffic Control Devices. A written Traffic Control Plan shall be submitted to the NRCS engineer at the pre-construction conference.
3. Method of Payment Section F Measurement and Payment does not apply. No separate payment will be made for Traffic Control. Compensation for this item will be included in the payment for Bid Item 1 – Mobilization and Demobilization.
210 H 642 CS 11 (June 2024) 1
Construction Specification 11 — Removal of Water
Tile 210 – Engineering Part 642 – Specifications for Construction Contracts Subpart B – National Construction Specifications June 2024
A. Scope
1. The work consists of the removal of surface water and ground water as necessary to perform the construction required by the contract in accordance with the specifications. It must include: (1) constructing, installing, building, and maintaining all necessary temporary water containment facilities, channels, and diversions; (2) furnishing, installing, and operating all necessary pumps, piping, and other facilities and equipment; and (3) removing all such temporary works and equipment after their intended function is no longer required.
B. Diverting Surface Water
1. The contractor must install, maintain, and operate all cofferdams, channels, flumes, sumps, and all other temporary diversion and protective works needed to divert streamflow and other surface water through or around the construction site.
Control of surface water must be continuous during the period that damage to construction work could occur. Unless otherwise specified or approved, the diversion outlet must be into the same drainageway that the water would have reached before being diverted.
2. The contractor must furnish the contracting officer, in writing, a proposed plan for diverting surface water before beginning any construction activities for which a diversion is required, unless waived in Section H of this specification. Acceptance of this plan or the waiving of the plan requirement will not relieve the contractor of the responsibilities related to this activity during the process of completing the work as specified.
C. Dewatering the Construction Site
1. Foundations, cutoff trenches, and all other parts of the construction site must be dewatered and kept free of standing water and muddy conditions as necessary for the proper execution of the work. The contractor must furnish, install, operate, and maintain all drains, sumps, pumps, casings, well points, and all other equipment required to properly dewater the site as specified. Dewatering systems that cause a loss of soil fines from the foundation areas will not be permitted.
2. The contractor must furnish the contracting officer, in writing, a proposed plan for dewatering before commencing with any construction activity for which dewatering may be required unless waived in Section H of this specification.
210 H 642 CS 11 (June 2024) 2
Acceptance of this plan or the waiving of the plan requirement will not relieve the contractor of the responsibilities for completing the specified work.
D. Dewatering Borrow Areas
1. The contractor must maintain all borrow areas free of surface water or otherwise provide for timely and effective removal of surface and subsurface water that accumulates within the borrow area unless waived in Section H of this specification. Process borrow material as necessary to achieve proper and uniform moisture content at the time of placement.
2. If pumping to dewater borrow areas is included as a bid item of work in the bid schedule, equip each pump discharge pipe with a water meter. The meter must be such that the measured quantity of water is accurate within 3 percent of the true quantity. The contractor must provide necessary support to perform accuracy tests of the water meter when requested by the contracting officer.
E. Erosion and Pollution Control
1. Removal of water from the construction site, including the borrow areas, must be accomplished so that erosion and the transporting of sediment and other pollutants are minimized. Dewatering activities must be accomplished in a manner that the water table water quality is not altered. Pollution control activities must not conflict with the requirements of Construction Specification 5, Pollution Control, if it is a part of this contract.
F. Removal of Temporary Works
1. When temporary works are no longer needed, the contractor must remove and return the area to a condition similar to that which existed before construction.
Areas where temporary works were located must be graded for sightly appearance and proper functioning and access to the installed works of improvement and may not obstruct natural surface waterflows. The contractor must exercise extreme care during the removal stages to minimize the loss of soil sediment and debris that was trapped during construction.
2. Pipes, casings, and any other material used to dewater the site must be removed from temporary wells. Fill the wells to ground level with clean gravel or other suitable material approved by the contracting officer. The contractor must exercise extreme care to prevent pollution of the ground water by these actions.
G. Measurement and Payment
1. Method 1.
a. Items of work listed in the bid schedule for removal of water, diverting surface water, and dewatering construction sites and borrow areas are paid for at the contract lump-sum prices. Such payment will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
2. Method 2.
210 H 642 CS 11 (June 2024) 3
a. Items of work listed in the bid schedule for removal of water, diverting surface water, dewatering construction sites, and dewatering borrow areas are paid for at the contract lump-sum prices. Such payment will constitute full compensation for furnishing, installing, operating, and maintaining the necessary trenches, drains, sumps, pumps, piping, and for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work. The exception is that additional payment for pumping to dewater borrow areas and the removal of water will be made as described in the following paragraph.
b. If pumping to dewater borrow areas is a contract bid item, payment is made at the contract unit price, which must be the price per 1,000 gallons shown in the bid schedule. Such payment will constitute full compensation for pumping only. Compensation for equipment, preparation, and other costs associated with pumping is included in the lump-sum payment for removal of water or the lump-sum payment for dewatering the borrow areas. Payment is made only for pumping that is necessary to dewater borrow areas that cannot be effectively drained by gravity or that must have the water table lowered to be usable as a suitable borrow source. Pumping for other purposes will not be included for payment under this item.
3. All Methods. The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract but not listed in the bid schedule is included in the payment for the contract line item to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in Section H of this specification.
H. Items of Work and Construction Details Items of work to be performed in conformance with this specification and the construction details therefore are:
Subsidiary Item – Removal of Water
1. This item shall consist of all dewatering required for the work under this contract.
2. A written dewatering plan is required and shall be submitted to the COR at the pre-construction meeting.
3. Method of Payment Section G Measurement and Payment does not apply. No separate payment will be made for Removal of Water. Compensation for this item will be included in the payment for Bid Item 2 – Rock Riprap, Type C, and Bid Item 3 – Woven Wire Gabion Baskets.
210 H 642 CS 21 (June 2024) 1
Construction Specification 21 — Excavation
Title 210 – Engineering Part 642 – Specifications for Construction Contracts Subpart B – National Construction Specifications June 2024
A. Scope
1. The work consists of the excavation required by the drawings and specifications, as well as the disposal of the excavated materials.
B. Classification
1. Excavation is classified as common excavation, rock excavation, or unclassified excavation in accordance with the following definitions.
2. Common excavation is defined as the excavation of all materials that (1) can be excavated, transported, and unloaded using heavy ripping equipment and wheel tractor-scrapers with pusher tractors or (2) can be excavated and dumped into place or loaded onto hauling equipment by excavators having a rated capacity of 1 cubic yard or larger and equipped with attachments (shovel, bucket, backhoe, dragline, or clam shell) appropriate to the material type, character, and nature of the materials.
3. Rock excavation is defined as the excavation of all hard, compacted, or cemented materials that require blasting or the use of ripping and excavating equipment larger than defined for common excavation. The excavation and removal of isolated boulders or rock fragments larger than 1 cubic yard encountered in materials otherwise conforming to the definition of common excavation must be classified as rock excavation. The presence of isolated boulders or rock fragments larger than 1 cubic yard is not in itself sufficient cause to change the classification of the surrounding material.
a. For the purpose of these classifications, the following definitions apply:
(1) Heavy ripping equipment is a rear-mounted, heavy-duty, single-tooth, ripping attachment mounted on a track-type tractor having a power rating of at least 250-flywheel horsepower, unless otherwise specified in Section J.
(2) A wheel tractor-scraper is a self-loading (not elevating) and unloading scraper having a struck-bowl capacity of at least 12 cubic yards.
(3) A pusher tractor is a track-type tractor having a power rating of at least 250-flywheel horsepower equipped with appropriate attachments.
210 H 642 CS 21 (June 2024) 2
4. Unclassified excavation is defined as the excavation of all materials encountered, including rock materials, regardless of their nature or the manner in which they are removed.
C. Blasting
1. The transportation, handling, storage, and use of dynamite and other explosives must be directed and supervised by someone of proven experience and ability who is authorized and qualified to conduct blasting operations.
2. Blasting must be done in a manner that prevents damage to the work or unnecessary fracturing of the underlying rock materials. It must conform to any special requirements in Section J of this specification. When specified in Section J, the contractor must furnish the engineer, in writing, a blasting plan before blasting operations begin.
D. Use of Excavated Material
1. Method 1. To the extent they are needed, all suitable material from the specified excavations must be used in the construction of required permanent earthfill or rockfill. The suitability of material for specific purposes is determined by the engineer. The contractor must not waste or otherwise dispose of suitable excavated material.
2. Method 2. Suitable material from the specified excavations may be used in the construction of required earthfill or rockfill. The suitability of material for specific purposes is determined by the engineer.
E. Disposal of Waste Materials
1. Method 1. All surplus or unsuitable excavated materials are designated as waste and must be disposed of at the locations shown on the drawings.
2. Method 2. All surplus or unsuitable excavated materials are designated as waste and disposed of by the contractor at chosen sites away from the site of the work.
The disposal must be in an environmentally acceptable manner that does not violate local rules and regulations.
F. Excavation Limits
3. Excavations must comply with the Occupational Safety and Health
Administration Construction Industry Standards Subpart P, Excavations, Trenching, and Shoring (29 CFR pt. 1926). All excavations must be completed and maintained in a safe and stable condition throughout the total construction phase. Structure and trench excavations must be completed to the specified elevations and to the length and width required to safely install, adjust, and remove any forms, bracing, or supports necessary for the installation of the work.
Excavations outside the lines and limits shown on the drawings or specified herein are required to meet safety requirements and must be the responsibility of the contractor in constructing and maintaining a safe, stable excavation.
210 H 642 CS 21 (June 2024) 3
G. Borrow Excavation
1. When the quantities of suitable material obtained from specified excavations are insufficient to construct the specified earthfills and earth backfills, obtain additional material from the designated borrow areas. The extent and depth of borrow pits within the limits of the designated borrow areas are as specified in Section J or as approved by the engineer.
2. Borrow pits must be excavated and finally dressed to blend with the existing topography. They are sloped to prevent ponding and to provide drainage.
H. Over Excavation
1. Correct excavation in rock beyond the specified lines and grades by filling the resulting voids with Portland Cement concrete. Materials and mix proportions must be approved by the engineer. Concrete that will be exposed to the atmosphere when construction is completed must meet the requirements of concrete selected for use under Construction Specification 31, Concrete for Major Structures, or 32, Structure Concrete, as appropriate.
2. Concrete that will be permanently covered must contain not less than five bags of cement per cubic yard. The concrete must be placed and cured as specified by the engineer.
3. Correct excavation in earth beyond the specified lines and grades by filling the resulting voids with approved compacted earthfill. The exception to this is that if the earth will become the subgrade for riprap, rockfill, sand or gravel bedding, or drainfill, the voids may be filled with material conforming to the specifications for the riprap, rockfill, bedding, or drainfill. Before correcting an over excavation condition, the contractor must review the planned corrective action with the engineer and obtain approval of the corrective measures.
I. Measurement and Payment
1. Unit Price Methods. For items of work for which specific unit prices are established in the contract, the volume of each type and class of excavation within the specified pay limits is measured and computed to the nearest cubic yard by the method of average cross-sectional end areas or by methods outlined in Section J of this specification. Regardless of quantities excavated, the measurement for payment is made to the specified pay limits except when excavation outside the specified lines and grades directed by the engineer to remove unsuitable material is included. Excavation required because unsuitable conditions result from the contractor’s improper construction operations, as determined by the engineer, is not included for measurement and payment.
2. Method 1. The pay limits are as designated on the drawings.
3. Method 2. The pay limits are defined as follows:
a. The upper limit is the original ground surface as it existed before the start of construction operations, unless excavation is performed within areas designated for previous excavation or earthfill; then the upper limit is the
210 H 642 CS 21 (June 2024) 4 modified ground surface resulting from the specified previous excavation or earthfill.
b. The lower and lateral limits are the neat lines and grades shown on the drawings.
4. Method 3. The pay limits are defined as follows:
a. The upper limit is the original ground surface as it existed before the start of construction operations, unless excavation is performed within areas designated for previous excavation or earthfill; then the upper limit is the modified ground surface resulting from the specified previous excavation or earthfill.
b. The lower and lateral limits is the true surface of the completed excavation as directed by the engineer.
5. Method 4. The pay limits are defined as follows:
a. The upper limit is the original ground surface as it existed before the start of construction operations, unless excavation is performed within areas designated for previous excavation or earthfill; then the upper limit is the modified ground surface resulting from the specified previous excavation or earthfill.
b. The lower limit is at the bottom surface of the proposed structure.
c. The lateral limits are 18 inches outside of the outside surface of the proposed structure or are the vertical planes 18 inches outside of and parallel to the footings, whichever gives the larger pay quantity, except as provided in paragraph d below.
d. For trapezoidal channel linings or similar structures that are to be supported by the sides of the excavation without intervening forms, the lateral limits are at the underside of the proposed lining or structure.
e. For the purposes of the definitions in paragraphs b, c, and d above, any specified bedding or drainfill directly beneath or beside the structure will be considered to be a part of the structure.
6. All Methods. The following provisions apply to all methods of measurement and payment.
a. Payment for each type and class of excavation is made at the contract unit price for that type and class of excavation. Such payment will constitute full compensation for all labor, materials, equipment, and other items necessary and incidental to the performance of the work with the exception that extra payment for backfilling over excavation will be made in accordance with the following provisions.
b. Payment for backfilling over excavation, as specified in Section H of this specification, is made only if the excavation outside specified lines and grades is directed by the engineer to remove unsuitable material and the unsuitable condition is not a result of the contractor’s improper construction operations as determined by the engineer.
c. Compensation for any item of work described in the contract but not listed in the bid schedule is included in the payment for the item of work to which it is
210 H 642 CS 21 (June 2024) 5 made subsidiary. Such items and the items to which they are made subsidiary are identified in Section J of this specification.
J. Items of Work and Construction Details
Items of work to be performed in conformance with this specification and the construction details therefor are:
Subsidiary Item – Excavation (Unclassified)
1. This item shall consist of all excavation required to construct this project. This includes excavation under and behind the drainfill, rock riprap, and woven wire gabion baskets.
2. All excavation on this project is designated as "unclassified excavation" and shall consist of all materials encountered regardless of their nature or the manner in which they are removed.
3. Section D, use of excavated material, shall be by Method 1
4. Section E, disposal of waste material, shall be by Method 2.
5. Method of Payment
Section I Measurement and Payment does not apply. No separate payment will be made for Excavation. Compensation for this item will be included in the payment for Bid Item 2 – Rock Riprap, Type C, and Bid Item 3 – Woven Wire Gabion Baskets.
210 H 642 CS 23 (June 2024) 1
Construction Specification 23 — Earthfill Title 210 – Engineering Part 642 – Specifications for Construction Contracts Subpart B – National Construction Specifications June 2024
A. Scope
1. The work consists of the construction of earth embankments, other earthfills, and earth backfills required by the drawings and specifications.
2. Earthfill is composed of natural earth materials that can be placed and…