This is a Statement of Work (SOW) for architectural and engineering services required by the Hampton VA Medical Center to renovate 51,808 square feet of Building 27 and its exterior in accordance with historical preservation guidelines. The project requires comprehensive A/E services including site investigation, architectural/engineering design across multiple disciplines (civil, structural, mechanical, electrical, environmental), cultural resource management under Section 106 of the National Historic Preservation Act, construction drawings/specifications, third-party cost estimates, and construction period services.
The period of performance is 860 calendar days total, comprising 315 days for design completion (including VA reviews), 6 months for procurement, and 365 days for construction period services. The estimated construction magnitude is over $10 million. Key deliverables include schematic designs, 25%/50%/95% construction documents, and final bid documents with all supporting calculations and estimates. The A/E must provide construction period services including submittal reviews within 14 days, RFI responses within 7 days, site visits as requested, and preparation of as-built drawings. The work requires expertise in historical preservation while integrating modern building systems and must comply with VA guidelines, specifications, and all applicable building codes.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24625R0011.docx | DOCX document | |
| Attachment B - Selection Criteria.docx | DOCX document | |
| Attachment C - Past Performance Questionnaire.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Hampton VA Medical Center
Architect Engineer (A/E)
SCOPE OF WORK
Campus Historical Preservation – Building 27 Project # 590-25-200
– Services –
Provide professional Architect/Engineer services to include:
1. Site investigation including permits, if applicable
2. Architectural, Civil, Structural, Mechanical, Electrical, and Environmental (e.g., soil boring)
3. Environmental survey (lead, asbestos, mold identification, etc.)
4. Cultural resource management specifically Section 106 of the National Historic Preservation Act and NEPA as negotiated on Programmatic Agreement
4.1. SHPO Intensive Level Survey
4.2. Archeological Testing Program
4.3. Data Recovery Plan
5. Construction drawings and specifications
6. Third party construction estimates
7. Construction period services
7.1. Submission review with recommendations and approvals (e.g., change proposals SOW/IGCE’s, Requests for Clarification, product submittals, shop drawings, tests)
7.2. Site visits per VA request
7.3. Update drawings as-built conditions from contractor record drawings, VA correspondence during construction
7.4. Air monitoring during abatement/remediation
7.5. A/E will respond either by phone, email, or on-site within a two-hour period.
7.6. Final Inspection
8. Conduct Infection Control Risk Assessment (ICRA) in conjunction with VA Safety/Infection Control staff
– Project Scope –
GENERAL:
The Architect/Engineer (A/E) shall provide design and construction period services for NRM construction project 590-25-200. The project requires the A/E to renovate 51,808sf of space in building 27 as well as the building exterior in accordance with historical preservation guidelines. Work includes architectural, mechanical, electrical, structural, telecommunication, fire protection and plumbing engineering along with historical preservation requirements. Building occupants and furnishings are to be moved into temporary trailers (or other locations on campus) and back into building 27 by the construction contractor.
Design for a construction budget is in accordance with FAR 36.204 the estimated magnitude of construction is more than $10,000,000. Completed design shall result in a cost that is within the budget limitations. To ensure this, the A/E shall set up one or more bid deduct alternatives totaling 10% of the construction cost. If the base bid cost exceeds budget and deduct alternates do not bring the project within the construction budget, the A/E shall re-design or take necessary steps to reduce the cost so that budget limitations are not exceeded.
The A/E shall include in his design any environmental permits (i.e. VPDES) and ensure proper erosion control measures are also included in the contract documents for construction.
Fire safety systems design to extend and or reconfigure existing systems. Provide complete systems including fire suppression, isolation, alarm, and sensing. Project documents will be approved by a licensed professional Fire Protection Engineer. Fire safety review will include a review of impact on life safety of adjacent spaces and coordination with all drawings including MEP drawings.
Hazardous materials investigations. All areas affected by construction will receive a thorough investigation for hazardous materials. A certified industrial hygienist will be retained by the designer to complete all site investigations and testing. The VA will make available existing records. If destructive testing is required, access holes will be provided by the VA as directed by the IH. The designer shall provide removal/containment documents and cost estimate. Provide air monitoring during construction.
The A/E shall make a thorough investigation of the existing site for the proper design of the project. Existing conditions shall be determined by verifying information from field investigations and any documentation that may be available. A survey shall be conducted to obtain sufficient information to permit designers to develop a detailed cost estimate and schematics. The entire Veterans Affairs drawing files (if existing) will be made available and accessible along with reproduction materials, but the A/E shall provide the manpower to reproduce prints. AutoCAD drawings are also available for use contingent they are existing. This information is the best available, but the Government does not guarantee its accuracy or completeness. The A/E investigation of field conditions shall be performed in a competent, professional manner in accordance with Architectural Design Manual PG 18-10. Site utility locations will be verified by the A/E (VA staff will not mark utilities but will assist with locating if workload permits).
Mechanical design including detail of the mechanical construction requirements for heating, ventilating, air conditioning, refrigeration, fire and safety, plumbing and sanitary engineering. Include commissioning of HVAC system. Design shall comply with the most current ASHRAE 90.1 and the VA Sustainability Program.
Electrical design documents which include electrical, data and telephone closets, power distribution systems, auxiliary power systems, lighting, switching, fire and safety, public address, security and signal systems. Existing systems will be evaluated and reused, extended or modified where feasible. The project will be designed utilizing emergency power panels per VA standards. The building will be designed to utilize combined infra-red/motion occupancy sensors, day lighting control for spaces with windows or skylights, and VA Required Foot-candle lighting levels shall be maintained within the lighting densities listed in the most current ASHRAE 90.1.
Structural design setting forth in detail the structural construction requirements including all structural plans, elevations, sections, structural construction requirements, schedules, and calculations sizing all columns, beams, slabs, and coordinate the work with other design disciplines, especially the mechanical and architectural disciplines.
Architectural design including facility floor and roof plans, sections, elevations, details, schedules, selection of building systems and materials, discipline coordination and fire safety systems and controls.
Provide bound specifications and 100% construction drawings with all xref’s bound. Construction documents will be required to be furnished in hard copy, electronic .dwg files (AutoCAD 2022 or most current at the time of final design submission) and electronic .pdf files. All AutoCAD drawings (including subcontractors) shall be in an organized drawing file system using its “Project Browser/Navigator”.
Cost estimates detailing quantities of materials, labor, profit, overhead, insurance, taxes, etc. in the format found at https://www.cfm.va.gov/til/dManual/dmCost.pdf
Life safety and infection control will be taken into account during all phases of design. Final construction documents will detail measures to be taken by the contractor to assure life safety and infection control. Laydown areas and storage for materials shall be identified in the early stages of the design. A preconstruction risk assessment will be completed and included in project submissions.
Plans for phasing construction to minimize impact on the medical center will be incorporated into the construction documents. Plan construction to include impacts on the medical center such as relocating patient and staff equipment, providing temporary barriers, providing temporary utilities, minimizing impact on patient flow, etc.
Incorporate in the preliminary drawings the pre-construction risk assessment/evaluation as the sample shown below.
PCRA Introductory Information and Instructions
Use this template as a baseline for performing facility Pre-Construction Risk Assessments (PCRA) for Construction, Renovation, and Maintenance work (referred to as the “activity” in this document). The template provides minimum requirements for categorizing activity type(s) and safety risk to determine the level of precautions needed to prevent impact related to Construction, Renovation and Maintenance on patients, employees, and contractors.
Ensure that the activity statement of work and any drawings available are used for the PCRA assessment and included in the project file with the completed PCRA.
Communication and coordination of all types of activity with affected areas are to be included among the control measures. The development of communication and coordination plans must begin during the activity planning phase.
Facilities may customize this template to incorporate site-specific information and requirements.
NOTE: This VHA PCRA template pertains specifically to non-infection-related safety for Construction, Renovation, and Maintenance activities. It must be used in conjunction with the VHA Infection Control Risk Assessment (ICRA) for the activity, if required, which specifically addresses infection risks outside the scope of this PCRA.
PERMIT: See the last page of this document for a fillable permit form to be used for posting at the activity site.
Activity Location:
Activity Name, Number, and/or Brief Description:
Table 1 - Construction, Renovation, and/or Maintenance Activity Type and Control Measures
NOTE: If any of the bulleted criteria in a higher activity type pertains to the work that will be done (even if the other criteria are in a lower type), use the higher activity type for the VHA PCRA.
Controls defined in Table 1 for the activity must be in place before the activity begins and maintained until work is completed and the area is activated. Control measures for each activity must also include the control measures in the preceding row(s).
As the activity progresses, a full re-evaluation of remaining activity type and risk is required prior to changing the level of control measures.
Activity Type determined from Table 1:
| Activity Type and Description |
| Control Measures |
Inspection/upkeep generally defined as follows:
· Work can be completed in a single shift, not to exceed 10 hours.
· Patients, employees and/or visitors may be in the area depending on the activity.
· Work that does not create dust or debris.
· Work that does not create vapors or fumes.
· Removal of ceiling tile or access to mechanical or electrical chase for visual inspection that will not impair fire safety systems and are limited to 1 tile per 50 square feet with limited exposure time (not to exceed an hour for each tile) within the shift.
· Minor interior updates (e.g., replacing floor or ceiling tiles, carpentry work to include hanging signage, and painting with hand tools) that do not create vibration or noise.
· Limited building system maintenance that does not require Lock Out Tag Out (LOTO) such as plumbing on potable systems limited to faucet replacement, steam trap replacement etc. and electrical work such as replacement of bulbs, receptacles, or switches.
1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.
2. Site visits of construction area are required weekly by member of multi-disciplinary team. Site visits will be documented on standard checklist.
3. Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved where a contact is in place. For internal work the shop involved must work with Safety to ensure proper precautions are in place.
4. Must address identified hazards and controls that will be implemented to ensure minimal impact to patients, employees, contractors and facility.
5. Communication and coordination plan for all affected areas
Small scale Construction, Renovation and general maintenance/repair work, generally defined as follows:
· Prolonged work that may take longer than a single shift but not exceeding six months.
· Patients and employees are not to be in the area until activity is completed.
· Work that creates some noise and vibration due to power tool use.
· Selective demolition/removal of preexisting floor covering, casework, lay-in ceiling, or other architectural elements that may
· disturb asbestos, lead or silica
· create the potential for falling objects
· create vibration and/or noise in excess of 80 dB(A) in surrounding areas.
· cause penetrations in fire or smoke barrier
· Plumbing work such as the installation of new sinks, showers and toilets and associated plumbing that requires utility outages or work on the steam system that may require:
· LOTO
· The use of compressed gas cylinders
· Electrical work such as installation of conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc. Electrical work such as installation of cabling/wiring/conduit for a single device, installation of new device such as a light fixture that require LOTO.
· Air Handler and/or fan shutdown/startup and HVAC work such as replacement of a single diffuser, single terminal unit, a single device and the installation of ductwork, diffusers, and terminal units for an area that may require:
· Work on ladders
· Rigging, hoisting or lifting of equipment or materials overhead
· Modification of existing fire alarm and suppression systems requiring system outages and ILSMs or obstruction of exits and or impact on corridors.
· Architectural, structural, or any other work that may cause vapors or fumes such as:
· Roofing work
· Flooring work
· Painting or other large-scale use of such substances.
All control measures in the row above and the following:
1. Hazard communication chemical inventory required to be provided by the contractor and approved.
2. Where construction, Renovation and maintenance are done in an accredited facility, and ILSM assessment is required to be done and ILSMs put into place in accordance with TJC LS.01.02.01 and the local facility policy including Fire watch if necessary. Staff is trained and the ILSM is verified regularly
3. Hot Work or burn permits in place and staff trained
4. LOTO procedures in place and staff trained on their use
5. Site visits will be reviewed using the criteria in standardized guide.
6. Daily inspections of the site are to be conducted by the General Contractor or shop supervisor and documented on their daily log.
Large-scale construction, renovation, or maintenance generally defined as follows:
· Work exceeding 6 months in duration.
· Patients and employees are not to be in the area until activity is completed.
· Excavation or heavy equipment use taking place
· Dig safe required utility location
· Trench safety
· Dust control plan
· Equipment exhaust, Noise, Vibration
· Confined space entry required (permit required or not)
· Requires crane work
· General crane work
· Lift over buildings
· Includes elevated work
· Roof work, fall protection
· Window work, scaffolding and fall protection
· Odor control
· Welding, cutting or use of torches requiring burn permits
· Demolition of building components and infrastructure including removal of multiple doors, walls, framing, ceilings, flooring, piping, electrical and HVAC that may
· require asbestos, lead or silica abatement
· create the potential for falling objects
· create vibration and/or noise in excess of 90 dB(A) in surrounding areas.
· cause breaches to fire or smoke barrier
· The installation building components such as new walls, ceilings and doors including framing, drywall and associated plaster work that requires transport of significant materials through building and up elevators i.e., weight limits of floors and elevators
· Plumbing work requiring LOTO and system shutdown and startup such as the installation of:
· new medical gas systems,
· steam/heating hot water, condensate systems,
· Potable water and sanitary drainage, multiple sinks, showers and toilets including associated plumbing.
· Electrical work such as installation of electrical feeders, distribution panels, conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc. requiring LOTO and system isolation.
· Installation of fire alarm and suppression systems requiring outages of those systems and ILSMs or closure of exits/corridors
· Mechanical work such as the installation of air handling equipment, associated ductwork, diffusers, heat exchangers, terminal units and controls requiring lifting and support of equipment and systems.
All control measures in the two rows above and the following Activity Hazard Analyses and Control Plans (check all that apply):
1. Excavation safety plan in place ☐
2. Dust control plan in place ☐
3. Pollution prevention plan in place ☐
4. Dig safe paper work in place ☐
5. Crane lift plan in place ☐
a. Crane placement
b. Crane swing
c. Crane load evaluation
6. Fall protection plan in place and staff trained ☐
7. Confined entry plan in place and staff trained ☐
Table 2. Affected Adjacent Area Assessment
In addition to the minimum precautions noted above for the Activity Type, it is critical that the activity be coordinated with the areas adjacent to the activity to ensure operations in those areas are not disrupted or impacted. List the adjacent areas in Table 2 below and develop activity-specific coordination plans and associated communication plans with each area to address activity work that could impact or disrupt the operation of the areas, in general as follows:
· If adjacent area is vacant (e.g., work outside, construction of new building, etc.):
· Coordination is typically not necessary other than potentially traffic flow and pedestrian access.
· If adjacent area is non-continuously occupied (e.g., areas where outpatient care is provided, employee health, etc.):
· Develop a list of activities that will potentially impact or disrupt the operation of the area (e.g., work involving noise, vibration or exit obstruction) and meet with POC to coordinate execution of work in a way that mitigates the impact (e.g., conduct work after hours).
· If adjacent area is occupied continuously (e.g., areas where inpatient care is provided, residential areas such as Community Living Centers, etc.):
· Develop a list of activities that will potentially impact or disrupt the operation of the area (e.g., work involving noise, vibration or exit obstruction) and meet with POC to coordinate execution of work in a way that mitigates the impact (e.g., move affected party temporarily).
| Area |
| Service(s)/Type(s) of Area(s) |
(e.g., OR, Unit/Ward, Sterile Processing, Administrative, etc)*
| Point of Contact (POC) |
| POC Contact Information |
| Construction plan communicated to POC? |
Activity Area**
Area Above
Area Below
Adjacent Area 1
Adjacent Area 2
Adjacent Area 3
Adjacent Area 4
* There may be more than one Service/type of area for each row. List all. The information entered on this table must be used in the ICRA if required.
** List the area(s) in which the construction/renovation/maintenance activity will occur.
Infection Control Risk Assessment (ICRA)
Consult with Infection Prevention and Control regarding the assessment of potential infection risks associated with the activity and the need for control measures. See VHA Directive 7715 and the VHA ICRA Template for more information.
Is an ICRA required for the Activity? Yes ☐ No ☐
Pre-Construction Risk Assessment (PCRA) Permit
This page must be posted at the entrance to the project area, or other designated area
Unique permit number:
Location and brief description of construction/renovation/maintenance
Project manager
Project start date
Contact phone number
Completion date
Contractor or lead shop
Permit expiration date
Activity Type Inspection/Upkeep, Small-scale, or Large-scale)
| Activity Type |
| Control measures to be in place for the duration of the activity |
(Check the box for the Activity Type to indicate the Control Measures)
Inspection/Upkeep
1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.
2. Site visits of construction area are required weekly by member of multi-disciplinary team. Site visits will be documented on standard checklist.
3. Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved.
4. Must address identified hazards and controls that will be implemented to ensure minimal impact patients, employees, contractors and facility.
5. Communication and coordination plan for all affected areas
Small-scale
All control measures in the row above and the following:
1. Hazard communication chemical inventory required to be provided by the contractor and approved.
2. ILSMs in place and staff trained on situation
3. Hot Work or burn permits in place and staff trained
4. LOTO procedures in place and staff trained on their use
5. Site visits will be reviewed using the criteria in standardized guide.
6. Daily inspections of the site are to be conducted by the General Contractor and documented on their daily log.
Large-scale
All control measures in both rows above and the following Activity Hazard Analyses and Control Plans as applicable (check all that apply):
1. Excavation safety plan in place ☐
2. Dust control plan in place ☐
3. Pollution prevention plan in place ☐
4. Dig safe paperwork in place ☐
5. Crane lift plan in place ☐
a. Crane placement
b. Crane swing
c. Crane load evaluation
6. Fall protection plan in place and staff trained ☐
7. Confined entry plan in place and staff trained ☐
Additional requirements:
Is an Infection Control Risk Assessment (ICRA) required for the Activity? Yes ☐ No ☐
Infection Prevention and Control signature:
Date:
Project Manager signature
Date
Safety Officer signature
Date
Chair, Construction Safety Committee signature
Date
*The location of all Activity Hazard Analyses and Control Plans (excavation, dust, pollution, etc.) as applicable shall be identified on this permit and shall be made available to all workers on the job.
Provide construction prior services to include shop drawings review, site inspections, and RFI response. In addition, the A/E shall provide scope of works, and estimates for any RFI response that causes a cost change due to design errors and omissions.
All design submissions will be submitted in accordance with the Program Guide PG-18-15, Volume C; A/E Submission Instructions for Minor and NRM Construction Program. These submission requirements may be found at the following web site http://www.cfm.va.gov/contract/aeDesSubReq.asp. Each review submission will require 1 CD with all documents included, 1 full size, bound sets of plans, 3 C size bound sets of plans, and 1 complete set of specifications, bound in 3 ring binders with specification sections clearly tabbed. Only 1 bound copy of calculations and cost estimates is required. Other applicable program guides can be found at http://www.cfm.va.gov/contract/ae.asp.
– Applicable References –
The references listed below are not intended to be all inclusive. The A/E shall ensure that all applicable references and/or standards are followed. http://www.cfm.va.gov/til/
| # |
| VA Standard Title/Section |
| 1 |
| Master Construction Specifications Index (PG-18-1) |
| 2 |
| VHA PROGRAM GUIDE (PG-18-3 Design and Construction Procedures) |
| 3 |
| Standard Details and CAD Standards (PG-18-4) |
| 4 |
| Equipment Guide List (PG-18-5) |
| 6 |
| VA Handbook H-18-8, Seismic Design Requirements |
| 7 |
| Space and Facility Planning (PG-18-9) |
| 8 |
| Design Manuals (PG-18-10) |
| 9 |
| Design Guides (PG-18-12) |
| 10 |
| Barrier Free Design Standard (PG-18-13) |
| 11 |
| Room Finishes, Door and Hardware Schedule (PG-18-14) |
| 12 |
| A/E Submission Instructions (PG-18-15) |
| 13 |
| A/E Design Submission Requirements (Submittal Guide PG-18-15) |
| 14 |
| Environmental Compliance Manual (PG-18-17) |
| 15 |
| VA Cost Estimating |
| 17 |
| VA Signage Design Manual |
| 18 |
| International Building Code Latest Edition (Current is IBC 2024) |
| 19 |
| National Electric Code – Latest Edition (Current is NEC 2023) |
| 20 |
| VHA Directive 1061 |
| 21 |
| VA OHI Report No. 13-01189-267 |
– Site Investigations –
EXPECTATION: A/E shall make site visits as necessary to survey existing conditions.
Make site visits as required to determine existing as-built conditions affecting this project. Note: Information including drawings and other documentation provided to the A/E is used as reference only. All additional references and specifications are available in VHA’s Technical Information Library at address https://www.cfm.va.gov/til/index.asp. A/E shall field verify every aspect that relates to the project. Coordinate visits with the Project Manager/Contracting Officer Representative (COR) as assigned after award. The A/E shall arrange for and oversee the performance of such investigations. Auto CAD architectural background drawings will be provided by the VA upon request. The A/E shall field verify all dimensions, wall layouts, etc. A/E shall field verify every aspect that relates to the project.
– Design Review Schedule –
EXPECTATION: Submit review package so they are received on the noted day.
| Review |
| Due Date (Calendar Days After NTP) |
| Initial Project Design Meeting (PDT) |
| 10 |
| Schematic Submission |
| 45 |
| VA Review Period (30 days) |
| 75 |
Section 106 documentation shall be completed and reviewed by SHPO before continuing with the 25% design. This shall be completed within the first 90 calendar days from NTP concurrent with the schematic submission.
| 25%percent construction documents |
| 120 |
| VA Review Period (30 days) |
| 150 |
Section 106 documentation shall be completed and reviewed by SHPO before continuing with the 50% design.
| 50%percent construction documents |
| 195 |
| VA Review Period (30 days) |
| 225 |
| 95% percent construction documents |
| 255 |
| VA Review Period (30 days) |
| 285 |
| 100% Construction Documents |
| 315 |
Note: NTP will be issued at award. A/E will be required to attend and take minutes from each PDT meeting. Minutes will be submitted electronically to the Project Manager/COR and Contracting Officer within three calendar days of each meeting.
– Design Requirements/Submissions –
EXPECTATIONS:
Submit complete review package in accordance with the following requirements and guidelines outlined in https://www.cfm.va.gov/til/aeDesSubReq.asp. Please pay specific attention to the schematic, design and construction submission requirements. As appropriate depending upon the complexity of the design, the A/E with VA approval, may elect to delete individual submissions where not required (i.e. Do not address A. Site Development, Landscaping for interior renovation projects). Design shall comply with the VA BIM & CAD standards located on the TIL at VA BIM & CAD Standards.
COST ESTIMATING:
Philosophy - Cost management is the task – the cost estimate is the tool. The AE shall manage the execution of the project within the VA programmed construction budget. The VA programmed construction budget will not be made known until after design award. The entire AE design team will take ownership of the project construction budget and be an advocate for successful execution of the project within the available funding. The cost estimator’s role must be viewed as a critical element of project cost management. Rather than limiting responsibilities to simply reporting costs, the estimator must be an integral part of the design team, continually interacting and providing input to design decisions at every stage of development.
Objective - Cost estimates for the base bid shall be within the VA programed construction budget. If the cost estimate is outside of the construction budget, the AE is responsible for notifying the VA of potential budget issues, providing non-scope impacting recommendations to get the estimate with the required budgeted construction cost while providing design documents that correspond accordingly. Design submissions with cost estimates greater than the allowable budget are grounds for rejecting a design submission. The final construction document submission estimate shall not be greater than the VA programed construction budget and not less the -5% of the VA programed construction budget.
Recapitulation and Level of Detail - Refer to VA Cost Estimating Manual.
Timing of Submission - Responsible decisions cannot be made without knowing the associated cost. Cost documentation must be delivered at the same time as other design submissions. The AE is responsible for managing workflow and communications to ensure that this can be accomplished. It is understood that some details may change in the final days preceding a submission. Cost data shall be submitted on the most up to date design information possible, with a narrative of any late developments that will affect cost.
FOR EACH SUBMISSION DELIVER ONE (1) CD CONTAINING ALL SUBMISSION DOCUMENTATION AND ONE (1) FULL SIZE, THREE (3) HALF SIZE DRAWINGS, AND ONE (2) SPECIFICATIONS BOOK AND (1) NARRATIVE REPORT PER SUBMISSION. Provide written Statement of Compliance stating the design meets all requirements of the Technical Information Library (TIL). If design is not in full compliance, list all deficiencies and include supporting documentation to support a deviation request.
Schematic Submission:
· Provide proposed space layout for renovated area and new construction, equipment, utility/infrastructure requirements, etc.
· Budget estimate for proposed with breakouts for equipment, materials, labor.
· Achieve a consensus on design approach before proceeding to 25% design.
· Complete SS1 and SS2 Checklist
Design Development (DD1) 25%:
· Address all comments from the Schematic Submission review.
· Identify all design calculations.
· Identify all existing utilities and utilities requirements.
· Complete DD1 Checklist
· Preliminary Estimate
· Provide written Statement of Compliance stating the design meets all requirements of the Technical Information Library (TIL). If design does not, all deviations must be noted in writing and supporting documentation stating why requirements can’t be met.
Design Development (DD2) 50%:
· Address all comments from the DD1 Submission review.
· Complete DD2 and remaining DD Checklists
· Updated Estimate
· Color boards showing the interior design scheme (fabrics, finishes, furniture layout and plans) for each area, east west and center, include an inventory of materials/manufactures recommended for use for approval and prepared for order by the VA Interior Designer. The color, name and all applicable identifying numbers shall be placed on the board and be easily read without removing the physical samples. All finishes to be approved by Director.
Construction Document Development (CD) 95%:
· Address all comments from the DD2 Submission review.
· Design all finishes
· Finalize required submittals.
· Complete CD1 Checklist
· Updated Estimate
· Provide a 3D model that includes FFE- furnishings and equipment (if vendor models are available). The model shall be able to be opened by Revit 2020.
· The Signage & Way-Finding Plan shall identify each type of sign and the planned location.
Contract Documents (Bid documents):
· Submit a complete document of all contract requirements including final estimate. The Cover Page shall be submitted for approval signatures. If necessary, update and submit until approved by the VA.
· Consolidate all necessary submittals by specification section on an Excel spreadsheet. Checklist to be utilized to track/monitor submittal process.
· Provide a Gantt chart of the estimated construction schedule showing work that is expected to last 30 or more days in duration, including submittals. Include expected material lead times.
· The final documents shall be complete, free of grammatical or typographical errors, all fill-ins from the TIL are filled in, and unused TIL references are removed.
– Construction Period Services –
PROVIDE:
· Assist the VA to determine whether the contractor or subcontractor meets qualification requirements, supported by written recommendations of any problems or litigation encountered in the past based on firsthand knowledge.
· Review all submittals and provide recommendations to the VA within fourteen (14) calendar days.
· Review and provide replies to contractor generated RFIs when required by the Project Manager/COR within seven (7) calendar days.
· Review contractor's cost estimates and provide recommendations to the VA.
· Make site visits on requests of the VA and prepare written reports to include agreed upon changes in design as determined necessary during the construction. Visits made based on errors and omissions in design will be at no cost to the VA.
· Participate in partial/final acceptance inspections as scheduled and generate punch list items for completion. The punch list shall reference the contract documents for specific deficiencies (i.e. specification section, drawing detail, etc.)
· Prepare as-built drawings on original set with A/E’s stamp, based on record drawings that the contractor kept during construction. Transpose contractor’s as-builts to AutoCAD (.dwg) and provide a set of updated as-builts on CD within 30 days to the Project Engineer. Final drawing submittal will include hard copies as described for other submissions as well as a CD clearly labeled with the project name, number and submittal date containing:
1. Folder labeled “bid documents”
0. All specifications bound in one (1) word document (make sure spec sections are separated by page breaks and that new sections start on right hand page)
0. All drawing sheets in one .pdf file.
1. Folder labeled “DWG’s” with subfolders containing engineering disciplines (Architectural, MEP, Structural, Civil, etc.) which includes the .arj file (for every discipline) to launch and organize the drawing file system and make all drawings the current project inside of AutoCAD.
1. Folder labeled “PDF sheets” containing separate .pdf documents for each discipline.
1. Folder labeled “cost estimate” containing a copy of the final construction cost estimate documents.
1. Folder labeled “calculations” containing final calculation documents.
1. Folder labeled “specifications” with a word document for each spec section.
1. Folder labeled “misc” for IH reports, materials testing, VPDES permit, soils tests, sustainability checklist, etc.
1. Upon construction completion, red line drawings will be furnished to the A/E to prepare as built drawings. Final as built drawings will be furnished as master building drawings in a project manager format prescribed by the VA.
· The A/E shall review and approve all specified equipment and installation submittals and shop drawings. During construction, the A/E shall allow for a minimum of twelve (12) site visits as directed and scheduled by the COR. The A/E shall also attend the final inspection and provide the COR with an itemized punch list.
– Period of Performance –
· Design completion: 315 calendar days; includes VA design reviews.
· Procurement timeframe: Six (6) months from the time Engineering submits package to contracting. Designer shall answer pre-bid RFIs and provide updated construction documents to capture any changes made through the procurement process.
· Construction period services: 365 calendar days from construction award date.
· Total contract period: 860 calendar days.