Attachment A SOW_1764111_Wash Rack.pdf
PDF 886 KB Posted
- Solicitation number
- N4008525R2689
About this file
This Scope of Work (SOW) details a contract for replacing two cracked sand filters at the LCAC Wash Rack located at Joint Expeditionary Base Little Creek/Fort Story in Virginia Beach, Virginia, for Assault Craft Unit 4 (ACU-4). The project involves removing two existing Astral Products Inc. filter tanks (approximately 9 feet tall with a 6.5-foot diameter), disposing of existing filter media, testing granular activated carbon, and installing new tanks with 4x8 mesh granular activated carbon filter media. Key requirements include maintaining flow requirements, providing new heat tracing and insulation, installing air and pressure relief valves, and completing a system flush and purge.
The contract has a 270-calendar day completion timeline and involves working in an active runway environment with strict safety, security, and environmental compliance requirements. Critical considerations include minimizing wash rack downtime, coordinating with site control tower for equipment movement, obtaining necessary permits (including FAA notification), and adhering to hazardous material handling protocols. The contractor must submit pre-construction documents including an Accident Prevention Plan, Activity Hazard Analysis, detailed schedule, and manufacturer's product data, with closeout submittals including a Demolition and Construction Debris Report and Granular Activated Carbon Test Report.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment E- One_Day_Pass_Request.xls | XLS spreadsheet | |
| Attachment G- PIEE_VENDOR_ACCESS_INSTRUCTIONS.pdf | ||
| Attachment F - PPI_Template.xlsx | XLSX spreadsheet | |
| Attachment C- Site Map.pdf | ||
| RFP LC-3827 Wash Rack.pdf | ||
| Attachment B WD-VA20240167_Mod3.pdf | ||
| Attachment D- SECNAV 5512.pdf | ||
| Attachment I- Solicitation Provisions.docx | DOCX document | |
| Attachment H- Price Proposal Form.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BUILDING #3827 – Replace 2 Cracked Filters eProjects WO#: 1764111
VIRGINIA BEACH, VIRGINIA
SCOPE OF WORK 14 November 2023 Page 1 of 11
***UNCLASSIFIED***
BUILDING #3827
Replace 2 Cracked Filters
At the
Joint Expeditionary Base Little Creek/Fort Story, Virginia Beach, Virginia
PREPARED BY:
NAVFAC MID-ATLANTIC, PWD Little Creek/Fort Story, FEAD FSC PRL23, JEB Little Creek, 1450 Gator Boulevard, Building 3165 Virginia Beach, Virginia 23459-8616
PREPARER(S):
FEAD ET: Adam McBride
SUBMITTED BY:
Facilities Support Contracts Branch Head: Chris Spelce
Date: 27 September 2023
APPROVED BY:
PRL1 Facilities Management Division Director: Craig Machmer
SCOPE OF WORK 14 November 2023 Page 2 of 11
1. POINTS OF CONTACT:
FEAD Contracting Officer: Kate Dinneen, 757-462-5347 FEAD Contract Specialist in charge: TBD FEAD Engineering Technician: TBD Facility Maintenance Specialist (FMS): Melvin Woolard, 757-462-4807 Activity POC (if applicable): Travis Francis, 757-339-8017
2. GENERAL:
2.1 The Contractor shall provide supervision, labor, material and equipment required to perform all work for the following project: Replace two cracked filters for wash rack. All work shall be done in a manner to provide a complete, usable and finished end product. See paragraph “7. WORK REQUIREMENTS” for an expanded and detailed scope of work.
2.2 The Contractor shall comply with the requirements of the most current Contract as prescribed by the Contracting Officer for use on this contract.
2.3 A Pre-Proposal site meeting shall be held at the project site to review and discuss the scope of work and assess existing field conditions, prior to Award of this Task Order. The Contractor and his key personnel involved with the project shall attend with the Government. Coordinate/schedule the date and time with the Contracting Officer’s approval.
2.4 Existing reference drawing CD’s are available upon request. Reference drawings shall be used for informational purposes only, and may not accurately reflect current as-built conditions. The Contractor must not solely rely on the reference drawings to determine existing conditions, but must field verify all existing conditions pertinent to the project.
2.5 All work shall be performed in accordance with, but not limited to, standard industry practices, applicable local, state and federal codes, laws and regulations, and the Unified Facilities Criteria (UFC’s).
2.6 FOR PROJECTS INVOLVING LESS THAN 10,000 SQUARE FEET OF LAND DISTURBANCE,
OR WHEN NO LAND DISTURBANCE PROPOSED BUT POTENTIAL FOR STORMWATER
POLLUTION STILL PRESENT (I.E. Painting, Service Connections, Minor building renovations, hazardous material abatement etc.): The contractor must utilize best management practices to ensure materials (Paints, Solvents, Petroleum Products, Trash, Sediment...Etc.)
associated with this activity do NOT become a pollutant in storm water runoff. The Contractor shall keep a spill kit on hand in case of any equipment failure, hydraulic line break, etc. if heavy equipment will be used for this project. No discharges to the sanitary sewer system, storm system or surface waters are permitted without prior coordination with, and approval from the Water Program Manager! Concrete mixing and/or pouring must be done in a way to prevent entry to storm water conveyances or surface waters. Notify NAVFAC EV-Environmental immediately of any spills (anything other than storm water) to the storm system as well as any spills to any sewer system since notifications will need to be made to the regulatory authorities within 24 hours of discovery.
2.7 Supervision: Have a Supervisor fluent in English on the job site during working hours at all times.
The Supervisor shall be a United States Citizen or a Documented Legal Resident of the United States of America.
SCOPE OF WORK 14 November 2023 Page 3 of 11
3. SPECIAL SCHEDULING REQUIREMENTS/WORK PROCEDURES:
3.1 The project Contract Completion Date (CCD) shall be 270 calendar days from Award of this Task
Order.
3.2 Existing and adjacent spaces to remain in operation during construction shall be protected from damage, dust, and debris at all times. Damage to any existing spaces, finishes, items, furniture and equipment, as a result of the Contractor’s operations, shall be replaced in-kind by the Contractor at no expense to the Government. This is an active runway for Landing Craft Air Cushion Hovercraft (LCAC).
3.3 FOD PREVENTION: The Contractor shall take any/all measures to prevent the spread of Foreign Object Debris (FOD) adjacent to, or onto runway/taxiway pavements or within active hangar bay areas. The Contractor shall take the necessary precautions to fully contain FOD producing operations to the limits of construction as approved by the Contracting Officer and Activity. The Contractor shall keep construction work areas clean to prevent the spread of FOD.
3.4 UTILITIES LOCATION AND VERIFICATION (Exterior): Prior to digging, the appropriate digging permit must be obtained. All underground utilities in the work area must be positively identified by a private utility locating service in addition to any station locating service and coordinated with the station utility department, prior to any digging. Any markings made during the utility investigation must be maintained throughout the contract. The Contractor must physically verify underground utility locations by hand digging using wood or fiberglass handled tools when any adjacent construction work is expected to come within three feet of the underground system. Digging within 2 feet of a known utility must not be performed by means of mechanical equipment; hand digging shall be used. If construction is parallel to an existing utility expose the utility by hand digging every 100 feet if parallel within 5 feet of the excavation. Utilities located within concrete slabs or pier structures, bridges, and the like, are extremely difficult to identify due to the reinforcing steel used in the construction of these structures. Whenever contract work involves concrete chipping, saw cutting, or core drilling, the existing utility location must be coordinated with station utility departments in addition to a private locating service. Outages to isolate utility systems must be used in circumstances where utilities are unable to be positively identified. The use of historical reference drawings does not alleviate the contractor from meeting this requirement. The contractor must perform positive identification and locating of existing utilities prior to any concrete chipping, saw cutting or core drilling of any kind.
3.5 The contractor shall utilize existing isolation valves (if available and usable/pressure holding) and other types of non-destructive system(s) isolation to minimize the draining of water and piping systems to provide the necessary system connections and disconnections. All water drained from existing systems shall be captured and containerized for sampling. Prior to any discharges, the Contractor shall submit the Water Test Report(s) to the JEB Little Creek/Fort Story Waste Water Manager (through the Contracting Officer) for determination and documentation of disposal method(s). The test report submittal(s) shall include an estimate of volume (gallons) and date of scheduled discharge(s). The contractor shall provide the disposal of all drained water in accordance with all applicable federal, state and local regulations. POC: Roger White, (757) 462-5361.
3.6 In the event that hazardous waste is generated, the hazardous waste program manager must be contacted for the appropriate guidance. In addition, any movement of soil/fill material outside of project boundaries, meaning both soil brought onsite and soil from the site relocated to other areas, must be coordinated with the hazardous waste program manager to ensure environmental compliance. POC: Roger White, (757) 462-5361.
3.7 Pre-Outage Coordination Meeting:
SCOPE OF WORK 14 November 2023 Page 4 of 11
Apply for utility outages at least 15 days in advance to the Contracting Officer. As a minimum, the request must include the location of outage, utilities being affected, duration of outage and any necessary sketches. Any/all utility outage requests must be approved by the Contracting Officer prior to starting the work. Once approved, and prior to beginning work on the utility system requiring shut down, attend a pre-outage coordination meeting with the Contracting Officer to review scope of work and the lock-out/tag-out procedures for worker protection.
3.8 Control of Hazardous Energy (Lock-out/Tag-out):
Provide and operate a Hazardous Energy Control Program (HECP) in accordance with EM 385-1- 1 Section 12, 29 CFR 1910.333, 29 CFR 1915.89, and paragraph HAZARDOUS ENERGY
CONTROL PROGRAM (HECP).
3.9 In general terms, demolition work and the use of word “demolish”, shall include the removal and effective management and disposal of existing construction and or structures. Contractor shall take care to prevent damage to existing utilities and construction that are not scheduled for demolition.
If damage occurs, the Contractor shall make repairs, or replacement with new, to the satisfaction of the Contracting Officer and at no cost to the Government. Selling of demolished or salvaged materials and equipment on government properties is prohibited.
3.10 Work Hours: The Contractor’s normal working hours shall be between 0700 to 1630, Monday through Friday, excluding Federal Holidays and other days specifically designated by the Contracting Officer. Advance approval from the Contracting Officer is required for contractor personnel to work outside of normal working hours. Any/all Contractor’s requests to work outside of normal working hours must be given to the Contracting Officer in a form of a written request, occurring no less than 5 calendar days prior to such work, to allow for appropriate approvals and inspections process. The written request must include as a minimum, the specific dates, hours, location, type of work performed, and contract personnel performing the work. Based on the written request, the Contracting Officer, at his discretion, may approve or disapprove the work outside of normal working hours.
3.11 Access to construction work areas shall be limited to the Contractor’s personnel, or other approved personnel as designated by the Contracting Officer. Construction work areas shall have complete and secure separation from adjacent occupied areas, as approved and directed by the Contracting Officer and Activity’s Security Officer.
3.16 Passes and Badges: All Contractor employees, including subcontractors, and subcontractors’ employees, suppliers, and suppliers’ employees shall be required to comply with the Installation Security Requirements regarding personnel, vehicle, equipment, security passes/badges and access to the jobsite. Nothing in the contract shall be construed in any way to limit the authority of the Commanding Officer to prescribe new, or to enforce existing security regulations governing the admission or exclusion of persons and the conduct of persons while aboard the station, including but not limited to, the rights of search of all persons or vehicles aboard the station. All Contractor employees/subcontractors shall have current and valid government issued Contractor Base Access Passes and Badges, in order to perform work under this contract.
Coordinate with the Contracting Officer for other specific security and access requirements.
a) Access to Buildings/ Occupied Buildings: The Contractor may work in or around existing occupied buildings. It shall be the Contractor’s responsibility, through the Contracting Officer, to obtain access to building and facilities and arrange for them to be opened and closed. Do not enter the building(s) without prior approval of the Contracting Officer. The existing buildings and their contents shall be kept secure at all times. Provide temporary closures as required to maintain security. Contract personnel will not be permitted in security-regulated buildings or areas unless cleared by the Security Officer.
SCOPE OF WORK 14 November 2023 Page 5 of 11
b) Passes and Badges: Contractor employees and representatives performing work under this contract are required to be either United States Citizens or Documented Legal Residents, status of which, MUST be verified/confirmed by the Prime Contractor. All Contractor employees shall obtain the required employee and vehicle passes/badges. Each employee shall wear the government issued badge, AT ALL TIMES, over the front of the outer clothing for awareness and visibility. Failure to obtain government issued security and base access passes/badges shall result in the revocation of the Prime Contractor’s Base Access Contractor Passes/Badges, at the sole discretion of the Contracting Officer and/or the Installation Security Officer. The Prime Contractor is totally responsible to instruct/verify/confirm that all employees and subcontractors obtain valid/approved government issued passes and badges. Any work stoppage or work delays caused by the Contractor/Subcontractor’s failure to comply with obtaining appropriate passes/badges or other Security compliance shall not be a cause for contract performance time extension. The Contractor shall be responsible for immediately turning in all terminated employee’s badges to the Pass and ID issuing office.
c) Responsibility for Escorts: The Contractor shall be responsible for coordinating escorts with the Building Activity/Tenant at all times. The Contracting Officer and other NAVFAC personnel “shall not” be responsible for the coordination of escorts for Contractor personnel.
3.17 The Contractor shall provide construction barriers for redirection of people and equipment during the entirety of construction. Barriers must be able to withstand being placed in an area with active LCAC operations.
3.18 To minimize downtime for the area, construction activities may not start until the Contractor provides confirmation of receipt of all new products and materials necessary to complete the work, prior to start of construction.
3.19 Minimize the wash rack downtime. The wash rack is critical to ACU-4’s operations. Preorder, pre-assemble and ensure all necessary material, tools and equipment are on-site prior to taking the wash rack out of service. Lock out/Tag out policies and procedures shall be utilized to take the wash rack out of service.
3.20 The LCAC wash rack is in the approach zone to Norfolk International Airport. The Contractor shall apply for “Notice of Proposed Construction or Alteration”, FAA form 7460-1 via the www.faa.gov website. Allow a minimum of 45 days for FAA approval. Any equipment required for this project having an elevation over approximately 100’ above mean sea level (elevation 0.0) may have restricted use. The contractor shall contact Norfolk Airport Authority for guidelines in the use and identification of all cranes and equipment prior to starting work. All Crane booms shall be flagged during the day and have lights provided for night.
3.21 Movement of manpower, vehicles, equipment and materials across the LCAC runway shall be coordinated with the site control tower.
SCOPE OF WORK 14 November 2023 Page 6 of 11
4. SAFETY:
4.1 The Contractor shall comply with the most current edition of EM-385-1-1.
4.2 The Contractor shall submit the Accident Prevention Plan (APP) and Activity Hazard Analysis (AHA) plan for approval by the Contracting Officer. Submit within 3 days from issuance of this Task Order, and obtain approval prior to start of any construction activities. Field work may not begin until the APP is accepted by the Contracting Officer.
4.3 Before beginning each activity, task or Definable Feature of Work (DFOW) involving a type of work presenting hazards not experienced in previous project operations, or where a new work crew or subcontractor is to perform the work, the Contractor(s) performing that work activity must prepare an Activity Hazard Analysis (AHA). AHAs must be developed by the Prime Contractor, subcontractor, or supplier performing the work, and provided for Prime Contractor review and approval before submitting to the Contracting Officer. AHAs must be signed by the SSHO, Superintendent, QC Manager and the subcontractor Foreman performing the work. Format the AHA in accordance with EM 385-1-1, Section 1 or as directed by the Contracting Officer. Submit the AHA for review at least 15 working days prior to the start of each activity task, or DFOW. The Government reserves the right to require the Contractor to revise and resubmit the AHA if it fails to effectively identify the work sequences, specific anticipated hazards, site conditions, equipment, materials, personnel and the control measures to be implemented.
4.4 Provide Competent Persons in accordance with EM 385-1-1, Appendix Q and herein. Competent Persons for high risk activities include confined space, cranes and rigging, excavation/trenching, fall protection, and electrical work. The CP for these activities must be designated in writing, and meet the requirements for the specific activity (i.e. competent person, fall protection). Provide the credentials of the Competent Persons(s) to the Contracting Officer for information in consultation with the Safety Office.
4.5 All hot work and hot work permits shall conform to EM-385-1-1 and any local policies. Hot work permits must be attained from JEB Little Creek/Fort Story Fire Dept. (757-462-4445) prior to performing activities which generate or have the potential to generate, heat, sparks, or open flames, such as abrasive blasting burning, brazing, cutting, grinding, powder-actuated tools, hot riveting, soldering, thawing activities, welding, or any similar operation capable of initiating fires or explosions.
SCOPE OF WORK 14 November 2023 Page 7 of 11
5. HAZARDOUS MATERIALS DISCLOSURE STATEMENT(S):
5.1 Asbestos and Lead test reports are not available for Building 3827 prior to issuance of this Task
Order. Since the building was built after 1985, it is not anticipated that any hazardous materials are present within the area of work. However, if hazardous materials are encountered during performance of the work, the Contractor must avoid disturbing any hazardous materials to the fullest extent possible while being able to accomplish the work. If hazardous materials are encountered and disturbed, the Contractor must adhere to the requirements as stated in the subsequent paragraphs below.
5.2 For repair, remodeling, or minor construction and demolition, the Contractor may be required to work in areas that have, but not limited to, flooring, walls, ceilings, insulation, roofing materials and paints etc. etc., that may have asbestos or lead paints, or PCB and/or other hazardous materials requiring abatement and/or management according to applicable National and Local Environmental Protection laws and regulations. For work in soil excavation and other exterior construction etc., the Contractor may be required to work with contaminated material involving abatement or management of these contaminated materials. However, if during the performance of the work the Contractor encounters hazardous substances not known prior to issuance of this Task Order; the Contractor shall immediately stop work and inform the Contracting Officer for direction. In no instance shall the Contractor perform the work involving the hazardous material without notifying and receiving approval from the Contracting Officer for direction.
5.2.1 Asbestos Containing Materials (For projects that require disturbance or removal): Asbestos containing materials shall be removed, transported and managed in accordance with the following regulations: 29 CFR 1926.1101, and 40 CFR 61-Subpart M.
Category I & II Nonfriable Asbestos: Disturbance, demolition/removal of Category I & II nonfriable asbestos containing materials (approved to be left in place during the work) shall be performed in accordance with 40 CFR 61-Subpart M.
5.2.2 Paint Containing Lead, Cadmium and Chromium (For projects that require disturbance or removal): Work which requires the disturbance or removal of paint that has been determined to contain all or any of the following: lead, cadmium and chromium, shall be performed in accordance with 29 CFR 1926.62, 29 CFR 1926.1126 and 29 CFR 1926.1127.
5.2.3 Other Hazardous Materials (For projects that require disturbance or removal): Work which requires the disturbance or removal of any of the following: mercury and LLR Components, and PCB’s, shall be performed in accordance with 29 CFR 1910.1000, 10 CFR 20, 40 CFR 273, and
40 CFR 761.
5.3 Hazardous Materials Reports: In the event that work involves hazardous materials, provide the following reports:
5.3.1 Daily Reports: Notify the Contracting Officer of work involving hazardous materials abatement and removal, including quantities involved, on daily reports.
5.3.2 Hazardous Material Inventory Report: The Contractor shall provide a list of all hazardous materials used on the site.
SCOPE OF WORK 14 November 2023 Page 8 of 11
6. SUBMITTALS:
6.1 Pre-Construction Submittals: The Contractor shall submit the following, for government approval, prior to the start of any construction activities and throughout the construction process:
Accident Prevention Plan and Quality Control Plan
Activity Hazard Analysis
Detailed schedule to include down times of wash rack
Manufacturer’s Product Data: Submit manufacturer’s written detailed product data cut sheets, with instructions for installation, adjustment, cleaning and maintenance instructions.
Site plan to include laydown areas
Manufacturer Warranties
6.2 Closeout Submittals: The Contractor shall submit the following, for government approval, upon completion of construction:
Demolition and Construction Debris Report
Granular Activated Carbon Test Report - TCLP Metals, TPH, DRO and GRO
Startup Report
SCOPE OF WORK 14 November 2023 Page 9 of 11
7. WORK REQUIREMENTS:
7.1 Assault Craft Unit 4 (ACU-4) requires replacement of the LCAC Wash Rack filters, Qty. 2, due to deterioration of the tanks and seals causing leaks. The filters are located in the immediate vicinity of Building 3827 at JEB Little Creek. The existing filter tanks are approximately 9 feet tall with an approximate diameter of 6 feet, six inches. The filter tanks are on an equipment pad measuring approximately 8 feet, six inches by 15 feet, six inches. Piping connections to the tank are made with 8-inch flanged connections.
7.2 Test the granular activated carbon for TCLP metals, TPH, DRO and GRO.
7.3 Remove and dispose of all filter media off site. Remove all external insulation. Demolish tanks complete (Qty. 2). Remove heat tape to nearest junction.
Existing Tanks:
o Astral Products Inc.
o Model: 2612H5A1 o Serial - Tank 1: 99008179 Tank 2: Unknown o Filtration Area: 33.80 SQ FT EA o Max Operating Pressure: 50 PSI
7.4 Install new tanks on existing equipment pad and 8-inch flanged pipe connections. Modify pad and piping as required. Flow requirements must be maintained. Install all new filter media per manufactured recommendations to include any de-gassing requirements. Filter media to be used:
4 x 8 mesh granular activated carbon
7.5 Provide new heat trace at 7 watt per linear foot for exposed water piping. Insulate piping with 2-inch cellular glass insulation and aluminum jacketing. Include new air relief, pressure relief and tank drain valves. Flush and purge and test entire system.
7.6 All information here-in is for reference only. The Contractor must FIELD VERIFY all existing conditions, prior to fabrication and placing orders for any new items/equipment. The Contractor must take sole ownership/cost responsibilities for re-work or re-ordering any new items/equipment provided that does not fit or function properly within existing conditions.
7.7 The contractor shall dispose of all existing demolished/removed materials off base and will completely clean up job site after work is performed. Maintain daily site clean-up at the end of every workday during the entirety of the construction period, to prevent any hazard potential. Disposal shall be in accordance with all existing Local, State, Federal and NAVFAC MIDLANT EV rules and regulations.
7.8 Shop Drawings and IOM supplied as separate attachment for reference
3827 Wash Rack Filters - Carbtrol Shop Drawings & IOM.pdf
SCOPE OF WORK 14 November 2023 Page 10 of 11
8. ATTACHMENTS (following the Scope of Work):
8.1 Location Map.
SCOPE OF WORK 14 November 2023 Page 11 of 11
8.2 Photographs.
**End of SCOPE OF WORK**
Figure 2 - Filters Figure 1 Connections
Figure 3 - Nameplate Figure 4 - Air Vent & Pressure Relief
File details come from the government source that posted it. Updated .