ATTACHMENT_A_Reevesville_Water_Line_Improvements_Specifications.Stamped_For_Bids.pdf
PDF 27 MB Posted
- Attached to
- Reevesville Water Line Improvements
- Solicitation number
- 2026-46
- Issued by
- Dorchester County, South Carolina
About this file
Summary: Reevesville Water Line Improvements Bid Documents
This set of contract documents comprises the technical specifications and permit approvals for the Reevesville Water Line Improvements project in Dorchester County, South Carolina. Dorchester County Water and Sewer (DCWS) is seeking qualified contractors to construct approximately 5,568 linear feet of 8-inch water main installation along Blossom Street, Main Street, Reeves Street, and Johnston Avenue (US Highway 78), including 935 linear feet of 8-inch DR18 C900 Fusible PVC pipe installed via horizontal directional drilling, six fire hydrants, twenty-six service reconnections, eight new 2-inch air release valves, and replacement of seven existing 2-inch air release valves in the Winterseat and Carolina Bay subdivisions. The bid for construction was due January 16, 2026, with work to be completed by October 2, 2028. The project includes mandatory pre-construction meetings, progress meetings scheduled monthly at minimum, submittal of detailed shop drawings, construction schedules, and quality assurance documentation. All work must comply with South Carolina Department of Environmental Services (SCDES) standards, South Carolina Department of Transportation (SCDOT) encroachment permits, and the National Pollutant Discharge Elimination System (NPDES) General Permit for Stormwater Discharges from Construction Activities.
The specifications require contractors to provide all labor, materials, equipment, and temporary facilities necessary for complete installation, testing, and commissioning of the water system at no additional cost to DCWS. Payment will be structured through lump sum and unit price bid items, with measurement and payment detailed in Section 01 20 00, including separate payment for mobilization (not to exceed 3% of total construction cost), pipe installation by linear foot, fittings by ton, valves and hydrants by unit, service reconnections, pavement restoration, erosion control, and traffic control. All materials must be 100% manufactured in the United States and comply with AWWA standards, NSF certification requirements for potable water contact, and ASTM specifications. The project has obtained Water Supply Construction Permit 38897-WS, SCDOT Encroachment Permit 296660, and Coastal Zone Consistency Determination GCZC-24-003, with all work subject to conditions requiring Best Management Practices, permanent stabilization of disturbed areas, compliance with stormwater management requirements, and notification protocols for any discovery of historic or archaeological materials.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DORCHESTER COUNTY, SOUTH CAROLINA
CONTRACT DOCUMENTS FOR
CONSTRUCTION OF:
REEVESVILLE WATER LINE IMPROVEMENTS
JANUARY 2026
FOR BIDS
January 16, 2026
DIVISION 01
GENERAL REQUIREMENTS
Sunnary of Work 01 11 00
Coordination with DCWS' Operations 01 14 00
Measurement and Payment 01 20 00
Project Meetings 01 31 19
Construction Project Schedule 01 32 00
Submittal Procedures 01 33 00
Temporary Utilities 01 51 00
Traffic Control 01 55 26
Temporary Controls 01 57 00
Product Delivery Requirements 01 65 00
Product Storage and Protection Requirements 01 66 00
Field Engineering 01 71 23
Protection of Work and Property 01 71 33
Closeout Requriements 01 77 19
Project Record Documents 01 78 19
DIVISION 31
EARTHWORK
Earthwork 31 00 01
Dewatering 31 23 19
Erosion and Sedimentation Control 31 25 00
DIVISION 33
UTILITIES
Water Distribution System 33 00 01
Water Service Connections 33 01 01
Sanitary Sewer Force Mains 33 05 01
Potable Water Mains Testing and Disinfection 33 10 01
Horizontal Directionally Drilled (HDD) Pipe 33 23 50
DIVISION 40
PROCESS INTERCONNECTIONS
Fusible Polyvinyl Chloride (fPVC) Pipe 40 05 32
APPENDIX
A Approved Permits
Reevesville Water Line improvements
January 2026
1/16/2026 01 11 00-1 Dorchester County Reevesville Water Line Improvements
SECTION 01 11 00
SUMMARY OF WORK
PART 1 – GENERAL
1.01 SUMMARY
A. Section Includes:
1. Summary
2. Location and Description of Work
3. Construction Contracts, This Project
4. Construction Contracts, other Projects
5. Work by Others
6. Work by DCWS
7. DCWS Furnished Equipment and Materials
8. DCWS Assigned Procurement Contracts
9. DCWS Pre-selected Equipment and Materials
10. Sequence and Progress of Work
11. Contractor’s Use of Site
12. Easements and Rights-of-Way
13. Notices to Owners and Authorities of Properties Adjacent to the Work
14. Salvage of Equipment and Materials
15. Partial Utilization by DCWS
1.02 LOCATION AND DESCRIPTION OF WORK
A. The Work is located at the following Site:
1. Along Blossom St, Main St, and Main St within the road right-of-way.
1/16/2026 01 11 00-2 Dorchester County
2. Temporary construction easement as shown on the plans.
B. The Work to be performed under this Contract includes, but is not limited to, constructing the Work described below and all appurtenances related to the Work. The Work shall be as follows:
1. Installation of approximately 5,568 linear feet (LF) of 8-inch water main, which includes 935 LF of 8-inch DR18 C900 Fusible PVC (fPVC) installed by horizontal directional drill method, six (6) fire hydrants, twenty-six (26) service reconnections, and necessary appurtenances. The project also includes eight (8) new 2-inch air release valves and replacing seven (7) 2-inch air release valves in the Winterseat and Carolina Bay subdivisions.
1.03 CONSTRUCTION CONTRACTS
1. Work specified in Divisions 1 through 40 (inclusive) of the Specifications.
2. Work shown on sheets 1 through 8 (inclusive) of the Drawings.
1.04 CONSTRUCTION CONTRACTS, OTHER PROJECTS (NOT USED)
1.05 WORK BY OTHERS (NOT USED)
1.06 WORK BY DCWS
A. DCWS will perform the following in connection with the Work: Operate all existing valves, gates, pumps, equipment, and appurtenances that are part of DCWS’ operation, unless otherwise specified or indicated.
1.07 DCWS-FURNISHED EQUIPMENT AND MATERIALS (NOT USED)
1.08 DCWS-ASSIGNED PROCUREMENT DOCUMENTS (NOT USED)
1.09 DCWS-PRE-SELECTED EQUIPMENT AND MATERIALS
A. None.
B. Contractor shall provide equipment and materials in accordance with the Contract
Documents.
1.10 SEQUENCE AND PROGRESS OF WORK
A. Requirements for sequencing and coordinating with DCWS’ operations, including maintenance of plant operation during construction, and requirements for tie-in and shutdown, are in Section 01 14 00 – Coordination with DCWS’ Operations.
1.11 CONTRACTOR’S USE OF SITE
1/16/2026 01 11 00-3 Dorchester County
A. Contractors’ use of the Site shall be confined to the areas shown. Contractors shall share use of the Site with other contractors and others specified in this Section.
B. Contractor shall move stored products that interfere with the operation of DCWS, other contractors, or others performing work for DCWS.
1.12 EASEMENT AND RIGHTS-OF-WAY
A. Easements and rights-of-way will be provided by DCWS in accordance with the General
Conditions. Confine construction operations to within DCWS’s property, public rights-of-way, easements obtained by DCWS, and the limits shown. Use care in placing construction tools, equipment, excavated materials, and products to be incorporated into the Work to avoid damaging property and interfering with traffic. Do not enter private property outside the construction limits without permission from the owner of the property.
1.13 NOTICES TO OWNERS AND AUTHORITIES OF PROPERTIES ADJACENT TO THE
WORK
A. Notify owners of adjacent property and utilities when execution of Work may affect their property, facilities, or use of property.
B. When it is necessary to temporarily obstruct access to the property, or when utility service connections will be interrupted, provide notices sufficiently in advance to enable affected persons to provide for their needs. Conform to Laws and Regulations, whether delivered orally or in writing.
C. Notify utility owners and other concerned entities at least 48 hours before cutting or closing streets or other traffic areas, excavating near underground facilities, or exposing utilities.
1.14 PARTIAL UTILIZATION BY DCWS
A. DCWS reserves the right to enter and use portions of the Work prior to the Certificate of
Substantial Completion being issued by DCWS.
B. DCWS shall be responsible for preventing premature connections by private and public parties, persons, or groups of people before DCWS issues a Certificate of Substantial
Completion for the portion of the Work being partially utilized by DCWS.
C. Contractor shall cooperate with DCWS and DCWS’s agents to accelerate completion of
Work designed for partial utilization by DCWS in accordance with Contractor’s progress schedule.
1/16/2026 01 11 00-4 Dorchester County
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION (NOT USED)
END OF SECTION
1/16/2026 01 14 00-1 Dorchester County
SECTION 01 14 00
COORDINATION WITH DCWS’ OPERATIONS
1. Requirements for coordinating with DCWS’ operations during the Work and included requirements for tie-ins and shutdowns necessary to complete the Work without impact on DCWS’ operations except as allowed in this Section.
2. The Contractor shall provide labor, materials, tools, equipment, and incidentals shown, specified, and required to coordinate with DCWS’s operations during the
Work.
B. General Requirements:
1. Except for shutdowns specified in this Section, perform the Work such that DCWS’s facility remains in continuous satisfactory operation during the Project Schedule and conduct the Work such that the Work does not: impede DCWS’ production or processes, create potential hazards to operating equipment and personnel, reduce the quality of the facility’s products or effluent, or cause odors or other nuisances.
2. Work not specifically covered in this Section or in referenced Sections may, in general, be completed at any time during regular working hours in accordance with the General Conditions and Supplementary Conditions, subject to the requirements in this Section.
3. Contractor has the option of providing additional temporary facilities that can eliminate or mitigate a constraint without additional cost to DCWS, provide such additional temporary facilities: do not present hazards to the public, personnel, structures, and equipment; that such additional temporary facilities do not adversely affect DCWS’ ability to comply with Laws and Regulations, permit, and operating requirements; that such temporary facilities do not generate or foster the generation of odors and other nuisances; and that requirements of the Contract Documents are fulfilled.
4. Coordinate shutdowns with DCWS. When possible, combine multiple tie-ins into a single shutdown to minimize impacts on DCWS’s operation and processes.
5. Do not shut off or disconnect existing operating systems, unless accepted by
DCWS in writing. Operation of existing equipment will be done by DCWS unless
1/16/2026 01 14 00-2 Dorchester County otherwise specified or indicated. Where necessary for the Work, the Contractor shall seal or bulkhead DCWS-operated gates and valves to prevent leakage that may affect the Work, DCWS’s operations, or both. Provide temporary watertight plugs, bulkheads, and line stops as required. After completing the Work, remove seals, plugs, bulkhead, and line stops to the satisfaction of DCWS.
C. Continuous Treatment Provisions:
1. Federal regulations prohibit bypassing of untreated or partially treated wastewater or sewer during construction Work.
2. The Contractor shall provide labor, equipment, materials, and incidentals to provide continuous treatment to the level prior to construction Work.
3. The Contractor shall be responsible for providing temporary pumping facilities, systems, piping, valves, appurtenances, equipment, materials, and temporary utilities necessary to complete the Work without treatment bypassing.
D. Related Sections:
1. Section 01 11 00 – Summary of Work
1.02 REFERENCES
1. Definitions: A “shutdown” is when a portion of the normal operations of DCWS’s facility, whether equipment, systems, piping, or conduit, must be temporarily suspended or taken out of service to perform the Work.
1.03 ADMINISTRATIVE REQUIREMENTS
A. Coordination:
1. Review installation procedures under other Specification sections and coordinate
Work that must be performed with or before the Work specified in this Section.
2. Notify other contractors in advance of Work requiring coordination with DCWS’s operations, to provide other contractors sufficient time for work included in their contracts that must be installed with or before Work specified in this Section.
3. When possible, combine multiple tie-ins into a single shutdown to minimize impacts on DCWS’s operations and processes.
B. Pre-Shutdown Meetings: The Contractor shall schedule and conduct a meeting with
DCWS prior to scheduling the shutdown.
C. Sequencing:
1/16/2026 01 14 00-3 Dorchester County
1. Perform the Work in the specified sequence. Certain phases or stages of the Work may require working 24-hour days or working during hours outside of regular working hours. Work may be accelerated from a later stage to an earlier stage if
DCWS’s operations are not adversely affected by the proposed sequence change, with DCWS’s acceptance. The stages specified in this Section are sequential in the performance of the Work.
D. Scheduling:
1. Work that may interrupt normal operations shall be accomplished at times convenient to DCWS.
2. Furnish at the Site, in close proximity to the shutdown and tie-in work areas, tools, equipment, spare parts, and materials, both temporary and permanent, necessary to successfully complete the shutdown. Complete to the extent possible, prefabrication of piping and other assemblies prior to the associated shutdown demonstrates to DCWS’ satisfaction that the Contractor has complied with these requirements before commencing the shutdown.
3. If the Contractor’s operations cause an unscheduled interruption of DCWS’ operation, immediately re-establish satisfactory operation for DCWS.
4. Unscheduled shutdowns or interruptions of continued safe and satisfactory operation of DCWS’ facilities that result in fines or penalties by authorities having jurisdiction shall be paid solely by the Contractor if, in DCWS’ opinion, the
Contractor did not confirm the requirements of the Contract Documents, or was negligent in the Work, or did not exercise proper precautions in conducting the
5. Work requiring service interruptions for tie-ins shall be performed during scheduled shutdowns.
6. Temporary, short-term shutdowns of smaller piping, conduits, equipment, and systems may be required. Coordinate requirements for such shutdown with DCWS.
1.04 SUBMITTALS
A. Action/Informational Submittals:
1. Substitute Sequence Submittal: When deviation from a specified sequence is proposed, provide a submittal explaining in detail the proposed sequence change and its effects, including evidence that DCWS’ operations will not be adversely affected by the proposed change. List benefits or proposed sequence changes, including benefits to the Progress Schedule.
2. Shutdown Planning Submittal:
1/16/2026 01 14 00-4 Dorchester County
a. For each shutdown, submit an inventory of labor and materials required to perform the shutdown and tie-in tasks, an estimate of the time required to accomplish the complete shutdown, including time for DCWS to take down and start up existing equipment, systems, or conduits, and a written description of the steps required to complete the Work associated with the shutdown.
b. Furnish submittal to DCWS at least thirty (30) days prior to the proposed shutdown start date. Do not start the shutdown until you obtain DCWS’ acceptance of the shutdown planning submittal.
B. Shutdown Notification: After acceptance of the shutdown planning submittal and prior to starting the shutdown, provide written notification to DCWS of the date and time each shutdown is to start. Provide notification at least 72 hours in advance of each shutdown.
1.05 SITE CONDITIONS
A. General Constraints: Specified in the Contract Documents are the sequence and shutdown durations, where applicable, for DCWS’s equipment, systems, and conduits that are to be taken out of service temporarily for the Work. New equipment, materials, and systems may be used by DCWS after the specified field quality controls and testing are successfully completed, and the materials or equipment are Substantially Complete.
B. The following constraints apply to coordination with DCWS’ operations:
1. Operational Access: DCWS personnel shall have access to equipment and areas that remain in operation.
2. Schedule and perform equipment and system start-ups for Monday through
Thursday. Equipment and systems shall not be placed into operation on Friday, Saturday, or Sunday without prior approval of DCWS.
3. Dead-End Valves or Pipe: Provide blind flanges, watertight bulkheads, or valves at temporary and permanent terminuses or pipes and conduits. Blind flanges and bulkheads shall be suitable for the service and braced and blocked, as required, or otherwise restrained as directed by DCWS. Temporary valves shall be suitable for their associated service. Where the valve is provided at the permanent terminus of pipe or conduits, it also provides, on the downstream side of the valve, a blind flange with a drain/flushing connection.
1.06 SUGGESTED SEQUENCE OF WORK
A. Perform the Work in the specified sequence or as otherwise approved by DCWS.
Certain phases or stages of the Work may require working 24-hour days or working during hours outside of regular working hours. Work may be accelerated from a later stage to an earlier stage if DCWS’s operations are not adversely affected by the
1/16/2026 01 14 00-5 Dorchester County proposed sequence change, and with DCWS’s acceptance. The stage specified in this
Section is sequence dependent.
1. Stage 1: Pre-construction meeting
2. Stage 2: Install erosion and sediment control
3. Stage 3: Field verify all underground utilities along the water main alignment.
4. Stage 4: Install a new 8-inch fPVC water main by the horizontal directional drill method.
5. Stage 5: Install a new 8-inch PVC water main by open-cut and necessary appurtenances.
6. Stage 6: Perform necessary testing on the new 8-inch water main.
7. Stage 7: The Engineer shall apply for a permit to operate from DHEC.
8. Stage 9: The Contractor shall coordinate with DCWS for tie-in work at STA 0+00 once PTO has been obtained.
9. Stage 10: Stabilize grassing. Once stabilized, remove all temporary silt fence and other BMP’s.
1.07 TIE-INS
A. Contractor shall perform all required tie-ins to complete the Work.
1.08 SHUTDOWNS
A. General:
1. Work that may interrupt normal operations shall be accomplished at times convenient to DCWS.
2. Furnish at the Site, in close proximity to the shutdown and tie-in work areas, tools, equipment, spare parts, and materials, both temporary and permanent, necessary to successfully complete the shutdown. Complete to the extent possible, prefabrication of piping and other assemblies prior to the associated shutdown.
Demonstrate to DCWS’ satisfaction that the Contractor has complied with these requirements before commencing the shutdown.
3. If the Contractor’s operation causes an unscheduled interruption of DCWS’ operations, immediately re-establish satisfactory operation for DCWS.
1/16/2026 01 14 00-6 Dorchester County
4. Unscheduled shutdowns or interruptions of continued safe and satisfactory operation of DCWS’ facilities that result in fines or penalties by authorities having jurisdiction shall be paid solely by the Contractor if, in DCWS’ opinion, the
Contractor did not confirm the requirements of the Contract Documents, or was negligent in the Work, or did not exercise proper precaution in conducting the
PART 3 – EXECUTION
3.01 GENERAL
A. In addition to the requirements of this Section, conform to the requirements in the
Contract Documents.
3.02 DETAILED SHUTDOWN REQUIREMENTS
A. Prior to Typical Shutdown:
1. Obtain DCWS’ acceptance of the proposed shutdown planning submittal and shutdown notification submittal.
2. Submittal and approval of all shop drawings required.
3. Coordinate with DCWS’s operations staff on the timing of shutdown and provide the required notification to DCWS.
4. Bring necessary piping, couplings, valves, equipment, and appurtenances to the work areas.
5. Assist DCWS in preparing to temporarily take the Project out of service.
6. Coordinate other tie-ins to be performed simultaneously.
7. Install and ensure the functionality of temporary systems as applicable.
B. During Typical Shutdown:
1. Verify operations of sewer systems.
2. Following approval from DCWS, return the system to operation.
C. Following Typical Shutdown:
1/16/2026 01 14 00-7 Dorchester County
1. Verify functionality of equipment and system.
2. Verify operation of the new system and verify that joints in piping are watertight as applicable.
3. Repair joints that are not watertight as applicable.
4. Remove temporary systems as applicable.
1/16/2026 01 20 00-1 Dorchester County
SECTION 01 20 00
MEASUREMENT AND PAYMENT
1. Items listed in this Section refer to and are the same pay items listed in the Bid
Form and constitute all pay items for completing the Work.
2. Compensation for all services, items, materials, and equipment shall be included in prices stipulated for lump sum and unit price pay items listed in this Section and included in the Contract.
3. No direct or separate payment will be made for providing miscellaneous temporary or accessory works, bonds, insurance, or other requirements of the General
Conditions, Supplementary Conditions, General Requirements, and other requirements of the Contract Documents.
4. Each lump sum and unit bid price shall include an amount considered by the
Contractor to be adequate to cover the Contractor’s overhead and profit for each separately identified item.
B. Related Sections:
1. Payments to Contractor: Refer to General Conditions, Supplementary Conditions, and Agreement.
2. Changes to Contract Price: Refer to General Conditions, Supplementary
Conditions.
3. Schedule of Values: Refer to General Conditions, Supplementary Conditions.
1.02 DCWS’ ESTIMATE OF QUANTITIES
A. DCWS’ estimated quantities for unit price pay items, as listed in the Bid Form, are approximate only and are included solely for the purpose of comparison of Bids. DCWS does not expressly or by implication agree that the nature of the materials encountered below the surface of the ground or the actual quantities of material encountered or required will correspond therewith and reserves the right to increase or decrease any quantity or to eliminate any quantity as DCWS may deem necessary. The Contractor will not be entitled to any adjustment in a unit price bid as a result of any change in an
1/16/2026 01 20 00-2 Dorchester County estimated quantity and agrees to accept the aforesaid unit bid prices as complete and total compensation for any additions caused by changes or alterations in the Work ordered by DCWS.
A. Contractor shall include all additional Work items, services, goods, resources, and manpower necessary for the installation of the Work to provide a completely functional system in accordance with the Contract Documents. The Contractor shall include these costs associated with providing a completely functional system within the listed items on the Bid Form and as specified herein.
B. LUMP SUM BID ITEMS:
1. Lump Sum measurement will be for the entire items, unit of work, structure, or combination thereof, as specified and as indicated in the Schedule of Prices in the
Bid Form. Measurement and payment for all bid items indicated as Lump Sum shall include the cost of all labor, materials, and equipment necessary to furnish, install, clean, test, and place each bid item into operation, including permitting, general conditions, overhead, and profit.
2. Progress payments will be based on the Schedule of Values prepared by the Contractor and approved by DCWS before acceptance of the first Application for Payment.
3. For the Contractor to request progress payments against Lump Sum items, the Contractor shall provide a disaggregation or breakdown in sufficient measurable detail that is acceptable to DCWS.
4. Measurement shall be based on the estimated percent complete of each Lump
Sum item of the Schedule of Values, as determined by DCWS.
5. Payment will be made at the lump sum price proportional to the completion percentages approved by DCWS.
C. UNIT PRICE BID ITEMS
1. Quantity and measurement estimates stated in the Schedule of Prices in the Bid
Form are estimates for bidding purposes only. Actual payment shall be based on actual quantities installed, in-place, as measured and/or verified by DCWS.
2. Unless otherwise provided in the General Conditions, the bid unit prices shall be in effect throughout the contract duration, regardless of variances between the estimated quantities and the actual installed quantities.
3. The Contractor shall make no claim, nor receive any compensation, for anticipated profits, loss of profit, damages, or any extra payment due to any difference
1/16/2026 01 20 00-3 Dorchester County between the amounts of work completed, or materials or equipment furnished, and the estimated quantities.
4. Unless otherwise approved by DCWS, any unit quantities exceeded may not be invoiced until the estimated quantity is increased by the contract change order.
5. The Contractor shall assist DCWS by providing necessary equipment, workers, and survey personnel as required to measure quantities.
6. Measurement
a. Measurement for progress payment shall be made by, or approved by, DCWS based on the estimated effective quantity installed. The effective quantity installed represents the actual units or quantities installed, adjusted for incomplete elements or components.
b. Unless otherwise provided for in the Schedule of Prices in the Bid Form, unit price items are all inclusive of all related work, direct and indirect, to provide a complete and functional item. For example, water pipe installation would include pipe, trenching, temporary sheeting/shoring, dewatering, bedding, installation, backfill, compaction per detail and specification, testing, flushing, disinfection, and commissioning; including all labor, materials, site access and equipment necessary to furnish, install, clean, test, and place into operation; including permitting, general conditions, overhead, and profit.
c. The final measurement shall be based on actual quantities, jointly measured by the Contractor and DCWS, complete, fully tested, and placed into service.
7. Payment
a. Progress payments shall be in accordance with the contract documents based on estimated effective quantities installed, paid at the bid unit price.
b. The final payment shall be based on actual quantities, fully installed, tested, and placed into service, paid at the bid unit price.
PART 2 – BID ITEMS:
1. BID ITEM NO. 1 – MOBILIZATION
a. Payment for Bid Item No. 1 shall be made in the lump sum price in the Bid
Form and shall also include, but not be limited to, any permits, licenses, fees, assembling all equipment, materials, tools, etc., and transporting them to and from the worksite. The amount bid for Bid Item No. 1 – Mobilization shall not exceed (3) percent of the Total Construction Cost. All costs
1/16/2026 01 20 00-4 Dorchester County associated with demobilization shall also be included herein under Bid Item
No. 1.
b. No separate payment for access outside the existing easements as shown on the Contract Drawings will be made. All costs of equipment, labor, and materials required for additional access outside of existing easements shall be included in the price bid items to which they pertain.
2. BID ITEM NO. 2 – NEW 8” C900 DR18 FUSIBLE PVC BY HORIZONTAL
DIRECTIONAL DRILL
a. Payment for Bid Item No. 2 shall be made in the unit price per linear foot
(LF) as stated in the Bid Form shall also all costs of mobilization, demobilization, materials, layout of work, transport of pipe to the project site, locating/potholing of existing utilities, excavation, trench box and/or sheeting
(if needed), pipe fusion, drilling operations, overhead, profit, insurance, tracer wire, dummy valve boxes (if required), testing, drill path survey, pipe support, ballast (if required), record keeping, backfilling, proper bedding & compaction (per detail and specifications), cleanup, restoration, protection of all existing utilities, all requirements per Section 33 23 50, etc. for complete installation.
b. Measurement will be the horizontal length along the centerline of the water main from the beginning to the end of the drilling as indicated on the plans.
c. The depth and length of the pipe shown on the plans are the minimum required. The additional length required to increase the depth radius to accommodate the pipe installation will be the responsibility of the contractor.
3. BID ITEM NO. 3 THRU 5 – 8” C900 DR18 PVC AND 6” DUCTILE IRON C153
WATER MAIN PIPING
a. Payment for Bid Item No. 3 through 5 shall be made in the unit price per linear foot (LF) as stated in the Bid Form shall also include transport of pipe to the project site, locating/potholing of existing utilities along the route, excavation, dewatering/well points (if needed), proper bedding & compaction
(per specifications), tracer wire, metallic detection tape, dummy valve boxes, backfilling, trench box/sheeting (if needed), testing, etc. for complete installation. Measurement will be from the center to the center of fittings; no deduction will be made for the space occupied by valves or fittings.
b. Restrained joint pipe will be paid for at unit prices per LF as stated in the Bid
Form and include all items described in “3.a.” above and the cost of all restrained joint accessories.
1/16/2026 01 20 00-5 Dorchester County
4. BID ITEM NO. 6 – FITTINGS
a. Measurement for fittings, including couplings/sleeves/plugs, shall be per unit per ton as stated in the Bid Form and shall include cost for restraint, with the weight of fittings being based upon the published weight of the compact
(C153) fitting body. No payment will be made for the weight of joint accessories for mechanical joints, including joint restraints.
5. BID ITEM NO. 7 AND NO. 8 – 6”/8” GATE VALVE WITH VALVE BOX & MARKER
a. Valves will be paid at the unit price per each as stated in the Bid Form and shall include the cost of the valve, valve box, concrete marker, concrete collar, cleanup, per detail, etc., for complete installation.
6. BID ITEM NO. 9 – FIRE HYDRANT
a. Hydrants will be paid at the unit price per each as stated in the Bid Form and shall include the cost of the hydrant, excavation, stone, cleanup, per detail, etc., for complete installation.
7. BID ITEM NO. 10 & NO. 11 – 8” & 6” TIE-IN CONNECTION TO EXISTING
WATER MAIN
a. Payment will be made at the unit price per each as stated in the Bid Form and shall include the cost of labor, excavation, dewatering, equipment, trench box/sheeting (if needed), materials, structural fill, compaction, cleanup, etc., for complete installation. Payment for the fittings used at tie-ins will be paid for as stated in bid item “6” above. No separate measurement or extra payment will be made for temporary fittings associated with the tie-in.
b. Tie-in to the existing line: Where connection to an existing main is made by removing an existing plug, no payment will be made for this work.
8. BID ITEM NO. 12 & NO. 13 – SERVICE RECONNECTIONS (LONG & SHORT)
a. Measurement will be made at the unit price per each as stated in the Bid
Form and shall include all materials, tapping sleeve & saddle, curb stops, piping, tracer wire, stone, meter box, connection to the existing service line after the new meter box, casing pipe (for long side services), excavation, dewatering, backfill, compaction, grading, cleanup, etc., for complete installation.
1/16/2026 01 20 00-6 Dorchester County
9. BID ITEM NO. 14 THROUGH 16 – CUT& REPLACE (CONCRETE DRIVEWAY,
ASPHALT DRIVEWAY, AND ASPHALT ROADWAY)
a. Measurement will be made at the unit price per square yard (SY) as stated in the Bid Form and shall include all labor, materials, saw cutting, hauling, removal, proper disposal, subgrade preparation & compaction, formwork, clean-up, etc. for complete installation.
10. BID ITEM NO. 17 – FILL ABANDONED WATER MAIN WITH FLOWABLE FILL
a. Measurement will be made at the unit price per cubic yard (CY) as stated in the Bid Form and shall include all labor, materials, clean-up, etc. for complete installation. Any fittings used for the cut & cap of abandoned force main lines will be paid for as stated in line item “6” above.
11. BID ITEM NO. 18 – EROSION AND SEDIMENT CONTROL
a. Erosion and Sediment Control (i.e., silt fencing, temporary grassing, permanent grassing, erosion control matting) will be measured and paid for at the price per lump sum (LS) as stated in the Bid Form and shall include the costs for materials, installation, maintenance, replacement, inspections, removal, and cleanup.
b. No measurement and payment or direct payment will be made for temporary grassing and temporary construction entrance/exit.
c. Payment shall be based upon percentage complete and as authorized by
Dorchester County.
12. BID ITEM NO. 19 – RESTORE DITCHES AND REMOVE AND RESET STORM
DRAINS
a. Payment will be made at the cost per lump sum (LS) as stated in the Bid
Form. The lump sum price shall include labor to include reshaping existing ditches, removing and resetting of existing storm drains, hauling and removing excess soil, #57 stone under existing storm drain (if needed), stabilization of ditches, etc., for complete installation.
b. Temporary and permanent grassing and other soil stabilization measures
(i.e., erosion control matting) on steep slopes will be paid for at unit prices per LS as stated in the Bid Form and include items described in “18.a.”
13. BID ITEM NO. 20 – TRAFFIC CONTROL
a. Payment will be made at the cost per lump sum (LS) as stated in the Bid
Form. The lump sum price shall include all necessary signage, labor to include installation/removal/re-installation, barrels, flagmen, traffic control
1/16/2026 01 20 00-7 Dorchester County plans, coordination with the related requirements of the South Carolina
Department of Transportation (SCDOT), and Dorchester County.
14. BID ITEM NO. 21 – RECORD DRAWINGS
a. Measurement will be made at the unit price per lump sum (LS) as stated in the Bid Form. The price shall include all requirements per Section 01 78 39
– Project Record Documents and Dorchester County.
AIR RELEASE VALVE INSTALLATIONS
1. BID ITEM NO. 1 – 2” AIR RELEASE VALVE WITH PEDESTAL ASSEMBLY
a. Measurement will be made at the unit price for each as stated in the Bid
Form and shall include a release valve, tapping sleeve and saddle, isolation valve, stone bedding, assembly, cover, per detail, excavation, dewatering/well points (if necessary), trench box and/or sheeting (if necessary), backfill, structural fill, tracer wire connection, compaction, grading, clean up, etc. for complete installation.
2. BID ITEM NOS. 2 – 2” AIR RELEASE VALVE (REMOVE AND REPLACE)
a. Measurement will be made at the unit price for each as stated in the Bid
Form and shall include removal of existing and replacement of a release valve, haul out of old ARV, discharge PVC piping attachment, access inside the ARV manhole, safety procedure, and equipment per OSHA.
3. BID ITEM NO. 3 - EROSION AND SEDIMENT CONTROL
the Bid Form. The price shall include items described in Bid Item No. 18.
4. BID ITEM NO. 4 - TRAFFIC CONTROL
the Bid Form. The price shall include items described in Bid Item No. 20.
3.01 INSTALLATION
A. Install temporary facilities in a neat, orderly manner, and make them structurally, mechanically, and electrically sound throughout.
B. Location of Temporary Utilities and Temporary Facilities:
1/16/2026 01 20 00-8 Dorchester County
1. Locate temporary systems for proper function and service.
2. Temporary systems shall not interfere with or provide hazards or nuisances to: the
Work under this and other contracts, movement of personnel, traffic areas, materials handling, hoisting systems, storage areas, finishes, and work of utility companies.
3. Do not install temporary utilities on the ground, with the exception of temporary extension cords, hoses, and similar systems in place for short durations.
C. Modify and extend temporary systems as required by the progress of the Work.
3.02 MAINTENANCE
A. Maintain temporary systems to provide safe, continuous service as required.
B. Properly supervise the operation of temporary systems:
1. Enforce compliance with Laws and Regulations.
2. Enforce safe practices.
3. Prevent abuse of services.
4. Prevent nuisances and hazards caused by temporary systems and their use.
3.03 CLOSEOUT ACTIVITIES
A. Completely remove temporary utilities, facilities, equipment, and materials when no longer required. Repair damage caused by temporary systems and their removal and restore the Site to the condition required by the Contract Documents: if restoration of damaged areas is not specified, restore to preconstruction conditions.
B. Contractor is responsible for and shall return to original condition those portions of the permanent electric system used in completing the Work.
C. Where temporary utilities are disconnected from existing utilities, provide a suitable, watertight or gastight (as applicable) cap or blind flange, as applicable, on the service line, in accordance with the requirements of the utility owner.
D. When permanent utilities and systems that were used for temporary utilities, upon
Substantial Completion, replace all consumables such as filters and light bulbs, and parts used during the Work.
1/16/2026 01 31 19-1 Dorchester County
SECTION 01 31 19
PROJECT MEETINGS
1. Pre-Construction Meeting:
a. The purpose of the conference is to designate responsible personnel, establish collaborative relationships, review the Contractor’s preliminary schedules, and outline the project’s administrative and procedural requirements. Topics requiring attention will be addressed, and methods for managing these issues will be defined.
b. Date, Time, and Location: The conference will be held after the execution of the Contract and before Work starts at the Site. DCWS will establish the date, time, and location of the conference and notify the interested and involved parties.
2. Progress Meetings:
a. Progress Meetings will be held throughout the Project. The Contractor shall attend each progress meeting prepared to discuss in detail all items on the agenda.
b. DCWS will preside at progress meetings and will prepare and distribute minutes of progress meetings to all meeting participants and others as requested.
c. Date, Time, and Location:
i. Regular Meetings: Every month on a day and time agreeable to DCWS and Contractor.
ii. Field Office at the Site or other location mutually agreed upon by DCWS and Contractor.
d. Additional meetings may be conducted as the progress of the Work requires at a mutually agreed date, time, and location.
1/16/2026 01 31 19-2 Dorchester County
1.02 ADMINISTRATIVE REQUIREMENTS
A. Pre-Construction Meeting:
1. The Contractor shall provide pre-construction meeting submittals with sufficient number of copies of each attendee:
2. Required Attendees:
a. Contractor
i. Project manager
ii. Site superintendent
iii. Safety representative
iv. Major Subcontractors
b. DCWS Representative
c. Representatives of governmental or other regulatory agencies, if needed.
3. The Contractor shall prepare and submit a health and safety plan, including a confined space entry plan, as specified in this Section prior to the pre-construction meeting.
4. Agenda, minimum:
a. Procedural requirements:
i. Designation of responsible personnel
ii. Use of Site and DCWS requirements, including general regards for community relations
iii. Delivery of materials and equipment to the Site
iv. Safety and first aid procedures
v. Confined space entry plan
vi. Security procedures
vii. Housekeeping procedures
b. Administrative requirements:
i. Distribution of Contract Documents
1/16/2026 01 31 19-3 Dorchester County
ii. Shop Drawing submittal procedures
iii. Maintaining record documents at the Site
iv. Contract modification procedures
v. Processing of Payment Application
c. Site mobilization requirements:
i. Working hours, overtime, and holidays
ii. Field offices, trailer, and staging areas.
iii. Temporary facilities and utilities, including usage and coordination.
iv. Temporary controls, such as sediment and erosion control, noise, dust, stormwater, and other measures.
v. Access to the Site, access roads, and parking of construction vehicles.
vi. Protection of traffic and existing property, including site barriers and temporary fencing.
vii. Security
viii. Storage of materials and equipment
ix. Reference points and benchmarks, surveys, and layouts
x. Site maintenance during the project, including cleaning and removal of trash and debris.
d. Schedules
i. Preliminary construction schedule
ii. Critical work sequencing
iii. Preliminary Shop Drawings submittal schedule
iv. Preliminary Schedule of Values
B. Progress Meetings:
1. Progress meeting frequency shall be conducted as specified in this Section, unless modified and agreed upon by DCWS and Contractor. Additional meetings may be conducted as the progress of the Work requires.
1/16/2026 01 31 19-4 Dorchester County
2. Contractor shall provide submittals specified in this Section prior to each progress meeting.
3. Attendance:
a. Contractor, including project manager, site superintendent, safety representative, and representatives of Subcontractor and Suppliers as required.
b. DCWS, including the County’s Site Representative (if any).
c. Subcontractors, only with DCWS’ approval or request, as required in the agenda.
4. Agenda, minimum:
a. Review, comment, and amend (if required) of minutes of the previous progress meeting.
b. Review of progress since the previous progress meeting
c. Planned progress through the next 30 – 60 days.
d. Review of Progress Schedule
i. Contract Times, including Milestones (if any)
ii. Critical path
iii. Schedules for fabrication and delivery of materials and equipment
iv. Corrective measures, if required
e. Submittals:
i. Review of status of critical submittals
ii. Review revisions to the schedule of submittals
f. Contract Modifications:
i. Requests for interpretation
ii. Clarification notices
iii. Field Orders
iv. Proposal requests
1/16/2026 01 31 19-5 Dorchester County
v. Change proposals
vi. Work Change Directives
vii. Change Orders
viii. Claims
g. Applications for progress payments
h. Problems, conflicts, and observations
i. Quality standards, testing, and inspections
j. Coordination between parties
k. Site management issues, including access, security, maintenance and protection of traffic, maintenance, cleaning, and other Site Issues.
l. Safety
m. Permits
n. Record documents status
o. Punch list status, as applicable
p. Other business
1.03 SUBMITTALS
A. Pre-Construction Meeting Submittals:
1. Prior to the conference, submit the following preliminary schedules in accordance with the General Conditions:
a. Progress schedule
b. Schedule of submittals
c. Schedule of values
2. Contractor’s safety and first aid procedures.
3. Confined space entry plan
4. List of emergency contact information
B. Progress Meeting Submittals:
1/16/2026 01 31 19-6 Dorchester County
1. List of Work accomplished since the previous progress meeting.
2. Up-to-date Progress Schedule.
3. Up-to-date Schedule of Submittals.
4. Detailed “look-ahead” schedule of Work planned through the next progress meeting, with specific and ending dates for each activity, including shutdowns, deliveries of important materials and equipment, Milestones (if any), and important activities affecting DCWS, Project, and Site.
5. When applicable, a list of upcoming, planned time off (with dates) for personnel with significant roles on the Project, and the designated contact person in their absence.
1.04 EMERGENCY CONTACT INFORMATION
A. The Contractor shall provide a list of emergency contact information for 24-hour use throughout the Project. Emergency contact information shall be updated and kept current throughout the Project. If personnel or contact information changes, provide an updated emergency contact information list at the next progress meeting.
B. Contractor’s list of emergency contact information shall include:
1. Contractor’s project manager’s office, field office, and mobile telephone numbers.
2. Contractor’s Site superintendent’s office, field office, and mobile telephone numbers.
3. Contractor’s foreman’s office, field office, and mobile telephone numbers.
4. Major Subcontractor’s and Suppliers’ office, field office, and mobile telephone numbers of the project manager and foreman (when applicable).
1/16/2026 01 32 00-1 Dorchester County
SECTION 01 32 00
CONSTRUCTION PROJECT SCHEDULE
A. The Contractor shall prepare and submit Progress Schedules and related documents in accordance with the General Conditions, as may be modified by the Supplementary
Conditions, and this Section, unless otherwise accepted by DCWS.
1. Maintain and update Progress Schedules and related documents.
B. DCWS’ acceptance of the Progress Schedule or related documents, and comments or opinions concerning activities in the Progress Schedule and related documents shall not control the independent judgment of the Contractor concerning means, methods, techniques, sequences, and procedures of construction unless the associated means, method, technique, sequence, or procedure is directed by the Contract Documents. The
Contractor is solely responsible for complying with the Contract Times.
A. Definitions:
1. Activity: An element of the construction work that has the following specific characteristics: consumes time, consumes resources, has a definable start and finish, is assignable, and is measurable.
2. Constraint: An imposed date on the Progress Schedule or an imposed tie between
Activities. The Contract Time are Constraints.
3. Critical Path: The continuous chain of Activities with the longest duration for completion within the Contract Times.
4. Early Start: The earliest possible date an Activity can start according to the assigned relationships among Activities.
5. Early Finish: The earliest date an Activity can finish according to the assigned relationships.
6. Late Finish: The latest date an Activity can finish without extending the Contract
Times.
1/16/2026 01 32 00-2 Dorchester County
7. Late Start: The latest date an Activity can start without extending the Contract
Times.
8. Float: The time difference between the calculated duration of the Activity chain and the Critical Path.
9. Total Float: The total number of days that an Activity (or chain of Activities) can be delayed without affecting the Contract Times.
10. Network Diagram: A time-scaled logic diagram depicting the durations and relationships of the Activities.
11. Work Areas, Area, or System: A logical breakdown of the Project elements or a group of Activities which, when collectively assembled, are readily identifiable on the Project (for example, yard piping, a structure or building, a treatment process, or other logical grouping).
A. Initial Progress Schedule:
1. Type and Organization of Progress Schedules:
a. Prepare one Progress Schedule covering the entire Project using schedule software that is acceptable to DCWS.
b. Sheet Size: 11” by 17”, unless otherwise accepted by DCWS.
c. Time Scale: Indicate the first date of each work week.
d. Activity Designations: Indicate title and related Specification Section number.
e. Organization:
i. Indicate on the separate Schedule of Submittals dates for submitting and reviewing Shop Drawings, Samples, and other submittals.
ii. Group deliveries of materials and equipment into a separate sub-schedule that is part of the Progress Schedule.
iii. Group construction into Work Area sub-schedules (that are part of the
Progress Schedule) by Activity.
iv. Clearly indicate the Critical Path on the Progress Schedule.
v. Organize each Work Area sub-schedule by Specification Section number.
1/16/2026 01 32 00-3 Dorchester County
2. Preliminary Progress Schedule:
a. Contractor shall submit to DCWS the preliminary Progress Schedule within
30 days after the Contract Times commence running.
b. Submit an electronic copy of the preliminary Progress Schedule and associated reports and schedule-related documents to accompany the preliminary Progress Schedule, in accordance with the Submittal Article of this Section. Submit in accordance with Section 01 33 00 – Submittal
Procedures.
3. Initial Acceptance of Progress Schedule:
a. At least ten (10) days before submission of the first Application for Payment, the Contractor shall include a conference at the Site for review of the preliminary Progress Schedule.
i. Attendees shall include the Contractor, DCWS, and others as required.
ii. The Contractor shall have an additional ten (10) days to make corrections and adjustments and to complete and resubmit the
Progress Schedule and associated Network Diagram.
iii. DCWS reserves the right not to make a progress payment to the
Contractor until an acceptable Progress Schedule, Network Diagram, and other reports and schedule-related documents required are submitted to DCWS.
b. Submit an electronic copy of the acceptable Progress Schedule, reports, and other schedule-related documents required to accompany the initial acceptable Progress Schedule, in accordance with the Submittals Article of this Section.
c. Initially accepted Progress Schedule shall be identified as the baseline
Progress Schedule.
B. Progress Schedule Updates:
1. Update the Progress Schedule each month. If during the progress of the Work, events develop that necessitate changes in the initially accepted Progress
Schedule (i.e., baseline Progress Schedule), identify updated Progress Schedules sequentially as Progress Schedule Revision 1, 2, 3, and continue in sequence as
2. The updated Progress Schedule shall be based on retained logic. Progress override logic is not allowed.
1/16/2026 01 32 00-4 Dorchester County
3. Required scheduling software, schedule organization, format, and content for updated Progress Schedules are identical to that required in this Section for initial
Progress Schedules.
4. Submit to DCWS an electronic copy of the updated Progress Schedule, narrative report, and other schedule-related reports and documents required.
5. Submit an updated Progress Schedule when revisions are proposed to the logic.
Indicate in the narrative report the delays that have occurred since the previous updated Progress Schedule. DCWS will not approve payment of progress payments until the updated Progress Schedule is received, reviewed, and accepted by DCWS. Payment for out-of-sequence Work is not allowed.
1.04 TIME IMPACT ANALYSIS
1. Prepare and submit a time impact analysis when one or more of the following occur:
a. Change Order proposal is prepared
b. Work Change Directive is issued that will affect the Progress Schedule
c. When delays are experienced
2. Time impact analysis shall illustrate the influence of each Change Order, Work
Change Directive, or delay.
3. Each time impact analysis shall include a sketch (fragnet) demonstrating how the
Contractor proposes to incorporate the changes in the Project or, as applicable, delays into the Progress Schedule. Fragnet shall include all logic, and additional requirements as a result of said Change Order, Work Change Directive, or delay.
4. Fragnet shall show all logic revisions for the Work associated with the Change
Order, Work Change Directive, or delay, and its relationship to other Activities in the Network Diagram.
5. Timing of Time Impact Analysis:
a. Submit each time impact analysis within seven (7) days after the following, as applicable:
i. Start of delay
1/16/2026 01 32 00-5 Dorchester County
ii. After the submittal of the Change Order proposal to DCWS
iii. After Contractor’s Receipt of Work Change Directive
b. Failure to Submit Time Impact Analysis: When the General Contractor does not submit a time impact analysis for a specific change or delay under the
General Contract, within the specified period of time for such submittal, such non-submittal shall be construed as no extension of the Contract Times is
B. Evaluation by DCWS and Acceptance:
1. DCWS’s evaluation of each time impact analysis, comprised of complete information, will be completed in a timely manner after DCWS’s receipt. Changes in the Contract Times will be made only by a Change Order.
2. When a mutual agreement is reached between the parties on the effect of the change or delay in the Project, incorporate into the next Progress Schedule update the associated fragnets illustrating the influence of changes and delays.
1.05 RECOVERY SCHEDULES
1. When updated Progress Schedule indicates that the ability to comply with the
Contract Times falls thirty (30) or more days behind schedule, and there is no excusable delay, Change Order, or Work Change Directive to support an extension of the…