ATTACHMENT A - PWS - Design Support - West LA Critical Care Center 5.30.2024.pdf
PDF 519 KB Posted
- Solicitation number
- 36C77624Q0228
About this file
This document is a Performance Work Statement (PWS) for a design support contract to support the activation of the new West LA Critical Care Center (CCC) for the Department of Veterans Affairs (VA) Greater Los Angeles Healthcare System (VAGLAHCS).
The key objectives of the contract are to provide design support services, including project management, interior design, furniture/equipment planning, and space planning, to support the activation and initial outfitting of the new CCC facility. The contract is a firm-fixed-price, 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside. Key personnel include an Activation Project Manager, Senior Designer, and Medical Equipment Planner. The PWS details the tasks, deliverables, and quality assurance requirements for the contractor. Travel for the contractor is authorized on a case-by-case basis with pre-approval. The performance period and beneficial occupancy date are not specified in the PWS.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C77624Q0228 0001.docx | DOCX document | |
| ATTACHMENT I - Wage Determination.pdf | ||
| ATTACHMENT D - Risk Management Plan and Register Template.xlsx | XLSX spreadsheet | |
| ATTACHMENT B - Travel Authorization Request.pdf | ||
| ATTACHMENT F - QASP.docx | DOCX document | |
| ATTACHMENT G - PDAT Summary.pdf | ||
| ATTACHMENT H - VSC Security Package 3.4.2024.pdf | ||
| 36C77624Q0228_1.docx | DOCX document | |
| ATTACHMENT J - WLA CCC - Planning Support - FFE List 05012024.xlsx | XLSX spreadsheet | |
| ATTACHMENT E - Room Contents Plan for Design Support template 23-11-03.xlsx | XLSX spreadsheet | |
| ATTACHMENT C - Contract Staff Roster.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
PERFORMANCE WORK STATEMENT
“Attachment A”
DEPARTMENT OF VETERANS AFFAIRS
Veteran’s Health Administration
Veterans Affairs Greater Los Angeles Healthcare System
West Los Angeles Veterans Affairs Medical Center
Project Title Project 691 – 408: West LA New Critical Care Center (CCC)
Design Support Contract
Date:
05/30/2024
2 | P a g e
1.0 Objective
The purpose of this acquisition is to provide the Department of Veterans Affairs, Veterans Health Administration (VHA) with design support services for the West Los Angeles New Critical Care Center (CCC). The objective is to have the IOT&A project completed by the first day of clinical services, which is projected for November 28, 2030. North American Industry Classification System (NAICS) code for these services is 541614, Process, Physical Distribution, and Logistics Consulting Services.
2.0 Introduction
Activation is defined as the process of identifying, planning, managing, and executing the logistical and operational requirements to bring a new medical center into full planned operations. The medical center assigns VHA staff to an Activation Team which is responsible for managing the Activation Project and ensuring the West Los Angeles New Critical Care Center (CCC) is in full planned operations on ‘Day One’ (the first day clinical services are scheduled to be available to Veterans). Contractor services are often required to support the medical center's Activation Team.
3.0 Background
In Fiscal Year 2018, the United States Congress approved the construction of the West LA New Critical Care Center (CCC) for the VA Greater Los Angeles Healthcare System (VAGLAHCS). This project is a Major Construction project that will construct a new West Los Angeles Critical Care Center (CCC). The project will be a joint effort between VA CFM, VHA, USACE, and VAGLAHCS.
The Greater Los Angeles VA Healthcare System (VAGLAHCS) has been approved for this major construction project to create an expanded service opportunity for Veteran health care. VAGLAHCS proposed to build a new “Critical Care Center” (CCC) with approximately 450,000 new gross square feet (GSF). This proposed new “Critical Care Center” building provides for the construction of a new bed tower, as well as the renovation of the existing bed tower, building 500, to consolidate services across the VAGLAHCS West LA Campus. The new “Critical Care Center” will consist of six
(06) floors. Each floor will have the following departments and/or services: ground floor - Inpatient Pharmacy, SPS, Morgue, police and touchdown spaces for engineering, Biomed, EMS, first floor - Lobby, Chapel, Canteen, ED, radiology, Admitting and Discharge, Multipurpose rooms, On- Call rooms, second floor - ICU (18 beds), Surgery (2 IR Lab, 1 Cath lab, 1 EP Lab, 6 General; 2 hybrid OR) and Peri-operative departments (57 bays), third floor – Inpatient metal health (44 beds) and patient courtyard, fourth floor – PCU (10 beds), ARU (16 beds) and Med/ Surge (22 beds), and fifth floor – Med/ Surg (50 beds).
4.0 Scope
Conduct all necessary design support activities, in accordance with the PWS, in support of the project(s) identified in paragraph 3.0 above. The contractor shall provide professional services to include all labor, materials, transportation, and equipment to conduct and provide IOT&A support services to accomplish the PWS tasks. The scope includes project support for design associated with the project. The scope of services includes Project Management and Interior Design, FF&E, and Space Planning Support.
The Beneficial Occupancy Date (BOD) is planned for May 28, 2030. The CCC “Day One” is anticipated to be November 28, 2030.
5.0 Applicable Documents
Applicable documents are listed below. Contractor shall use the most current versions of all applicable documents listed below.
A. Construction contract: TBD
3 | P a g e
B. Federal Information Processing Standards (FIPS) Publication 140-2, “Security Requirements For Cryptographic Modules”
C. FIPS Pub 201, “Personal Identity Verification of Federal Employees and contractors,” March 2006
D. 5 U.S.C. § 552a, as amended, “The Privacy Act of 1974”
E. Public Law 109-461, Veterans Benefits, Health Care, and Information Technology Act of 2006, title IX Information Security Matters
F. 42 U.S.C. § 2000d “Title VI of the Civil Rights Act of 1964”
G. Department of Veterans Affairs (VA) Directive 0710 Personnel Security and Suitability Program dated May 18, 2007 (https://www.voa.va.gov/)
H. Department of Veterans Affairs (VA) Directive 6102 (Internet/Intranet Services) (https://www.voa.va.gov/)
I. Health Insurance Portability and Accountability Act (HIPAA); 45 CFR Part 160, 162, and 164; Health Insurance Reform: Security Standards; Final Rule dated February 20, 2003
J. VHA Security Handbook 1600.01, Business Associate Agreements (https://www.voa.va.gov/)
K. 36 C.F.R. Part 1194 “Electronic and Information Technology Accessibility Standards,” July 1, 2003
L. Office of Management and Budget Circular A-130, “Management of Federal Information Resources’, November 28, 2000
M. U.S.C. Section 552a, as amended
N. Title 32 CFR 199, “Civilian Health and Medical Program of the Uniformed Services (CHAMPUS)”
O. An Introductory Resource Guide for Implementing the Health Insurance Portability and Accountability Act (HIPAA) Security Rule, October 2008
P. Sections 504 and 508 of the Rehabilitation Act (29 U.S.C. Section § 794d), as amended by the Workforce Investment Act of 1998 (P.L. 105-220), August 7, 1998
Q. Homeland Security Presidential Directive (12) (HSPD-12), August 27, 2004
R. Department of Veterans Affairs (VA) Directive 6500, “VA Cybersecurity Program,” January 23, 2019
S. VA Handbook 6500, “Risk Management Framework for VA Information Systems – Tier 3: VA Information Security Program,” March 10, 2015
T. VA Handbook 6500.1, “Electronic Media Sanitization,” March 22, 2010.
U. VA Handbook 6500.2, “Management of Data Breaches Involving Sensitive Personal Information”, March 12, 2019
V. VA Handbook 6500.3, “ASSESSMENT, AUTHORIZATION, AND CONTINUOUS MONITORING OF VA INFORMATION SYSTEMS,” February 3, 2014.
W. VA Handbook, 6500.5, Incorporating Security and Privacy in System Development Lifecycle,” March 22, 2010
X. VA Handbook 6500.6, “Contract Security,” March 12, 2010
Y. Federal Travel Regulation (FTR) (www.gsa.gov/federaltravelregulation)
Z. VA Directive 6508, Implementation of Privacy Threshold Analysis and Privacy Impact Assessment, October 15, 2014
AA. VA Handbook, 6300.1, Records Management Procedures, March 24, 2010
BB. VA Handbook 7002, Logistics Management Procedures, January 8, 2020
CC. VHA DIRECTIVE 1761(1)/Supply Chain Inventory Management
DD. VA Directive 6404, VA Systems Inventory (VASI)
4 | P a g e
EE. HISD Medical Device Protection Program (MDPP) National Cyber Security Risk Assessment for VHA Networked Medical Devices, Version 2.1
FF. ANSI/EIA/TIA 568B Commercial Building Telecommunications Wiring Standard
GG. VA Handbook, 0730/4, Security and Law Enforcement, March 29, 2013
HH. U.S. Department of Veterans Affairs, Office of Construction & Facilities Management, Physical Security Design Manual for Life-Safety Protected Facilities, January 2015
II. U.S. Department of Veterans Affairs, Office of Construction & Facilities Management, Physical Security Design Manual for Mission Critical Facilities, January 2015
JJ. MIL-STD-1691 Construction and Material Schedule for Military Medical, Dental, Veterinary and Medical Research Laboratories, December 1, 2016 (https://ms1691.facilities.health.mil/milstd1691/#/)
KK. 44 U.S.C chapters 21, 29, 31 and 33; Freedom of Information Act (5 U.S.C. 552); Privacy Act (5 U.S.C.
552a); 36 CFR Part 1222 and Part 1228.
LL. Architectural Barriers Act Accessibility Standards (ABAAS) including VA supplement, PG-18-13 Barrier Free Design Standard
MM. VA PG-18-14 Room Finishes, Door, and Hardware Schedule
NN. VA PG 18-4 Standard Details and CAD Standards
OO. VA H-18-8 Seismic Design Handbook
PP. VA Signage Design Guide https://downloads.va.gov/files/CFM-TIL/signs/
QQ. VA BIM Standard
RR. International Building Code (IBC)
SS. NFPA 10: Standard for Portable Fire Extinguishers
TT. NFPA 70: National Electrical Code (NEC)
UU. NFPA 72: National Fire Alarm and Signaling Code
VV. NFPA 101: Life Safety Code
WW. International Plumbing code (IPC)
XX. Occupational, Safety, and Health Administration (OSHA) Standards
YY. Federal Acquisition Regulation (FAR)
ZZ. Veterans Affairs Acquisition Regulation (VAAR)
6.0 Contract Type
This is a Firm-Fixed-Price (FFP) Contract. This Contract is a 100% Service-Disabled Veteran Owned Small Business (SDVOSB) set-aside under FAR Parts under 12, 13 and 37.
7.0 Non-Personal Services
In accordance with FAR 37.104 and 5 U.S.C. 3109, this requirement has been determined to be a non-personal services contract. A non-personal services contract is a contract under which the contractor personnel providing the services are not subject to continuous Government supervision and or control, either by the contract's terms or by the manner of its administration.
8.0 Organizational Conflict of Interest
Per FAR Subpart 9.5, Organizational Conflict of Interest, due to the requirement of the contractor providing support services for Furniture, Fixtures, and Equipment (FF&E) and the possibility that any FF&E may be available through the prime contractor or its subcontractors, which may be regarded as a potential conflict of interest as seen by the Contracting Officer (CO), neither the prime contractor nor its subcontractors or consultants may participate as an https://ms1691.facilities.health.mil/milstd1691/#/ https://downloads.va.gov/files/CFM-TIL/signs/
5 | P a g e offeror, subcontractor, or consultant on any procurement of FF&E conducted by the prime contractor or its subcontractors/consultants under this contract.
a. Contractor to provide a complete list as part of the proposal submission of all proposed subcontractors in performance of this contract.
b. Contractor to provide notice to the contracting office immediately if any proposed subcontractors are changed during the course of the period of performance of this contract.
c. If procurement related tasks are divided by prime and sub, contractor to provide a list of which activities are performance by which contractor.
d. Contractor to mitigate any risk associated with an OCI. Non-disclosure agreements may become necessary as part of Contract award.
e. Contractor to work will all subcontractors in reviewing subcontract terms and conditions associated with the awarded Contract.
9.0 Location and Hours of Work
The primary place of performance is at the Government’s facility, with necessary work to be done off-site at the contractor’s facility. All Face-to-Face meetings will be held at the Government’s facility VAGLAHCS, West Los Angeles Campus, located at 11301 Wilshire Blvd., Los Angeles, CA. Normal workdays are Monday through Friday, except US Federal Holidays. Typical workdays are eight (8) hours per day, forty (40) hours per week. Core hours of work are from 0800 to 1630 daily. All contract employees are expected to be available during core hours. Work shall not take place on Government site after normal working hours, on weekends, or on Federal holidays unless specified in the contract or approved by the Contracting Officer’s Representative (COR). Some weekend hours are expected (i.e., inventory services, activation services).
There are eleven (11) Federal holidays set by law (USC Title 5 Section 6103) that the Department of Veterans Affairs follows:
• Six (6) Federal holidays are set by day of the week and month:
(1) Martin Luther King's Birthday - Third Monday in January
(2) Washington's Birthday - Third Monday in February
(3) Memorial Day - Last Monday in May
(4) Labor Day - First Monday in September
(5) Columbus Day - Second Monday in October
(6) Thanksgiving - Fourth Thursday in November
• Five (5) Federal holidays are set by date. If any of these dates fall on a Saturday, the Friday before shall be observed as a holiday. If any of these dates fall on a Sunday, the following Monday shall be observed as a holiday.
(1) New Year's Day - January 1st
(2) Juneteenth – June 19th
(3) Independence Day - July 4th
(4) Veterans Day - November 11th
(5) Christmas Day - December 25th
• Any other Federal Holiday declared by the President of the United States
10.0 Reserved
11.0 Travel
Cost-reimbursable travel will be included in the final award based upon the Government’s estimated need. The Government will not reimburse any living or relocation costs of contractor employees from other geographic areas. The purpose of staffing the contract is considered the cost of doing business and is not subject to reimbursement. It is the responsibility of the contractor to mobilize employees and pay living expenses for non-local employees, if it is necessary contractor personnel be located near project site.
6 | P a g e
Local travel, within a 50-mile radius from the place of performance will not be reimbursed. The Government will not pay travel charges for travel to and from the contractor employee’s home and government office or from one Government facility to another. Travel beyond a 50-mile radius of the contractor’s facility is authorized for reimbursement on a case-by-case basis and must be pre-approved by the Contracting Officer’s Representative (COR) via the Travel Authorization Request (Attachment B). The contractor must obtain written approval from the VA COR BEFORE any travel begins, utilizing the Travel Authorization Request form. Other documents or e-mails will not be accepted as pre-approval. Travel that occurs without written pre-approval will not be reimbursed. Travel expenses will be reimbursed on an actual expenditure’s basis in accordance with FTR and FAR 31.205-46. Per diem expenses will be paid per the GSA daily rates for the location of travel. To be reimbursed for travel, the Contractor shall submit supporting documentation as required by FTR with invoices. FTR requires for any temporary travel destination you must provide a receipt to substantiate your claimed travel expenses for lodging and a receipt for any authorized expenses costing over $75 (FTR 301-11.25).
Expenses for subsistence and lodging will be reimbursed to the Contractor only to the extent where an overnight stay is necessary and authorized by FTR in effect at the time of the stay for the specific location. Approval for rental vehicles is discouraged and will be approved on an individual basis. Additional information can be found at:
http://www.gsa.gov/ftr.
12.0 Key Personnel
The contractor shall provide the necessary qualified personnel, materials, resources, and infrastructure to manage, perform, and administer the contract. The contractor shall accomplish the assigned work by employing and utilizing the identified key personnel with appropriate combinations of education, training, and experience as well other identified personnel with education and experience appropriate for the tasks assigned.
The personnel identified herein are considered essential to the work being performed. In the event changes to key personnel are required during the performance of this contract, replacement key personnel must meet or exceed the experience and qualifications of the individual the contractor included in its submitted proposal. Prior to substituting, removing, or replacing any key personnel, the contractor shall notify the CO and COR 10 working days in advance. The contractor shall submit to the CO and COR the resume of the replacing individual that demonstrates skills and background at least equivalent to those of the individual the contractor included in its proposal within 10 days of replacement. The CO and COR will evaluate the replacing person's resume to determine the experience and qualifications of the replacement are equal or exceed those of the person's resume submitted with the contractor's proposal for that position. New personnel shall not commence work until all necessary security requirements have been fulfilled and résumé provided and accepted. The CO and COR will evaluate such requests and promptly notify the contractor, within 5 business days of approval or disapproval in writing.
For the purposes of this contract, key personnel are listed below:
• Activation Project Manager o A minimum of seven (7) years of experience as a Project Manager, acting in a lead role over healthcare space related projects o A minimum five (5) years of experience in initial outfitting, transitioning, and activating
(IOT&A) healthcare facilities.
o Demonstrated experience in healthcare infrastructure and operations.
• Senior Designer o A minimum of five (5) years of experience in healthcare facility design http://www.gsa.gov/ftr
7 | P a g e o National Council for Interior Design Qualification (NCIDQ) Certification or American Academy of Healthcare Interior Designers (AAHID) certification o Demonstrated experience in healthcare operations and related furniture, fixtures, casework/case goods and signage, and be able to translate requirements into design/construction/installation documents.
• Medical Equipment Planner o A minimum of five (5) years of experience in medical equipment planning and Implementation o A minimum of three (3) years of experience in healthcare facility design o Experience in Federal healthcare setting
13.0 Employee Identification
All contractor employees working at a Government facility shall wear company Identification and Government issued identification to distinguish themselves as contractor personnel. When conversing with Government personnel during business meetings and over the telephone, contractor employees shall identify themselves as such. Where practicable, contractor employees occupying space within a Government facility should identify their workspace area with their name and company affiliation.
14.0 Conduct of Personnel
The CO may require the contractor to remove from the job site any employee working under this contract for reasons of misconduct, security violations, or found to be or suspected to be under the influence of alcohol, drugs, or other incapacitating agents. Contractor employees shall be subject to dismissal from the premises upon determination by the CO that such action is in the best interests of the Government. Such removal from the job site or dismissal from the premises shall not relieve the contractor of the requirement to provide sufficient personnel to perform the services as required by this contract.
15.0 Contract Kick-Off Meeting
The Government activation team will schedule an onsite Kick-Off meeting for this contract after award. Attendees should include the Contractor, key stakeholders, site activation team, subject matter experts, NAO Program Manager, COR, CFM Resident Engineer, and the CO. The Contractor, in collaboration with the COR and CO, shall coordinate dates and an agenda. The COR will include the Resident Engineer to complete a roles and responsibilities review of the construction project and activation project during the kick-off. The Contractor is to provide meeting minutes within three (3) business days after the Kick-Off meeting. At the Kick-Off meeting, the Government will discuss administrative functions (i.e., security background process, reporting, COR responsibilities, invoicing, deliverable submission process), and contractual expectations. The Contractor shall be prepared to present the details of the intended approach, work plan, and project schedule, as well as make personnel introductions. Contractor will be given the opportunity to clarify contract requirements and expectations. The Government may elect to do a telephonic contract administrative kick-off meeting immediately following contract award, and an on-site programmatic kick-off meeting separately. If feasible, the IOTA contractor will also participate in the building contractor Kick-Off. Ideally, these would occur on the same day.
16.0 Tasks and Deliverables
8 | P a g e
16.1 Project Management Services
Provide Design Support and Activation Project Management Services integral to the execution of tasks ensuring effective, efficient, and timely completion of contracted services. The Activation Project Manager shall not be reassigned without notification to the CO. The Project Manager may be required to be onsite as required per contract and lead user group meetings. The Project Manager will ensure close coordination with the design contractor.
Project Plans, Schedules, and Reports:
The contractor shall support the VHA Activation Team’s planning, scheduling, and reporting requirements.
In the event a schedule deviation impacts the period of performance of this contract, the contractor shall provide in writing to the CO the reason for the delay, associated points of contact, and a request for extension. Extension requests must detail the amount of additional time required and are not automatically granted. The contractor shall document lessons learned throughout the project in the monthly status report.
Meeting Facilitation Services:
The contractor shall provide group facilitation services to key stakeholders, Integrated Project Team (IPT) and work groups for meetings required to perform contract PWS tasks. Key stakeholders include, but not limited to, # Deliverable Name Deliverable Description
16.1.1 Monthly Project
Status Report
The Monthly Project Status report shall give an overview of the progression of the project and describe the work completed during the reporting/billing period. The report shall include status of milestone items in the Master Project Schedule, discuss moderate to high-risk items, and a summary of meetings attended. The report shall discuss any “lessons learned” during the reporting/billing period. If any changes to staff (prime or sub), or Key Personnel change during the month, and updated Attachment C, Contract Staff Roster shall be included. The Monthly Project Status Report shall correlate to and be submitted with the monthly invoice.
The report shall cover the same time period as the invoice.
16.1.2 Risk Management
Plan and Log
(Attachment D is a representation of required data/information.
The contractor shall update and maintain the Risk Management Plan. The plan shall include an itemized listing of project-specific risks, challenges and perceived problems that are anticipated to threaten the project. Risks identified shall include probability of occurrence, and level of impact. With each issue specified, the contractor shall list their proposed solution to mitigate or resolve the risk/challenge/problem. The plan shall cover all phases of the work. When identifying risks/solutions the contractor should consider items in areas that may cause the project to:
• not be completed on time.
• not finish within budget;
• generate change orders;
• result in owner dissatisfaction;
• result in poor quality of services; and/or
• any other areas identified by the IOT&A contractor.
Risk Management should be a regular coordination meeting agenda item to ensure Risks are being managed per the RMP. The existing Risk Register shall be updated as additional risks are identified through coordination meetings or day to day project execution.
9 | P a g e
Activation Team Members, Integrated Project Team members, and Program Support Staff from Facilities, Medical Maintenance, and other project-related Government and Medical Staff as necessary. The contractor may identify additional ad hoc groups as approved by the COR. The contractor shall guide groups to consensus by identifying requirements, facilitating group discussions, and documenting decisions. The contractor shall coordinate meetings, and facilitate the groups to assess, analyze, recommend, and document solutions as developed jointly by the contractor and the stakeholders and/or group members.
The contractor shall be responsible for coordinating and planning. The contractor shall coordinate the meeting locations and audio/visual support as needed for these meetings with the COR. The COR will finalize arrangement with the facility for rooms and audio/visual support. For meetings requiring teleconferencing capability, the contractor shall provide the teleconferencing service and call-in numbers and host the meetings. The contractor shall not meet with any end users, the A/E firm, the construction contractor, etc. without first coordinating with the CFM RE, COR, and VA PM. The contractor shall participate in design/construction meetings as determined by the
COR.
The design support contractor may not make changes to the items above (with the exception of the room contents list – provided there is no impact to infrastructure requirements). Any changes resulting from such an instance without the approval of the VA Construction CO will be borne on the design support contractor. In regard to changes to the room contents list, the design support contractor is allowed to make changes only within the building contract parameters, with approval of user groups. This would entail further defining equipment listed in the room contents list. The design support contractor will also be responsible for scrubbing the equipment list via user group meetings, to identify any equipment that is to be deleted or added.
The contractor will be responsible for the equipment planning within the contractual boundary of the CFM and USACE Contract Room Content List and defined floor layouts. Any deviations will have to be routed through the COR and approved through the CFM RE and CFM CO.
The contractor shall assure that all appropriate personnel are invited to attend each meeting either telephonically, video conferencing, or in person. The contractor’s PM should be available to attend requested meetings in person, as determined by the COR prior to the meeting. Beyond the contractor’s Project Manager, the total number of personnel required to attend meetings to support successful execution of the work for any given meeting is to be determined by the contractor and must be approved by the COR.
# Deliverable Name Deliverable Description
16.1.3 Meeting Minutes
and Meeting Agendas
Agendas shall be distributed no less than 3 days prior to the meeting. Contractor to work with COR or designee in creating the agendas. VA meeting agenda template to be used if available.
Minutes shall be distributed no more than 3 days post meeting. Minutes of all meetings shall include agenda, attendees, action items and who is responsible for completion of the action items. If the facility has a standardized template, that template must be used.
PWS Deliverable Updates:
After initial acceptance of any developed deliverable under any of the task(s) identified in the PWS, those deliverables will be updated and maintained as part of the Comprehensive Project Management Services Task.
16.1.4 PWS Deliverable
Updates
Updates must be completed no later than 10 business days after identification of need by either the Government or the Contractor. Note: all updates shall
10 | P a g e reference this deliverable and the original deliverable numbers (i.e., 15.1.11 update for 15.2.1)
16.2 Interior Design, FF&E, and Space Planning Services
Provide and coordinate comprehensive interior design (CID) services or coordination of CID services, ensuring incorporation of evidence-based health care concepts. FF&E must complement any interior packages developed by the Architect/Engineer firm associated with the construction project and/or the health care facility’s standards as provided by the Government. Design support services include preparing cut sheets for FF&E and artwork, updating the room’s content list, including updating spaces to be consistent with A/E drawings. Contractor is to work closely with the VA Interior Designer on all furnishings, space planning, and selections.
Contractor may provide their own system for tracking, managing and validating FF&E. It is the official repository for all project information and is utilized by outside bodies for budgetary and tracking purposes. The contractor will be validating all FF&E and defining all salient characteristics. “Validating” in the sense means a generic item has been identified by a specific manufacturer and model has not yet been identified. The contractor shall then develop the list to the “Approved” phase. “Approve” in this sense means the manufacturer and model has been selected, to include the salient characteristics of the item. The contractor will be responsible for finalizing furniture, fixtures, and artwork with the appropriate VA IPT representative to sign off on the final cut sheets and specifications. The COR (or other designated representative decision authority) will direct the contractor to the appropriate stakeholder for approval.
The IOT&A contractor will be responsible for identifying salient characteristics for all FF&E with end users and the VA Interior Designer for recording in the FF&E tracking system.
The general contractor will be required to identify all Mechanical Electrical and Plumbing (MEP) information necessary and timelines needed. IOT&A contractor is to develop the make and model of all equipment with the Design Documents. The VA will be responsible to provide the correct POC’s as members of the IPT, for the user group meetings who has the authority to make equipment decisions, such as identification of make and model of equipment, locations for all equipment – consistent with A/E drawings, and any J&As planned for the procurement of specified equipment. The IOT&A contractor is to ensure all identified FF&E or architectural significant items are in accordance with the Design Documents to minimize any need to change the Mechanical, Electrical, Plumbing or Architectural support systems and locations. Any future changes to FF&E that have an impact on MEP will be routed through the Change Management process.
The IOT&A contractor is to ensure all identified FF&E or architectural significant items are in accordance with the Design Documents to minimize any need to change the Mechanical, Electrical, Plumbing or Architectural support systems and locations. Any impact to MEP resulting from equipment changes must go through the Change Request process. The contractor shall utilize Space, Equipment, and Planning System (VA-SEPS) Joint Service Number (JSN) nomenclature in accordance with the VA BIM Guide (available at VA BIM GUIDE, https://www.cfm.va.gov/til/bim/VA-BIM-Guide.pdf) for all unique ID numbering. The cut sheets shall identify the basis of design item and shall show appropriate VA-SEPS JSNs. New JSN requests and JSN searches can be conducted at https://dha.max.gov/milstd1691. The contractor shall develop a ROM to include estimated costs for storage, delivery, and installation.
The general contractor will be required to identify all Mechanical Electrical Plumbing (MEP) information necessary, and timelines needed. The IOT&A contractor is to develop the make and model of all equipment with the Design Documents. The VA will be responsible to provide the correct POC’s as designees to the IPT, for the user group meetings who have the authority to make equipment decisions, such as identification of make and model of equipment, locations for all equipment, and any J&As planned for the procurement of specified equipment. The IOT&A contractor is to ensure all identified FF&E or architectural significant items are in accordance with the Design https://www.cfm.va.gov/til/bim/VA-BIM-Guide.pdf https://dha.max.gov/milstd1691
11 | P a g e
Documents to minimize any need to change the Mechanical, Electrical, Plumbing or Architectural support systems and locations.
16.2.1 FF&E Cut Sheets Cut Sheets shall include a photo of the item, finishes, specifications, instructions, dimensions, etc., that apply to that specific item. Cut sheet information shall be specific enough to convey information to the VA as they will need to purchase and install the product, but general enough to allow competition across multiple manufacturers. Contractor shall prioritize cut sheets for long lead time items.
16.2.2 Artwork Cut Sheets Artwork Cut Sheets shall include the following information:
1) Job name, number, location, and date.
2) The title of the artwork and the artist’s name, manufacturer (if applicable), item number, size and room number where it is to be placed.
3) A picture of the proposed artwork in color. If the piece is recommended or commissioned, provide a picture or brochure showing the commissioned artist’s work.
4) Frame description and sample
5) Installation type (i.e. Security hardware, cleats, stand-offs, etc.)
16.2.3 Room-by-Room
Master Equipment and Furniture List
(MEL)
(Attachment E is a representation of required data/information.
The Room-by-Room room contents, identifies all items listed by room. The contractor shall provide a complete and finalized room by room contents list for each room throughout the project. This includes, but is not limited to, artwork, OI&T equipment, other equipment, and furniture. The Design Support contractor shall perform QA against the design documents to avoid conflict.
Initial Data collected, updated, and maintained includes space identification that matches schematic drawings, VV vs VC vs CC, historical item cost to include any purchased install and/or training, contracting and historical vendor lead times, funding appropriation, recurring vs non-recurring expense, functional area, room code, # of rooms, room name, quantity per room, estimated historical costs, projected need by date, historical vendor lead time, and acquisition method as well expected need by dates based on preliminary construction award and building delivery date.
16.2.4
FF&E Layouts Space plans showing FF&E furniture and equipment placement. FF&E layouts are to be used for end-user/VA designer group meetings, to assist in the validation of the FF&E, and to facilitate outfitting as an installation guide. Items shall be color-coded on the drawings for easy identification (i.e. red for reuse, black for construction contractor provided and installed, green for manufacturer installed).
The initial layouts will be for the typical rooms in the concept drawings for the VHA Medical Center. Updated drawings will be provided to update FF&E placement using basis of design dimensions using Revit. The IOT&A contractor is to ensure all identified FF&E or architectural significant items are in accordance with the Design Documents to minimize any need to change the
12 | P a g e
Mechanical, Electrical, Plumbing or Architectural support systems and locations. The contractor will work closely with VA Interior Designer.
Hard copies shall be available to the VA as soon as an update is completed.
Floor plans and elevations to be printed on half-size sheets (15”x21”). All others may be printed on 11”x17” or 8.5”x11” paper with a 1/4" scale.
16.2.5 3-Dimensional Design Renditions
3D design renditions of FF&E items within planned spaces using AutoCAD, or another similar program agreed upon between the contractor and the VA Interior Designer.
16.2.6 Rough Order of
Magnitude (ROM)
The ROM is the total estimated cost by item to purchase, install, test, and train (as applicable) for the project. The ROM should be provided with the final DD.
16.2.7 Design Submittal 1
Contractor must deliver to the COR, used by the A/E all latest project information such as specific design requests as a result of user group meetings that occur prior to the delivery of DD1. Site activation team to provide due date of information to the A/E contractor to the activation contractor so to ensure A/E has time to include.
Design submittal 1 shall include:
1) Generic Cut Sheets for all JSNs for the equipment on the drawings if selected by the VA prior to activation contractor on-board.
2) Room by room should match drawings and be reflected in the Contents
Acquisition plan
3) All Rooms Contents List (Attachment E). (Attachment E is a representation of required data/information.
16.2.8 Design Submittal 2
Contractor must deliver to the COR, used by the A/E all latest project information such as specific design requests as a result of user group meetings that occur prior to the delivery of DD2. Site activation team to provide due date of information to the A/E contractor to the activation contractor so to ensure A/E has time to include.
Design submittal 2 shall include:
1) Basis of Design Cut Sheets for all JSNs for the equipment on the drawings if selected by the VA prior to the activation contractor on board.
2) Room by Room should match drawings and be reflected in the Contents
Acquisition plan
3) All Rooms Contents List (Attachment E). (Attachment E is a representation of required data/information.
16.2.9 Discrepancy Report Discrepancy Report between final room contents and USACE equipment list:
Report to show any discrepancies between the design support services contractor final room contents list and those found in the building contracting agencies list. Final report due after Pre-Construction RFP Support contractor has made final resolutions, which tracks the resolutions. Final report should show no discrepancies.
13 | P a g e
17.0 Reserved
18.0 Deliverables
Deliverables have established delivery schedules as specified in the PWS. Failure to comply with the delivery schedule will cause the contractor to be delinquent in performance. Such tardiness will be annotated in the Contractor Performance Assessment Rating System (CPARS) interim and/or final ratings.
18.1 Deliverable Schedule
Submittals are required deliverables mutually agreed upon within the contract. Submittals have established delivery schedules as specified in the PWS. Failure to comply with these delivery schedules makes the contractor delinquent in performance. Such tardiness will be annotated in the contractor Performance Assessment Rating System (CPARS) interim and/or final ratings.
Delivery schedule for deliverables is identified below. Due to the variations in project schedules, construction timelines, etc., deliverable due dates may be adjusted with prior notification and approval by the VA CO. For deliverables with a schedule yet to be determined, a mutually agreed upon schedule and/or format will be determined during the performance period. The agreed upon date must not delay the project schedule and must be tracked in the Activation Project Schedule for verification.
The contractor shall provide deliverables per the task/delivery schedule. Deliverables may be a “moving target date” depending on construction schedule. Deliverables with a “moving target date” dependent on construction schedule will be identified as "Building Occupancy Date (date building is turned over for outfitting etc.) minus X number of days".
Deliverable No.
Deliverable Name Due
16.1.1 Monthly Project Status Report Monthly
16.1.2 Risk Management Plan and Log 1 month after effective date of contract;
updated as required
16.1.3 Meeting Minutes and Meeting Agendas Agendas shall be distributed no less than 3 days prior to the meeting. Minutes shall be distributed no more than 3 days post meeting
16.1.4 PWS Deliverable Updates No later than 10 business days after identification of required updates
16.2.1 FF&E Cut Sheets 3 months after effective date of contract;
updated as required
16.2.2 Artwork Cut Sheets 3 months after effective date of contract;
updated as required
16.2.3 Room-by-Room Master Equipment and
Furniture List (MEL)
1 month after effective date of contract;
updated as required
16.2.4 FF&E Layouts 3 months after effective date of contract;
updated as required
16.2.5 3-Dimensional Design Renditions 3 months after effective date of contract;
updated as required
16.2.6 Rough Order of Magnitude (ROM) 3 months after effective date of contract;
updated as required
16.2.7 Design Submittal 1 TBD based on design schedule
16.2.8 Design Submittal 2 TBD based on design schedule
14 | P a g e
16.2.9 Discrepancy Report Interim Report due 2 months after effective date of contract and Final Report due 1 month prior to the end of the contract
33.8.1 Quality Control Plan 1 month after effective date of contract;
updated as required
18.2 Deliverable Formatting
Reports and documents delivered by the Contractor in performance of this contract will be considered "technical data" as defined in the applicable "Rights in Data" clause of the contract. All documentation shall reflect the latest version number, unless specifically directed otherwise by the Government. All documentation shall be prepared in accordance with standard industry practices, ensuring electronically produced documents, which reflect logical flow of material, tables of contents, indices, and page numbering. The unexcused failure to comply with the delivery schedule makes the contractor delinquent in performance. Such tardiness will be annotated in the Contractor's past performance evaluation.
The Contractor shall deliver documentation in electronic format unless otherwise directed in the solicitation/contract. Contractor may be required to submit deliverables using software, such as MS Word 2010/2016, MS Excel 2010/2016, MS PowerPoint 2010/2016, MS Project 2010/2016, MS Access 2010/2016, MS Visio 2010/2016, AutoCAD 2010/2016, Adobe Postscript Data Format (PDF), Adobe Acrobat Pro, Revit 2010/2016, SPEXX, Submittal Exchange or similar, and Bluebeam, unless otherwise directed in the PWS, solicitation, or contract. All deliverables must be submitted in an editable format, such as Word. Example, PDFs are acceptable for final deliverables, as long as the Government is provided an editable version.
The contractor is responsible for determining additional software needs, acquiring the software licenses, installing, and maintaining necessary software (to include PlanGrid) throughout the project is at the cost of the contractor.
18.3 Files
The contractor shall maintain complete and accurate files of documentation, records, copies of original results and reports, verified original data, corrected data, and corrected supporting final report required under the terms of the contract. The contractor shall not allow access to the files by any Government agency, non-Government agency, or individual unless specifically authorized by the CO or designated representative. Files shall be made available to the CO, COR, or designated representative upon request. All files will become the property of the Government and shall be turned over to the CO, COR, or designated representative at the completion or termination of this contract. All briefings, reports, and other files produced by the contractor for the Government under the terms of this contract shall be property of the Government.
18.4 Government Submission Review
Unless specifically stated in the deliverable schedule, the Government has 10 business days to review and provide comments on submitted deliverables, unless deliverable reviews and changes are dependent upon third parties (i.e., construction Contractor, A/E firm, RE, etc.), in which case a reasonable review period will be discussed with the Contractor. The Contractor has five (5) business days to complete any necessary revisions and resubmit for Government review and acceptance. Any deliverable submitted to the Government that is not reviewed and returned within 10 business days shall be considered “accepted” by the Government, except in the case described above regarding third party dependencies. The Government will make every effort to accomplish review in as little time as practicable.
19.0 National Archives Records Administration (NARA) Management A. Applicability
15 | P a g e
This clause applies to all Contractors whose employees create, work with, or otherwise handle Federal records, as defined in Section B, regardless of the medium in which the record exists.
B. Definitions
“Federal record” as defined in 44 U.S.C. § 3301, includes all recorded information, regardless of form or characteristics, made or received by a Federal agency under Federal law or in connection with the transaction of public business and preserved or appropriate for preservation by that agency or its legitimate successor as evidence of the organization, functions, policies, decisions, procedures, operations, or other activities of the United States Government or because of the informational value of data in them.
The term Federal record:
1. includes VHA records.
2. does not include personal materials.
3. applies to records created, received, or maintained by Contractors pursuant to their VHA contract.
4. may include deliverables and documentation associated with deliverables.
C. Requirements
1. Contractor shall comply with all applicable records management laws and regulations, as well as National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. Ch.
21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.
2. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.
3. In accordance with 36 CFR 1222.32, Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.
4. VAGLAHCS and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of VAGLAHCS or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, the Contractor must report to VHA. The agency/VAGLAHCS must report to promptly to NARA in accordance with 36 CFR 1230.
5. The Contractor shall immediately notify the appropriate Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the Purchase Order. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to VAGLAHCS control, or the Contractor must hold it until otherwise directed. Items returned to the
16 | P a g e
Government shall be hand carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer or address prescribed in the design support contract. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).
6. The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, contracts. The Contractor (and any sub-contractor) is required to abide by Government VAGLAHCS guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.
7. The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with VAGLAHCS policy.
8. The Contractor shall not create or maintain any records containing any non-public VAGLAHCS information that are not specifically tied to or authorized by the contract.
9. The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.
10. The VAGLAHCS owns the rights to all data and records produced as part of this contract. All deliverables under the contract are the property of the U.S. Government for which VAGLAHCS shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest. Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-20.
11. Training. All Contractor employees assigned to this contract who create, work with, or otherwise handle records are required to take VHA-provided records management training, Talent Management System (TMS) Item #3873736, Records Management for Records Officers and Liaisons. The Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training.
[Note: To the extent an agency requires contractors to complete records management training,…