Attachment A_Performance Work Statement (PWS).pdf
PDF 119 KB Posted
- Attached to
- Paving and Drainage Improvements at Eisenhower Lock Federal contract opportunity
- Solicitation number
- 6923G524Q1362
About this file
This document is a Performance Work Statement (PWS) for the Eisenhower Lock Paving & Drainage Improvements project. The Great Lakes St. Lawrence Seaway Development Corporation (GLS) has a requirement for new pavement, drainage structures, and fencing in the parking area next to the new Visitors Center; new pavement, drainage swales, and a concrete slab at the downstream stop log storage area; new pavement and drainage swale around the downstream emergency generator; and new top course pavement on the access road to the Eisenhower Lock Overlook area.
The related federal contract opportunity is for the Paving and Drainage Improvements at Eisenhower Lock in Massena, NY. It is a 100% Small Disadvantaged Business Set-aside with a NAICS code of 238990 and a magnitude between $500,000 and $1,000,000. The solicitation number is 6923G524Q1362 and offers are due on 25 October 2024 by 2:00pm EST. Performance and Payment bonds are required within 10 days of award. The Department of Transportation Saint Lawrence Seaway Development Corporation is the federal agency issuing this opportunity.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 6923G524Q1362_REV1.pdf | ||
| 6923G524Q1362 QA.pdf | ||
| 6923G524Q1362.pdf | ||
| Attachment E_Davis-Bacon Act WD NY20240009.pdf | ||
| Attachment B_Pricing Sheet.xlsx | XLSX spreadsheet | |
| Attachment C_Eisenhower Lock Paving and Drainage Technical References.pdf | ||
| Attachment D_Eisenhower Lock Technical Exhibits.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
EISENHOWER LOCK PAVING & DRAINAGE IMPROVEMENTS
SECTION 1 – Scope
1.1 – Purpose/Introduction/Overview
The Great Lakes St. Lawrence Seaway Development Corporation (GLS) has a requirement for the installation of new pavement, drainage structures, and fencing in the parking area next to the new Visitors Center; new pavement, drainage swales, and a concrete slab at the downstream stop log storage area; new pavement and drainage swale around the downstream emergency generator; and new top course pavement on the access road to the Eisenhower Lock Overlook area. Over time the existing parking areas and access roads have begun to show signs of wear and deterioration, thus prompting construction of new parking areas and access roads with added drainage and fencing. This work shall be completed at Eisenhower Lock located at 76 and 190A&B Barnhart Island Road, Massena New York.
1.2 – Background
Part of the Department of Transportation (DOT), the Great Lakes St. Lawrence Seaway
Development Corporation (GLS) is a wholly owned government corporation created by statute
May 13, 1954, to construct, operate and maintain the U.S. portion of the St. Lawrence Seaway between the Port of Montreal and Lake Erie. The mission of the GLS is to serve the U.S.
intermodal and international transportation system by improving the operation and maintenance of a safe, reliable, efficient, and environmentally responsible deep-draft waterway, in cooperation with its Canadian counterpart. The GLS also encourages the development of trade through the Great Lakes Seaway System, which contributes to the comprehensive economic development of the entire Great Lakes region.
SECTION 2 – APPLICABLE DOCUMENTS
The documents listed in this section, combined with the other sections of the PWS, form the contract requirements for the project. These documents are being furnished to the Contractor in electronic format only. References to Owner in the Technical Specifications shall mean GLS, and references to
Owner’s Representative shall mean the GLS appointed Contracting Officer’s Representative (COR).
Drawings:
SLS-326-310/1 – Cover Sheet
SLS-326-310/2 – Vicinity and Locality Maps
SLS-326-310/3 – Existing Site Utility Map – Visitors Center
SLS-326-310/4 – Existing Site Utility Map – Stop Log Storage Area
SLS-326-310/5 – Existing Site Utility Map – Emergency Generator
SLS-326-310/6 – Existing Site Utility Map – Overlook Access Road
SLS-326-310/7 – Site Paving Plan – Visitor Center
SLS-326-310/8 – Site Paving Plan – Stop Log Storage Area
SLS-326-310/9 – Site Paving Plan – Emergency Generator
SLS-326-310/10 – Site Paving Plan – Overlook Access Road
SLS-326-310/11 – Site Grading & Drainage Plan – Visitors Center
SLS-326-310/12 – Site Utility & Fencing Plan – Visitors Center
SLS-326-310/13 – Paving & Manhole Details
SLS-326-310/14 – Fencing & Gate Details
SLS-326-310/15 – Electrical Details
Technical References:
Section 02200 – Earthwork
Section 02505 – Gravel and Crush Stone Base and Subbase Course
Section 02511 – Hot-Mixed Asphalt Paving
Section 033000 – Cast In Place Concrete
Section 323119 – Decorative Metal Fences and Gates
Section 334211 – Stormwater Gravity Piping
Section 334230 – Stormwater Drains
SECTION 3 – REQUIREMENTS
3.1 – Scope Requirements
This PWS overall is for the removal of an existing parking area, and installation of new pavement, drainage, and fencing on the south side of Eisenhower Lock west of the Visitor
Center; the removal of an existing access road and parking area, installation of new pavement, drainage swale, and a concrete slab at the downstream stop log storage area; installation of new pavement and drainage swale around the downstream emergency generator; and milling and topping of the access road to the Eisenhower Overlook parking area. The existing parking area and access roads have deteriorated over time and are in need of replacement and improved drainage. The Contractor shall be responsible for the excavation and removal of all existing pavement and fill within the limits of the paving area as shown in the contract drawings. During excavation the contractor shall ensure that grades are maintained to promote drainage away from the lockwalls and to the catch basins on the south side of the parking area at the Visitor Center parking area, as well as maintaining grades at the remaining paving areas.
The elevations at the concrete wall on the north side of the parking area shall be kept and the new pavement shall be flush with the concrete to ensure a smooth driving transition. Spoils shall be transported to GLS property as identified by the COR prior to the start of the project.
After the existing parking area and access roads are excavated the Contractor shall install the proposed catch basins and storm piping, where required, per the contract drawings and specifications. Positive drainage from the lock walls to the catch basins shall be maintained.
The Contractor shall also install all electrical conduits and electrical manholes per the contract drawings and specifications after the excavation of the existing parking area.
The Contractor shall also install new fencing per the contract drawings and technical specifications. The proposed fencing shall match the existing black ornamental fencing that is currently installed around the new Visitor Center. The fencing shall be Ameristar Echelon II or an approved equal. This fencing also includes the installation of a 5’ wide swing man-gate and a
25’ wide sliding gate with an automatic gate controller. The automatic gate controller shall be compatible with GLS standard system detention loops per the manufacturers recommendation.
Final placement/location of the gates shall be field verified with the GLS COR. GLS will be responsible for the final integration of the automatic gate controller into their system.
Once all utilities are installed the Contractor shall install the pavement per the contract drawings and technical specifications. Note that some paving areas require full depth replacement of the pavement, while some areas require milling and topping of the existing pavement as shown in the contract drawings. The Contractor shall maintain grades per the contract drawings to promote drainage away from the lock walls and to the catch basins on the south side of the parking area (at the Visitor Center parking area), as well as maintaining grades and elevations for the remaining paved areas to ensure smooth driving transitions. The elevations at the concrete wall on the north side of the parking area shall be kept and the new pavement shall be flush with the concrete to ensure a smooth driving transition.
The Contractor shall also install the concrete slab at the stop log storage area per the contract drawings and technical specifications. The concrete slab shall be installed after GLS has removed the stop logs from the construction area, this is anticipated to be completed before construction starts. The Contractor shall also employ a third-party testing firm to perform inspection to include, slump, air, water/cement ratio, and collect concrete cylinders to verify the concrete compressive strength at 3-days, 7-days, and 28-days and a spare cylinder to test at 56-days if the 28-day compressive strength is less than 5,000 psi. Concrete shall be vibrated during placement as necessary to ensure no void spaces in and around the steel.
Drainage swale shall be installed where indicated on the contract drawings.
The Contractor shall be responsible for all labor, equipment, materials, utilities, and any other costs required to complete all requirements of this project. The Contractor shall perform all work in a safe manner in accordance with applicable Federal regulations and shall submit a
Health and Safety Plan (HASP) for GLS approval prior to commencing work.
3.2 – Task Requirements
CLIN 0001 – Mobilization/Demobilization
Task 1 – Attend pre-construction meeting. Review construction/installation with GLS, provide project schedule, schedule of values, Health and Safety Plan (HASP), and provide material submittals log.
Task 2 – Mobilize all construction equipment and materials to site.
Task 3 – Demobilize all construction equipment and remove excess materials from site after project completion.
CLIN 0002 – Paving Area 1 (Visitor Center)
Task 4 – Per the contract drawings and specifications, excavate the existing Visitor Center parking area to the depth indicated and remove all existing pavement and subbase.
Compact existing subgrade as necessary.
Task 5 – Per the contract drawings and specifications, install new subbase, geotextile fabric, binder course, and top course pavement in all areas of the Visitor Center parking area as indicated. Ensure all site drainage is directed away from the lock walls and to the catch basins or drainage swales.
CLIN 0003 – Paving Area 2 (Stop Log Storage Area)
Task 6 – Per the contract drawings and specifications, excavate the existing Stop Log Storage Area parking area and access road to the depth and limits indicated, and remove all existing pavement and subbase. Compact existing subgrade as necessary.
Task 7 – Per the contract drawings and specifications, install new subbase, geotextile fabric, binder course, and top course pavement in all areas of the Stop Log Storage Area parking area and access road as indicated. Ensure all site drainage is directed away from the lock walls and to the catch basins or drainage swales.
CLIN 0004 – Paving Area 3 (Emergency Generator)
Task 8 - Per the contract drawings and specifications, excavate the existing downstream Emergency Generator parking area to the depth and limits indicated, and remove all existing pavement and subbase. Compact existing subgrade as necessary.
Task 9 – Per the contract drawings and specifications, install new subbase, geotextile fabric, binder course, and top course pavement in all areas of the downstream Emergency Generator parking area as indicated. Ensure all site drainage is directed away from the lock walls and to the catch basins or drainage swales.
CLIN 0005 – Paving Area 4 (Overlook Access Road)
Task 10 – Per the contract drawings and specifications, mill the existing top course pavement of the Overlook Access Road to the depth and limits indicated. Remove all millings and compact the remaining binder course as necessary.
Task 11 – Per the contract drawings and specifications, install new top course pavement, after applying tack coat, to the depth and limits indicated.
CLIN 0006 – Concrete Slab (Stop Log Storage Area)
Task 12 – Per the contract drawings and specifications, excavate the existing Stop Log Storage area to the depth and limits indicated for the new concrete slab. Compact remaining subgrade as necessary.
Task 13 – Per the contract drawings and specifications, install geotextile fabric on the compacted subgrade, and place new subbase on geotextile fabric and compact. Once compacted, install steel reinforcement and pour the new concrete slab to the limits indicated maintaining widths and installing dowels where required. Ensure all site drainage is directed away from the lock walls and to the catch basins or drainage swales.
CLIN 0007 – Drainage Swale (Stop Log Storage Area)
Task 14 – Per the contract drawings and specifications, excavate and install geotextile fabric and rip-rap drainage swale to the limits indicated. Install rip-rap stone along the riverbank at the Stop Log Storage Area where indicated.
CLIN 0008 – Storm Piping and Catch Basins
Task 15 – Per the contract drawings and specifications, after the existing parking area at the Visitor Center is excavated and prior to the placement of new pavement, install new catch basins and storm piping in the locations and elevations indicated.
CLIN 0009 – Electrical Conduits and Manhole
Task 16 – Per the contract drawings and specifications, after the existing parking area at the Visitor Center is excavated and prior to the placement of new pavement, install new electrical conduits and electrical manholes where indicated.
CLIN 0010 – Fencing and Gates
Task 17 – Per the contract drawings and specifications, remove existing jersey barriers and fencing where indicated.
Task 18 – Per the contract drawings and specifications, install new fencing, gates, and automatic gate controller where indicated. Fencing, gates, and automatic gate controller shall also be installed per the manufacturer’s recommendations. GLS shall be responsible for final integration of the automatic gate controller into their system.
3.3 – Deliverables
Tasks Deliverables Date/Frequency
CLIN 0001 Mobilization/Demobilization IAW Contractors Project Plan
Task 1 Attend pre-construction meeting, review construction/installation with GLS, provide Construction Schedule, Schedule of Values, HASP and submittal log in accordance with Technical Specifications and PWS.
Within 15 days of Award
Task 2 Mobilize equipment and materials to the site. IAW Contractors Project Plan
Task 3 Demobilize equipment and remove excess materials from the site.
IAW Contractors Project Plan
CLIN 0002 Paving Area 1 (Visitors Center) IAW Contractors Project Plan
Task 4 Excavate existing Visitor Center parking area and remove existing pavement and subbase.
IAW Contractors Project Plan
Task 5 Install new pavement at the Visitor Center parking area.
IAW Contractors Project Plan
CLIN 0003 Paving Area 2 (Stop Log Storage Area) IAW Contractors Project Plan
Task 6 Excavate existing Stop Log Storage Area parking area and access road and remove existing pavement and subbase.
IAW Contractors Project Plan
Task 7 Install new pavement at the Stop Log Storage Area parking area and access road.
IAW Contractors Project Plan
CLIN 0004 Paving Area 3 (Emergency Generator) IAW Contractors Project Plan
Task 8 Excavate existing downstream Emergency Generator parking area and remove existing pavement and subbase.
IAW Contractors Project Plan
Task 9 Install new pavement at the downstream Emergency Generator parking area.
IAW Contractors Project Plan
CLIN 0005 Paving Area 4 (Overlook Access Road) IAW Contractors Project Plan
Task 10 Mill the existing Overlook Access Road top course pavement and remove the millings.
IAW Contractors Project Plan
Task 11 Install new top course pavement at the Overlook Access Road.
IAW Contractors Project Plan
CLIN 0006 Concrete Slab (Stop Log Storage Area) IAW Contractors Project Plan
Task 12 Excavate existing Stop Log Storage Area and remove materials.
IAW Contractors Project Plan
Task 13 Install new concrete slab at the Stop Log Storage Area.
IAW Contractors Project Plan
CLIN 0007 Drainage Swale (Stop Log Storage Area) IAW Contractors Project Plan
Task 14 Install new drainage swale at the Stop Log Storage Area.
IAW Contractors Project Plan
CLIN 0008 Storm Piping and Catch Basins IAW Contractors Project Plan
Task 15 Install new storm piping and catch basins in the Visitor Center parking area.
IAW Contractors Project Plan
CLIN 0009 Electrical Conduits and Manhole IAW Contractors Project Plan
Task 16 Install new conduits and electrical manholes in the Visitor Center parking area.
IAW Contractors Project Plan
CLIN 0010 Fencing and Gates IAW Contractors Project Plan
Task 17 Remove existing jersey barriers and fencing at the Visitor Center parking area.
IAW Contractors Project Plan
Task 18 Install new fencing, gates, and automatic gate controller at the Visitor Center parking area.
IAW Contractors Project Plan
3.4 – General Conditions
3.4.1 – Period of Performance The period of performance is anticipated to be 90 days after being issued the Notice to Proceed
(NTP). The NTP is expected to be issued on or about April 01, 2025.
3.4.2 – Place of Performance
All work shall take place at Eisenhower Lock, located at 76 and 190A&B Barnhart Island Road, Massena New York.
3.4.3 – Government Furnished Equipment/Information
The Contractor shall supply all materials needed to complete the project.
3.4.4 – Facilities
GLS will provide access to all required areas to complete the project.
3.4.5 – Safety
The Contractor shall be responsible for a safe work environment at all times. The Contractor shall comply with Federal Regulations. The Contractor shall submit a safety plan for approval prior to commencing work.