This document is a Statement of Work and Technical Specification (SOW/SPC) for a Helium Storage Tank (HST) for the National Synchrotron Light Source II (NSLS-II) at Brookhaven National Laboratory. The project requires manufacturing a horizontal 30,000-gallon helium storage tank with specific technical requirements, including a maximum working pressure of 250 PSI at 140°F, outside dimensions of 10' 11-7/8" diameter x 46' 8-7/8" length, and zero corrosion allowance on internal and external surfaces.
The contractor must design and manufacture the HST in compliance with the 2015 edition of the ASME Boiler and Pressure Vessel Code, with code stamping by a certified ASME pressure vessel manufacturer. Key deliverables include design and engineering documentation, pre-production meeting, progress reports, and an End Item Documentation (EID) package. The project timeline is approximately 26 weeks after contract award, with documentation due at 6 weeks, pre-production meeting at 7 weeks, and HST fabrication and delivery by week 25-26. The tank will store ultra-pure helium (99.9995% purity) and must meet rigorous quality assurance and vacuum service requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment (B) Specs RF-CRY-TNK-0100.pdf | ||
| Enclosure (D) W-9.pdf | ||
| Enclosure (C) Vendor ACH Authorization.pdf | ||
| Enclosure (A) Draft Contract 462180.docx | DOCX document | |
| RFQ 462180.pdf | ||
| Enclosure (B) Quotation Pricing Sheet AMS-Form-043.docx | DOCX document | |
| Attachment (C) BNL-QA-101.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Brookhaven National Laboratory Number: NSLSII-RF-SOW-SPC-002
Brookhaven Science Associates Version: 1
National Synchrotron Light Source II (NSLS-II) Effective: 13 MAR 2025
RF Cryogenic System – Helium Storage Tank
Statement of Work and Technical Specification
QA Category: A-3
Reviewed and Approved By:
William Gash NSLS-II Mechanical Engineer
James Rose NSLS-II RF System Group Leader
Robert Lee NSLS-II ES&H Manager
This information is controlled by the U.S. Department of Commerce Export Administration Regulations
15 CFR Parts 730-774 as EAR99 Technology.
Version 1 ii Brookhaven National Laboratory
VERSION CONTROL SHEET
VERSION DESCRIPTION DATE AUTHOR
1 First Issue 13 MAR 2025 W. Gash
MDC No. 1 – Added the Export Control disclaimer statement on the bottom of page 1.
28 MAR 2025 W. Gash
NSLSII-RF-SOW-SPC-002: RF Cryogenic System – Helium Storage Tank Statement of Work and Technical Specification iii
NSLS-II iii 13 MAR 2025
Contents
1 Introduction and Overview
2 References
3 Requirements
3.1 Contractor Responsibilities
3.2 Design, Engineering, and Manufacturing Documentation
3.3 Pre-Production Meeting
3.4 Contractor Required Inspection and Testing
3.5 Progress Reporting
3.6 Documentation and Data Management
3.6.1 General Documentation Requirements
3.6.2 Drawing and Model File Format Requirements
3.6.3 End Item Documentation (EID)
3.7 Spare Parts
3.8 Environment, Safety and Health (ES&H)
3.9 Warranty
3.10 Shipping
4 Quality Assurance
4.1 Quality Assurance Requirements
4.2 Material Review Board (MRB) Authority
4.3 QA Flow-Down
5 Schedule / milestones
6 Deliverables
7 Value Engineering
8 Technical Specif ications
Version 1 iv Brookhaven National Laboratory
Definitions/Acronyms
ASME American Society of Mechanical Engineers
BNL Brookhaven National Laboratory
BPVC Boiler and Pressure Vessel Certification
BSA Brookhaven Science Associates
CAD Computer Aided Design
EID End Item Documentation
ESH Environment, Safety, and Health
HST Helium Storage Tank
MRB Material Review Board
NSLS-II National Synchrotron Light Source II
QA Quality Assurance
PSI Pounds Per Square Inch
RF Radio Frequency
SOW/SPC Statement of Work/Technical Specification
NSLSII-RF-SOW-SPC-002: RF Cryogenic System – Helium Storage Tank Statement of Work and Technical Specification 1
NSLS-II 1 13 MAR 2025
1 INTRODUCTION AND OVERVIEW
This Statement of Work and Technical Specification (SOW/SPC) is the basis for the procurement of the Helium Storage Tank (HST) for the RF Cryogenic system of the National Synchrotron Light Source II (NSLS-II) at Brookhaven National Laboratory (BNL). The Helium Storage Tank, hereafter will be referred to as the “HST”.
The cryogenic system used for cooling the superconducting RF cavities was installed during construction of the NSLS-II accelerator facility at BNL. Three (3) HSTs were included in the original cryogenic system installation.
Currently there is a requirement to add an additional HST, which will increase the helium storage capacity and enhance the performance of the existing cryogenic system. This additional HST will be built to the same specifications as the original (3) HSTs.
This document outlines the Contractor’s responsibilities and obligations necessary for completing the requirements as set forth herein.
2 REFERENCES
The following documents are an integral part of this document; the applicable revision level will be the latest that is in effect at the time of award or as stated herein:
Document Number Document Title
ASME Y14.5 Dimensioning and Tolerancing: Engineering Drawing and Related Documentation Practices
BNL-QA-101 BNL Supplier Quality Assurance Requirements
ASME BPVC Section VIII Division 1
ASME Boiler and Pressure Vessel Code
RF-CRY-TNK-0100 Helium Storage Tank – BNL Drawing
3 REQUIREMENTS
3.1 Contractor Responsibilities
The Contractor shall be responsible for the engineering, design, procurement of all materials, manufacturing, assembly, inspection/testing, and delivery of the HST. It is the Contractor’s responsibility to ensure that the HST complies with all the specifications, referenced documents, and instructions as referenced herein.
3.2 Design, Engineering, and Manufacturing Documentation
To ensure compliance with this document, and all referenced documents the Contractor shall provide the following documentation to BSA for review one (1) week prior to the Pre-Production Meeting.
• Pressure Vessel Design Calculations that conform to the 2015 edition of the ASME BPVC, Section VIII, Division 1, (the current edition of this code may be used with BSA concurrence).
2 National Synchrotron Light Source II
Version 1 2 Brookhaven National Laboratory
• Stress/deflection calculations and analyses for the lifting lugs using an engineering analysis technique approved by BSA. Calculations and analysis models/files shall be provided to BSA.
• Specifications, sourcing, and catalog cut sheets for all commercially purchased components.
• Manufacturing drawings and Part Lists if not embedded in the drawing.
• Manufacturing/Inspection/Test-Plan. The plan shall identify the manufacturing processes, inspections, and tests required to complete all efforts identified in this document.
• Manufacturing schedule (Gantt type chart) showing the timeline for each major activity necessary to meet the overall BSA schedule requirements shown in Section 5.
3.3 Pre-Production Meeting
A pre-production meeting by video conference between the Contractor and BSA shall be held in accordance with the schedule set forth herein, at a mutually agreed upon time.
The required documentation shown in Section 3.2 shall be presented by the Contractor at the pre-production meeting to validate compliance with this document and all referenced documents.
Upon written approval from BSA the design shall be considered “locked”, and no changes are permitted to the design, materials, processes, methods, or component-level substitutions, without written approval by BSA. BSA approval of the Contractor’s documentation does not relieve the Contractor’s responsibility for meeting the specifications, requirements, and referenced documents listed herein. Ordering of materials and components prior to BSA approval are done solely at the Contractor’s risk and responsibility .
3.4 Contractor Required Inspection and Testing
The Contractor shall inspect and test the HST at the Contractor’s facility to demonstrate full compliance to the requirements, specifications, and referenced documents listed herein. BSA reserves the right to witness the final inspection and hydrostatic pressure test at the Contractor’s facility.
3.5 Progress Reporting
Within two (2) weeks after award of contract, bi-weekly progress reports shall be emailed to the BNL technical representative. If additional information is needed, a conference call or video conference meeting between the Contractor and BSA shall be held at a mutually agreed upon time.
3.6 Documentation and Data Management
3.6.1 General Documentation Requirements
▪ All documentation provided by the Contractor shall be in English.
▪ Electronic documents other than drawings can be furnished in PDF format.
▪ All Contractor drawings shall:
Be formatted in accordance with ASME Y14.5 or equivalent (requires written approval by BSA)
Have views shown in third-angle projection
Have a separate parts list if not embedded in the drawing
Be provided to BSA in electronic format as defined below.
NSLSII-RF-SOW-SPC-002: RF Cryogenic System – Helium Storage Tank Statement of Work and Technical Specification 3
NSLS-II 3 13 MAR 2025
3.6.2 Drawing and Model File Format Requirements
The Contractor shall provide and maintain, as well as have the capability to receive and send, CAD files of all components or assemblies in the following formats:
▪ 2D formats: AutoCAD 2D drawings (.DWG format).
▪ 3D solid model formats: IPT (preferably), IAM, STP or SAT.
▪ IGES files and surface models are not acceptable.
3.6.3 End Item Documentation (EID)
At a minimum, the Contractor shall provide an electronic copy and one hard copy of the EID package in accordance with the schedule set forth in this document. The EID package for the HST shall consist of the following documentation:
▪ ASME Form U-1, Manufacturer’s Data Report
▪ Name plate rubbing or photo
▪ Paint safety data sheet
▪ Manufacturer warranty statement
▪ Final (as-built) manufacturing drawings
▪ Material certification for all parts.
▪ Source inspection documents for all major items purchased by the Contractor (source inspections would be those conducted at a subcontractor to the Contractor)
▪ Dimensional inspection report per the HST design
▪ Radiographic inspection reports
▪ Hydrostatic pressure test report
▪ HST interior surface cleanliness inspection report (performed after hydrostatic pressure testing)
3.7 Spare Parts
The Contractor shall provide BNL with the specifications and sourcing information for the manway flange and gasket.
3.8 Environment, Safety and Health (ES&H)
The Contractor shall design and build the HST in accordance with ES&H requirements in the appropriate specifications, codes, standards, and other documents listed herein.
3.9 Warranty
The Contractor shall provide a warranty for the HST, against failure and defects for a minimum period of 2 years (24 months) from final acceptance of the HST at BNL.
3.10 Shipping
• After the HST has been cleaned and tested, all openings shall be sealed with metal flanges and metal plugs and the HST shall be purged and pressurized with dry nitrogen to an internal pressure of 15 PSI.
• The HST shall be properly braced and cushioned so that it will not shift during handling and shipment.
4 National Synchrotron Light Source II
Version 1 4 Brookhaven National Laboratory
• The Contractor shall arrange transportation services with a specialized truck carrier. A drawing of the BNL on-site access tunnel is supplied for reference to determine the type of truck necessary for delivery to the BNL site.
• The HST shall be delivered to:
Brookhaven National Laboratory
Central Receiving Department
98 Rochester Street
Upton, New York 11973
• BNL requires a minimum of five (5) business days’ notice prior to the date and time of the carrier’s arrival at the BNL site.
• The BNL receiving department hours of operation are Monday through Friday between 9:00AM and 3:00PM Eastern Time zone.
4 QUALITY ASSURANCE
The Contractor shall maintain and apply an effective QA program for the design, manufacture, inspection and testing of all equipment provided. The equipment shall comply with the requirements of the ISO-9001 Standard, “Quality Management System Requirements.” The Contractor shall supply the necessary documentation to demonstrate this compliance. Pre-award and post-award surveys may be required and shall be supported.
4.1 Quality Assurance Requirements
As set forth in BSA Form BNL-QA-101, “Brookhaven National Laboratory Supplier Quality Assurance Requirements,” as amended herein, forms a part of this statement of work. Specifically, this includes the following sections: 1, 2, 3.0, 3.1, 3.1.2, 3.2 to 3.8, 4.0, 4.1, 4.2, 4.10.4, 4.29.
4.2 Material Review Board (MRB) Authority
Unless, and until Material Review Board (MRB) authority has been requested and received, the Contractor shall be restricted to dispositions of rework, scrap, and return-to-vendor; i.e., the Contractor shall not use nonconforming materials via unique or standard repair processes, nor via use -as-is-dispositions.
The Contractor shall not delegate MRB authority to suppliers without the prior knowledge and written approval of BSA.
BSA may delegate MRB Authority to the Contractor, when requested by the Contractor. Such request shall be accompanied by 1) the Contractor’s procedure for the identification, evaluation, disposition, and control of nonconformances; and 2) the resumes of personnel to be assigned as MRB members.
All nonconformances requiring MRB action shall be documented and sent to the BNL technical representative within five (5) working days of the decision.
4.3 QA Flow-Down
The Contractor shall ensure a proper and complete flow-down of all applicable QA requirements to its suppliers and sub-tier suppliers.
NSLSII-RF-SOW-SPC-002: RF Cryogenic System – Helium Storage Tank Statement of Work and Technical Specification 5
NSLS-II 5 13 MAR 2025
5 SCHEDULE / MILESTONES
The following schedule is for planning purposes only. Schedule requirements as set forth in the contract will take precedence.
SCHEDULE IN WEEKS AFTER AWARD OF CONTRACT
Submittal of the Design, Engineering, & Manufacturing documentation (Section 3.2) 6
Pre-Production Meeting & BSA approval of the Contractor documentation (Sect ion 3.3) 7
Procurement of Materia ls (after BSA approval of the Contractor documentat ion) 8
Start fabrication of the HST 9
The HST has been fabricated, inspected, tested, and ready for shipment 25
Receipt of the EID, and acceptance of the HST at BNL 26
6 DELIVERABLES
The Contractor shall supply the following:
Item Deliverable Due Approval
Required
1 Design, Engineering, & Manufacturing Documentation (Section 3.2)
6 weeks after award of contract Yes
2 Pre-Production Meeting (Section 3.3) 1 week after BSA receives the Item #1 documentation from the Contractor
No
3 Progress Reports (Section 3.5)
2 weeks after award & bi-weekly thereafter No
4 Receipt of the EID package (Section 3.6.3) With delivery of the HST Yes
5 Delivery of the HST at BNL As set forth in the contract Yes
7 VALUE ENGINEERING
The Contractor is encouraged to make recommendations for changes that might lead to an improvement in performance, reliability, quality, safety, or reduction in cost. Simplicity in operation, ease of maintenance, and an improvement in the performance and reliability of the specific functions beyond the requirements of this SOW/SPC are objectives which shall be considered in the production of each component type. Where it appears a substantial improvement in simplicity of design, performance, ease of maintenance or reliability will result from the use of materials, parts and processes other than those specified, it is desirable that their use be investigated. When investigations point to advantages that may be realized, the recommendation for change shall be presented to BSA for review and, if approved, authorized in writing. An equitable agreement will be negotiated between BSA and the Contractor to share the savings of any recommended change that is approved and implemented.
6 National Synchrotron Light Source II
Version 1 6 Brookhaven National Laboratory
8 TECHNICAL SPECIFICATIONS
This section of the SOW/SPC document defines the technical specifications for the HST.
• The HST design, inspection/testing, and associated manufacturing drawings shall conform to the 2015 edition of the ASME BPVC, Section VIII, Division 1 (the current edition of this code may be used with BSA concurrence).
• The HST shall be code stamped by a certified ASME pressure vessel manufacturer.
• HST Configuration: Horizontal
• Ultra-Pure Helium (99.9995% purity) will be stored in the HST. Any debris or corrosion on the interior surfaces will degrade the quality of the helium and performance of the system. There shall be no corrosion (zero corrosion allowance) on any of the HST internal and external surfaces.
• HST Capacity: 30,000-gallon
• Maximum Working Pressure: 250 PSI at 140o F
• HST Outside Dimensions: 10’ 11-7/8” Diameter x 46’ 8-7/8” in length
• Full vacuum service is not required during system operation, however when the HST is being prepared for service, a vacuum down to 0.1 milli-bar is required for cleaning to remove contamination. The HST shall meet this requirement.