This is a Manufactured Housing Installation Manual produced by TIE DOWN Inc. for use in South Carolina, specifically related to a Manufactured Home project in Myrtle Beach. The manual serves as a technical installation guide for manufactured home anchoring and foundation systems compliant with HUD Code standards (24 CFR 3280 and 3285). The document provides comprehensive installation instructions for ground anchors, stabilization plates, strapping systems, foundation pads, and support piers, with detailed specifications for wind zones I, II, and III. The manual includes soil classification testing procedures using torque probes to determine appropriate anchor selection, electrical drive machine operation guidelines, and installation methodologies for various anchor types including cross drive rock anchors, deep set anchors, concrete anchors, and asphalt anchors. Product listings reference multiple anchor models with working load capacities of 3,150 pounds minimum and ultimate load capacities of 4,725 pounds, along with alternative anchor options for specialized soil conditions.

The manual contains RADCO (Radiant Controlled Products) Design Listings #1349 and #1345, certifying that TIE DOWN Engineering ground anchors and foundation pads meet federal manufactured home construction and safety standards. Specifications detail ABS and steel foundation pads with load capacities ranging from 1,778 to 9,187 pounds depending on soil bearing capacity and pad configuration, as well as steel support piers rated at 6,000 pounds capacity. The document includes installation tables for propane tank anchorage, adjustable outriggers rated up to 5,000 pounds, and emergency spring hanger kits. All products are manufactured in accordance with ASTM standards and ISO 9001:2015 certification, with galvanized strapping meeting minimum weathering requirements of 0.60 ounces per square foot. The manual emphasizes compliance with state, county, and municipal regulations and includes critical safety warnings regarding underground utility location before anchor installation.

View the file

Other files

File Type Posted
No Award.pdf PDF
Solicitation-Mfg Home.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MANUFACTURED

HOUSING

INSTALLATION

MANUAL

605 Stonehill Drive SW | Atlanta, Georgia 30336 | 404.344.0000 | www.tiedown.com2

TABLE OF CONTENTS

Description Page

ABS Stabilizer Plate10
Anchors - Asphalt17
Anchors - Concrete “J”18
Anchors - Concrete Slab18
Anchors - Cross Drive Rock19
Anchors - Deep Set17
Anchors - Installation6
Anchors - Stabilizers9
Anchors - X-Plate/Stabilizer19
Drive Machine (EDM)7-8
Hardware Kits - Adjustable Outrigger28
Hardware Kits - Perimeter Pier Support29
Hardware Kits - Propane Anchor Kits30
Hardware Kits - Spring Hanger Kits31
Pad Installation - ABS22-23
Pier Installation - Steel23
Quik Set Stabilizer10
Radco Listings - ABS & Steel Pads24-25
Radco Listings - Anchors20-21
Soil Classification Charts4-5
Stabilizer Plate Installation10
Strap - Angle Frame16
Strap - Buckle14
Strap - Certification11
Strap - Crimping Seals11
Strap - Frame Tie14
Strap - Gator Beam Clamp16
Strap - Installation13
Strap - Protectors13
Strap - Sidewall Connector15
Strap - Speed Wrench12
Strap - Strap Tensioning12
Strap - Swivel Connector15
Wind Zone Chart3

Manufactured Housing Products Division 605 Stonehill Drive SW, Atlanta, Georgia 30336 800-241-1806 • 404-344-0000 • www.tiedown.com ISO 9001:2015 Certification Intellectual property of TIE DOWN Inc. ©2018 TIE DOWN, Inc.

Instruction #08235 (D12 Rev. 3/11/20)

KNOW YOUR WIND ZONE

Zone I

Zone III

Zone II

Zone III

Zone II

Zone I

Zone I

Zone II

Zone II

Zone IIIZone III

Zone III

Alaska Hawaii

WIND ZONE III

HawaiiEntire State
AlaskaCoastal regions
FloridaBroward, Charlotte, Collier, Dade, Franklin, Gulf, Hendry, Lee, Martin, Manatee, Monroe, Palm Beach,
Pinellas, & Sarasota
LouisianaParishes of Jefferson, La Fourche, Orleans, Plaquemines, St. Bernard, St Charles, St. Mary,
& Terrebonne
North CarolinaCarteret, Dare, and Hyde
TerritoriesAmerica Samoa, Guam, Northern Mariana Islands, Puerto Rico, Trust Territory of the Pacific
Islands & The US Virgin Islands

WIND ZONE II

AlabamaBaldwin & Mobile
FloridaAll counties except those listed below as within Wind Zone III
GeorgiaBryan, Camden, Chatham, Glynn, Liberty & Macintosh
LouisianaParishes of Acadia, Ascension, Assumption, Calcasieu, Cameron, East Baton Rouge,
East Feliciana, Evangeline, Iberville, Jefferson Davis, Lafayette, Livingston, Pointe Coupee,
St. Helena, St. James, St. John the Baptist, St. Landry, St. Martin, St Tammany, Tangipahoa,
Vermillion, Washington, West Baton Rouge & West Fleliciana
MaineHancock & Washington
MassachusettsBarnstable, Bristol, Dukes, Nantucket & Plymouth
MississippiGeorge, Hancock, Harrison, Jaskson, Pearl River & Stone
North CarolinaBeaufort, Brunswick, Camden, Chowan, Columbus, Craven, Currituck, Jones, New Hanover, Onslow,
Pamlico, Pasquotank, Pender, Perquimans, Tyrrell, & Washington
South CarolinaBeaufort, Berkeley, Charleston, Colleton, Dorcherster, Georgetown, Horry, Jasper, & Williamsburg
TexasAransas, Brazoria, Calhoun, Cameron, Chambers, Galveston, Jefferson, Kenedy,
Kleberg, Matogorda, Nueces, Orange, Refugio, San Patricio & Willacy
VirginaCities of Chesapeake, Norfolk, Portsmouth, Princess Anne & Virginia Beach

WIND ZONE I

All States, Counties, Parishes or Cities not listed above.

US WIND ZONE CHART

Each manufactured home must be designed according to the federal Manufactured Home Construction and Safety Standards at 24 CFR 3280, commonly called the HUD Code.

The HUD Code stipulates, at §3280.305(c)

(1) and §3280.305(c)(2), that the home shall be designed and constructed to conform to one of three wind load zones. The appropri-ate wind zone used in design is dependent on where the home will be initially installed.

Homes designed and constructed to a higher Wind Zone can be installed in a lower Wind Zone (a Wind Zone III home can be installed in a Wind Zone I or II location).

However, a Wind Zone I home cannot be installed in either a Wind Zone II or III area.

605 Stonehill Drive SW | Atlanta, Georgia 30336 | 404.344.0000 | www.tiedown.com4

SOIL CLASSIFICATION CHARTS

Ground anchors are designed for different soil classifications: longer models for loose soils, shorter models for harder soils. Prior to installing any ground anchor model, the soil must be tested (with a Soil Test Probe) in order to match approved ground anchor model with site soil class.

WARNING: Before ground anchor installation, determine that the anchor locations around home will not be close to any underground electrical cables, water lines or sewer piping. Failure to determine the location of electrical cables may result in serious personal injury.

Soil Test Probe The Soil Test Probe is used to determine the soil conditions below the surface near the anchor’s helix. Using the Soil Test Probe will ensure maximum anchor holding strength by indicating the proper anchor model for each soil condition.

Using the chart provided, a probe reading can be converted to the recommended anchor for every soil condition.

Instructions

1.Place probe tip into ground where you intend to place the anchor. Using a 15/16” hex socket with a ratchet or
breaker bar, rotate the probe in a clockwise direction. (An electric drive machine with an adapter head may
also be used)
2.Drive (rotate) the torque probe into the soil until reaching a depth equal to the length of the anchor being installed.
3.To determine the soil classification:
•Place wrench adapter onto torque wrench.
•Insert hex portion of wrench adapter onto the earth probe.
•Support probe shaft with one hand, while rotating probe steadily with the wrench. (Do not exceed 600 in. lbs.)
•Read the torque wrench while rotating probe clockwise.
•Use the soil classification chart to cross reference probe readings. Color codes match those printed on Tie
Downs torque probe.
4.If probe reading does not match the anchor for that depth, rotate probe to next anchor depth and check reading.
Continue until reading on probe matches anchor length for depth of reading.
5.To remove probe, use wrench or electric drive machine in reverse (counter clockwise).

34b C

SOI

* Below 175 in. lbs., a professional engineer should be consulted

Soil Test Value Soil Class (in. lbs.) Description

4b

4a

551 + Very dense and/or cemented sands, coarse gravel, cobbies, preloaded silts, clays and coral.

N/A Sound hard rock.

351 to 550 Medium dense coarse sands sandy gravels very stiff silts and clays.

276 to 350 Loose to medium dense sands, firm to stiff clays and silts, alluvial fill.

175* to 275 Loose sands, firm clays and silts, alluvial fill.

4b4a31 551 lbs +N/A 351 to 550 lbs. 276 to 350 lbs. 175 to 275 lbs.

Blue Yellow Green Red

SOIL CLASSIFICATION

ANCHOR CHART

Soil Class &RecommendedPart ID:
Test Values (in. lbs.)Anchor / StabilizersBlackGalvanized
30 in. Cross Drive Rock Anchor59110N/A
48 in. Cross Drive Rock Anchor59111N/A
30 in. x 5/8 in. rod / 2 - 4 in. helix5909059078
30 in. x 3/4 in. rod / 2 - 4 in. helix5909559079
60 in. x 3/4 in. rod / 2 - 4 in. helix5909759097G
All anchors above should use one of the following
when subjected to lateral loads:
12 in. Stabilizer Plate5929259292G
Quik-Set Stabilization Plate5929159291G
X-Plate Anchor with 2-23/32 in. Rods59118N/A
48 in. x 5/8 in. rod / 1 - 6 in. helix5908059081
48 in. x 3/4 in. rod / 1 - 6 in. helix5908559094
36 in. x 3/4 in. rod / 1 - 6 in. helix & 1 - 4 in. helix5925059250G
All anchors above should use one of the following
when subjected to lateral loads:
12 in. Stabilizer Plate5929259292G
Quik-Set Stabilization Plate5929159291G
Deepset Anchor w/7” Cap - 30” X 3/4” rod / 2 - 4” helix5909159091G
Deepset Anchor w/6” Cap - 30” X 3/4” rod / 2 - 4” helix5966459664G
48 in. x 5/8 in. rod / 1 - 6 in. helix5908059081
48 in. x 3/4 in. rod / 1 - 6 in. helix5908559094
36 in. x 3/4 in. rod / 1 - 6 in. helix & 1 - 4 in. helix5925059250G
3/4 in. rod, 42 in. long, 2 - 4 in. helix, Class 4A5912859128G
3/4 in. rod, 48 in. long, 2 - 4 in. helix, Class 4A5908659086G
All anchors above should use one of the following
when subjected to lateral loads:
12 in. Stabilizer Plate5929259292G
17 -1/2 in. Stabilizer Plate (Florida Only)NA59286
Quik-Set Stabilization Plate5929159291G
ABS Stabilization Plate (Florida Only)59293NA
Deepset Anchor w/7” Cap - 36” X 3/4” rod / 4” & 6” helix5909259092G
Deepset Anchor w/6” Cap - 36” X 3/4” rod / 4” & 6” helix5966559665G
60 in. x 3/4 in. rod / 1 - 7 in. helixNA59099
All anchors above should use one of the following
when subjected to lateral loads:
17 -1/2 in. Stabilizer PlateNA59286
ABS Stabilization Plate59293NA

34b C

SOI

* Below 175 in. lbs., a professional engineer should be consulted

Soil Test Value Soil Class (in. lbs.) Description

4b

4a

551 + Very dense and/or cemented sands, coarse gravel, cobbies, preloaded silts, clays and coral.

N/A Sound hard rock.

351 to 550 Medium dense coarse sands sandy gravels very stiff silts and clays.

276 to 350 Loose to medium dense sands, firm to stiff clays and silts, alluvial fill.

175* to 275 Loose sands, firm clays and silts, alluvial fill.

4b4a31 551 lbs +N/A 351 to 550 lbs. 276 to 350 lbs. 175 to 275 lbs.

Blue Yellow Green Red

34b C

SOI

* Below 175 in. lbs., a professional engineer should be consulted

Soil Test Value Soil Class (in. lbs.) Description

4b

4a

551 + Very dense and/or cemented sands, coarse gravel, cobbies, preloaded silts, clays and coral.

N/A Sound hard rock.

351 to 550 Medium dense coarse sands sandy gravels very stiff silts and clays.

276 to 350 Loose to medium dense sands, firm to stiff clays and silts, alluvial fill.

175* to 275 Loose sands, firm clays and silts, alluvial fill.

4b4a31 551 lbs +N/A 351 to 550 lbs. 276 to 350 lbs. 175 to 275 lbs.

Blue Yellow Green Red

34b C

SOI

* Below 175 in. lbs., a professional engineer should be consulted

Soil Test Value Soil Class (in. lbs.) Description

4b

4a

551 + Very dense and/or cemented sands, coarse gravel, cobbies, preloaded silts, clays and coral.

N/A Sound hard rock.

351 to 550 Medium dense coarse sands sandy gravels very stiff silts and clays.

276 to 350 Loose to medium dense sands, firm to stiff clays and silts, alluvial fill.

175* to 275 Loose sands, firm clays and silts, alluvial fill.

4b4a31 551 lbs +N/A 351 to 550 lbs. 276 to 350 lbs. 175 to 275 lbs.

Blue Yellow Green Red

34b C

SOI

* Below 175 in. lbs., a professional engineer should be consulted

Soil Test Value Soil Class (in. lbs.) Description

4b

4a

551 + Very dense and/or cemented sands, coarse gravel, cobbies, preloaded silts, clays and coral.

N/A Sound hard rock.

351 to 550 Medium dense coarse sands sandy gravels very stiff silts and clays.

276 to 350 Loose to medium dense sands, firm to stiff clays and silts, alluvial fill.

175* to 275 Loose sands, firm clays and silts, alluvial fill.

4b4a31 551 lbs +N/A 351 to 550 lbs. 276 to 350 lbs. 175 to 275 lbs.

Blue Yellow Green Red

34b C

SOI

* Below 175 in. lbs., a professional engineer should be consulted

Soil Test Value Soil Class (in. lbs.) Description

4b

4a

551 + Very dense and/or cemented sands, coarse gravel, cobbies, preloaded silts, clays and coral.

N/A Sound hard rock.

351 to 550 Medium dense coarse sands sandy gravels very stiff silts and clays.

276 to 350 Loose to medium dense sands, firm to stiff clays and silts, alluvial fill.

175* to 275 Loose sands, firm clays and silts, alluvial fill.

4b4a31 551 lbs +N/A 351 to 550 lbs. 276 to 350 lbs. 175 to 275 lbs.

Blue Yellow Green Red

NOTE: Each State, County or Municipality may require a specific anchor from the groups shown for each soil classification. Check local and State regulations first.

SOIL CLASSIFICATION

605 Stonehill Drive SW | Atlanta, Georgia 30336 | 404.344.0000 | www.tiedown.com6

Step 2Step 1 Step 3

Skirting/Side Wall

FRAME ANCHOR INSTALLATION

Manual Anchor Installation

1. Dig holes to a depth of 2/3 of the anchor length. Install anchor with rod or length of pipe for leverage.

2. Replace earth in hole after anchor/plate is installed at full depth. Pack dirt with a tamping rod every 6 inches of fill.

3. Testing may be required in loose soil conditions to check that anchor has proper holding power.

IMPORTANT!

Anchor must be installed to full depth. Anchor head must be at ground level or at the top of the stabilizer plate which is fully installed to ground level.

ANCHORS

1.Position anchor at a slight back angle (10˚) so that when fully installed, the anchor head will be inside any
skirting or side wall.
2.Install anchor to +/- 2/3 depth, then install stabilizer vertically, within 3 in. - 4 in. of anchor shaft, parallel to
wall of home. Fully drive anchor down the anchor head.

3. Attach strap (see proper strap tensioning), and pretension strap to pull anchor rod against the stabilizer plate.

Operating Instructions:

1.Attach adapter head to shaft of the EDM motor, tighten
set screw.
2.It may not be needed but it is highly recommend to
attach the handle extension. Using the handle
extension increases stability while reducing muscle
strength during installation.
3.Plug in the drive machine.
•Electrical cords must be a minimum 12-2 cord
up to 50’, 10-2 cord over 50’.
•Recommended minimum 1500w generator.
4.The GFI will shut off power when a ground fault is
detected. The GFI will also shut off power when it
detects low voltage or improper amps required to drive
the motor. Many times the problem will be the use of an
extension cord that is too long or is too light in gage.
•Never operate without the factory installed GFI
(Ground Fault Interrupter) power cord.

CALL BEFORE YOU DIG... DIAL 811

Before installation of any ground anchor, determine that the ground anchors to be installed will not be near any under ground electrical cables, phone lines, water lines, sewer pipes, or gas lines. Failure to do so may result in serious injury or death.

1. Attach adapter head to shaft of the EDM motor, tighten set screw.

2. It may not be needed but it is highly recommend to attach the handle extension. Using the handle extension increases stability while reducing muscle strength during installation.

3. Plug in the drive machine.

• Electrical cords must be a minimum 12-2 cord up to 50’, 10-2 cord over 50’.

• Recommended minimum 1500w generator.

4. The GFI will shut off power when a ground fault is detected.

The GFI will also shut off power when it detects low voltage or improper amps required to drive the motor.

Many times the problem will be the use of an extension cord that is too long or is too light in gage.

• Never operate without the factory installed GFI (Ground Fault Interrupter) power cord.

Safety Pin Hole

Motor Shaft

Press “Reset” if the motor fails to run. Ground Fault has interrupted the power supply

Press “Test” to check the power interrupt is working “No Power”

Set Screw

Safety Pin Hole

Anchor Adapter Head

Operation Instructions

1. Attach adapter head to shaft of the EDM motor, tighten set screw.

2. It may not be needed but it is highly recommend to attach the handle extension. Using the handle extension increases stability while reducing muscle strength during installation.

3. Plug in the drive machine.

• Electrical cords must be a minimum 12-2 cord up to 50’, 10-2 cord over 50’.

• Recommended minimum 1500w generator.

4. The GFI will shut off power when a ground fault is detected.

The GFI will also shut off power when it detects low voltage or improper amps required to drive the motor.

Many times the problem will be the use of an extension cord that is too long or is too light in gage.

• Never operate without the factory installed GFI (Ground Fault Interrupter) power cord.

Safety Pin Hole

Motor Shaft

Press “Reset” if the motor fails to run. Ground Fault has interrupted the power supply

Press “Test” to check the power interrupt is working “No Power”

Set Screw

Safety Pin Hole

Anchor Adapter Head

Operation Instructions

Extension Handle

GFI Switch

Adapter Head

ELECTRIC DRIVE MACHINE INSTALLATION

ELECTRIC DRIVE MACHINE

605 Stonehill Drive SW | Atlanta, Georgia 30336 | 404.344.0000 | www.tiedown.com8

Electric Drive Machine Cautions and Warnings:

•Before installation of any ground anchor, determine that the ground anchors to be installed will not be near any
underground electrical cables, phone lines, water lines, sewer pipes, or gas lines. Failure to do so may result in
serious injury or death

• The EDM is designed for operation by two people.

• Do not allow the EDM to be wedged against the home or other solid objects, when operating the EDM.

•Electrical cord must be a minimum of 12-2 wire size w/ground up to 50 ft.. Longer cords should be 10-2 wire size
with ground.

• Never operate the EDM in wet or rainy conditions.

• Frayed or patched electrical cords should never be used with the EDM.

• Care should be taken to keep electrical cords away from anchors.

•Never operate drive machine without the GFI power cord. Damage to motor and injury to operator can result from
by passing the GFI.

5. Place anchor tip in location where anchor is to be buried.

The Electric Drive Machine (EDM) is designed for operation by two people. Hold anchor in place at the desired installation angle.

6. Place anchor head into adapter, line up anchor shaft with EDM shaft. For easier installation place a 1/2” pull pin or a slotted bolt thru the adapter head (Safety Pin Hole) and anchor head. Make sure the pull pin/bolt comes out the other side. This will prevent the EDM from separating from the anchor.

7. Flip forward/reverse switch to forward.

8. Hold the power switch on until anchor reaches proper depth. The power switch is spring loaded.

If you encounter any problems release the switch and the machine will shut off automatically.

Forward

Reverse Power Switch

• CALL BEFORE YOU DIG... DIAL 811

Before installation of any ground anchor, determine that the ground anchors to be installed will not be near any under ground electrical cables, phone lines, water lines, sewer pipes, or gas lines. Failure to do so may result in serious injury or death.

Operation Instructions

605 Stonehill Drive SW, Atlanta, GA 30336 404-344-0000 • tiedown.com

5.Place anchor tip in location where anchor is to be
buried. The Electric Drive Machine (EDM) is designed
for operation by two people. Hold anchor in place at the
desired installation angle.
6.Place anchor head into adapter, line up anchor shaft
with EDM shaft. For easier installation place a 1/2” pull
pin or a slotted bolt though the adapter head (Safety
Pin Hole) and anchor head. Make sure the pull pin/
bolt comes out the other side. This will prevent the EDM
from separating from the anchor.

7. Flip forward/reverse switch to forward.

8.Hold the power switch on until anchor reaches
proper depth. The power switch is spring loaded. If
you encounter any problems release the switch and the
machine will shut off automatically.

ELECTRIC DRIVE MACHINE

ANCHOR STABILIZERS

In order to prevent lateral movement of manufactured homes subjected to high wind loads and to comply with HUD’s Wind Zone I, II, & III requirements, all lateral frame ties must be attached to a properly stabilized ground anchor.

(Two approved methods illustrated below.)

Class 4B Stabilizer Plate 17-1/2 in. x 13-1/2 in.

Galvanized Part ID: 59286

12” wide Stabilizer Plate

Painted BlackPart ID: 59292
GalvanizedPart ID: 59292G

Ground Level

"In Line" Installed:

Minimum anchor length of 36"

STABILIZER PLATE INSTALLATION

1. Refer to any and all local, state and federal regulations.

2.Use the Soil Test Probe at the anchor location in order to match soil class with the anchor/stabilizer
(see page 16).

3. Partially install anchor to allow 14 in. to 16 in. remaining above ground level.

4.Utilizing oversized hammer, vertically install stabilizer plate, nesting anchor rod in between formed channels on
outside of stabilizer plate (between anchor and frame).
5.Fully install anchor so that head is at the surface of the soil (1” tolerance, if necessary) and pretension anchor
until touching stabilizer plate.

STABILIZERS

605 Stonehill Drive SW | Atlanta, Georgia 30336 | 404.344.0000 | www.tiedown.com10

ABS STABILIZER PLATE

Part ID: 59293

1.Determine correct anchor to be used with the home
installation and use the manufacturer instruction for
installation, following all safety precautions.
2.Using an electric drive machine, install anchor to a depth of
approximately 28 inches at a slight back angle.
3.Dig out an 8” wide area so that the ABS stabilizer will be
placed on undisturbed soil at a 10 to 15 degree angle
toward the home. The bottom center of the plate should be
touching the anchor rod.
4.Complete the installation of the ground anchor until the
bottom of the anchor head is flush with the ground.
5.Attach proper strap and tension strap until anchor head is
flush against the ABS plate and strap is tight. At this point,
soil should be tamped into the vacant area behind the
anchor rod, tamping approximately 6” and repeating until
the vacant area is flush with the surface of the
surrounding ground.

Place ABS Plate Here

Tamp Soil In 6" increments

5" to 6"

Home Direction

10˚-15˚

QUIK-SET STABILIZER INSTALLATION

Black PaintPart ID: 59291
GalvanizedPart ID: 59291G
1.Install ground anchor inside skirting line at a slight back
angle of 10˚ - 15˚.
2.While anchor head is still 5 in. to 6 in. above ground level:
install Quik Set stabilization plate around anchor shaft,
referring to the direction imprinted on the top of the plate.
3.Install ground anchor until Quik-Set plate is fully set.
Hammering may be required at the corners to insure plate
being fully driven.
4.Install strap(s) to anchor head and pretension according to
approved methods. Maximum anchor load in conjunction
with the “Quik-Set” device is4725 lbs. (ultimate).

STABILIZERS

STRAP

CERTIFIED GALVANIZED STRAPPING

DescriptionLengthPart ID:
G60 Strap35 ft.59150
G60 Strap37 ft.59155
G60 Strap60 ft.59165
G60 Strap600 ft.59170
G120 Strap37 ft.59218
G120 Strap600 ft.59219

The steel strapping by Tie Down for the manufactured housing industry has been tested to, and conforms to, the HUD Code as referenced in Part 3280 of the Manufactured Home Construction and Safety Standards and Part 3285 of the installation standards; Final Rule.

3280.306(f), 3285.402(b2) Anchoring Equipment – Load Resistance. Anchoring equipment shall be capable of resisting an allowable working load equal to or exceeding 3,150 pounds and shall be capable of withstanding a 50 percent overload (4,725 pounds total) without failure of either the anchoring equipment or the attachment point on the manufactured home.

3280.306(g), 3285.402(b2) Anchoring Equipment – Weatherize Anchoring equipment exposed to weathering shall have a resistance to weather deterioration at least equivalent to that provided by a coating of zinc on steel of not less than 0.30 ounces per square foot of surface coated, and in accordance with the following:

(1) Slit or cut edges of zinc-coated steel strapping do not need to be zinc coated.
(2) Type 1, Finish B, Grade 1 steel strapping, 1-1/4 inches wide and 0.035 inches in thickness, certified by a
registered professional engineer or architect as conforming with ASTM Standard Specification D3953-97,
Standard Specification for Strapping, Flat Steel, and Seals.

The above specification of a minimum coating of 0.30 ounces per square foot equates to a designation of “G30.”

Tie Down strapping exceeds this minimum requirement with a coating of 0.60 (G60) or 1.20 (G120) ounces as per above. Similarly, Tie Down strapping exceeds, in testing, the minimum load requirements of 3,150 pounds design (working) load and 4,725 pounds (ultimate) overload.

DOUBLE THICK G-60

GALVANIZED PROTECTION

TIE DOWN ENGINEERING

CERTIFIED TO

ANSI A225.1 ASTM D3953-97

TIE DOWN ENGINEERING

CERTIFIED TO

ANSI A225.1 ASTM D3953-97

File name "strapping2.eps"

DOUBLE THICK G-60

GALVANIZED PROTECTION

TIE DOWN ENGINEERING

CERTIFIED TO

ANSI A225.1 ASTM D3953-97

TIE DOWN ENGINEERING

CERTIFIED TO

ANSI A225.1 ASTM D3953-97

File name "strapping2.eps"

CRIMPING SEALS

Part ID: 59175

To lengthen strap in the field, a double crimp seal splice is required. Overlap strap approximately 12 inches and use two crimp seals evenly spaced, with 2 crimps per seal.

One crimp seal is used when strap is attached to a sidewall bracket or a strap connector. If the brack-et does not have a radius edge, a radius clip (short “U” shaped piece of strap) must be placed between the strap and contact point to protect the strap from sharp edges. Verify state requirements for number of crimp seals required.

DOUBLE THICK G-60

GALVANIZED PROTECTION

TIE DOWN ENGINEERING

CERTIFIED TO

ANSI A225.1 ASTM D3953-97

TIE DOWN ENGINEERING

CERTIFIED TO

ANSI A225.1 ASTM D3953-97

File name "strapping2.eps"

2 Seals - 2 Crimps Per Seal

1 Seal - 2 Crimps

605 Stonehill Drive SW | Atlanta, Georgia 30336 | 404.344.0000 | www.tiedown.com12

PROPER STRAP TENSIONING

Step 1 Insert slotted bolt into anchor head, attach loosely. Pull strap past bolt head and cut strap so that 12-15 inches of strap are available to wrap onto the slotted bolt.

Step 2 Insert the strap end into the slot in bolt until flush with opposite side of bolt.

Step 3 Using 15/16” wrench or socket, turn the bolt, winding the strap so that a minimum of four to five complete turns are made, and the strap is adequately tensioned.

Step 4 Hold the bolt under tension while tightening the nut, drawing the head of the bolt into the recess. After the bolt is within the recess, continue to tighten the nut until securely fastened.

12-15 inches

Cut

12-15 inches

Cut

12-15 inches

Cut 12-15 inches

Cut

STRAP TENSIONING - SPEED WRENCH

Part ID: 48900

Tie Downs SPEED WRENCH simplifies anchor installation with a design that allows for one handed operation for installing slotted bolts and tensioning strap. The SPEED WRENCH has a 15/16 in. impact socket on one side and a 15/16 in. “nut” on the other. Combine this with your own ratchet and 15/16 in.

socket and you have the fastest way to tighten slotted bolts!

Step 1 Place Speed Wrench over the bolt head. Insert the strap end into the slot in bolt until flush with opposite side of bolt.

Step 2 Hold Speed Wrench in place, tighten bolt with socket wrench on outside of Speed Wrench (bolt head side).

Step 3 Move socket to the opposite (nut) side. Hold Speed Wrench in place. Use socket wrench to tighten nut.

STRAP

Step 1

Step 3

Step 2

Step 4

Ground Level

Shown with Hook

Alternative set to avoid crushing “Bellyboards” , with manfuacturers approval

"I" Beam Frame

If this angle exceeds 60˚, See Note Below

Frame with Strap

FRAME TIE TO ANCHOR

If this angle exceeds 60˚, an additional frame tie must be attached to the opposite beam as indicated by the dotted line.

A Stabilizer Plate must be installed on all frame Ties. (or alternate method of stabilizing ground anchor.)

Select proper anchor for soil conditions using the Soil Test Probe, or other approved method of determining soil classification.

STRAP PROTECTORS

For protecting Vertical and Diagonal Strapping at sharp corners when wrapping the top and bottom of the beam.

Step 1 Attach hook between strap and I-beam and fold perforated lip around the beam

Step 2 Fold the middle table down bending around the I-beam leaving 2 legs to guide the strap into position.

Step 3 Feed the strap over the I-beam though the two legs on the strap protector.

605 Stonehill Drive SW | Atlanta, Georgia 30336 | 404.344.0000 | www.tiedown.com14

FRAME TIE WITH BUCKLE

Step 1 Install strap by pushing the end between the inside of the frame “I” beam and the floor.

Step 2 Position the buckle at upper end of the “I” beam frame. Wrap the end of the strap around the “I” beam. Thread the end of the strap through the slot in the buckle as shown. Push the end of strap in-between “I” beam and floor.

Step 3 Pull the strap, making certain the buckle stays in position. Thread loose end of strap though slotted tensioning bolt attached to tension head of anchor. Tighten slotted tensioning bolt a minimum of 4 to 5 full turns until all slack in strap is removed.

STRAP BUCKLE - MBU

Step 1 Thread length of frame tie strap through strap buckle as shown.

Step 2 Next, thread long end of strap between frame and floor of home.

Bring strap through buckle as shown in diagram and fasten to anchor head.

Step 3 Diagram shows strap in position around frame and through buckle. It is important to remove all slack from system.

FRAME TIE WITH HOOK

Step 1 Attach frame hook to top inboard location of I-beam.

Step 2 Keeping in line with the hook, wrap galvanized strap completely around I-beam. Strap protectors may be installed on bottom of the I-beam

Step 3 Thread loose end of strap through slotted tensioning bolt attached to tension head of anchor. (Anchor must be properly installed into the ground before proceeding with step #4.)

Step 4 Tighten slotted tensioning bolt a minimum of 4 to 5 full turns until all slack in strap is removed.

SWIVEL STRAP CONNECTORS

Beam Method:

Step 1 In order to assure adequate compliance refer to all local, State, and Federal Regulations, as well as manufacturer’s recommended tie down method.

Step 2 Frame ties attach to the beam with a swivel frame connector placed over the top of the beam. The hook end of the connector should be snug against the beam. Longitudinal ties would attach to Gator clamps bolted to bottom of the beam.

Step 3 Attach the swivel connector to the underside of the flange and frame hook or bracket with a 1/2” grade 5 nut and bolt. This allows swivel to pivot and lock onto I-beam.

Step 4 Pull strap past anchor head 12 to 15” and cut strap. Thread the end of the strap through the slotted tensioning bolt attached to the tensioning head for the anchor. Tighten slotted tensioning bolt 4 - 5 full turns until all slack is removed and strap is tight.

Universal Strap Connector

I Beam

I Beam

Gator Clamp

Beam Clamp

Swivel Connector

Swivel Connector

Home

Home HomeHome

Home Home

STRAP

Sidewall w/Nut & Bolt Attach strap connector to sidewall connector with nut & bolt, then attach to ground anchor.

Sidewall & Longitudinal Slotted Insert strap connector at a 45 degree angle.

Return to 90 degree angle, pull down and attach to ground anchor. (Slotted connections must be straight pull. Bolted connections can have 15 degree max. angle.)

605 Stonehill Drive SW | Atlanta, Georgia 30336 | 404.344.0000 | www.tiedown.com16

ANGLE FRAME BRACKET

Part ID: 59009

Step 1 Determine anchor/stabilizer plate location and bracket location on I-beam to insure a 60˚ or lower strap angle .

Step 2 Drill a 1/2” hole, centered in the I-beam as shown. Hole must be a minimum of 4” from any edge of the I-beam.

Step 3 Connect the two Frame Brackets (R & L) with a 1/2” Grade 5 bolt and nut for Wind Zone II & III and one frame bracket right or left for Wind Zone I.

Step 4 Attach swivel connector and strap to Angle Frame Brackets with 1/2” Grade 5 bolts and nuts. Tighten all bolts.

GATOR BEAM CLAMP

4 Bolt Gator Clamp (Wind Zone 1, 2 & 3)Part ID: 58999
8 Bolt Gator Clamp (Wind Zone 3 - and Florida)Part ID: 59011

Step 1 Determine anchor/stabilizer plate location and bracket location on I-beam to insure a 45˚ or lower strap angle.

Step 2 Attach beam clamp with 1/2 in. Grade 5 bolts and nuts as shown.

Step 3 Connect swivel connector and strap to bolt nearest to anchor with a 1/2 in. Grade 5 bolt and nut.

1 Strap for Wind Zone I 2 Straps for Wind Zones II & III

60˚ Longitudinal Strap

I-beam

Pier

Factory Longitudinal Bracket or Gator Clamp

Anchor with Stabilizer Plate

NOTE:

Gator Beam Clamps must be attached with a Swivel Strap Connector #59002.

NOTE:

Gator Beam Clamps must be attached with a Swivel Strap Connector #59002.

ASPHALT ANCHOR INSTALLATION

Part ID: 59367

For horizontal anchorage at a maximum of 50 degrees, not for vertical anchorage.

1.Using a masonry or similar abrasive blade in a circular saw,
cut a slot 8” long x 1 ½” deep in the asphalt where the anchor
is to be installed with the plates of the anchor parallel
to the structure.
2.With a 5/8”masonry bit installed in a hammer drill, pre-drill a
hole approx. 12” deep through the asphalt in the center
of the slot.
3.Drive the anchor into the asphalt using a minimum 10 lb.
sledge hammer or heavy hammer drill until the upper edge of
the top anchor plate is 1” under the asphalt.

ANCHORS

Wrap strap onto tension bolt (minimum 4-5 turns)

NOTE:

45˚ maximum (if angle exceeds 45˚ attach additional strap tie to opposite frame)

1.Confirm soil classification using standard torque probe at proper depth below ground surface, make certain
readings meet or exceed torque readings for Class 2 and 3 soils at the depths of 30 in. & 36 in..
2.Clear loose vegetation where anchor will be installed. Install anchor vertically to its’ full depth. Stabilizer plate at
the top of anchor must be fully embedded into soil.
3.Pull strap past anchor head and cut strap so that there is 12 in. to 15 in. of strap to wrap onto anchor bolt insuring
4 to 5 wraps minimum.
4.Insert strap into anchor bolt flush with opposite side of bolt. Tighten bolt/strap until tight. Secure anchor
bolt with nut.

DEEP SET ANCHOR/STABILIZER INSTRUCTIONS

30 in. w/7 in. DiscBlack Paint, Class 2Part ID: 59091
30 in. w/6 in. DiscBlack Paint, Class 2Part ID: 59664
36 in. w/7 in. DiscBlack Paint, Class 3Part ID: 59092
36 in. w/6 in. DiscBlack Paint, Class 3Part ID: 59665

Class 3 Class 4A

605 Stonehill Drive SW | Atlanta, Georgia 30336 | 404.344.0000 | www.tiedown.com18 Part 59125

CONCRETE SLAB ANCHOR

This anchor is designed to be bolted to an expansion sleeve in an existing concrete slab.

1.Drill a 5/8 in x 3 in. hole in the slab where the anchor head is to be located.
2.Place steel expansion sleeve over bolt and place into the drilled hole.
3.Place the washer onto the expansion bolt.
4.Thread nut onto expansion bolt and tighten until maximum expansion of steel
expansion sleeve has been achieved.
5.Remove nut and washer and place anchor head over exposed bolt.
6.Place washer and nut onto bolt to attach anchor head, tighten nut.
7.Concrete must be a 2500 PSI minimum slab with 4” minimum thickness.
8.Concrete slab must allow 4725 lbs of vertical tension on anchor without
lifting. This assumes that the concrete weighs 150 lbs per cu. ft.
9.Minimum distance from the anchor shaft to one edge of the slab is 4 in.
from one edge and 6” from any other edge.

Notes:

•Maximum load per anchor is 4725 lbs.
•Minimum slab area per anchor for 4725 lbs.:
4” Thick Slab: 95 S. F.
6” Thick Slab: 65 S. F.
8” Thick Slab: 48 S. F.
•When installed in slabs with a thickness of 4” or less,
a layer of 6/6 or 10/10 mesh in recommended.

Note Applies to all anchors on this page:

•Maximum load per anchor is 4725 lbs.
•Minimum slab area per anchor for 4725 lbs.:
4” Thick Slab: 95 S. F.6” Thick Slab: 65 S. F.8” Thick Slab: 48 S. F.
•When installed in slabs with a thickness of 4” or less, a layer of 6/6 or 10/10 mesh in recommended.

Part 59120

CONCRETE “J” ANCHOR

DescriptionBlack PaintGalvanized
12 in. Anchor5912059121
8 in. Anchor5912359123G
12 in. w/Swivel Head5910959109G
8 in. w/Swivel Head5914759147G

The MIJ2 is designed to be installed into a concrete slab at the time the concrete is being poured.

•Concrete must be a 2500 PSI minimumslab with
4” minimum thickness.
•Concrete slab must allow 4725 lbs of vertical tension on anchor

without lifting. This assumes that the concrete weighs 150 lbs per cu. ft.

•Minimum distance from the anchorshaft to one edge of the slab
is 4” from one edge.
•Concrete slab must have a minimumthickness equal to the anchors

length plus 2” at installed locations.

ANCHORS

Black PaintedPart ID: 59125
GalvanizedPart ID: 59124

CROSS DRIVE ROCK ANCHOR - MRA

30 in. Part ID: 59100 48 in. Part ID: 59111

Engineered for installation into solid rock within 1 in. from bottom of the anchor base. Exact alignment is achieved with the swivel tensioning head.

1. Drill 5/8” diameter hole 5-1/2” deep in center of anchor location.

Insert pilot stud into hole.

2. Drill two 3/4” diameter holes, (the length of the rods) into the rock at 45° angles, using the anchor head as a locating guide.

3. Place rod through top and corresponding bottom web flange and

into 45° hole. Drive rod into rock. Rod must be driven into rock at
least 80% of it’s length to achieve minimum allowable pullout resistance.
Repeat using 2nd rod.
•Maximum pullout resistance is developed when ground surface is solid rock.
Maximum distance from lowest edge of anchor flange to rock surface is 1 in.

ANCHORS

23/32" x 30" steel rod #59118

(2 included)

Part #59118-1 (1 required)

X-PLATE ANCHOR WITH STABILIZATION PLATE

PaintedPart ID: 59118
GalvanizedPart ID: 59118G

Engineered for installation into difficult ground conditions that, when tested with a soil test probe, exceed 500 in. lbs. (see notes below).

Using a soil test probe, determine the soil classification. Place the X-Plate parallel to the building being secured with the flat plate to the inside. Pound the plate into the ground so that the upper lip is ground level. Using a heavy hammer or electric hammer gun, pound rods into the ground through the box tubing guides welded onto the back side of the stabilizer plate. Rods should be installed until maximum 2 in. above the box tubing. Install strap as required.

Notes:

1.For Wind Zone 1 use only, max working load of the X-Plate is
2,200 lb. (3,300# ultimate).
2.It takes 1-1/2 X-Plate anchors to replace 1 standard class 2
ground anchor with a 3150 lb. working load.
3.Difficult Soils Only - Defined as “Extremely hard soil preventing
the installation of an auger anchor to its full depth using a
1/2 HP Drive Machine”. Torque probe readings at 12 in. to
18 in. of the surface must be 500 “/# min.
4.Cross drive anchor is NOT rated or intended to be used for
direct pull in vertical direction. Angle of resultant load must be
at 40-50 degrees from vertical. This anchor may not be
appropriate for shear wall or column anchorage.

605 Stonehill Drive SW | Atlanta, Georgia 30336 | 404.344.0000 | www.tiedown.com20 Page 1 οf 3

PRODUCT: CONCRETE, ROCK, AND SOIL GROUND

ANCHORS

MANUFACTURER: Tie Down Engineering 255 Villanova Dr. SW Atlanta, GA 30336

PLANT LOCATION: 255 Villanova Dr. SW Atlanta, GA 30336

APPLICATION: HUD Code Manufactured Homes & Modular Homes

1. INTRODUCTION

At the request of Tie Down Engineering, RADCO investigated the possibility of listing ground anchors produced by Tie Down Engineering, for approval of ground anchors in accordance with RADCO’s Listing Requirements for Ground Anchors.

RADCO’s Listing Requirements for Ground Anchors defines the classification and performance requirements of each respective ground anchor model. The requirements are in general accordance with those developed by the MHI Ground Anchor Task Force and adopted by HUD’s MHCC on March 9, 2011 after accepting minor revisions offered by HUD staff.

2. DESCRIPTION

There are three categories of ground anchors that are specified in this listing. The first group is soil ground anchors, which pertain to all anchors designated for soil classes 2, 3, 4, and 5. The second group is concrete (non-soil) ground anchors, which are designed for installation into class 1 conditions. The third group is a set of soil ground anchors which serve as an alternate to the HUD minimum requirements and are listed with a working load which is less than the requirements prescribed by the MHI Ground Anchor Task Force and adopted by HUD’s MHCC on March 9, 2011.

All Tie Down Engineering Ground Anchors are manufactured using steel in conformance with ASTM A-36. The models under this listing vary with respect to shaft diameter, number and location of helixes, length of shaft and stabilizer device. Table 1 shows a complete description of each ground anchor model, as well as a corresponding stabilizer device.

All ground anchors have a minimum working load of 3,150 lbs and a minimum ultimate load of 4,725 lbs, with the exception of the anchors listed in Table 3.

3. INSTALLATION

The Installation of the ground anchors is to be in accordance with the Manufacturer’s Installation Instructions, as well as:

a) The proper soil class. (Tables 1 & 3, and notes)

b) Minimum angle of pull to the horizontal. (Tables 1 - 3)

4. EVIDENCE SUBMITTED

4.1 Testing has been conducted to verify the compliance of

Tie Down Engineering ground anchors to the RADCO Listing Requirements for Ground Anchors.

4.2 The Quality and process control system used in the

manufacture has been submitted to RADCO. An adequate method of traceability is maintained by the manufacturer. A follow-up Quality assurance audit program is maintained by

RADCO.

5. RECOMMENDATIONS

RADCO recommends that Tie Down Engineering ground anchors be accepted for use with HUD code manufactured homes and modular homes provided that:

5.1 Each ground anchor will be marked with a label, a facsimile of which is shown in figure 1. The label for each facility denotes the RADCO name, and Listing #1349.

5.2 All products are produced only at the facility referenced in this listing.

5.3 The quality control procedures are maintained by the

manufacturing facility as submitted.

5.4 The audit system of RADCO is maintained.

5.5 All products are installed per the manufacturers installation instructions and section 3 of this listing.

6. APPROVAL

This listing is subject to approval on an annual basis by RADCO. Updating and further information will be included and/or resubmitted as necessary.

LISTING & TESTING DIVISION

LISTING

#1349

Issued: Dec 2013

Renewed: Sept. 2019

Subject to Review :

Sept. 2020

RADCO, A Twining Company 3220 E. 59th Street Long Beach, CA 90805 Tel: (562) 272-7231 Fax: (562) 529-7513 d1731

Page 2 οf 3

Table 1: Properties of HUD Approved Ground Anchors

Model

Shaft Diameter

Shaft Length Helix

Working Load (lbs)

Min. Ultimate Load Capacity

Min. Stabilizer Device (See

Min. Soil Class (See

Min. Angle of Pull to

M1C2 0 625 30 2 Barbs 3655 5483 None 2 vertical only MRA 0 718 30 Cross Drive 3611 5417 None 1 vertical only

59664 .75 30 2-4” 3200 4800 None 4a 45 59665 .75 36 1 @6”, 1 @ 4” 3200 4800 None 4a 45 59091 0 719 29 5 2 @ 4" 3150 4725 7" Dia Cap 3 45 59092 0 719 34 1 @ 6" 1 @ 4" 3150 4725 7" Dia Cap 4 45 59097 0 75 60 2 @ 4" 3267 4900 None 2 45 59128 0.75 42 2 @ 4" 3200 4800 No 59292 4a 45 59086 0 75 47 2 @ 4" 3200 4800 No 59292 3 45

M12H64 0 719 34 1 @ 6" 1 @ 4" 3467 5200 No 59292 4 45 M12H 3/4 0 742 48 1 @ 6" 3645 5467 No 59292 4 45

MI2H 0 625 48 1 @ 6" 4045 6067 MLATSTA 4 45

MI2H6 0 625 36 1 @ 6" 3700 5550 MLATSTA 3 45

MI22 0 75 30 2 @ 4" 3567 5350 MLATSTA 2 45

M607 0 75 60 1 @ 7" 3922 5883 No 59285 4b 45 59085 0 75 48 1 @ 6" 3467 5200 No 59286 4b 45

Table 2: Properties of HUD Approved Concrete Anchors Model / Part No. Working Load (lbs) Min. Ultimate Load

C it (lb ) Min. Angle of Pull

(h i )59109 3333 5000 45 59120 3333 5000 45

ICS1 3200 4800 45

ICS2 3167 4750 45

MIJ2 3333 5000 45

MIT2 4000 6000 45

Table 3: Properties of Alternate (Non-HUD Approved) Ground Anchors

Model

Shaft Diameter

(i )

Shaft Length (in) Helix

Working Load (lbs)

Min. Ultimate Load Capacity

(lb )

Min. Stabilizer Device (See

N t 2)

Min. Soil Class (See

N t 1)

Min. Angle of Pull to

H i t l59113 0.72 30 none 2200 3300 No. 59118-1 3 45 59080 0.625 48 1 @ 6" 3722 5583 No. 59292 4 45 59050 0.5 15 1 @ 4" 533 800 None 2 Vertical 59055 0.5 30 1 @ 4" 1600 2400 None 2 Vertical 59060 0.625 40 1 @ 6" 3000 4500 None 3 Vertical 59065 0.625 48 1 @ 6" 2000 3000 None 4 Vertical 59040 0.75 60 1 @ 8" 2267 3400 None 4 Vertical

Note 1: See 24 CFR Part 3285 Model Manufactured Home Installation Standards, section 202: Soil Classification and Bearing Capacity & Table 3285.202 for an explanation of soil classification numbers. Please note that anchors approved for use in soil class 4 may be used in soil classes 3 or 2, and anchors approved for use in soil class 3 may be used in soil class 2.

605 Stonehill Drive SW | Atlanta, Georgia 30336 | 404.344.0000 | www.tiedown.com22

INSTALLATION INSTRUCTIONS FOR ABS PADS

1.Pier spacing must be in accordance with the Manufacturers
Installation Manual and/or State or local requirements.
2.Clear all vegetation and debris from area where pads are to
be placed.
3.The ground under the pads must be leveled and evenly
compacted or undisturbed soil.
4.Determine pad size by testing for the soil bearing capacity,
if soil testing not available, use the 1000 PSF soil column of
the instructions.
5.Place ABS pad with grid side up, smooth side down. Center
blocks or pier on pad and complete Installation.

IMPORTANT

If pad deflects more than 3/8” when installed correctly with home’s dead load applied, then the pier spacing is incorrect for soil conditions

Single Stack Course

Double Stack Course

Multi Pad Layout

Concrete Blocks

Concrete Blocks

Ground Level

ABS

Pad

Max. 3/8 in.

Deflection

Ground Level

ABS

Pad

WRONG RIGHT

Single Stack Course

Double Stack Course

Multi Pad Layout

Concrete Blocks

Concrete Blocks

Ground Level

ABS

Pad

Max. 3/8 in.

Deflection

Ground Level

ABS

Pad

WRONG RIGHT

General Notes:

1.Any configuration from the chart may be used to replace a concrete or wood base pad per 3282.312(A)(3).
2.The maximum load at any intermediate soil value may be interpolated between the next lower and next higher
soil values given in the pad bearing capacity chart.
3.Pad sizes are shown in nominal dimensions and may vary slightly.
4.Maximum deflection 3/8”, measured from the highest point to the lowest point of the top side of pad.
5.In areas susceptible to frost heave, the pad must be at the frost line or otherwise protected from the effects of
frost. Refer to NCSBCS/ANSI A225.1 “Manufactured Home Installations” Homes set to Standard 24 CFR 3285
should not be susceptible to frost heave.

PAD INSTALLATION

Single Stack Course

Double Stack Course

Multi Pad Layout

Concrete Blocks

Concrete Blocks

Ground Level

ABS

Pad

Max. 3/8 in.

Deflection

Ground Level

ABS

Pad

WRONG RIGHT

Multi Pad Soil Capacities

Multi PadTotal1000 lbs.1500 lbs.Part
DimensionsSquare Feet/InchesSoilSoilID:
32 in. x 22.5 in. (a)5 sq. ft. (720 sq. in.)5,000 lbs.10,000 lbs.(c)59301 (x3)
34.4 in. x 25.2 in.(b)6 sq. in. (864 Sq. In.)6,000 lbs.12,000 lbs.(c)59302 (x3)

NOTES:

(a)The 32 X 22.5 Pyramid configuration uses (2) 16 X 22.5 pads placed side by side with (1) 16 X 22.5 pad on top in
the opposite direction.
(b)The 34.4 X 25.4 Pyramid configuration uses (2) 17.2 X 25.2 pads placed side by side with (1) 17.2 X 25.2 pad on
top in the opposite direction.
(c)Concrete Block rated @ 8,000 lbs. Double block any higher loads.

PAD INSTALLATION

Pad Bearing Capacity

* Concrete Block rated @ 8000 lbs. Double block any higher loads.

1. The 32 X 22.5 Pyramid configuration uses 2 - 16 X 22.5 pads placed side by side with 1 – 16 X 22.5 pad on top in the opposite direction.

2. The 34.4 X 25.4 Pyramid configuration uses 2 – 17.2 X 25.2 placed side by side with 1 – 17.2 X 25.2 Pad on top in the opposite direction.

Multi Pad Layout 32” X 22.5” (See 1 below) 5,000 Lbs. 7,500 lbs. 10,000 Lbs.* 5 Sq. Ft. - 720 Sq. In.

34.4 X 25.2 (See 2 below) 6,000 Lbs. 9,000 lbs. 12,000 Lbs.*

6 Sq. Ft. - 864 Sq. In.

ABS Pad Part 1000 lbs. 1500 lbs. 2000 lbs. 3000 lbs.

Square Feet/Inches Number Soil Soil Soil Soil 16 in. x 16 in. 59660 1,778 lbs. 2,667 lbs. 3,556 lbs. 5,333 lbs.

1.77 sq. ft. (256 sq. in.)

16 in. x 18 in. 59300 2,000 lbs. 3,000 lbs. 4,000 lbs. 6,000 lbs.

2 sq. ft. (288 sq. in.)

16 in. x 22.5 in. 59301 2,500 lbs. 3,750 lbs. 5,000 lbs. 7,500 lbs.

2.5 sq. ft. (360 sq. in.)

17 in. x 25 in. 59302 3,000 lbs. 4,500 lbs. 6,000 lbs. N/A 3 sq. ft. (432 sq. in.)

24 in. x 24 in. 59303 4,000 lbs. 6,000 lbs. 8,000 lbs. N/A 4 sq. ft. (576 sq. in.)

605 Stonehill Drive SW | Atlanta, Georgia 30336 | 404.344.0000 | www.tiedown.com24

LISTING & TESTING DIVISION

DESIGN

LISTING

# 1345

Renewed: Jan 2018 Revised: Oct. 2019

Subject to Review:

Sept.2020

RADCO, A Twining Company 3220 E. 59th Street Long Beach, CA 90805

Tel: (562) 272-7231 Fax: (562) 529-7513

PRODUCT: ABS & Steel FOUNDATION PADS

LISTEE: TIE DOW N ENGINEERING, INC.

5901 W heaton Drive

Atlanta, GA 30336

CATEGORY: DESIGN - FOUNDATION

APPLICATION: MANUFACTURED HOME - FOUNDATION

SECTION 1: INTRODUCTION

At the request of Tiedown Engineering, Inc., RADCO has examined their ABS Foundation Pads and Steel Pads to determine the design load capacity in accordance with Section 3280.401(b) of The Federal Manufactured Home Construction and Safety Standards.

SECTION 2: DESCRIPTION

ABS pads are molded pads having continuous ribs running parallel and diagonal with the pad sides. The Steel pads are made of 12 gage galvanized steel. The pads may be used to distribute concentrated pier loads to underlying soil for manufactured housing constructed in accordance with The Federal Manufactured Home Construction and Safety Standards 24 CFR Part 3280. The ABS pads are available in various sizes as noted in Table 1.

SECTION 3: APPLICATION

The pads shall be installed in accordance with the manufacturer’s installation instructions. The maximum design concentrated loads are provided in Table 1.

SECTION 4: EVIDENCE SUBMITTED

a) Test report of “Full Scale ABS Footer Test: by K2 Engineering, Inc.

Test Report #99-MH01-TDE, January 1999.

b) Test report of “Full Scale ABS Footer Test: by K2 Engineering, Inc.

Test Report #99-MH05-TDE, May 1999.

c) Test report of “Full Scale ABS Footer Test: by K2 Engineering, Inc.

Test Report #99-MH06-TDE, May 1999.

d) Test report of “Full Scale ABS Footer Test: by K2 Engineering, Inc.

Test Report #99-MH07-TDE, May, 1999.

e) Test report of “Full Scale ABS Footer Test: by K2 Engineering, Inc.

Test Report #99-MH09-TDE, September, 1999.

f) Test report of “Full Scale ABS Footer Test: by K2 Engineering, Inc.

Test Report #00-MH15-TDE, September, 2000.

g) Test report of “Full Scale ABS Footer Test: by K2 Engineering, Inc.

Test Report #01-MH17-TDE, August 2001.

h) Test report of “Vector-Xi Foundation Pad: by RADCO

TestReport # RAD-3849, May 2006

SECTION 5: RECOMMENDATIONS

RADCO recommends that these pads be accepted for use of pads in bearing capacity of soils listed in Table 1 for support of concrete masonry unit piers, provided that:

a) Each pad shall be fabricated, identified and installed in accordance with this listing, the manufacturer’s published installation instructions, and the applicable code(s). In the event of a conflict between the manufacturer’s published installation instructions and this listing, this listing shall govern. The installation instructions shall be available at the point of installation.

b) Each pads shall be marked with manufacturer name and address, product name, RADCO name/logo and Listing #1345.

c) The ABS pads are of the same quality and size as tested by K2 Engineering, Inc.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .