Attachment A Draft_SOW_493.0-00XXX_SWO-Coronagraph-Phase A_Formulation_SOW_08242022_v3.pdf
PDF 236 KB Posted
- Solicitation number
- 80GSFC22R0054
About this file
This draft request for proposal (DRFP) solicits comments on a future solicitation for the Space Weather Next Lagrange 1 (SW Next) Series Coronagraph formulation study. The National Aeronautics and Space Administration Goddard Space Flight Center will award up to four fixed-price contracts valued at $800,000 each for an eight-month base period. An optional four-month extension is available at $400,000 per contract to advance the study to preliminary design review level. The final report is due 12 months after award. The North American Industry Classification System code is 336414 with a small business size standard of 1250 employees. The solicitation involves the National Oceanic and Atmospheric Administration and seeks a coronagraph instrument as part of the Space Weather Next satellite system to provide coronal imagery for detecting and characterizing earth-directed coronal mass ejections. Potential offerors are invited to comment on requirements, schedules, risks, and other solicitation aspects. The final request for proposal is anticipated in November 2022 with proposals due in January 2023 and award by April 13, 2023.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Effective Date: TBD
Expiration Date: TBD
Confirm with SWFO CM to verify that this is the correct version prior to use.
DRAFT
Space Weather Next (SW Next))
Coronagraph Phase A Study Statement of Work (SOW)
W
U.S. Department of Commerce (DOC)
National Oceanic and Atmospheric Administration (NOAA)
NOAA Satellite and Information Service (NESDIS)
National Aeronautics and Space Administration (NASA)
Space Weather Observations (SWO) Program
SWO CMO
<Date>
Released
Space Weather Observations Program Division, Code 490.0
493-xxxx, Revision –
SW Next Coronagraph Phase A SOW 490.0-XXXXX, Revision – ii
Check the SWFO CM tool Server at Windchill (nasa.gov)to verify that this is the correct version prior to use.
SW Next Coronagraph Phase A Study SOW
Review/Signature/Approval Page Prepared by:
TBD
SWO Instrument Systems Manager
NASA Goddard Space Flight Center
Reviewed by:
SWO Program System Engineer
Date
SWO Deputy Program Director
Chief, Project Management and Execution Division
NOAA NESDIS/OPPA
Approved by:
SW Next Project Manager iii
Check the SWFO CM tool Server at Windchill (nasa.gov)to verify that this is the correct version prior to use.
Electronic Approval available on-line at: Windchill (nasa.gov) iv
Check the SWFO CM tool Server at Windchill (nasa.gov)to verify that this is the correct version prior to use.
Preface
This document is under SWO Division configuration control. Once this document is approved, approved changes are handled in accordance with Class I and Class II change control requirements as described in the SWO Configuration Management Procedure, and changes to this document shall be made by complete revision.
In this plan, all mandatory actions (i.e., requirements) are denoted by statements containing the term “shall.” The terms “may” or “can” denote discretionary privilege or permission; “should” denotes a good practice and is recommended but not required; “will” denotes expected outcome;
and “are/is” denotes descriptive material.
Any questions should be addressed to:
SWO Configuration Management Office
NASA/GSFC
Code 490.0
Greenbelt, MD 20771 v
Check the SWFO CM tool Server at Windchill (nasa.gov)to verify that this is the correct version prior to use.
Change History Log
Revision Effective Date Description of Changes
(Reference the CCR & CCB/ERB Approval Date)
Rev - TBD This is the initial baselining of the document. The document will be placed under CM control upon receipt of all required approvals.
vi
Check the SWFO CM tool Server at Windchill (nasa.gov)to verify that this is the correct version prior to use.
Table of Contents
1 INTRODUCTION
1.1 Top Level Summary of Work Required
1.2 Guiding Assumptions About the Eventual Flight Program
1.3 Study Milestones Schedule
1.4 Applicable and Reference Documents
2 TASKS
2.1 Trade Studies (needs update)
2.1.1 Seven (7) Year Mission Duration Trade Study
2.1.2 Contract Deliverables Requirements List (CDRL) Trade Study
2.1.3 Field Programable Gate Array (FPGA) Trade Study
2.1.4 Adaptability to Different Orbital Regimes
2.1.5 Manufacturability
2.2 Coronagraph Design Concept Development and Related Analyses (Needs Update)
2.3 Technology Assessment and Demonstration
2.4 Management Planning
3 REVIEWS, REPORTING, AND DELIVERABLE PRODUCTS
3.1 Status Meetings and Reviews
Kickoff Meeting
Monthly Progress Review (MPR)
Midterm Review (MTR)
Final Studies Review (FSR)
Final Report Package (FRP)
3.2 Contract Data Requirements List (CDRL)
Contract Deliverables Requirements List (CDRL) Trade Study
APPENDIX A ACRONYMS
List of Tables
Table 3-1. CDRLS
Check the SWFO CM tool Server at Windchill (nasa.gov) to verify that this is the correct version prior to use.
1 INTRODUCTION
The Space Weather Next (SW Next) Coronagraph shall be a Sun-pointing imaging instrument designed to accommodate the brightness range of the solar scene and detect transient and small local increases in solar coronal brightness associated with Coronal Mass Ejection (CME) plasma density pulses. The instrument must measure the coronal white light intensity as well as CME velocity, direction, width, and mass. A CME is an eruption of solar plasma that propagates at velocities of a few thousand kilometers per second outward into the heliosphere. To an observer on earth, an Earth-directed CME is viewed as a radially expanding circle of enhanced brightness centered on the Sun. The velocity of CMEs is obtained from two or more CME time-lapse images showing the radial expansion of the CME circle. A CME plasma density increase is observed by the detection of solar photons that are Thomson-scattered by coronal plasma electrons. The CME mass is proportional to the scattered photons.
The NOAA NESDIS has the responsibility to provide continuity of critical space-based space weather observations consistent with the goals outlined in the National Space Weather Strategy and Action Plan (https://www.sworm.gov/publications.htm). Design, development and deployment of satellite systems to meet this responsibility is through a joint NOAA/NASA
Space Weather Observations (SWO) Program Division within the Goddard Space Flight
Center’s Flight Projects Directorate. The SWO Program Division is exploring with industry partners the possibility to build subsequent coronagraph instruments.
NOAA and NASA acknowledge that there may industry interest to either collaborate in the use of compact coronagraph (CCOR) technology developed by Naval Research Laboratory (NRL) or to independently develop their own coronagraph technology.
Any industry partner that wishes to collaborate to use CCOR technology with NRL is required to be certified in the Joint Certification Program (JCP). The Joint Certification Program (JCP) certifies United States (U.S.) contractors for access to unclassified military technical data belonging to the U.S. Department of Defense (DOD). An active DD2345 "Military Critical
Technical Data Agreement" is required to access unclassified technical data with military or space application and may be required to partner with NRL. Any partnership with NRL, like any subcontracting agreement, is the sole responsibility of the industry partner; NOAA has no preference or preferred method of implementing the commercial Coronagraph development, other than to assure mission success, minimize cost, and mitigate schedule and risk.
It is anticipated that at the conclusion of this Phase A study any industry partner will be prepared to enter directly into a Systems Requirements Review approximately one month after
Implementation contract award followed by a Preliminary Design Review. The Government will consider a Contractor proposed pre-priced option for four (4) TBR) additional months of performance that mitigates technical, cost and schedule risk associated the Coronagraph design, development, and delivery, and includes the completion of this formulation study at a Preliminary
Check the SWFO CM tool Server at Windchill (nasa.gov) to verify that this is the correct version prior to use.
Design Review level readiness.
1.1 Top Level Summary of Work Required
The details of the deliverables are described in later sections. At the top level, the Government requires:
a) A Coronagraph Design that satisfies the baseline requirements defined in the SPEC and
IMAR. Suggested feedback to Coronagraph requirements, enhancements to the design beyond the baseline requirements will be entertained if they mitigate risk, schedule, cost, and can be implemented within the specified delivery timeline.
b) Feedback and an assessment of Coronagraph performance against requirements specified in the SPEC.
c) Trade Studies as specified in section 2.1 (TBR)
▪ Industry partner proposed trade study(s)
d) Technical Analysis as described in section 2.2
e) Notional Development Schedule as described in section 2.4
f) Cost Analysis as described in section 2.4
g) Technology Readiness Level (TRL) Assessment and a Technology Development Plan as described in section 2.3
h) Identification of Development Risks as defined in section 2.4
i) As applicable, performance of any work awarded for Technology Development and/or
Risk Mitigation effort(s)
j) Identification of hardware and software heritage assumptions as defined in section 2.3
1.2 Guiding Assumptions About the Eventual Flight Program
The Flight hardware development cost and schedule estimates shall be based on the following assumptions:
A. One (1) Engineering Development Unit (EDU).
a. That includes representative spacecraft mechanical and electrical interfaces
B. Two (2) Flight Units, plus parts for 2 more flight units to be procured concurrently, plus parts for sparing philosophy, with contractual options to build units 3 and 4; and a flight spare instrument philosophy to mitigate risk of issues identified late in the launch integration flow.
Deliveries as shown in the following notional schedule (all dates are for the Government
Fiscal Year).
Check the SWFO CM tool Server at Windchill (nasa.gov) to verify that this is the correct version prior to use.
MILESTONE DATE (assume 1st day of quarter)
Flight Contract Award Q2 FY24 (TBR)
Flight Model 1 Pre-Ship Review (PSR1) Q4 FY26 (TBR)
Launch 1 Planning Date Q4 FY28 (TBR)
Launch 2 Planning Date Q2 FY31 (TBR)
C. No Government Furnished Equipment (GFE) will be provided. If there is specific Government owned equipment which the contractor is proposing to use, then this equipment must be specifically identified, along with the benefit and verification of availability.
D. Mission Durations: See the SPEC. All requirements must be met at the End of Life.
The following instrument-level reviews are planned to be held for the first flight build:
SRR, IBR, PDR, CDR, PER, PSR. Subsequent flight builds will hold a PER and a
PSR. Review pre-requisites, content, and success criteria are documented in NPR
7123.1.
1.3 Study Milestones Schedule
The Contractor shall execute the study in accordance with the following milestone schedule.
Requirements and deliverables for these milestones are described in Section 3.
Milestone Schedule
Kickoff Meeting Within two weeks of award
Monthly Progress Reviews Kickoff + 1, 2, 3, 4, 5, 7 months
Mid-Term Review Kickoff + 4 months
Final Study Review Kickoff + 7.5 months
Final Report Package Kickoff + 8 months
Risk Mitigation Report (as applicable) Kickoff + 8 months
Technology Assessment and Development Report (as applicable)
Kickoff + 8 months
Check the SWFO CM tool Server at Windchill (nasa.gov) to verify that this is the correct version prior to use.
1.4 Applicable and Reference Documents
Reference Number Title
Applicable Documents
Draft_493-00XXX_SWO
COR 08242022
SW Next Coronagraph Specification (SPEC) Document (TBR)
4XX- COR-ICD-xx SW Next Coronagraph Interface Document (TBS)
4XX-COR-TBD-00xx SW Next Coronagraph General Interface Requirements Document
(TBS)
Draft_493.0-
00XXX_SWO IMAR
NEXT 08242022
SWO Instrument Mission Assurance Requirements (TBR)
Draft_493-
000XX_SWO_COR-
CDRL 08242022
SW Next Coronagraph Contract Deliverables Requirements List
(CDRL) (TBR)
GPR 7120.4D GSFC Guideline for Performing Risk Assessments
Reference Documents
CCSDS 120.0-G-2 CCSDS Informational Report Concerning Lossless Data Compression, Green Book, April 2013
CCSDS 120.1-G-2 CCSDS Informational Report Concerning Image Data
Compression, Green Book, February 2015
CCSDS 121.0-B-3 CCSDS Recommended Standard for Lossless Data Compression, Blue Book, August 2020 NPR 7123.1 NASA Systems Engineering Process and Requirements
SP-2016-6105 NASA Systems Engineering Handbook
Check the SWFO CM tool Server at Windchill (nasa.gov) to verify that this is the correct version prior to use.
2 TASKS
The Contractor shall analyze the Coronagraph requirements, perform trade studies to justify design decisions, develop a conceptual design for the Coronagraph, and perform all other tasks as specified below.
2.1 Trade Studies
The Contractor shall perform the following trade studies and report on the results at the Midterm and
Final reviews.
2.1.1 Seven (7) Year Mission Duration Trade Study
The Contractor shall study the 7-year mission duration contemplated for the SW Next L1 mission, including risks, opportunities, cost and schedule trades. (CDRL 1).
2.1.2 Contract Deliverables Requirements List (CDRL) Trade Study
The Contractor shall study the proposed CDRL document for the Coronagraph Instrument implementation, including risks, opportunities, cost and schedule trades. (CDRL 2).
2.1.3 Field Programable Gate Array (FPGA) Trade Study
The Contractor shall perform a trade study on FPGA’s to be used within their Coronagraph design. Include risks, opportunities, cost and schedule trades along with redundancy (including Triple
Modular Redundancy (TMR)) and rationale. (CDRL 3)
2.1.4 Adaptability to Different Orbital Regimes
The Contractor shall study the suitability and adaptability of the Coronagraph instrument design to be hosted on space platforms in different orbital regimes including in Earth geosynchronous orbit, at Earth-Sun Lagrange Point 1, and at Earth-Sun Lagrange Point 5.
2.1.5 Manufacturability
The Contractor shall study the manufacturability of the Coronagraph instrument, identifying complex parts, systems, and opportunities to mitigate and reduce complexity, cost and schedule. (CDRL 5)
2.1.6 Instrument Mission Assurance Requirements (IMAR) Trade Study
The Contractor shall study the proposed IMAR document for the COR Instrument implementation, including risks, opportunities, cost and schedule trades. (CDRL 4).
Check the SWFO CM tool Server at Windchill (nasa.gov) to verify that this is the correct version prior to use.
2.1.7 Contractor Proposed Trade Study & Pre-Priced Option
The Government will consider Contractor proposed Trade Studies and a pre-priced option for four (4) (TBR) additional months of performance that mitigates technical, cost and schedule risk associated the Coronagraph design, development, and delivery, and includes the completion of this formulation study at a Preliminary Design Review level readiness.
Milestone Schedule
Optional MPR #1 One month after 7-month milestone review
Optional MPR #2 Option MPR #1 + 1 month
Optional MPR #3 Option MPR #2 + 1 month
Optional MPR #4 Final Report Option MPR #3 + 1 month
2.2 Coronagraph Design Concept Development and Related Analyses
The Contractor shall develop a Coronagraph design concept and perform associated engineering analyses to justify design parameters, tolerances, design/performance margins, and associated budgets.
Included in this study shall be a discussion(s) on technical redundancy requirements and cost and schedule mitigation(s) to provide a Preliminary Design Review (PDR) level output at the end of this formulation effort. (CDRL 7)
The Contractor shall provide a quantitative comparison of the Coronagraph performance against the performance requirements in Section 3 of the SPEC. (CDRL 8)
The Contractor shall provide a summary of compliance to the Level 3 requirements (SPEC and
IMAR), including initial engineering analyses showing compliance to environmental requirements.
(CDRL 9)
The Contractor shall review all requirements listed as "TBR" and either concur or suggest new requirement values. (CDRL 11).
The Contractor shall quantify potential cost, schedule, and risk impacts of any suggested requirements changes. (CDRL 11)
The Contractor shall analyze the performance of the instrument concept including the development of a preliminary radiometric model and uncertainty budgets to achieve the required SNR. (CDRL 16)
The Contractor shall describe the systems approach to meeting all navigation requirements in the
SPEC. Such descriptions, including a preliminary error budget, will span relevant flight hardware characteristics, operational aspects, and ground processing. (CDRL 13)
Check the SWFO CM tool Server at Windchill (nasa.gov) to verify that this is the correct version prior to use.
The Contractor shall describe the algorithms to be used on the ground system for decompression (if needed) and processing to data Level 1b, as described in the SPEC. (CDRL
14)
The contractor shall review zones of reduced data quality (ZRDQ) and provide stray light mitigation concept. (CDRL 15)
The Contractor shall describe a reliability approach (planned redundancy, parts selection, etc.) to meet the SPEC required reliability for the specified lifetime. (CDRL 20)
The Contractor shall identify single-point failures and fault critical elements. As part of this analysis the
Contractor will describe the fault tolerant/graceful degradation features of the design. (CDRL 21)
The Contractor shall develop a Master Equipment List (MEL). The MEL will document the mass, power, and TRL of each major sub-component. A template for the MEL will be provided by the
Government. (CDRL 22)
The Contractor shall provide descriptions of any simulation and analytical tools used in the assessment of the design and/or performance, including the heritage and validation of the tools. (CDRL 23)
2.3 Technology Assessment and Demonstration
The Contractor shall assess the technology readiness of all components of the instrument design.
(CDRL 24)
If applicable, the Contractor shall provide a detailed Technology Development Plan (TDP), including a schedule, explaining how all technologies will achieve TRL 6 by the instrument PDR. If the study effort includes Technology Development effort, the TDP and associated schedule will clearly identify all of the work covered by the Technology Development. (CDRL 25)
The Contractor shall develop an EDU Model Philosophy and Plan that describes test plans, schedule, and cost of development for an end-to-end Engineering Development Unit and a test regime proposed by the Contractor. (CDRL 27)
The Contractor shall document the flight hardware and software heritage as well as any relevant differences between the claimed heritage and the proposed design (for example, on-orbit environment, mission duration, requirements, etc.). (CDRL 28)
2.4 Management Planning
The Contractor shall identify and rank risks to the development of the Coronagraph and describe associated mitigations. The likelihood and criticality of risks will be ranked on a 5x5 matrix per GPR
Check the SWFO CM tool Server at Windchill (nasa.gov) to verify that this is the correct version prior to use.
7120.4D. The Contractor will identify alternate implementation paths for all high-risk items.
(CDRL 29)
If the study effort includes Risk Mitigation effort, the Contractor shall implement the Risk
Mitigation effort under contract, brief the status of this effort at the reviews described in section
3, and provide a final report detailing the work completed, associated results, and the level to which the risk has been mitigated. (CDRL 30)
The Contractor shall define a Sparing Philosophy approach for procuring and maintaining an adequate supply of spare parts and subassemblies to minimize cost, schedule, and performance risks caused by part damage or shortages. (CDRL 26)
The Contractor shall develop an implementation phase schedule. The Contractor will assume that the parts for the 4 Flight models and any spare hardware needed for sparing philosophy will be procured at the same time. The schedule will show the following major instrument reviews: SRR, IBR, PDR, CDR, MRRs, TRRs, PER, and PSR, achievement of TRL6, development of the instrument physical model(s), long-lead (> 1 year) procurements, I&T and V&V activities, and the top three critical paths. The schedule will identify any flight hardware procurements that are started ahead of the completion of the EDU (or equivalent). (CDRL 3).
The Contractor shall suggest dates for the contract starts and other milestones that will minimize the overall cost and minimize the developmental risks. The schedule required to meet the program level milestones is shown in section 1.2 under item b. (CDRL 31)
The Contractor shall suggest dates for the FM3 and FM4 contract starts, deliveries, and other milestones that will minimize the overall cost and minimize the developmental risks to FM1 and FM2. The nominal PSR dates and Launch Planning Dates (LPDs) for these units are as follows: (CDRL 32).
Mission PSR (Gov. FY) LPD (Gov. FY)
FM3 Q2 FY32 (TBR) Q3 FY34 (TBR)
FM4 Q2 FY35 (TBR) Q3 FY37 (TBR)
The Contractor shall provide a parametric cost estimate for the development and production of four flight model instruments, any spare hardware needed for sparing philosophy, and the engineering model recommended in the EDU Model Philosophy & Plan (see section 2.3). The costs will be separately identified for each model, flight unit, required GSE (ground support equipment), and technology development(s) and organized by WBS element. The costs will be shown phased by Government fiscal year. The Contractor will state what parametric model was used in the analysis and provide any inputs to the model beyond the MEL (section 2.2), describing the heritage of the model. (CDRL 33)
Check the SWFO CM tool Server at Windchill (nasa.gov) to verify that this is the correct version prior to use.
3 REVIEWS, REPORTING, AND DELIVERABLE PRODUCTS
The Contractor shall perform the reviews and reporting tasks and provide deliverable products as specified below. The Contracting Officer's written determination that Government requests for action
(RFA's) or requests for information (RFI's) regarding the deliverable reviews and products have been closed out will constitute acceptance of the deliverable.
3.1 Status Meetings and Reviews
Kickoff Meeting
The Contractor shall support a kickoff meeting within 2 weeks of the Authorization to proceed to provide a team introduction, summary of the proposed work for the study, proposed study schedule, and a high-level introduction to the initial Coronagraph design concept. The Contractor will plan for a 2-hour virtual meeting. The Contractor will deliver a soft copy of the Kickoff chart set 24 hours prior to the meeting.
(CDRL 34)
Monthly Progress Review (MPR)
The Contractor shall present the results of the work performed since the previous MPR and discuss relevant technical and programmatic issues and findings. The topics expected to be covered are listed in the
CDRLs table in section 3.2. The MPRs will be planned as 4-hour virtual meetings. The Contractor will deliver a soft copy of the MPR chart set 24 hours prior to the meeting. (CDRL 35)
Midterm Review (MTR)
The Contractor shall present a summary of the results of the work performed for the Midterm Review. This review will be held at the NASA Goddard Space Flight Center, pending travel restrictions. The Contractor will plan on a one-and-a-half-day review. The topics expected to be covered are listed in the CDRLs table in section 3.2. The Contactor will deliver a soft copy of the MTR chart set 72 hours prior to the meeting. (CDRL 36).
Final Studies Review (FSR)
The Contractor shall present a summary of the results of the work performed for the Final Study Review.
The Contractor will plan on a one-and-a-half-day review at the Contractor’s facility. If possible, the
Government will travel to attend the review in-person, pending travel restrictions. The topics expected to be covered are listed in the CDRLs table in section 3.2. The Contractor will deliver a soft copy of the FSR chart set 72 hours prior to the meeting. (CDRL 37).
Check the SWFO CM tool Server at Windchill (nasa.gov) to verify that this is the correct version prior to use.
Final Report Package (FRP)
The Contractor shall deliver any CDRLs that were not delivered and approved by the Government
Contracting Officer (CO) prior to the FSR or any CDRLs requiring updates in the Final Report Package. The
Contractor will address any open action items remaining after the FSR in the Final Report Package. The FRP will be delivered within 2 weeks after the FSR. (CDRL 38)
3.2 Contract Data Requirements List (CDRL)
The Contractor shall deliver the data products specified in the following table
Update as Necessary (UAN)
Table 3-1. CDRLS
ID Deliverable/Task Deliverable
Format
Kickoff MPR MTR FSR FRP SOW
Ref
1 Seven (7) Year Mission
Duration Trade Study
Briefing Charts Status Prelim Final UAN 2.1.1
Contract Deliverables
Requirements List
(CDRL) Trade Study
Briefing Charts Status Prelim Final UAN 2.1.2
3 Field Programable
Gate Array (FPGA)
Trade Study
Briefing Charts Status Prelim Final UAN 2.1.3
4 Adaptability to Different
Orbital Regimes
Briefing Charts Status Prelim Final UAN 2.1.4
5 Manufacturability Briefing Charts Status Prelim Final UAN 2.1.5
6 IMAR Trade Study Briefing Charts Status Prelim Final UAN 2.1.6
Check the SWFO CM tool Server at Windchill (nasa.gov) to verify that this is the correct version prior to use.
7 Coronagraph Design Briefing Charts
+ Models
Status Prelim Final UAN 2.2
8 Predicted performance
vs. SPEC
Briefing Charts Status Prelim Final UAN 2.2
9 Level-3 Requirement
Compliance
Spreadsheet Status Prelim Final UAN 2.2
10 Vendor Proposed
Trades/Pre-priced option
Briefing Charts Status Prelim Final UAN 2.1.7
11 Suggested values for TBRs Briefing Charts Status, final answer by 3rd
MPR
UAN UAN UAN 2.2
12 Reserved
13 Navigation Approach Briefing Charts Status Prelim Final UAN 2.2
14 Level 1b
Algorithm
Description
Briefing Charts Status Prelim Final UAN 2.2
15 Straylight Mitigation
Concept
Briefing Charts Status Prelim Final UAN 2.2
16 Radiometric Performance and Uncertainty Budgets
Briefing Charts
+ Model +
Budget
Spreadsheets
Status Prelim Final UAN 2.2
17 Reserved
18 Reserved
19 Reserved
20 Reliability Approach Briefing Charts Status Prelim Final UAN 2.2
21 Single-Point Failures &
Fault Critical Elements
Briefing Charts Status Prelim Final UAN 2.2
22 MEL Spreadsheet Status Prelim Final UAN 2.2
Check the SWFO CM tool Server at Windchill (nasa.gov) to verify that this is the correct version prior to use.
23 Analytical Tools, Simulations, and Models
Briefing Charts Status Final UAN UAN 2.2
24 TRL Assessment Briefing Charts Status Final UAN UAN 2.3
25 Technology Development
Plan (As required)
Briefing Charts Status Prelim Final UAN 2.3
26 Sparing Philosophy and
Plan
Briefing Charts Status Prelim Final UAN 2.4
27 EDU Model Philosophy
& Plan
Briefing Charts Status Prelim Final UAN 2.3
28 Heritage Assessment Briefing Charts Status Final UAN UAN 2.3
29 Risk Assessment Briefing Charts Status Prelim Final UAN 2.4
30 Risk Mitigation Effort (if applicable)
Briefing Charts Status SU SU UAN 2.4
31 Flight Implementation
Schedule
MS Project +
Briefing
Charts
Status Prelim Final UAN 2.4
32 Options Schedule MS Project +
Briefing
Charts
Status Prelim Final UAN 2.4
33 Flight Cost Estimate Spreadsheet Status Prelim Final UAN 2.4
34 Kickoff Meeting Briefing Charts Charts due 24 hours before
3.1.1
35 MPR Charts Briefing Charts 24 hrs before
MPR
3.1.2
36 MTR Charts Briefing Charts 72 hrs before
MTR
3.1.3
37 FSR Charts Briefing Charts 72 hrs before
FSR
3.1.4
Check the SWFO CM tool Server at Windchill (nasa.gov) to verify that this is the correct version prior to use.
38 FRP NA 2
wks post
FSR
3.1.5
Check the SWFO CM tool Server at Windchill (nasa.gov) to verify that this is the correct version prior to use.
Appendix A Acronyms
A/D Analog-to-Digital
ACS Attitude Control System
ADC Analog to Digital Converter
AR Acceptance Review
CDR Critical Design Review
CDRL Contract Data Requirement List
CO Contracting Officer
CSCI Computer Software Configuration Item
DNB Day-Night Band
EDU Engineering Development Unit
EOL End of Life
ESD Electro-Static Discharge
ENOB Effective Number of Bits (ADC)
ESTE Electrical System Test Equipment
FM Flight Model
FOR Field of Regard
FRP Final Report Package
FSDE Flight Software Development Environment
FSR Final Study Review
GFE Government Furnished Equipment
GIRD General Interface Requirements Document
GPR Goddard Procedural Requirements
GSE Ground Support Equipment
GSFC Goddard Space Flight Center
IBR Integrated Baseline Review
NASA National Aeronautics and Space Administration
NOAA National Oceanic and Atmospheric Administration
NPR NASA Procedural Requirements
IBR Integrated Baseline Review
IMAR Instrument Mission Assurance Requirements
INR Image Navigation and Registration
IR Infrared
K Kelvin kHz Kilohertz km Kilometers
LMX GEO-XO Lightning Mapper
LRD Launch Readiness Date m meters
MAT Mission Allowable Temperature
Mbps Mega-bits-per-second
MEL Master Equipment List
Check the SWFO CM tool Server at Windchill (nasa.gov) to verify that this is the correct version prior to use.
MLI Multi-Layer Insulation
MMD Mean Mission Duration
Check the SWFO CM tool Server at Windchill (nasa.gov) to verify that this is the correct version prior to use.
MPR Monthly Progress Review
MRR Manufacturing Readiness Review
MTF Modulation Transfer Function
MTR Mid-Term Review mW Milliwatt
NASA National Aeronautics and Space Administration
NEDN Noise Equivalent Delta Radiance
NEDT Noise Equivalent Delta Temperature
NIST National Institute of Standards and Technology
NOAA National Oceanic and Atmospheric Administration
NOL Non-Operating Limits
NOT Non-Operating Temperature
NPR NASA Procedural Requirements
OAT Outgassing Allowable Temperature
OT Operating Temperature
PDR Preliminary Design Review
PER Pre-Environmental Review
PORD Performance and Operation Requirements Document
Qx FYz Quarter x of Fiscal Year z
PSR Pre-Shipment Review rad Radian
RFA Request for Action
RFI Request for Information
RMS Root Mean Square
SNR Signal-to-Noise Ratio
SOW Statement of Work sr Steradian
SRR System Requirements Review
SU Status Update
S/W Software
TBD To Be Determined
TBR To Be Reviewed
TBS To Be Supplied
TDI Time Delay and Integration
TDP Technology Development Plan
TM Thermal Margin
Tmin Minimum Scene Temperature
Tmax Maximum Scene Temperature
TRL Technology Readiness Level
TRR Test Readiness Review
UAN Update as Necessary
UIID Unique Instrument Interface Document um Micrometers (Microns) urad Microradian
WBS Work Breakdown Structure
ZRDQ Zones of Reduced Data Quality