About this file

This is a Cost Calculation Table for a Disaster Debris Removal, Management, and Disposal Services pre-event contract opportunity issued by Dorchester County, South Carolina. The table outlines hypothetical quantities and unit pricing structures used exclusively for scoring purposes in the proposal evaluation process. The itemized services include push operations (150 miles), vegetative debris removal (75,000 cubic yards), construction and demolition debris (25,000 cubic yards), mixed debris (10,000 cubic yards), sand (5,000 cubic yards), white goods (2,000 units), stump grinding in three size categories ranging from 24 inches to over 36 inches (totaling 2,500 stumps), grinding operations (60,000 cubic yards), Temporary Disaster Debris Reduction Site (TDSRS) services including setup, operation for 90 days, and closeout (3 each), hazardous household waste (1,000 units), and dead animal removal (300 units). The table explicitly states these are hypothetical quantities for scoring evaluation only and do not represent actual quantities or guaranteed work volumes.

The pricing structure requires vendors to provide unit prices for each service category, with the total evaluated cost calculated as the sum of all line items multiplied by their respective unit prices. The document serves as an informational reference tool for proposers to understand how their cost proposals will be scored, though proposers do not submit completed versions of this table. This standardized approach enables Dorchester County to compare proposals on a consistent basis across multiple vendors by applying uniform quantity assumptions to each submitted unit price.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cost Calculation Table

This table is for informational purposes only and will be used to determine cost scores for all responses. This is not intended for Proposers to fill out and submit. These are hypothetical quantities used for scoring only and do not represent actual quantities or guaranteed work.

Item Qty Vendor A Unit Price Vendor A Total

Push (Miles) 150 $ $

Vegetative (CY) 75,000 $ $

C&D (CY) 25,000 $ $

Mixed (CY) 10,000 $ $

Sand (CY) 5,000 $ $

White Goods 2,000 $ $

Stumps ≤24" 1,500 $ $

Stumps 25–36" 750 $ $

Stumps >36" 250 $ $

Grinding 60,000 $ $

TDSRS Setup 3 $ $

TDSRS Operation 90 $ $

TDSRS Closeout 3 $ $

HHW 1,000 $ $

Dead Animals 300 $ $

TOTAL EVALUATED COST $X