This is a Scope of Work and Specification document for Building Renovations at the Cardinal Shehan Center, located at 1494 Main Street, issued by the City of Bridgeport Housing & Community Development Department. The project involves comprehensive renovation work across multiple areas of the facility, including replacing eighteen double-hung windows with new vinyl windows, installing approximately 80 linear feet of leaders, replacing rubber mats, chairs, padding, vinyl flooring, tiling in the boy's locker room, lighting, acoustical ceiling, and bathroom refinishing. The renovation scope covers roughly 1,200 square feet of flooring and includes specific requirements for materials, installation techniques, and aesthetic matching of existing building elements.
The document requires contractors to provide detailed line-item pricing for each renovation component, with an emphasis on using specific materials like Home Depot Life Proof Rigid Core Luxury Vinyl Flooring and ensuring professional installation following manufacturer recommendations. Contractors must secure necessary permits, maintain insurance, adhere to OSHA safety standards, and follow state and local building codes. The project includes a one-year warranty on all work, materials, and labor, and strictly prohibits direct negotiations with homeowners. While specific funding sources are not detailed, the document indicates this is a publicly funded project requiring Davis Bacon Wage standards, with a mandatory site visit scheduled for February 11, 2024, to help bidders accurately assess the project scope.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CGB030252
Cardinal Shehan Center - 1494 Main Street
Building Renovations Scope of Work and Specification
PY48
Exterior Windows
• The contractor will field approximately eighteen (18) double hung windows. Remove all broken and deteriorated windows and dispose of them legally off site.
• Contractor will purchase and install new welded frame vinyl windows to match same type and style that currently exists.in building. Vinyl windows shall have low-e argon gas as part of the windows energy efficiency.
• All windows will be installed plumb and level. Windows will need to be shimmed as part of the installation. All windows will be filled with batt and foam insulation to fill any voids or air pockets when installing new windows. Before windows are inserted into place all exterior window stops will be clean, caulked, and new windows will be pushed against exterior stop to make a weather tight seal.
• If the interior or exterior window trim stops are damaged, the contractor will purchase and modify to match the existing if necessary. Install new window stops and trims to match existing ones. The contractor will patch and paint to match existing window trim.
All interior and exterior stops will be reinstalled if not damaged. All window trim must be painted.
• All stops will be nailed and caulked where the windows meet the stop, and at the beginning of the window stop for a total of three separate caulking. All trim will be painted with one coat of primer and one coat of finish. The contractor will smoothly finish all exterior & interior caulking that's adjacent to all windows, so they are aesthetically pleasing.
• Contractor will repair or replace aluminum coil over existing exterior window trim if damage as part of the installation. The contractor will repair or replace any vinyl siding materials as part of their installation. Any damage from the installation of the new windows in this area will be the sole responsibility of the contractor to make all matching necessary repairs.
* ELECTRONIC SUBMITTALS WILL SUBMIT DOLLAR ABOUTNS PRICING CHART VIA OPENGOV
PAPER SUBMITTAL MUST FILL IN DOLLAR AMOUNTS AND SUBMIT WITH BID
Leaders
• Contractor will field measure leaders buy and replace est.80’ linear ft. of leaders and install into existing drains. Contractor will purchase and install new leaders to existing building. Leaders will be secured with proper leader screws (brown). Galvanized or coated screws will be accepted if colored screws are not available. Contractor will install gutter seal to all joints and splices. Contractor will ensure proper fit and pitch to building.
Contractors will use no less than 032-gauge leaders. The owner to pick color (Brown).
Rubber Mats
• Contractor will field measure and replace the existing rubber or vinyl floor mats by water fountain roughly 4x12sf and vending machines 5x30sf.
Chairs
• Contractor will purchase and replace the existing deteriorated sitting foldable chairs in gym area with color red with white lettering same in-kind. The contractor will have padding same in-kind, and lettering approved by owner. The number of the chairs to be replaced is thirty (30).
Padding
• Contractor will purchase and install approved padding on both upper basketball hoops color red sane in-kind.
Vinyl Flooring
• Contractor will prep the existing floors in hallways, and landing flooring in all hallways on office floor. The prepping of the floor is to receive new flooring including patching and a smooth finish.
• Contractor will field measure these areas by removing existing carpet in upstairs and downstairs areas and discard to legal dumping area. Contractor will field measure purchase and install new vinyl flooring to these areas including landings. One (1) office upstairs and gym area office on lower level roughly twelve hundred sf (1,200).
Contractor will also remove the existing vinyl base and discard. Buy and install vinyl base same in-kind to the same areas.
• Contractor will purchase and install Home Depot Life Proof Rigid Core Luxury Vinyl Flooring or equal for installation in these areas. This floor is a floating floor contractor will follow all manufacture recommendation for the installation of this floor. Including all accessories but not limited to reducers, transition strips,1/4 round, t-molding or what is needed for the completion of this flooring project. (Owner to pick color). Contractor will buy and install new vinyl base in these areas (Owner to pick color
Boy’s Locker Room Tiling
• Contractor will field measure the existing flooring roughly 20 x 25 sf in the boy’s locker room and bath area. Demo the existing flooring tiles and remove to a legal dumping area.
• Contractor will patch and level the existing cement floor before installing new tiles.
Contractor will patch and paint the existing baseboard cement. Contractor will buy and install new mosaic tiles no larger than two inches (2”) in-kind to this area floor and install with thinset cement. Contractor will ensure that the newly installed flooring is level with no and high & low areas. (Owner to pick color and style).
Lighting
• Contractor will buy and replace the existing lighting in locker room with new 2’ x 4’ LED lights. Contractor will jack chain to ceiling joist the new LED light fixture. All four corners of the new light fixtures will be connected and placed in the ceiling grids without stress to lights & grids.
Acoustical Ceiling
• Contractor will remove all ceiling tiles and grids throughout locker room area and discard to a legal dumping area. Contractor will Purchase and install new 2x4 ceiling tiles and grids to this area roughly 20 x 25sf. (Owner to pick style).
Bathroom
• Contractor will scrape patch and paint the entire bathroom & locker-room areas.
• Contractor will warrant all work, equipment, materials, and labor for a period of one (1) year.
• Contractor SHALL NOT negotiate directly with homeowners for any changes to this contract. Any changes will be brought to the attention of the Office of The Housing Community Development office.
• Contractor will secure all necessary permits and follow all current State and local building codes for the duration of this project. Contractor will have and maintain all necessary certificates of insurance for the duration of this project. All work will be done in a professional manner throughout the duration of this project. All waste must be discarded in a legal manner.
• Contractor will keep the worksite clean daily (Construction or Working Area) until the construction is complete. Contractor will adhere to all OSHA safety standards while working on the site.
• Contractor cannot deviate from the specs without permission from construction manager. Contractor cannot negotiate with homeowner under any circumstances.
• Contractor will fill in each line item. Not filling each line could result in not being awarded this contract.
Total Price $ ____________________
| Contractor will buy and replace the existing lighting in locker room with new 2’ x 4’ LED lights. Contractor will jack chain to ceiling joist the new LED light fixture. All four corners of the new light fixtures will be connected and placed in the c... |
| $____________________ |
| Acoustical Ceiling |
| Contractor will remove all ceiling tiles and grids throughout locker room area and discard to a legal dumping area. Contractor will Purchase and install new 2x4 ceiling tiles and grids to this area roughly 20 x 25sf. (Owner to pick style). |
| Contractor will scrape patch and paint the entire bathroom & locker-room areas. |
| Contractor will keep the worksite clean daily (Construction or Working Area) until the construction is complete. Contractor will adhere to all OSHA safety standards while working on the site. |