Attachment A - Approved for Const Project Manual - 10.13.26.pdf
PDF 3 MB Posted
- Attached to
- Fenwick Library Masonry Rehabilitation
- Solicitation number
- IFB-130124
- Issued by
- Fairfax County, Virginia
About this file
This is a Project Manual and Construction Documents set for the Fenwick Library Masonry Rehabilitation project at George Mason University in Fairfax, Virginia (Project Code 247-252241). The work consists of masonry rehabilitation repairs to the Fenwick D addition, including brick masonry rehabilitation at building corners, relieving angles, and expansion joints. The additive scope includes reconstructing existing parapet coping stones and removing, storing, reinstalling, and recertifying the lightning protection system at the coping stones. The documents were approved for construction on October 13, 2026, and prepared by Simpson Gumpertz & Heger Inc. as the Engineer of Record. The project manual includes comprehensive contract requirements, general conditions, technical specifications across multiple divisions, and detailed drawings and details for construction execution.
The specifications establish unit price work for additional spalled brick replacement at a rate per square foot, with a base bid quantity of zero square feet, to be authorized by the Owner prior to demolition in specific areas. Two additive bid items are included: Additive Bid Item 1 for coping stone replacement including removal, reinstallation, flashings, sealants, and mechanical attachment, and Additive Bid Item 2 for removal and reinstallation of the lightning protection system with certification upon completion. The Contractor is responsible for all temporary services, protection measures, site management, waste disposal, worker parking permits, compliance with fire prevention and safety requirements, and coordination with the occupied facility. Shop drawings require fourteen calendar days for Engineer review and must be submitted through an online database or cloud-based project management software, with all final submittals to be provided to the Owner in both hard copy and electronic format upon project completion.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Fenwick Library Masonry Rehabilitation
George Mason University
Fairfax, VA
Project Code: 247-252241 SGH Project No.: 251308.00
PROJECT MANUAL
October 9, 2026
Construction Documents
SIMPSON GUMPERTZ & HEGER INC.
1625 Eye Street NW, Suite 900 Washington, DC 20006
202.239.4199 sgh.com
APPROVED FOR
CONSTRUCTION
Date = 10/13/2026
These construction documents have been examined in accordance with the 2021 Virginia Uniform Statewide Building Code (USBC). Submittals and/or shop drawings have not been provided or reviewed as part of this process.
The Registered Design Professional and/or Building/Tradesman Contractor shall be solely responsible for the correct installation and construction of all required systems in compliance with Federal, State, Local codes and manufacturing installation instructions. Request required special inspections and provide to A&E for review. Request inspections required by OUBO in accordance with OUBO policies and procedures. Any revisions that occur during the course of construction shall not be made to this set without the explicit permission of the OUBO in accordance with OUBO policies and procedures.
THIS PAGE LEFT INTENTIONALLY BLANK
SGH Project No. 251308
Fenwick Library Masonry Rehabilitation George Mason University Table of Contents Fairfax, VA TOC - 1
TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
TABLE OF CONTENTS
DESIGNER OF RECORD PROFESSIONAL SEAL
000115 LIST OF DRAWING SHEETS
BIDDING INFORMATION DGS FORM HECO FORM
N/A N/A N/A
Notice of Invitation for Bids Instructions to Bidders Standard Bid Form
N/A
HECO 7A-EB
N/A
GENERAL CONDITIONS & FORMS
All required project forms / documents can be found on Mason’s Facilities website by utilizing this link: https://facilities.gmu.edu/resources/heco-dgs-forms/
General Conditions of the Construction Contract DGS-30-054 CO-7 Statement of VUSCB Special Inspections N/A HECO-6A 2021 USBC Special Inspections N/A HECO-6B Contract Between George Mason University and Contractor N/A HECO-9 Workers Compensation Certificate of Coverage N/A HECO-9A Standard Performance Bond N/A HECO-10 Standard Labor and Material Payment Bond N/A HECO-10.1 Construction Change Order and Justification N/A HECO-11 General Contractor Estimate for Change Order N/A HECO-GC-1 Subcontractor Estimate for Change Order N/A HECO-SC-1 Sub-Subcontractor Estimate for Change Order N/A HECO-SS-1 Schedule of Values and Certificate for Payment N/A HECO-12 Affidavit of Payment and Claims N/A HECO-13 Certificate of Completion by A/E of Record N/A HECO-13.1 Certificate of Partial or Substantial Completion by A/E N/A HECO-13.1a Final Report of Structural & Special Inspections N/A HECO-13.1b Certificate of Substantial Completion by Construction N/A HECO-13.1c Inspector, Manager, or Administrator Certificate of Completion by Contractor N/A HECO-13.2 Certificate of Partial or Substantial Completion by Contractor N/A HECO-13.2a Checklist for Beneficial Occupancy N/A HECO-13.2b Project Completion Report N/A HECO-14 Submittal Register Format DGS-30-364 N/A
George Mason University Table of Contents Fairfax, VA TOC - 2
DIVISION 01 – GENERAL REQUIREMENTS
SECTION 010200 CONTRACT CONSIDERATIONS AND SPECIAL CONDITION
SECTION 011000 SUMMARY OF WORK
SECTION 012200 UNIT PRICES
SECTION 012300 ADDITIVES
SECTION 013000 SUBMITTALS
SECTION 014000 QUALITY REQUIREMENTS
SECTION 016300 SUBSTITUTIONS
SECTION 017700 CLOSEOUT PROCEDURES
SECTION 017836 WARRANTIES
DIVISION 02 – TECHNICAL SPECIFICATIONS
SECTION 040120 MASONRY REHABILITATION
SECTION 072100 THERMAL INSULATION
SECTION 076000 FLASHING AND SHEET METAL
SECTION 079200 JOINT SEALANTS
SECTION 264100 FACILITY LIGHTNING PROTECTION
END OF TABLE OF CONTENTS
George Mason University Fairfax, VA Designer of Record Seal
DESIGNER OF RECORD PROFESSIONAL SEAL
Fenwick Library Masonry Rehabilitation George Mason University, Fairfax VA
Project Code 247-252241
ENGINEER OF RECORD
Simpson Gumpertz & Heger, Inc.
1625 Eye St NW, Suite 900
Washington, DC 20006
Nicholas A. Piteo
Principal
10/9/2026
George Mason University List of Drawings Fairfax, VA 000115 - 1
SECTION 000115
LIST OF DRAWINGS
A000 Cover Sheet A002 Special Inspections A001 General Notes A101 Overall Roof Plan A102 Conceptual Overhead Protection Plan A201 East Elevations A202 Partial East Elevations A203 West Elevations A204 North & South Elevations A301 Details A302 Details
END OF SECTION
Masonry Rehabilitation 100% CONSTRUCTION SET George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 1
SECTION 010200
CONTRACT CONSIDERATIONS AND SPECIAL CONDITIONS
PART 1 – GENERAL
1.01 GENERAL REQUIREMENTS
A. All Contract Documents, including General and Supplementary Conditions, Drawings, and Specifications, apply to this Section.
B. Refer to the George Mason University Design Manual for additional requirements.
1.02 SUMMARY
A. Quality Requirements.
B. Building Permits and Licenses.
C. Time and Materials Work Records.
D. Work Requirements.
E. Tests and Inspections.
F. Project Coordination.
G. Working Hours.
H. Use of Site.
I. Temporary Services During Construction.
J. Construction Light and Power – Existing Buildings.
K. Communication Service.
L. Office of the Contractor – Existing Buildings.
M. Storage Sheds.
N. Sanitary Facilities.
O. Waste Disposal Facilities.
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 2
P. Temporary Elevator Use.
Q. Scaffolding.
R. Cranes.
S. Construction Access.
T. Parking for Construction Workers.
U. Haul Routes.
V. Site Fence.
W. Temporary Partitions.
X. Jobsite Security.
Y. Environmental Quality Control.
Z. Soil Erosions and Sedimentation Control During Construction Period.
AA. Mold and Moisture.
BB. Project Sign.
CC. Progress Cleaning.
DD. Safety Requirements.
EE. Fire Prevention Planning for Construction, Renovations, or Demolition Projects.
FF. Supplemental Safety Instructions.
GG. General Workmanship.
HH. Product Delivery, Storage, and Handling.
II. Project Conditions and Protection.
JJ. Interruptions of Existing Utilities During Construction.
KK. Vibration Control.
LL. Noise Control.
MM. Hazardous Materials Identification.
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 3
NN. Hazardous Materials Procedures.
OO. Owner-Owned Equipment.
PP. Eating Area and Disposal of Food Wastes.
QQ. Blasting.
RR. Advertising.
SS. Salvaged Materials.
TT. Phased Construction for Existing Building Alterations.
UU. Governing Law.
VV. Standard Forms.
WW. Conduct and Supervision.
XX. Project Documents for Information.
1.03 QUALITY REQUIREMENTS
A. Refer to Section 014000.
1.04 BUILDING PERMITS AND LICENSES
A. Building Permits: The Owner will obtain and pay for the Building Permit, including applicable plan review, approval, and hearing fees.
B. Other Permits and Fees: Obtain and pay for all other permits, assessments, fees, bonds, and other charges as necessary to perform and complete the Work of the Contract. The Owner will reimburse the Contractor for any permit fees.
1.05 TIME-AND-MATERIALS WORK AND UNIT PRICE RECORDS
A. Maintain detailed records of all work done on a Time-and-Material or Unit Price basis. Provide full and timely information required for the evaluation of any proposed changes, and substantiate costs associated with changes in the Work.
1.06 WORK REQUIREMENTS
A. All buildings, site areas, and building contents are a critical part of George Mason University’s operations, and all interior and exterior spaces shall be managed by the
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 4
Contractor with stringent temporary protection measures commensurate with an active University environment and significant monumental building construction.
B. Verify all site conditions and dimensions with field measurements in consideration of the special conditions associated with alteration of existing construction and reconstruction.
C. Notify the Engineer immediately of any inconsistency between field conditions found during demolition and those shown in the Drawings or described in the Specifications.
The Engineer will determine what modifications or additional work may be necessary.
D. The Contractor affirms that he has carefully examined the site and all conditions affecting the work of these Specifications. No extra payment will be allowed for additional work caused by unfamiliarity with site conditions that are visible or readily construed by an experienced observer.
1.07 TESTS AND INSPECTIONS
A. Coordinate necessary tests and inspections as required, including, but not limited to, the following:
1. Inspections by the Building Official and the Owner’s third-party independent inspection firm.
2. The Engineer will perform tests and inspections as described in the Specifications.
B. Allow the Building Official and Engineer full access to all portions of the work;
temporarily stop work in specific areas when the work interferes with tests and/or inspections.
C. Provide the Engineer, or any other testing agency or regulatory authority, with all labor, materials, and access equipment necessary to perform tests or inspections.
D. Engineer's Inspection: The Engineer will observe the work and will interpret the Contract Documents. Provide the Engineer three workdays’ advance notice before starting the work or portions thereof. Do not conceal or allow to be concealed any portion of work subject to inspection and not yet approved by the Engineer. The Contractor shall bear all costs incurred to open and reinstall any such work.
1.08 PROJECT COORDINATION
A. Prior to the start of the Work, submit to the Owner’s Project Manager and Engineer for approval a project schedule for the entire scope of Work per the General Conditions of the Contract for Construction and Section 013000.
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 5
1. Phasing: Submit a detailed phasing plan, including construction schedules for each building portion, proposed laydown areas (including overhead protection plan, fencing, etc.), traffic management plan, interior and exterior temporary protection measures, and any other information necessary to articulate the Contractor’s work plan to the Owner for discussion. For preliminary planning and cost-estimating purposes, assume that laydown areas are limited to those shown on the overhead protection plan in the Drawings. The interior/exterior temporary protection plan shall address all interior and exterior hardscaping and landscaping, and features to remain.
B. Coordinate the various trades by the timely performance of work. Coordinate the various trades to maximize efficient use of scaffolding and to ensure that work is performed in proper sequence.
C. Notify the Owner’s Project Manager no less than 48 hrs in advance of proposed changes to the approved schedule and location of work.
D. Arrange the work sequence to avoid use of or travel on newly installed work.
1.09 WORKING HOURS
A. Unless otherwise stated in the Contract Documents, the Contractor's working hours shall be in accordance with a schedule agreed upon by the Contractor and the Owner. Work during evenings and weekends shall be scheduled and fully coordinated with the Owner’s Project Manager.
1.10 USE OF SITE
A. Leave the premises in a neat, clean, and safe condition at the end of each day's work.
Protect the building and site. Clean work areas at the end of each workday.
B. Site Logistics: The Contractor shall coordinate site restrictions and requirements with the Owner and shall submit an operations, egress, logistics, and safety plan for review prior to starting the work.
C. Perform all work without interfering with the scheduled normal operation of the building and coordinate the work properly with the building's function. Do not interfere with or disrupt activities without the specific approval of the Owner. Do not block or obstruct any building egress points. Notify the Owner 48 hrs in advance of any construction work that will disrupt any building system or operation.
D. Interior Access: Provide the Owner 48 hrs’ advance written notice of any operations that require interior access to the building, operations that are expected to create excessive vibration to interior areas, operations that involve the use of hazardous or
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 6 noxious chemicals, and any other operation that will potentially affect the building occupants. No exterior door shall be propped open unless it is continuously supervised.
E. The Contractor is responsible for supervising the use of keys issued to them to ensure that the building's security is maintained.
F. Safe Work Access: Provide safe access, including ladders and staging, to the work for the Contractor’s own personnel, authorized public officials, the Owner, and the Engineer. The access provided must comply with all applicable Federal, State, and Local regulations.
G. Provide the Engineer with access and assistance to all areas of the building where the work will be performed, including incidental labor and facilities.
1.11 TEMPORARY SERVICES DURING CONSTRUCTION
A. The Contractor shall, at their own cost and expense, install, operate, protect, and maintain the respective temporary services as hereinafter specified during the construction period of this project. These temporary services shall include water supply, electric light and power, material hoists, fire protection, sanitary facilities, access roads, and other services as may be stipulated in the Contract Documents.
B. The Contractor shall pay the costs for electric power and fuel required for the operation of temporary services except where it is stipulated herein that these items will be furnished free of charge to the Contractor by the Owner or will be furnished by other Contractors.
C. Temporary connections to new and existing permanent service lines shall be made at locations as directed by the Owner, and when temporary service lines are no longer required, they shall be removed by the Contractor installing same. Permanent service lines, grounds, and buildings disturbed or damaged by installation and removal of temporary service lines shall be restored to their original condition by the Contractor responsible for temporary installation, at no cost to the Owner.
D. Contractors who fail to carry out their responsibility in supplying temporary services as set forth in their contract shall be held responsible for such failure, and the Owner shall have the right to take such actions as it deems proper for the protection and conduct of the work and shall deduct the cost involved from the amount due of the Contractor at fault.
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 7
1.12 CONSTRUCTION LIGHT AND POWER – EXISTING BUILDINGS
A. The Contractor shall, at their own cost and expense, extend temporary lighting and power from existing service in the buildings to work areas. The Contractor shall fully coordinate loads required to perform the work and to maintain existing lighting and power circuits in use.
1. The Owner, within its facilities, will furnish electricity for construction purposes free of charge to the Contractors.
1.13 COMMUNICATION SERVICES
A. Communication Services: The Contractor shall provide their own communications (telephones and other devices) at their cost to meet their needs. The Owner’s telephones and other communication devices shall not be used unless in case of an emergency.
1.14 OFFICE FOR THE CONTRACTOR – EXISTING BUILDINGS
A. The Contractor shall establish an area at the worksite as may be feasible for conducting their operations, as agreed upon by the Owner.
1.15 STORAGE SHEDS
A. The Contractor shall, at their own cost and expense, provide upon the premises, at a location directed by the Owner and maintain and remove when directed, suitable substantial watertight storage sheds. Contractors shall not store materials in existing building or beyond the Contract limits.
B. The Owner shall not be held responsible for stored items at the sites. This shall be the sole responsibility and liability of the Contractors.
C. Storage of combustibles shall not be permitted within Owner buildings. Corridors, hallways, stairwells, loading docks, and egress ways shall not be used for storage of materials.
1.16 SANITARY FACILITES
A. The Contractor shall provide and maintain in a clean and sanitary condition temporary sanitary facilities until structures are enclosed and sanitary facilities are fully operational. Thereafter, the Contractor's workforces may use the project’s sanitary facilities only within areas where construction work is being completed but not those within the areas already occupied by the Owner. Permanent sanitary facilities shall be maintained in a sanitary condition and shall be thoroughly cleaned immediately prior to occupancy by the Owner.
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 8
B. Contractors shall not dispose of flammables and solids such as paint thinners, plaster, concrete, or other debris in the Owner's sanitary facilities. Construction and demolition waste products shall be properly disposed of off the site and the Owner's property.
1.17 WASTE DISPOSAL FACILITES
A. The Contractor shall provide waste-collection containers in a location as agreed upon between the Owner and Contractor for disposal of waste generated at the construction site. Waste-collection containers shall be emptied on a schedule as required by project activities and shall be removed immediately when no longer required. On project sites where there are no locations acceptable for waste collection containers, the Contractor shall remove trash, rubbish, and construction debris on a daily basis.
B. Use of Owner waste-collection containers for disposal of materials is prohibited.
1.18 TEMPORARY ELEVATOR USE
A. The Owner will designate one elevator for movement of workers and materials as is permissible within load limits of elevator cab and equipment. The Contractor shall schedule use of the elevator with the Owner prior to construction operations. The Contractor shall provide protection pads and covering for the walls, ceilings, and floors of elevator cab and shall provide an elevator operator, if required.
B. At Substantial Completion, the Contractor shall restore the elevator to the condition existing before initial use, including cleaning of shaft and replacing worn cables, guide shoes, and similar items of limited life.
1.19 SCAFFOLDING
A. The Contractor shall provide at their own cost and expense materials required for scaffolding, trestles, platforms, flooring, railings, ladders, overhead protection, and other equipment as required by authorities having jurisdiction and applicable requirements of OSHA for execution of the Work and protection of employees on the Work. The Contractor shall be held responsible for installation, maintenance, and removal of scaffolding and equipment required for construction.
B. Contractors shall be required to receive permission from the Owner for the display of signs, banners, and emblems prior to erecting same on Contractor-owned equipment.
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 9
1.20 CRANES
A. Cranes: Contractors and their Subcontractors utilizing cranes, rigging, and cribbing during execution of their work shall be solely responsible for the proper setup, inspection, operation, maintenance, and disassembly of said equipment. Contractor and Subcontractor management shall not allow untrained or unauthorized personnel to perform activities involving the assembly, use, and disassembly of cranes, rigging, and cribbing. Crane Lift Plan shall be provided to both the Owner’s Project Manager and Safety Department.
B. Crane Inspection Report: Submit a copy of the Annual Crane Inspection Report prior to starting work. The report shall conform to either OSHA or authority having jurisdiction standards and requirements. If a crane is brought on site without proper documentation or inspection, said crane shall be removed at once from the site with associated charges borne by the Contractor.
1.21 CONSTRUCTION ACCESS
A. The Contractor shall provide and maintain construction access to the site for construction operations.
B. Contractors shall be responsible for keeping public and private roads clean of mud, dirt, or debris originated by the construction operations. Mud, dirt, or debris deposited on Campus roads and adjacent public roads by construction operations or construction traffic shall be cleaned daily by the Contractor to the satisfaction of the Owner.
1.22 PARKING FOR CONSTRUCTION WORKERS
A. Facilities for Contractor Parking: There will be no Contractor parking at the project site.
B. Contractors are required and responsible for all parking permits required to perform and complete all work associated with this Invitation for Bid. Vehicles without authorized Permits/Decals will be ticketed.
C. Temporary Parking Permit(s)/Decal(s) must be purchased by the Contractor for each Subcontractor or employee vehicle to be parked at the site. All parking permit requirements, guidelines, and fees can be found by utilizing the links below:
1. Virtual Permit Program: https://transportation.gmu.edu/virtual-permit/ .
2. Parking Permit Rates:
https://transportation.gmu.edu/policies/#ParkingPermitsFees .
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 10
1.23 HAUL ROUTES
A. Haul Routes: Contractors shall consult with the Owner’s Project Managers and the authority having jurisdiction to establish public thoroughfares and Campus roads to be used for haul routes and site access. Contractors shall provide traffic control at critical areas of haul routes to regulate traffic to minimize interference with public and Owner traffic. Contractors shall pay bonds and fees required by the authority having jurisdiction.
B. Traffic Controls: Comply with requirements of authorities having jurisdiction.
1. Protect existing site improvements to remain, including curbs, pavement, and utilities.
2. Maintain access for firefighting equipment and access to fire hydrants.
3. Signs, Signals, and Devices: Provide signs, signals, control devices, and personnel as approved and required by the authority having jurisdiction.
1.24 SITE FENCE
A. The Contractor shall provide and maintain a temporary site fence on the perimeter of the site to meet the requirements of the Owner and local authorities having jurisdiction. Refer to the design drawings for conceptual site protection and general requirements.
B. Before construction begins, furnish and install a minimum of a 8 ft high, chain link, site enclosure fence, completely surrounding construction area, in a manner that will prevent people and animals from easily entering the site except by entrance gates.
The fence must be capable of withstanding anticipated wind and service loads.
Provide tamper-resistant hardware to prevent easy disassembly. Provide “anticlimb” welded wire mesh or plastic slats in conventional chain link fence to discourage climbing.
1.25 TEMPORARY PARTITIONS
A. The Contractor shall protect work, including existing property affected by work activities, against weather and maintain work, materials, apparatus, and fixtures free from injury and damage during the entire construction period. Work likely to be damaged shall be covered and protected at the end of each day’s work. Remove and replace damaged work with new at no additional cost to the Owner.
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 11
B. Temporary Exterior Enclosures:
1. The Contractor shall provide weather enclosures protecting Owneroccupied areas with an average overall thermal resistance value of R11.
2. Doors: Provide plywood or metal doors with locks; provide hardware complying with governing codes and regulations.
3. Windows: Provide windows covered with transparent plastic or tempered glass at openings; maintain in satisfactory condition until installation of permanent materials and equipment.
4. Walls: 1/2 in. plywood on wood or metal studs with insulation and one layer of 1/2 in. gypsum board on interior side. Seal joints to provide a weathertight partition. Paint with one primer coat and one finish paint coat.
C. Temporary Interior Partitions: The Contractor shall isolate work areas from Owner-occupied areas to prevent dust, fumes, noise, and odors from entering occupied areas. Maintain negative air pressure within work area using HEPAequipped air filtration units.
1. The Contractor shall provide floor-to-ceiling dustproof partitions to limit dust and dirt migration and to separate areas occupied by the Owner from fumes and noise.
2. Long-Term Partitions: Construct with wood or metal studs with water-resistant gypsum wallboard on public sides. Provide a Level 3 finish with one prime coat and one finish paint coat on public side.
3. Short-Term Partitions – Less than 24 Hours Use: Construct with wood or metal studs with polyethylene sheeting free of dirt, holes, and tears.
4. Provide fire-rated partitions and doors where required by governing codes and regulations.
5. Elevator shafts shall be protected with polyethylene sheeting taped to elevator door frames to reduce dust from entering the shaft. Damage to walls and frames shall be repaired to like-new conditions.
6. Where indicated on Drawings or as may be required, provide negative air vestibules using partitions described above along with doors and frames with locks.
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 12
1.26 JOBSITE SECURITY
A. Jobsite security will not be provided by the Owner.
B. The Owner assumes no responsibility for damage or loss to Contractor's property.
The Contractor shall be responsible for the security and protection of their own materials, equipment, tools, and toolboxes both on and off-site.
C. Security Enclosure and Lockup: Install temporary enclosure around partially completed areas of construction. Provide lockable entrances to prevent unauthorized entrance, vandalism, theft, and similar violations of security. Lock entrances at the end of each workday.
D. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.
1.27 ENVIRONMENTAL QUALITY CONTROL
A. The Contractor and subcontractors shall perform their work in a manner that shall minimize the possibility of air, water, land, and noise pollution, and in accordance with authority having jurisdiction. The Contractor shall comply with local laws and ordinances and Federal and local environmental and antipollution regulations. The Contractor shall be solely responsible for any violations and shall be responsible for securing required permits.
1.28 MOLD AND MOISTURE
A. Contractor’s Moisture Protection Plan: The Contractor shall submit a plan describing procedures and controls for protecting materials and construction from water absorption and damage. Document visible signs of mold that may appear during construction. Remove materials that cannot be completely restored to their manufactured moisture level.
1.29 PROJECT SIGN
A. If identified and requested by the Owner, the Contractor shall provide at a prominent location as selected by the Owner, a 6 ft x 8 ft sign, well braced, and supported by 4 in. x 4 in. posts identifying the project under construction. Signboard shall be constructed from weatherproof plywood, hardboard, or other smooth-faced material that will weather and remain intact throughout the job. The sign shall be placed with 8 ft dimension horizontal. Information to be provided on the project sign shall be with the Owner's approval. At project completion, the Contractor shall remove the sign from the site.
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 13
1.30 PROGRESS CLEANING
A. The Contractor shall be responsible for the overall cleanliness of the project site.
Clean the project site and work areas daily, including common areas. Enforce requirements strictly. The Contractor shall remove their construction debris, trash, and rubbish from the point of origin daily to the Contractor’s waste collection containers. Construction debris, trash, and rubbish shall not be allowed to accumulate. The Owner shall have the right to direct the Contractor to establish a cleanup routine. The Contractor shall be expected to participate fully in this routine.
1.31 SAFETY REQUIREMENTS
A. The Owner expects each contractor and their employees to perform their individual duties in a manner that is not injurious or otherwise dangerous to themselves or others. Each contractor and by default Contractor personnel, Subcontractors, and their personnel are solely responsible for their own safety and required safety training.
B. Employer Certification: The employer shall certify that employees have been trained by preparing a certification record that includes the identity of the person trained, the signature of the employer or the person who conducted the training, and the date that training was completed. The certification record shall be maintained in a file and be kept readily available for review by the Owner’s Project Manager.
C. Contractors are contractually obligated to comply with applicable Federal, State, and Local health rules and regulations, including applicable Owner site-specific and business unit policies and procedures. Each Contractor and Subcontractor is responsible for assessing the hazards associated with their activities and develop sitespecific safety strategies and procedures to mitigate risks.
D. The Contractor shall have a written health and safety program that outlines safe work practices and procedures expected to be followed by workers and shall have it available for review by the Owner’s Project Manager or by representatives of the Environmental Health and Safety Department (EH&S). A copy of this plan shall be forwarded to the Owner’s Project Manager and maintained on site.
E. The Contractor shall have a Competent Person(s) or Qualified Person(s) as defined by OSHA on the project site to support Environmental, Health, and Safety Efforts and to monitor hazardous work activities.
1. Competent Person: “One who is capable of identifying existing and predictable hazards in the surrounding or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 14 authorization to take prompt corrective measures to eliminate them.” (OSHA 29 CFR 1926.32(f)).
2. Qualified Person: “One who by possession of a recognized degree, certificate or professional standing or who by extensive knowledge, training, and experience, successfully demonstrate the ability to solve problems related to the subject matter, the work, or the project.” (OSHA 29 CFR 1926.32(m)).
F. Contractor’s Site-Specific Safety Plan: Documents of this plan shall detail the scope of the work in concert with the safety processes affiliated with each work activity. The plan shall include, but not limited to, the following:
1. Compliance with Applicable Federal, State, and Local safety requirements.
2. Protection of the students and public.
3. Personal Protective Equipment (PPE): Minimum PPE requirements for projects include hard hats, safety glasses, appropriate shoes, long pants, and shirts with minimum one-quarter sleeves.
4. High-Hazard Activities: Notify Owner’s Project Manager two weeks prior to high-hazard activity that may impact public or pedestrians (i.e., crane, scaffolding, trenching, etc.). Notice shall accompany an Activity Hazard Analysis (AHA) or comparable safety plan.
G. Chemical Safety Plan: Contractors shall have an up-to-date Safety Data Sheet (SDS) for chemical products used on the project site. SDSs shall be maintained on the project site and be readily accessible to Owner staff upon request. If the use of any chemical product has the potential for harmful exposure to students, staff, and visitors, the EH&S shall be notified. At project completion, chemicals shall be removed from the project site.
H. Electric Safety: Affected Contractors and Subcontractors shall be responsible for implementing electrical safety requirements in accordance with OSHA and National Fire Prevention Association requirements. Temporary wiring shall have ground fault circuit interrupter protection for personnel.
I. Fall Protection: Contractors shall follow OSHA’s requirements and recommendations when Contractor’s personnel are exposed or have the potential to be exposed to a fall hazard. This requirement applies to floor, roof, and wall openings and perimeters.
J. Incident Investigation: When an event of an unusual and significant nature occurs at the project site, regardless of whether it is related directly to the Work, prepare and submit a special report to the Owner’s Project Manager and Safety Department. List
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 15 chain of events, persons participating, response by Contractor's personnel, evaluation of results or effects, and similar pertinent information. Advise the Owner’s Project Manager in advance when these events are known or predictable.
1.32 FIRE PREVENTION PLANNING FOR CONSTRUCTION, RENOVATIONS, OR
DEMOLITION PROJECTS
A. Potentially applicable Codes include International Fire Code Chapter 14, International Building Code Chapter 33, NFPA 241, NFPA 70, and NFPA 3: Recommended Practice for Commissioning and Integrated Testing of Fire Protection and Life Safety Systems, current Edition.
1. Contractors working on new construction, renovation, or demolition projects at the Campus must familiarize themselves with the above Codes enforced by the Commonwealth of Virginia. The Contractor shall submit a Fire Prevention Plan prior to starting Work. The project-specific Plan is to be developed by the contractor/construction manager and must be submitted to George Mason University’s Facilities & Campus Operations. Facilities & Campus Operations shall submit each Fire Prevention Plan to Environmental Health and Safety (EH&S) for review.
B. During construction, renovation, or demolition, especially within buildings that will remain occupied during any portion of the project, the Fire Prevention Plan should address the potential fire and life safety hazards created by the project, and the maintenance of conditions and control measures that allow for continued building occupancy. It is not acceptable for any project to have a condition that lacks the required fire notification, fire protection, and safe egress features.
1. A thorough review of the existing fire alarm and fire protection systems along with review of any proposed modifications to these systems shall be performed by the Contractor. This review shall determine how modifications or removal of devices in the work zone may impact adjacent areas or the entire building. Maintaining existing systems (in full or in part), installing temporary systems or devices, or a combination of these approaches shall be included.
C. Fire Alarm Systems:
1. Existing fire alarm system consisting of, but not limited to, smoke detectors, heat detectors, water-flow switches for the sprinkler system, valve tamper switches, pull stations, and notification devices (horns/strobes/speakers) shall remain operational.
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 16
2. A “minimal level” of detection shall be maintained at all times. This is defined as active pull stations at both primary and secondary egress points and notification devices in the work zone. Smoke detectors in and adjacent to the work zone shall be temporarily bagged during construction to help reduce false alarms and keep dust from entering devices. Bags shall be cleaned and carefully removed to prevent activation at the end of each shift. Accepted bagging techniques involve paper bags temporarily fastened to the detector in a manner that covers the sensing device. Tape covering sensing device is not an acceptable method for bagging detectors. Specific detection devices (e.g., beam-type detectors or duct detectors) may be temporarily disabled upon approval of EH&S. Every effort shall be made to minimize the time that the devices are inactive.
a. Project’s Fire Prevention Plan shall address removal of devices on fire alarm system, including anticipated impact to adjacent areas on fire alarm system (or loop). Adjacent areas or zones shall remain properly protected and operation of fire alarm system shall remain unaffected.
If programming changes are required to fire alarm panel, these shall be documented in the Plan and coordinated with fire alarm panel manufacturer’s approved technicians.
b. If it is determined that there is no practical way to maintain fire alarm system components during any portion of the project, a fire watch shall be established. Fire watch and the impacts to fire alarm system shall be detailed in the Plan.
3. New system installations shall comply with applicable standards as listed in the IFC, IBC, and NFPA.
D. Fire Protection Systems:
1. Existing fire protection systems, including, but not limited to, sprinkler systems, fire hose standpipe systems, and fire pumps (including the controller and backup emergency generators) shall remain operational.
2. Consideration shall always be given to maintaining portions of sprinkler system within the work zone. When sprinklers are removed from service, temporary smoke detection shall be installed. Temporary smoke detectors shall be programmed into the fire alarm panel and shall remain in service until sprinkler protection is resumed. Temporary smoke detectors in and adjacent to the work zone shall be bagged during construction to help reduce false alarms and keep dust from entering the devices. Bags must be removed at the end of each workday.
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 17
3. If it is determined that there is no practical way to maintain fire protection systems during any portion of the project, a fire watch shall be established.
The fire watch and the impacts to fire protection systems shall be detailed in the Plan.
4. New system installations shall comply with applicable standards as listed in the IFC, IBC, and NFPA.
E. Other Responsibilities:
1. The Contractor must establish a designee or Program Superintendent to implement and supervise the following:
a. Verify that fire alarm and fire protection systems are arranged and operational as discussed in the Plan.
b. Verify that installation of new equipment, suspended ceilings, walls, cabinets, shelving, signs / displays, or other items do not interfere or obstruct sprinkler heads (existing or new), fire alarm initiating and notification devices, hose cabinets, fire extinguishers, fire alarm control panels, annunciators, and EXIT signs until relocation or new components are provided.
c. Coordinate with the Owner’s Project Manager to schedule emergency outages to fire alarm and fire protection systems.
d. Manage procedures established in the Plan for control of the following precautions against fire:
(1) The Owner’s Hot Work Permit System shall be followed. Hot Work Permits shall be obtained from the Owner’s Project Manager or EH&S. Hot Work is defined as any temporary operation involving open flames or producing heat and/or sparks, including, but not limited to, brazing, cutting, grinding, soldering, torch-applied roofing, applied roofing kettles, thermal spraying, welding, and similar operations.
(2) Fire watch is the action of an on-site person whose sole duty is to act as fire watch to include, but not limited to, the following:
(a) Fire watch shall be supplied by the Contractor with suitable extinguishers. Owner-owned fire extinguishers shall not be used by the Contractor for this purpose.
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 18
(b) Fire watch must be trained in use of equipment and in sounding alarm.
(c) Fire watch may also be required in adjoining areas, above and below the Hot Work area.
(d) Fire watch shall watch the area during Hot Work and for a minimum of 60 min. after completion; longer durations may be required for some activities. Prior to leaving the area, fire watch shall remove bags from smoke or heat detectors, perform final inspection on the work area and all adjacent areas to which sparks and/or heat might have spread, and if found fire safe, shall sign the Hot Work Permit and return to the job foreman/supervisor, who will forward to EH&S as per Hot Work Permit section above.
e. Open burning for construction-related operations such as torch-applied roofing is prohibited unless a permit is obtained from the City.
Do not burn demolished materials. Demolished materials shall be removed from the site and properly disposed of in a waste landfill acceptable to authorities having jurisdiction.
f. Materials susceptible to spontaneous ignition, such as oily rags, shall be stored in a listed / approved disposal container.
g. Storage, use, and handling of flammable and combustible liquids shall be in accordance with IFC Section 1405 and applicable sections of Chapter 34.
h. Storage, use, and handling of flammable gas shall be in accordance with Chapter 35 of the IFC.
i. Combustible debris shall not accumulate within buildings.
Combustible debris, rubbish, and waste material shall be removed from buildings at the end of each work shift and shall be properly disposed.
j. Temporary wiring for electrical power and lighting installations shall comply with NFPA 70.
k. The use, type, and arrangement of temporary heating equipment shall be in accordance with Section 1403 of the IFC.
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 19
l. Do not refuel internal-combustion-powered construction equipment while in operation. Locate so that exhaust does not discharge against combustible material. Exhaust shall be piped outside of the building, shall be directed away from, and shall be located at 10 ft minimum from air intakes and operable windows. Store fuel in an approved area outside the building.
m. For roofing operations, use of heat-producing systems or other ignition sources shall be in accordance with IFC Section 1417 and Chapter 26.
n. The Contractor shall provide and maintain fire extinguishers that have current service inspection tags. There shall be at least one approved portable fire extinguisher in the worksite in accordance with IFC Section 906, and at each stairway on floor levels where combustible materials have accumulated and in every storage and construction shed. Additional portable fire extinguishers shall be provided where special hazards exist, including, but not limited to, storage and use of flammable or combustible liquids.
o. The Owner’s Project Manager will initiate Owner outage notification procedures and will coordinate activities with contractors and designated Facilities Trades staff responsible for the fire protection and fire alarm systems. The Contractor shall notify the Owner’s Project Manager at least ten working days in advance of the shutdown of utilities.
p. For areas under renovation, the Owner’s “Fire Alarm and Fire Protection Outage Procedures” shall be referenced in the Plan and implemented at all times.
q. The Plan shall address impairment procedures with a focus on reducing accidental fire alarm activation associated with demolition, renovation, and new construction.
r. The Contractor shall notify the Owner’s EH&S in advance of all planned or emergency impairments / outages so that these activities are documented with the Owner’s property insurance carrier.
F. Fire Department Access:
1. Exterior access for Fire Department apparatus and vehicles shall be maintained for the duration of the project. Alterations to Fire Department access shall be incorporated in the Plan.
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 20
2. Fire hydrants and building Fire Department connections shall remain accessible. Alterations and restrictions in access to hydrants or Fire Department connections shall be incorporated into the Plan.
3. An unobstructed path from the exterior through the interior of the building to the work zone shall be maintained for firefighter access. Provisions may be necessary for areas where secured access is required. If applicable, this shall be addressed in the Plan.
G. Fire Protection Testing System:
1. Fire protection and fire alarm system testing subsequent to modifications and prior to acceptance shall be performed in accordance with applicable NFPA standards. Tests shall be documented using appropriate acceptance forms, as completed by the installing contractor and witnessed by both the Owner and authority having jurisdiction personnel.
2. The Contractor shall notify the Owner’s EH&S when acceptance testing will be performed by the authority having jurisdiction (or FM Global). Provide the Owner’s EH&S with copies of test forms and test reports.
3. Applicable trades staff shall be involved with outages associated with acceptance testing and shall also be present to witness testing, especially when it involves specialized fire protection systems, components, or devices.
H. Means of Egress:
1. Whenever practical, at least two means of egress should be maintained from the work zone.
2. For the occupied areas of the building, the minimum number of required egress paths must be maintained and kept free of any obstructions. Phase construction as necessary to ensure that exits are not obstructed or reduced in width. If exits must be obstructed during construction, provide alternate exit routes during each phase of construction and identify the alternate routes on the construction drawings.
3. Directional signs or revisions to existing EXIT signage may be needed to direct occupants around the work zone to the new or existing egress path.
Alterations to directional signage and egress paths for building occupants must be addressed in the Plan. Existing Evacuation Maps may need to be altered to reflect these changes in projects of longer duration.
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 21
1.33 SUPPLEMENTAL SAFETY INSTRUCTIONS
A. Do not block any building entrances or exits. Use a safe method to lower debris directly to trucks or approved containers. Provide suitable barricades and warning signs near work areas to protect the Owner's staff and students.
B. Use appropriate safety harnesses, temporary guardrails, scaffolding, or other measures to ensure the safety of workers, in accordance with OSHA and other applicable safety regulations. Compliance with OSHA and all other safety laws and regulations is the exclusive responsibility of the Contractor, Subcontractors, suppliers, consultants, and servants.
C. Dispose all material waste and associated debris in a legal manner, off the site, as required by State and Local ordinances. Conduct waste and debris in an acceptable manner without disrupting building operations or exposing the public to danger. Use covered carts to move debris from work areas to the collection area and remove from the site.
D. Provide a fire-watch detail during and for 60 min. following all on-site welding and other hot work.
E. If any material(s) contain volatile organic compounds (VOCs) or if the demolition involves any release of debris, dust, or fumes into the atmosphere, the Contractor must take all necessary precautions to limit exposure to these materials and debris and their fumes. Ventilate the work area properly, dispose all contaminated debris (i.e., rags, towels, brushes, etc.), and avoid, protect, or shut down appropriate air intakes. Promptly and thoroughly clean all spillage and contamination. Keep all containers and packaging sealed completely when not in use.
1.34 GENERAL WORKMANSHIP
A. Obtain written approval from the Engineer to work in rain, snow, or temperatures below 40°F or above 90°F unless temporary protection measures, approved in advance by the Owner, are installed prior to beginning the work. Maintain the temporary protection until the work may be exposed to the weather, per the manufacturer’s written instructions and the Engineer's approval. Do not install any work in the presence of moisture. Comply with all applicable recommendations by the manufacturers of all equipment and materials for workmanship and handling, except as modified in these Specifications. Use special application procedures recommended by the manufacturer when working in high humidity and wind.
Observe more-stringent restrictions from manufacturers or industry standards that may apply.
George Mason University Contract Considerations and Special Conditions Fairfax, VA 010200 - 22
B. Do not dilute materials unless required by the manufacturer’s installation instructions. Keep containers closed, except when removing materials from them. Stir all liquid components before each use to disperse solids as recommended by the manufacturer. Use pump cans to dispense cleaning fluids or stripping agents; do not dip rags into solvents. Use only clean containers for dispensing or transporting.
Protect materials from heat, sparks, and flame. Volatile solvents can produce explosive and poisonous mixtures; provide adequate ventilation and protection.
Follow all manufacturers’ safety recommendations, cautions, and warnings.
C. Use clean gloves and tools free of dirt, grease, and asphaltic materials. Remove all tools, buckets, and materials from the work area at the end of each workday. Do not allow any debris, construction or wind blown, to become collected in any completed areas.
D. Notify the Engineer and halt all work promptly if an unusual or unsafe condition is discovered.
E. Workmanship shall comply…