This document is an Executable Scope of Work for the replacement of the existing roof, mold remediation, and interior repairs at building A-58 at the Naval Station in Norfolk, Virginia. The project requires the contractor to provide supervision, labor, material, and equipment to demolish approximately 5,000 square feet of the existing asphalt shingle roof and 60% of the plywood sheathing, as well as remove damaged and moldy interior finishes. The new work involves installing a 5,000 square foot wood-shake look architectural asphalt shingle roof, replacing ceiling and wall materials, and providing new flooring and finishes. The work must be performed in accordance with industry standards, local/state/federal codes, and the Unified Facilities Criteria. The project is soliciting proposals from 8(a) Multiple Award Construction Contract (MACC) contractors in the Hampton Roads area of Virginia under Solicitation Number N4008524F2746.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
eProjects No: 1733381
Executable Scope of Work Building A-58 Roof Replacement and Interior Repairs at the
Naval Station, Norfolk, Virginia
PREPARED BY:
NAVFAC MID-ATLANTIC
Facilities Engineering and Acquisition Division
Public Works Department
Norfolk, Virginia
SUBMITTED BY:
Design Manager: Richard Corbin
Architectural: Richard Corbin
Date: May 1, 2024
APPROVED BY:
Project Management & Engineering Director: John C. Miller, P.E.
Design Director: James M. Smith, R.A.
For Commander, NAVFAC MID-ATLANTIC:
Date:
A‐58 Replace Roof Executable Scope
PWD Norfolk, Facilities Engineering and Acquisition Division Form Version 2023.04.25 Page 1 of 21 eProjects Work Order No: 1733381
Maximo SR Number: 21544634
Building: A-58
Project Title: Replace Roof and Interior Repairs
Customer:
Commander, Navy Installations Command (CNIC)
FMD Hai Huynh hai.huynh.civ@us.navy.mil 757‐341‐1196 APWO LT. Chris Dunkelberg christopher.j.dunkelberg.mil@us.navy.mil 757‐341‐0504 Installation Director Shannon Lowe shannon.m.lowe.naf@us.navy.mil 757‐444‐3056
Scope By: Architectural / DM Richard Corbin richard.corbin19.civ@us.navy.mil 757‐341‐0208
Date:
May 1, 2024
1. Points of Contact:
FEAD Contracting Officer: Natalie Augsburger natalie.g.augsburger.civ@us.navy.mil
Facility Maintenance Specialist:
(FMS) A-58
Juanita Smith-Simmons juanita.f.smith‐simmons.civ@us.navy.mil
2. General Description:
Contractor must provide supervision, labor, material, and equipment required to perform all work for the following project: Building A-58 was constructed in 2009 as a residential type of facility used by the Child Youth Program as a group home for youth ages 6-18 years of age. (Norfolk 24/7 CDC) The original asphalt shingle roof and sheathing has sustained damage & deterioration over the years which has led to water intrusion into the building causing mold and water damage to existing finishes. Due to the visible mold in areas of the building, the facility has been deemed unsafe for children until the mold is completely remediated. This project will prepare construction documents for the replacement of the existing roofing system and mold remediation. Refer to section 7 “Project Overview and Work Requirements” for additional information.
All work must be performed in accordance with, but not limited to the following:
Standard industry practices.
Applicable local, state, federal codes, laws, and regulations.
The Unified Facilities Criteria.
3. Location:
The work is located at building A-58, Naval Station Norfolk, Virginia, approximately as indicated. The exact location will be shown by the Contracting Officer. Refer to attachment 8.1 Location map of Naval Station Norfolk – Building A-58.
A-58 Replace Roof Executable Scope eProjects No.: 1733381
Form Version 2023.04.25 Page 2 of 21
4. Special Scheduling Requirements / Work Procedures:
4.1 Utility Services will be in accordance with the procedures in FAR 41.202.
4.2 The work must be performed during regular Government working hours. Regular working hours must consist of an 8 1/2-hour period established by the Contracting Officer, Monday through Friday, excluding Government holidays.
4.3 The Contractor will be working around an existing building which is unoccupied. Do not enter the building without prior approval of the Contracting Officer.
4.4 The existing building and its contents must be always kept secure. Provide dust covers or protective enclosures to protect existing work and contents that remains.
4.5 Damage caused by construction operations must be repaired, patched and/or replaced to match adjacent areas to the satisfaction of the Contracting Officer at no additional cost to the Government.
4.6 Permission to interrupt any Activity roads, railroads, or utility services must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
4.7 When removing the existing roofing system, remove only as much roofing as can be recovered by the end of the workday, unless approved otherwise by the Contracting Officer. Do not attempt to open the roof covering system in threatening weather. Reseal all openings prior to suspension of work the same day.
4.8 The existing fire suppression system must remain operational during construction.
4.9 The Contractor must perform and provide a mold testing report before and after construction.
4.10 Contractor to investigate HVAC lines above kitchen for leakage and notify the Contracting
Officer of investigated findings.
5. Safety:
5.1 All work must be conducted in a safe manner and must comply with all requirements of the U.S.
Army Corps of Engineers Safety Health Requirements Manual EM-385-1-1.
5.2 Contractor must submit an Accident Prevent Plan (APP), and Activity Hazard Analysis (AHA) for approval by the Contracting Officer. Submit the APP and AHA to the Contracting Officer 15 calendar days prior to the pre-performance conference for acceptance.
6. Submittals:
6.1 The Contractor must submit the following documents required for government approval, prior to the start of any construction activities:
Manufacturer’s Product Data
Form Version 2023.04.25 Page 3 of 21
6.2 The Contractor must submit all required data together for the following roofing sections of the roofing IDIQ contract:
09 29 00 Gypsum Board 09 65 00 Resilient Flooring 09 90 00 Paints and Coatings
7. Project Overview and Work Requirements:
7.1 Project Overview:
a. This project will prepare construction documents for the replacement of the existing roofing system and mold remediation. The original asphalt shingle roof and sheathing has sustained damage & deterioration leading to water intrusion that is causing mold and water damage.
7.2 Demolition – Work Requirements
a. Demolish approximately 5,000 square feet of existing asphalt shingle roof, roofing felt, and approximately 60% of plywood sheathing.
b. Demolish approximately 80 linear feet of existing ridge vent complete.
c. Demolish approximately 160 linear feet of existing gutters complete.
d. Demolish approximately 100 linear feet of downspouts and splash blocks complete. Clean and snake each drain at bottom of downspouts to storm water tie-in (for bidding purposes assume a total of 6 drains).
e. Remove approximately 3,700 square feet of existing ceiling batt insulation complete. Remove and salvage approximately 1,200 square feet of existing plywood flooring in attic as required for insulation replacement.
f. Remove approximately 1,500 square feet of existing gypsum board ceiling in water damaged areas.
g. Remove approximately 500 square feet of existing gypsum board and insulation at wall damaged by water in Room 102.
h. Demolish approximately 185 square feet of existing wood flooring. Demolish existing quarter round at kitchen counters (for bidding purposes assume 36 linear feet). Demolish existing wall base where existing wood flooring is demolished (for bidding purposes assume 20 linear feet).
i. Remediate and treat all ceilings for mold in water damaged areas.
j. Disconnect, remove, and salvage existing light fixtures HVAC registers, fire alarm/sprinkler equipment, and cameras as required for ceiling repairs.
k. Disconnect, remove, and salvage exterior cameras and lighting as required to accommodate roof replacement.
Form Version 2023.04.25 Page 4 of 21
l. Remove, store, and protect existing furniture as required to accommodate repairs.
7.3 New Work – Work Requirements
a. Provide approximately 5,000 square feet of wood-shake look architectural asphalt shingle roof, leak & deck protection membrane, and approximately 60% of plywood sheathing at thickness to match existing adjacent. (for bidding purposes assume 3/4" plywood sheathing).
b. Provide approximately 80 linear feet of ridge vent.
c. Provide approximately 160 linear feet of galvanized steel gutters with white enamel coating and continuous leaf guard.
d. Provide approximately 100 linear feet of galvanized steel downspouts with white enamel coating.
e. Provide approximately 3,700 square feet of ceiling batt insulation R-38 minimum. Re-install salvaged plywood flooring in attic after insulation install.
f. Provide approximately 1,500 square feet of gypsum board ceiling in water damaged areas.
Thickness of gypsum board ceiling must match existing adjacent (for bidding purposes assume 5/8” gypsum board ceiling). Prep entire ceiling footprint in spaces of water damaged areas and apply one prime coat and two finish coats of paint to match existing, finished to level 5 standard (for biding purposes assume 2,200 square feet of prep, prime, and paint).
g. Provide approximately 500 square feet of gypsum board and insulation wall in Room 102.
Thickness of gypsum board must match existing adjacent (for bidding purposes assume 5/8” gypsum board). Prep entire wall repaired and apply one prime coat and two finish coats of paint to match existing, finished to level 5 standard. (for biding purposes assume 500 square feet of prep, prime, and paint).
h. Provide approximately 185 square feet of resilient LVT flooring. Basis of design: Patcraft Local
Reserve 1592V or equal. Provide transition strips where new flooring meets existing. Provide quarter rounds to match existing (for bidding purposes assume 36 linear feet). Provide wall base to match existing (for bidding purposes assume 20 linear feet).
i. Reconnect, and reinstall salvaged light fixtures, HVAC registers, fire alarm/sprinkler equipment, and cameras after ceiling repair.
j. Reconnect and install salvaged exterior cameras and lighting after roof replacement.
k. Provide concrete splash blocks.
l. Re-install existing furniture.
Form Version 2023.04.25 Page 5 of 21
7.4 The Contactor must dispose of all existing demolished / removed material off base and must completely clean up the job site daily at the end of each workday.
8. Attachments:
8.1 Location map of Naval Station Norfolk – Building A-58.
8.2 Overall Floor Plan
8.3 Overall Roof Plan
8.4 Photographs
Form Version 2023.04.25 Page 6 of 21
8.1 Location map of Naval Station Norfolk – Building A-58
LOCATION MAP
NOT TO SCALE
Form Version 2023.04.25 Page 7 of 21
8.2 Overall Floor Plan
Form Version 2023.04.25 Page 8 of 21
8.3 Overall Roof Plan
Form Version 2023.04.25 Page 9 of 21
8.4 Project Photographs:
A58 - Photo # 1
View of water damage from fasteners/nails of the plywood to the steel purlins.
Approximately 60% of the plywood shows signs of damage/mold.
A58 - Photo # 2
View of existing insulation to be removed and replaced.
The building structure is steel framed construction with steel trusses and purlins.
Form Version 2023.04.25 Page 10 of 21
A58 - Photo # 3
View of the existing roof’s asphalt shingles on felt on ½” plywood. The existing felt overlap and plywood edge thickness is visible at the roof ridge where the roof height changes.
A58 - Photo # 4
View of the existing damaged asphalt shingles on west side roofing of building A-58.
Form Version 2023.04.25 Page 11 of 21
A58 - Photo # 5
View of existing south side of the roof structure from the attic.
A58 - Photo # 6
View of existing roof vent from the attic.
Form Version 2023.04.25 Page 12 of 21
A58 - Photo # 7
View of existing east side of A-58. Overall, building A-58 has a recommended full roof, gutter, downspout, fascia, and soffit replacement.
A58 - Photo # 8
View of existing southeast corner of A-58 and downspouts, gutters, and roofing.
Form Version 2023.04.25 Page 13 of 21
A58 - Photo # 9
View of existing north east corner of A-58 and downspouts, gutters, splash blocks, and roofing.
A58 - Photo # 10
View of existing west side of A-58 and downspouts, gutters, splash blocks, and roofing.
Form Version 2023.04.25 Page 14 of 21
A58 - Photo # 11
View of existing ceiling damage in Room 104.
A58 - Photo # 12
View of existing ceiling damage in Room 104.
Form Version 2023.04.25 Page 15 of 21
A58 - Photo # 13
View of existing ceiling damage in Room 105.
A58 - Photo # 14
View of existing ceiling damage in Room 106. Disconnect, remove, and salvage existing HVAC register for reinstallation after ceiling work.
Form Version 2023.04.25 Page 16 of 21
A58 - Photo # 15
View of existing ceiling damage in Room 106. Disconnect, remove, and salvage existing light fixture for
A58 - Photo # 16
View of existing wall damage in Room 102.
Form Version 2023.04.25 Page 17 of 21
A58 - Photo # 17
View of existing ceiling damage in Room 102. Disconnect, remove, and salvage existing security camera for reinstallation after ceiling work.
A58 - Photo # 18
View of existing ceiling damage in Room 102.
Form Version 2023.04.25 Page 18 of 21
A58 - Photo # 19
A58 - Photo # 20
Form Version 2023.04.25 Page 19 of 21
A58 - Photo # 21
View of existing ceiling damage in Room 102. Disconnect, remove, and salvage HVAC register and existing light fixture for reinstallation after ceiling work.
A58 - Photo # 22
View of existing ceiling damage in Room 101. Disconnect, remove, and salvage existing light fixture for
Form Version 2023.04.25 Page 20 of 21
A58 - Photo # 23
View of existing ceiling damage in Room 101.
A58 - Photo # 24
View of existing ceiling damage in Room 116. Disconnect, remove, and salvage existing HVAC register for
Form Version 2023.04.25 Page 21 of 21
A58 - Photo # 25
View of existing floor damage in Room 111.
A58 - Photo # 25
View of existing ceiling damage in Room 112.
Building A-58 Roof Replacement and Interior Repairs 1733381
PROJECT TABLE OF CONTENTS
DI VI SI ON 09 - FI NI SHES
09 29 00 GYPSUM BOARD
09 65 00 RESILIENT FLOORING
09 90 00 PAINTS AND COATINGS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
THIS PAGE INTENTIONALLY LEFT BLANK
PROJECT TABLE OF CONTENTS Page 2
SECTION 09 29 00
GYPSUM BOARD
08/ 16, CHG 4: 02/ 20
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM C475/C475M (2017; R 2022) Standard Specification for Joint Compound and Joint Tape for Finishing Gypsum Board
ASTM C514 (2004; R 2020) Standard Specification for Nails for the Application of Gypsum Board
ASTM C840 (2020) Standard Specification for Application and Finishing of Gypsum Board
ASTM C954 (2022) Standard Specification for Steel Drill Screws for the Application of Gypsum Panel Products or Metal Plaster Bases to Steel Studs from 0.033 in. (0.84 mm) to
0.112 in. (2.84 mm) in Thickness
ASTM C1002 (2022) Standard Specification for Steel Self-Piercing Tapping Screws for the Application of Gypsum Panel Products or Metal Plaster Bases to Wood Studs or Steel Studs
ASTM C1047 (2019) Standard Specification for Accessories for Gypsum Wallboard and Gypsum Veneer Base
ASTM C1396/C1396M (2017) Standard Specification for Gypsum Board
ASTM C1629/C1629M (2023) Standard Classification for Abuse-Resistant Nondecorated Interior Gypsum Panel Products and Fiber-Reinforced Cement Panels
ASTM D1037 (2012) Evaluating Properties of Wood-Base Fiber and Particle Panel Materials
ASTM D2394 (2017) Standard Test Methods for Simulated Service Testing of Wood and Wood-Base Finish Flooring
ASTM D3273 (2021) Standard Test Method for Resistance to Growth of Mold on the Surface of
SECTION 09 29 00 Page 1
Interior Coatings in an Environmental Chamber
ASTM D5420 (2016) Standard Test Method for Impact Resistance of Flat, Rigid Plastic Specimen by Means of a Strike Impacted by a Falling Weight (Gardner Impact)
ASTM E695 (2022) Standard Test Method of Measuring Relative Resistance of Wall, Floor, and Roof Construction to Impact Loading
CALIFORNIA DEPARTMENT OF PUBLIC HEALTH (CDPH)
CDPH SECTION 01350 (2017; Version 1.2) Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources using Environmental Chambers
FM GLOBAL (FM)
FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/
GREEN SEAL (GS)
GS-36 (2013) Adhesives for Commercial Use
GYPSUM ASSOCIATION (GA)
GA 214 (2010) Recommended Levels of Gypsum Board Finish
GA 216 (2016) Application and Finishing of Gypsum Panel Products
SCIENTIFIC CERTIFICATION SYSTEMS (SCS)
SCS SCS Global Services (SCS) Indoor Advantage
SOUTH COAST AIR QUALITY MANAGEMENT DISTRICT (SCAQMD)
SCAQMD Rule 1168 (2017) Adhesive and Sealant Applications
UNDERWRITERS LABORATORIES (UL)
UL 2818 (2022) GREENGUARD Certification Program For Chemical Emissions For Building Materials, Finishes And Furnishings
UL Fire Resistance (2014) Fire Resistance Directory
1.2 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SECTION 09 29 00 Page 2
SD-03 Product Data
Abuse Resistant Gypsum Board
Accessories
Submit for each type of gypsum board and for cementitious backer units.
Gypsum Board
Recycled Content for Gypsum Board
Recycled Content for Paper Facing and Gypsum Cores
VOC Content of Joint Compound
SD-07 Certificates
Asbestos Free Materials; G
Certify that gypsum board types, gypsum backing board types, cementitious backer units, and joint treating materials do not contain asbestos.
Indoor Air Quality for Gypsum Board
Indoor Air Quality for Non-aerosol Adhesives
Indoor Air Quality for Aerosol Adhesives
SD-08 Manufacturer's Instructions
Safety Data Sheets
SD-10 Operation and Maintenance Data
Manufacturer Maintenance Instructions
1.3 CERTIFICATIONS
1.3.1 Indoor Air Quality Certifications
Submit required indoor air quality certifications in one submittal package.
1.3.1.1 Ceiling and Wall Systems
Provide products certified to meet indoor air quality requirements by UL 2818 (Greenguard) Gold, SCS Global Services Indoor Advantage Gold or provide certification or validation by other third-party program that products meet the requirements of this Section. Provide current product certification documentation from certification body. When product does not have certification, provide validation that product meets the indoor air quality product requirements cited herein.
1.3.1.2 Adhesives and Sealants
Provide products certified to meet indoor air quality requirements by UL 2818 (Greenguard) Gold, SCS Global Services Indoor Advantage Gold or
SECTION 09 29 00 Page 3 provide certification or validation by other third-party program that products meet the requirements of this Section. Provide current product certification documentation from certification body. When product does not have certification, provide validation that product meets the indoor air quality product requirements cited herein.
1.4 DELIVERY, STORAGE, AND HANDLING
1.4.1 Delivery
Deliver materials in the original packages, containers, or bundles with each bearing the brand name, applicable standard designation, and name of manufacturer, or supplier.
1.4.2 Storage
Keep materials dry by storing inside a sheltered building. Where necessary to store gypsum board and cementitious backer units outside, store off the ground, properly supported on a level platform, and protected from direct exposure to rain, snow, sunlight, and other extreme weather conditions. Provide adequate ventilation to prevent condensation. Store per manufacturer's recommendations for allowable temperature and humidity range. Do not store gypsum wallboard with materials which have high emissions of volatile organic compounds (VOCs) or other contaminants. Do not store panels near materials that may offgas or emit harmful fumes, such as kerosene heaters, fresh paint, or adhesives. Do not use materials that have visible moisture or biological growth.
1.4.3 Handling
Neatly stack gypsum board and cementitious backer units flat to prevent sagging or damage to the edges, ends, and surfaces.
1.5 QUALIFICATIONS
Furnish type of gypsum board work specialized by the installer with a minimum of 3 years of documented successful experience.
1.6 SCHEDULING
The gypsum wallboard must be taped, finished and primed before the installation of the highly-emitting materials.
Commence application only after the area scheduled for gypsum board work is completely weathertight. The heating, ventilating, and air-conditioning systems must be complete and in operation prior to application of the gypsum board. If the mechanical system cannot be activated before gypsum board is begun, the gypsum board work may proceed in accordance with an approved plan to maintain the environmental conditions specified below. Apply gypsum board prior to the installation of finish flooring and acoustic ceiling.
1.7 ENVIRONMENTAL REQUIREMENTS
Do not expose the gypsum board to excessive sunlight prior to gypsum board application. Maintain a continuous uniform temperature of not less than 50 degrees F and not more than 80 degrees F for at least one week prior to the application of gypsum board work, while the gypsum board application
SECTION 09 29 00 Page 4 is being done, and for at least one week after the gypsum board is set.
Shield air supply and distribution devices to prevent any uneven flow of air across the plastered surfaces. Provide ventilation to exhaust moist air to the outside during gypsum board application, set, and until gypsum board jointing is dry. In glazed areas, keep windows open top and bottom or side to side 3 to 4 inches. Reduce openings in cold weather to prevent freezing of joint compound when applied. For enclosed areas lacking natural ventilation, provide temporary mechanical means for ventilation.
In unglazed areas subjected to hot, dry winds or temperature differentials from day to night of 20 degrees F or more, screen openings with cheesecloth or similar materials. Avoid rapid drying. During periods of low indoor humidity, provide minimum air circulation following gypsum boarding and until gypsum board jointing complete and is dry.
1.8 FIRE RESISTIVE CONSTRUCTION
Comply with specified fire-rated assemblies for design numbers indicated per UL Fire Resistance or FM APP GUIDE.
PART 2 PRODUCTS
2.1 MATERIALS
Conform to specifications, standards and requirements specified. Provide gypsum board types, gypsum backing board types, cementitious backing units, and joint treating materials manufactured from asbestos free materials only. Submit Safety Data Sheets and manufacturer maintenance instructions for gypsum materials including adhesives.
2.1.1 Gypsum Board
ASTM C1396/C1396M . Gypsum board must contain a minimum of 5 percent post-consumer recycled content, or a minimum of 20 percent post-industrial recycled content. Provide data identifying percentage of recycled content for gypsum board. Paper facings must contain a minimum of 100 percent recycled paper content. Gypsum cores must contain a minimum of 95 percent post-industrial recycled gypsum content. Provide data identifying percentage of recycled content for paper facing and gypsum cores. Provide gypsum wall board and panels meeting the emissions requirements of CDPH SECTION 01350 (limit requirements for either office or classroom spaces regardless of space type). Provide certification or validation of indoor air quality for gypsum board.
2.1.1.1 Regular
48 inch wide, 5/8 inch thick, tapered edges.
2.1.1.2 Mold Resistant / Anti-Microbial Gypsum
ASTM D3273. 48 inch wide, 5/8 inch thick, tapered edges.
2.1.2 Gypsum Backing Board
ASTM C1396/C1396M , gypsum backing board must be used as a base in a multilayer system.
2.1.2.1 Regular
48 inch wide, 5/8 inch thick, square edges.
SECTION 09 29 00 Page 5
2.1.3 Abuse Resistant Gypsum Board
48 inch wide, 5/8 inch thick, tapered edges.
Reinforced gypsum panel with imbedded fiber mesh or lexan backing tested in accordance with the following tests. Hard body impact test must attain a Level 2 performance in accordance with ASTM C1629/C1629M . Provide fasteners that meet manufacturer requirements and specifications stated within this section.
2.1.3.1 Soft Body Impact Test
ASTM E695 or ASTM D2394 for impact penetration and deformation. ASTM E695 using a 60 lb leather bag filled with steel pellets, resisting no less than 300 ft. lb. cumulative impact energy before failure or ASTM D2394 using
5.5 inch hemispherical projectile resisting no less than 264 ft. lb.
before failure. Provide test specimen stud spacing a minimum 16 inch on center.
2.1.3.2 Hard Body Impact Test
Comply with hard body impact test in accordance with ASTM C1629/C1629M Classification Level 2.
2.1.3.3 Surface Abrasion Test
Comply with test surface abrasion test in accordance with ASTM C1629/C1629M .
2.1.3.4 Indentation Test
ASTM D5420 or ASTM D1037 for indentation resistance. ASTM D5420 using a 32 oz weight with a 5/8 inch hemispherical impacting head dropped once 3 feet creating not more than 0.137 inch indentation or ASTM D1037 using no less than 470 lb weight applied to the 0.438 inch diameter ball to create not more than a 0.0197 inch indentation depth.
2.1.4 Joint Treatment Materials
ASTM C475/C475M. Product must be low emitting VOC types with VOC limits not exceeding 50 g/L. Provide data identifying VOC content of joint compound. Use all purpose joint and texturing compound containing inert fillers and natural binders, including lime compound. Pre-mixed compounds must be free of antifreeze, vinyl adhesives, preservatives, biocides and other slow releasing compounds.
2.1.4.1 Embedding Compound
Specifically formulated and manufactured for use in embedding tape at gypsum board joints and compatible with tape, substrate and fasteners.
2.1.4.2 Finishing or Topping Compound
Specifically formulated and manufactured for use as a finishing compound.
2.1.4.3 All-Purpose Compound
Specifically formulated and manufactured to serve as both a taping and a finishing compound and compatible with tape, substrate and fasteners.
SECTION 09 29 00 Page 6
2.1.4.4 Setting or Hardening Type Compound
Specifically formulated and manufactured for use with fiber glass mesh tape.
2.1.4.5 Joint Tape
Use cross-laminated, tapered edge, reinforced paper, or fiber glass mesh tape recommended by the manufacturer.
2.1.5 Fasteners
2.1.5.1 Nails
ASTM C514.
2.1.5.2 Screws
ASTM C1002, Type "G", Type "S" or Type "W" steel drill screws for fastening gypsum board to gypsum board, wood framing members and steel framing members less than 0.033 inch thick. ASTM C954 steel drill screws for fastening gypsum board to steel framing members 0.033 to 0.112 inch thick. Provide cementitious backer unit screws with a polymer coating.
2.1.5.3 Staples
No. 16 USS gage flattened galvanized wire staples with 7/16 inch wide crown outside measurement and divergent point for base ply of two-ply gypsum board application. Use as follows:
Length of Legs Thickness of Gypsum Board
1-1/8 inches 1/2 inch
1-1/4 inches 5/8 inch
2.1.6 Adhesives
Provide non-aerosol adhesive products used on the interior of the building (defined as inside of the weatherproofing system) meeting either emissions requirements of CDPH SECTION 01350 (limit requirements for either office or classroom spaces regardless of space type) or VOC content requirements of SCAQMD Rule 1168 . Provide aerosol adhesive products used on the interior of the building (defined as inside of the weatherproofing system) meeting either emissions requirements of CDPH SECTION 01350 (limit requirements for either office or classroom spaces regardless of space type) or VOC content requirements of GS-36. Provide certification or validation of indoor air quality for non-aerosol adhesives applied on the interior of the building (inside of the weatherproofing system). Provide certification or validation of indoor air quality for aerosol adhesives used on the interior of the building (inside of the weatherproofing system).
2.1.6.1 Adhesive for Fastening Gypsum Board to Metal Framing
Not permitted.
SECTION 09 29 00 Page 7
2.1.6.2 Adhesive for Fastening Gypsum Board to Wood Framing
Not permitted.
2.1.6.3 Adhesive for Laminating
Not permitted.
2.1.7 Gypsum Studs
Provide one inch minimum thickness and 4 inch minimum width. Studs may be of one inch thick gypsum board or multilayers fastened to required thickness. Conform to ASTM C1396/C1396M for material and GA 216 for installation.
2.1.8 Accessories
ASTM C1047. Fabricate from corrosion protected steel or plastic designed for intended use. Accessories manufactured with paper flanges are not acceptable. Flanges must be free of dirt, grease, and other materials that may adversely affect bond of joint treatment. Provide prefinished or job decorated materials.
2.1.9 Water
Provide clean, fresh, and potable water.
PART 3 EXECUTION
3.1 EXAMINATION
3.1.1 Framing and Furring
Verify that framing and furring are securely attached and of sizes and spacing to provide a suitable substrate to receive gypsum board and cementitious backer units. Verify that all blocking, headers and supports are in place to support plumbing fixtures and to receive soap dishes, grab bars, towel racks, and similar items. Do not proceed with work until framing and furring are acceptable for application of gypsum board and cementitious backer units.
3.1.2 Gypsum Board and Framing
Verify that surfaces of gypsum board and framing to be bonded with an adhesive are free of dust, dirt, grease, and any other foreign matter. Do not proceed with work until surfaces are acceptable for application of gypsum board with adhesive.
3.1.3 Building Construction Materials
Do not install building construction materials that show visual evidence of biological growth.
3.2 APPLICATION OF GYPSUM BOARD
Apply gypsum board to framing and furring members in accordance with ASTM C840 or GA 216 and the requirements specified. Apply gypsum board with separate panels in moderate contact; do not force in place. Stagger end joints of adjoining panels. Neatly fit abutting end and edge joints.
SECTION 09 29 00 Page 8
Use gypsum board of maximum practical length; select panel sizes to minimize waste. Cut out gypsum board to make neat, close, and tight joints around openings. In vertical application of gypsum board, provide panels in lengths required to reach full height of vertical surfaces in one continuous piece. Lay out panels to minimize waste; reuse cutoffs whenever feasible. Surfaces of gypsum board and substrate members may not be bonded together with an adhesive. Treat edges of cutouts for plumbing pipes, screwheads, and joints with water-resistant compound as recommended by the gypsum board manufacturer. Minimize framing by floating corners with single studs and drywall clips. Install 5/8 inch gypsum ceiling board over framing at 24 inch on center. Provide type of gypsum board for use in each system specified herein as indicated.
3.2.1 Semi-Solid Gypsum Board Partitions
Provide in accordance with ASTM C840, System IV or GA 216 .
3.2.2 Solid Gypsum Board Partitions
Provide in accordance with ASTM C840, System V or GA 216 .
3.2.3 Application of Gypsum Board to Steel Framing and Furring
Apply in accordance with ASTM C840, System VIII or GA 216 .
3.2.4 Arches and Bending Radii
Apply gypsum board in accordance with ASTM C840, System IX or GA 216 .
3.2.5 Control Joints
Install expansion and contraction joints in ceilings and walls in accordance with ASTM C840, System XIII or GA 216 .
3.2.6 Application of Abuse Resistant Gypsum Board
Apply in accordance with applicable system of ASTM C840 as specified or GA 216 . Follow manufacturers written instructions on how to cut, drill and attach board.
3.3 FINISHING OF GYPSUM BOARD
Tape and finish gypsum board in accordance with ASTM C840, GA 214 and GA 216 . Finish plenum areas above ceilings to Level 1 in accordance with GA 214 . Finish water resistant gypsum backing board, ASTM C1396/C1396M , to receive ceramic tile to Level 2 in accordance with GA 214 . Finish walls and ceilings to receive a heavy-grade wall covering or heave textured finish before painting to Level 3 in accordance with GA 214 .
Finish walls and ceilings without critical lighting to receive flat paints, light textures, or wall coverings to Level 4 in accordance with GA 214 . Unless otherwise specified, finish all gypsum board walls, partitions and ceilings to Level 5 in accordance with GA 214 . Provide joint, fastener depression, and corner treatment. Tool joints as smoothly as possible to minimize sanding and dust. Do not use self-adhering fiber glass mesh tape with conventional drying type joint compounds; use setting or hardening type compounds only. Provide treatment for water-resistant gypsum board as recommended by the gypsum board manufacturer. Protect workers, building occupants, and HVAC systems from gypsum dust.
SECTION 09 29 00 Page 9
3.3.1 Uniform Surface
Wherever gypsum board is to receive eggshell, semigloss or gloss paint finish, or where severe, up or down lighting conditions occur, finish gypsum wall surface in accordance to GA 214 Level 5. In accordance with GA 214 Level 5, apply a thin skim coat of joint compound to the entire gypsum board surface, after the two-coat joint and fastener treatment is complete and dry.
3.4 SEALING
Seal openings around pipes, fixtures, and other items projecting through gypsum board and cementitious backer units as specified in Section 07 92 00 JOINT SEALANTS. Apply material with exposed surface flush with gypsum board or cementitious backer units.
3.5 PATCHING
Patch surface defects in gypsum board to a smooth, uniform appearance, ready to receive finishes.
-- End of Section --
SECTION 09 29 00 Page 10
SECTION 09 65 00
RESILIENT FLOORING
08/ 10, CHG 3: 08/ 18
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D4078 (2002; R 2015) Water Emulsion Floor Polish
ASTM E648 (2019a) Standard Test Method for Critical Radiant Flux of Floor-Covering Systems Using a Radiant Heat Energy Source
ASTM F710 (2022) Standard Practice for Preparing Concrete Floors to Receive Resilient Flooring
ASTM F1482 (2021) Standard Practice for Installation and Preparation of Panel Type Underlayments to Receive Resilient Flooring
ASTM F1869 (2023) Standard Test Method for Measuring Moisture Vapor Emission Rate of Concrete Subfloor Using Anhydrous Calcium Chloride
ASTM F2170 (2019a) Standard Test Method for Determining Relative Humidity in Concrete Floor Slabs Using in situ Probes
CALIFORNIA DEPARTMENT OF PUBLIC HEALTH (CDPH)
CDPH SECTION 01350 (2017; Version 1.2) Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources using Environmental Chambers
GREEN SEAL (GS)
GS-36 (2013) Adhesives for Commercial Use
SCIENTIFIC CERTIFICATION SYSTEMS (SCS)
SCS SCS Global Services (SCS) Indoor Advantage
SOUTH COAST AIR QUALITY MANAGEMENT DISTRICT (SCAQMD)
SCAQMD Rule 1168 (2017) Adhesive and Sealant Applications
SECTION 09 65 00 Page 1
UNDERWRITERS LABORATORIES (UL)
UL 2818 (2022) GREENGUARD Certification Program For Chemical Emissions For Building Materials, Finishes And Furnishings
1.2 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Resilient Flooring and Accessories; G
SD-03 Product Data
Resilient Flooring and Accessories; G
Adhesives
Luxury Vinyl Tile
Recycled content for Luxury Vinyl Tile
Wall Base
SD-04 Samples
Resilient Flooring and Accessories; G
SD-06 Test Reports
Moisture, Alkalinity and Bond Tests; G
SD-07 Certificates
Indoor Air Quality for Luxury Vinyl Tile
Indoor Air Quality for Wall Base
Indoor Air Quality for Adhesives
SD-08 Manufacturer's Instructions
Surface Preparation; G
Installation; G
SD-10 Operation and Maintenance Data
Resilient Flooring and Accessories; G
SECTION 09 65 00 Page 2
1.3 CERTIFICATES
1.3.1 Indoor Air Quality
Submit required indoor air quality certifications and validations in one submittal package.
1.3.1.1 Floor Covering Materials
Provide Luxury Vinyl Tile, and wall base products certified to meet indoor air quality requirements by FLOORSCORE, UL 2818 (Greenguard) Gold, SCS Global Services Indoor Advantage Gold or provide certification by other third-party programs. Provide current product certification documentation from certification body.
1.3.1.2 Adhesives, Caulking and Sealants
Provide products certified to meet indoor air quality requirements by UL 2818 (Greenguard) Gold, SCS Global Services Indoor Advantage Gold or provide certification or validation by other third-party programs that products meet the requirements of this Section. Provide current product certification documentation from certification body. When product does not have certification, provide validation that product meets the indoor air quality product requirements cited herein.
1.4 DELIVERY, STORAGE, AND HANDLING
Deliver materials to the building site in original unopened containers bearing the manufacturer's name, style name, pattern color name and number, production run, project identification, and handling instructions. Store materials in a clean, dry, secure, and well-ventilated area free from strong contaminant sources and residues with ambient air temperature maintained above 68 degrees F and below 85 degrees F, stacked according to manufacturer's recommendations. Remove resilient flooring products from packaging to allow ventilation prior to installation. Protect materials from the direct flow of heat from hot-air registers, radiators and other heating fixtures and appliances. Observe ventilation and safety procedures specified in the MSDS. Do not store rubber surface products with materials that have a high capacity to adsorb volatile organic compound (VOC) emissions. Do not store exposed rubber surface materials in occupied spaces.
1.5 ENVIRONMENTAL REQUIREMENTS
Maintain areas to receive resilient flooring at a temperature above 68 degrees F and below 85 degrees F for 3 days before application, during application and 2 days after application, unless otherwise directed by the flooring manufacturer for the flooring being installed. Maintain a minimum temperature of 55 degrees F thereafter. Provide adequate ventilation to remove moisture from area and to comply with regulations limiting concentrations of hazardous vapors.
1.6 SCHEDULING
Schedule resilient flooring application after the completion of other work which would damage the finished surface of the flooring.
SECTION 09 65 00 Page 3
1.7 WARRANTY
Provide manufacturer's standard performance guarantees or warranties that extend beyond a one year period.
PART 2 PRODUCTS
2.1 LUXURY VINYL TILE
Conform to ASTM F3261 Class III printed film with a minimum wear layer thickness 0.020 inch (20 mil) and minimum overall thickness 0.157 inch with non slip/skid backing, Type B (embossed). Provide 7 x 48 inch tile.
Provide tile with a factory protective finish that enhances cleanability and durability.
Provide Luxury Vinyl Tile containing a minimum of 20 percent recycled content. Provide data identifying percentage of recycled content for Luxury Vinyl Tile.
Provide certification of indoor air quality for Luxury Vinyl Tile.
2.2 WALL BASE
Provide wall base to match existing.
Provide certification of indoor air quality for Wall Base.
2.3 ADHESIVES
Provide adhesives for flooring, base and accessories as recommended by the manufacturer and comply with local indoor air quality standards. Submit manufacturer's descriptive data, documentation stating physical characteristics, and mildew and germicidal characteristics.
Provide non-aerosol adhesive products used on the interior of the building (defined as inside of the weatherproofing system) that meet either emissions requirements of CDPH SECTION 01350 (limit requirements for either office or classroom spaces regardless of space type) or VOC content requirements of SCAQMD Rule 1168 . Provide aerosol adhesives used on the interior of the building that meet either emissions requirements of CDPH SECTION 01350 (use the office or classroom requirements, regardless of space type) or VOC content requirements of GS-36. Provide certification or validation of indoor air quality for adhesives.
2.4 SURFACE PREPARATION MATERIALS
Provide surface preparation materials, such as panel type underlayment, lining felt, and floor crack fillers as recommended by the flooring manufacturer for the subfloor conditions. Comply with ASTM F1482 for panel type underlayment products.
2.5 POLISH/FINISH
Provide polish finish as recommended by the manufacturer and conform to ASTM D4078 for polish.
2.6 CAULKING AND SEALANTS
Provide caulking and sealants as recommended by the manufacturer.
SECTION 09 65 00 Page 4
2.7 MANUFACTURER'S COLOR, PATTERN AND TEXTURE
Provide color, pattern and texture for resilient flooring and accessories selected from manufacturer's standard colors. Color listed is not intended to limit the selection of equal colors from other manufacturers.
Provide flooring in any one continuous area or replacement of damaged flooring in continuous area from same production run with same shade and pattern. Submit manufacturer's descriptive data and three samples of each indicated color and type of flooring, base, mouldings, and accessories sized a minimum2-1/2 by 4 inch. Submit Data Package 1 in accordance with Section 01 78 23 OPERATION AND MAINTENANCE DATA.
2.8 FIRE RESISTANCE TESTING REQUIREMENTS
Provide a minimum average critical radiant flux of 0.45 watts per square centimeter for flooring in corridors and exits when tested in accordance with ASTM E648.
PART 3 EXECUTION
3.1 EXAMINATION
Examine and verify that site conditions are in agreement with the design package. Report all conditions that will prevent a proper installation.
Do not take any corrective action without written permission from the Government. Work will proceed only when conditions have been corrected and accepted by the installer. Submit manufacturer's printed installation instructions for all flooring materials and accessories, including preparation of substrate, seaming techniques, and recommended adhesives.
3.2 SURFACE PREPARATION
Provide a smooth, true, level plane for surface preparation of the flooring, except where indicated as sloped. Floor to be flat to within 3/16 inch in 10 feet. Prepare subfloor in accordance with flooring manufacturer's recommended instructions. Prepare the surfaces of lightweight concrete slabs (as defined by the flooring manufacturer) as recommended by the flooring manufacturer. Comply with ASTM F710 for concrete subfloor preparation. Floor fills or toppings may be required as recommended by the flooring manufacturer. Install underlayments, when required by the flooring manufacturer, in accordance with manufacturer's recommended printed installation instructions. Comply with ASTM F1482 for panel type underlayments. Before any work under this section is begun, correct all defects such as rough or scaling concrete, chalk and dust, cracks, low spots, high spots, and uneven surfaces. Repair all damaged portions of concrete slabs as recommended by the flooring manufacturer.
Remove concrete curing and sealer compounds from the slabs, other than the type that does not adversely affect adhesion. Remove paint, varnish, oils, release agents, sealers, waxes, and adhesives, as required by the flooring product in accordance with manufacturer's printed installation instructions.
3.3 MOISTURE, ALKALINITY AND BOND TESTS
Determine the suitability of the concrete subfloor for receiving the resilient flooring with regard to moisture content and pH level by moisture and alkalinity tests. Conduct moisture testing in accordance with ASTM F1869 or ASTM F2170, unless otherwise recommended by the
SECTION 09 65 00 Page 5 flooring manufacturer. Conduct alkalinity testing as recommended by the flooring manufacturer. Determine the compatibility of the resilient flooring adhesives to the concrete floors by a bond test in accordance with the flooring manufacturer's recommendations. Submit copy of test reports for moisture and alkalinity content of concrete slab, and bond test stating date of test, person conducting the test, and the area tested.
3.4 GENERAL INSTALLATION
Do not install building construction materials that show visual evidence of biological growth.
3.5 PLACING LUXURY VINYL TILES
Install luxury vinyl tile flooring using glue down installation. Install flooring and accessories in accordance with manufacturer's printed installation instructions. Prepare and apply adhesives in accordance with manufacturer's directions for installation method specified. Keep tile lines and joints square, symmetrical, tight, and even. Keep each floor in true, level plane, except where slope is indicated. Vary edge width as necessary to maintain full-size tiles in the field, no edge tile to be less than one-half the field tile size, except where irregular shaped rooms make it impossible. Cut flooring to fit around all permanent fixtures, built-in furniture and cabinets, pipes, and outlets. Cut, fit, and scribe edge tile to walls and partitions after field flooring has been applied.
3.6 PLACING FEATURE STRIPS
Install feature strips in accordance with manufacturer's printed installation instructions. Prepare and apply adhesives in accordance with manufacturer's printed directions.
3.7 PLACING MOULDING
Provide moulding where flooring termination is higher than the adjacent finished flooring and at transitions between different flooring materials. When required, locate moulding under door centerline. Moulding is not required at doorways where thresholds are provided. Secure moulding with adhesive as recommended by the manufacturer. Prepare and apply adhesives in accordance with manufacturer's printed directions.
3.8 PLACING WALL BASE
Install wall base in accordance with manufacturer's printed installation instructions. Prepare and apply adhesives in accordance with manufacturer's printed directions. Tighten base joints and make even with adjacent resilient flooring. Fill voids along the top edge of base at masonry walls with caulk. Roll entire vertical surface of base with hand roller, and press toe of base with a straight piece of wood to ensure proper alignment. Avoid excess adhesive in corners.
3.9 CLEANING
Immediately upon completion of installation of flooring in a room or an area, dry and clean the flooring and adjacent surfaces to remove all surplus adhesive. Clean flooring as recommended in accordance with manufacturer's printed maintenance instructions and within the recommended time frame. As required by the manufacturer, apply the recommended number
SECTION 09 65 00 Page 6 of coats and type of polish and finish in accordance with manufacturer's written instructions.
3.10 PROTECTION
From the time of installation until acceptance, protect flooring from damage as recommended by the flooring manufacturer. Remove and replace flooring which becomes damaged, loose, broken, or curled and wall base which is not tight to wall or securely adhered.
SECTION 09 65 00 Page 7
SECTION 09 65 00 Page 8
SECTION 09 90 00
PAINTS AND COATINGS
02/21
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONFERENCE OF GOVERNMENTAL INDUSTRIAL HYGIENISTS (ACGIH)
ACGIH 0100 (2017; Suppl 2020) Documentation of the Threshold Limit Values and Biological Exposure Indices
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
ASME A13.1 (2020) Scheme for the Identification of Piping Systems
ASTM INTERNATIONAL (ASTM)
ASTM D235 (2002; R 2012) Mineral Spirits (Petroleum Spirits) (Hydrocarbon Dry Cleaning Solvent)
ASTM D4214 (2007; R 2015) Standard Test Method for Evaluating the Degree of Chalking of Exterior Paint Films
ASTM D4444 (2013; R 2018) Standard Test Method for Laboratory Standardization and Calibration of Hand-Held Moisture Meters
CENTERS FOR DISEASE CONTROL AND PREVENTION (CDC)
Intelligence Bulletin 65 (2013) Occupational Exposure to Carbon Nanotubes and Nanofibers
MASTER PAINTERS INSTITUTE (MPI)
MPI 9 (2016) Alkyd, Exterior Gloss (MPI Gloss Level 6)
MPI 39 (2018) Primer, Latex, for Interior Wood
MPI 45 (2016) Primer Sealer, Interior Alkyd
MPI 46 (2016) Undercoat, Enamel, Interior
MPI 51 (2016) Alkyd, Interior, (MPI Gloss Level 3)2
MPI 72 (2016) Polyurethane, Two-Component, Pigmented, Gloss (MPI Gloss Level 6-7)
SECTION 09 90 00 Page 1
MPI 139 (2016) Latex, Interior, High Performance Architectural, (MPI Gloss Level 3)
MPI 144 (2016) Latex, Interior, Institutional Low Odor/VOC, (MPI Gloss Level 2)
MPI 145 (2016) Latex, Interior, Institutional Low Odor/VOC, ( MPI Gloss Level 3)
MPI 149 (2016) Primer Sealer, Interior, Institutional Low Odor/VOC
MPI ASM (2019) Architectural Painting Specification Manual
MPI GPS-1-14 (2014) Green Performance Standard GPS-1-14
MPI GPS-2-14 (2014) Green Performance Standard GPS-2-14
MPI MRM (2015) Maintenance Repainting Manual
SOCIETY FOR PROTECTIVE COATINGS (SSPC)
SSPC PA 1 (2016) Shop, Field, and Maintenance Coating of Metals
SSPC QP 1 (2019) Standard Procedure for Evaluating the Qualifications of Industrial/Marine Painting Contractors (Field Application to Complex Industrial Steel Structures and Other Metal Components)
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA Method 24 (2000) Determination of Volatile Matter Content, Water Content, Density, Volume Solids, and Weight Solids of Surface Coatings
U.S. GENERAL SERVICES ADMINISTRATION (GSA)
FED-STD-313 (2018) Material Safety Data, Transportation Data and Disposal Data for Hazardous Materials Furnished to Government Activities
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910.1000 Air Contaminants
1.2 SCHEDULING
Allow paint, polyurethane, varnish, and wood stain installations to cure
SECTION 09 90 00 Page 2 prior to the installation of materials that adsorb VOCs, including unprimed gypsum wallboard.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
Samples of specified materials may be taken and tested for compliance with specification requirements.
SD-02 Shop Drawings
Piping Identification
SD-03 Product Data
Coating; G
SD-04 Samples
Color; G
SD-07 Certificates
Qualification Testing laboratory for…