This document is a Repair Qualification Requirements specification for a Power Supply (NSN: 6130-01-555-6140, P/N: ESP6D013340-00) used in the AN/FRC-178(V) application. To become a qualified repair source, offerors must satisfy nine mandatory requirements: submit a prequalification notice to the appropriate government Small Business Office or contracting officer; certify possession of required facilities, equipment, tooling, and personnel for repair, inspection, testing, packaging, and storage; verify possession of a complete data package including all procedures, drawings, specifications, and change notices; repair items in conformance with ESA-approved engineering/technical data and demonstrate compliance with Unique Identification requirements per DFARS 211.274; prepare and submit a qualification test plan to 415 SCMS/GUEA for approval detailing verification of performance, environmental, mechanical, and quality assurance requirements per Drawing 873-09-00086; and demonstrate ability to meet all standards before the contract award date. The estimated cost to complete qualification is $6,000, with an estimated completion time of 30 days based on the power supply's complexity.

Four Source Qualification Waiver Criteria (QWC) are available to eligible sources: QWC1 allows waiver consideration if the potential source submits written certification that articles have been previously supplied to the government or original equipment manufacturer; QWC2 permits qualification on mirror-image left-hand articles if already qualified on right-hand articles; QWC3 qualifies sources providing assemblies to also provide subassemblies, major components, and items of those assemblies; and QWC4 allows sources qualified on earlier dash numbers of a basic part number to provide other dash numbers provided there is no increase in complexity, criticality, or other relevant requirements. Full qualification requires meeting all stated requirements in writing before the award date, after which successful offerors are listed as approved repair sources, though approval does not guarantee subsequent contract award.

View the file

Other files

File Type Posted
FA825026Q0557 amend 1.pdf PDF
FA825026Q0557.pdf PDF
ATTACHMENT_5_PWS.pdf PDF
ATTACHMENT_6_RDL_REPORT.pdf PDF
ATTACHMENT_1_CAVAF_REPORTING.pdf PDF
ATTACHMENT_2_ITMDESC_REPORT.pdf PDF
ATTACHMENT_3_PKGRQMT_REPORT.pdf PDF
ATTACHMENT_8_CDRLs.pdf PDF
ATTACHMENT_4_PKG_SOW.pdf PDF
ATTACHMENT_7_IUID.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REPAIR QUALIFICATION REQUIREMENTS

NSN: 6130-01-555-6140

P/N: ESP6D013340-00

Noun: Power Supply Application: AN/FRC-178(V)

9 Apr 2025 Section C 1/3

SECTION C:

1. QUALIFICATION REQUIREMENTS THAT MUST BE SATISFIED TO BECOME A QUALIFIED SOURCE

a. Prequalification Notice: The offeror shall notify the appropriate government Small Business Office or, if responding to a solicitation, the contracting officer in the appropriate government contracting office, of intent to qualify as a source for this Power Supply.

b. Facilities, Testing, and Inspection Capabilities: The offeror must certify to the government that they have, or have access to, the required facilities and equipment to repair, inspect, test, package, and store the item. The offeror shall make their facilities, equipment, tooling, and personnel available for evaluation and inspection by the government.

c. Data Verification: The offeror must verify that they have a complete data package. This verification must include a complete list of all procedures, drawings, and specifications, including change notices, in the offeror’s possession. The offeror may also be required to produce copies of all applicable procedures, drawings, or specifications.

d. Repair Process Verification: The offeror must repair this item to conform to the government requirements as prescribed within the ESA-approved engineering/technical data package. The offeror must show compliance with Unique Identification (UID) requirements in accordance with DFARS 211.274 as prescribed within the ESA-approved engineering/technical data package. The offeror must provide, at their own expense, data showing the results of all quality, performance, and environmental evaluations conducted by the offeror to show compliance with the government requirements as prescribed by 415 SCMS/GUEA. The offeror shall also identify its sources for materials and its standards for internally used processes.

e. Test and Evaluation and/or Verification: The offeror, at their own expense, shall prepare and submit to 415 SCMS/GUEA for their prior approval, a qualification test plan/procedure detailing how they intend to verify compliance with all performance, environmental, mechanical, and quality assurance requirements identified by Drawing 873-09-00086.

f. Qualification Requirement Cost Estimate: Estimated likely costs for testing and evaluation, which will be incurred by the potential offering party to become qualified are $6000.

g. Qualification Time Completion Estimate: It is the estimate of the engineering support activity that completion of this qualification effort should require 30 days. This is based on complexity of the Power Supply and other factors.

h. Qualification Time Limitation: An offeror may not be denied the opportunity to submit and have considered an offer for a contract if the offeror can demonstrate to the satisfaction of the contracting officer that the offeror (or its product) meets these standards for qualification or can meet them before the date specified for award of the contract. The award will not be delayed

P/N: ESP6D013340-00

9 Apr 2025 Section C 2/3 to provide the vendor with an opportunity to demonstrate its ability to meet the standards specified in this qualification requirement.

i. Evaluation of Proposals Not Previously Qualified: The offeror must be fully qualified in order to be eligible for a contract award. Therefore, the offeror must fulfill all of the requirements stated, in writing, in the qualification requirement before the date specified for award of the contract. Once all requirements are met, the offeror will be listed as an approved repair source for this item. Approval, however, does not guarantee subsequent contract award.

P/N: ESP6D013340-00

9 Apr 2025 Section C 3/3

2. SOURCE QUALIFICATION WAIVER REQUIREMENTS

Sources who meet any of the following Source Qualification Waiver Criteria (QWC) may apply for a waiver of all or part of the qualification requirements. If a waiver is granted and the offeror is awarded a contract, the offeror may still be required to provide a post-contract award first article exhibit to verify production capability:

a. QWC1: The potential source submits written certification that the articles have been supplied to the government or original equipment manufacturer (e.g., DD Form 250, Material Inspection and Receiving Report, Purchase Order invoice, etc).

b. QWC2: The potential source is qualified on the right-hand article and requests to be qualified on the left-hand article. If the right-and left-hand articles are mirror images of each other, then approval can generally be given.

c. QWC3: A source qualified to provide an assembly is usually qualified to provide subassemblies, major components, and items of that assembly.

d. QWC4: A source qualified to provide earlier dash numbers of a basic P/N may be qualified to provide other dash numbers of that same basic P/N, provided there is no increase in complexity, criticality, or other relevant requirements.