Attachment 9 - B1643 - RFI.pdf

PDF 51 KB Posted

Attached to
Repair B1643 Federal contract opportunity
Solicitation number
FA667522R0007
Issued by
Department of the Air Force Reserve Command

About this file

This document contains a solicitation for a federal construction contract opportunity. The Air Force is seeking proposals for the phased renovation of Maintenance Hangar Building 1643 at NAS Fort Worth JRB in Fort Worth, Texas, including demolition, construction, renovation, and related work. The project involves civil, architectural, mechanical and electrical components. Phase 3 construction must be performed by U.S. persons. The estimated construction schedule and contract type are to be determined at award. The NAICS code is 236220 with a $39.5 million size standard. The small business set-aside contract will be awarded on a lowest price technically acceptable basis. The site visit is scheduled for July 12, 2022 and requests for information are due by July 21, 2022, with proposals due August 1, 2022. The solicitation is available at SAM.gov and prospective contractors must register in SAM to receive notifications or be eligible for award.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION / CLARIFICATION FORM

FOR CONTRACTOR USE ONLY

CONTRACT NO: RFI NUMBER: DATE (MM/DD/YY)

SUBJECT: DRAWING REFERENCE / DETAIL:

ATTACHMENT SENT UNDER SEPARATE

COVER(__)

RESPONSE NEEDED BY:

REQUEST:

PROPOSED SOLUTION (If applicable):

TO(Contracting Officer): 301 CONF/PK FROM (Contractor):

DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:

REQUEST FOR INFORMATION / CLARIFICATION FORM

FOR GOVERNMENT USE ONLY

FROM CONTRACTING

TO:

For Evaluation and Action

DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:

RFI RESPONSE / CLARIFICATION (refer to page 2)

RFI RESPONSE / CLARIFICATION:-

Government to complete following sections:

TO:(AF Contracting Office)

DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:

TO:(Contractor)

DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:

CONTRACTOR REVIEW

After reviewing the Government response, does the contractor anticipate A change order will be required? YES NO There will be an increase in the cost of the project? YES NO

Reviewer:

DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:

*Contractor- return reviewed form to Contracting Officer. Should the review results in YES for either of the two questions, if any further action is required by the contractor (i.e. submission of change proporsal), they will be notified by the contracting office.

TOContractor:
Reviewer:
Text1:
Text2: 001
Date3_af_date:
Text4:
Text5:
Check Box6: Off
Date7_af_date:
Text9:
Text10:
Text11:
Text12:
Date13_af_date:
Text14:
Text16:
Date17_af_date:
Text18:
Text20:
Date21_af_date:
Text22:
Date24_af_date:
Text25:
Check Box27: Off
Check Box28: Off
Check Box29: Off
Check Box30: Off
Date31_af_date:
Text32:

File details come from the government source that posted it. Updated .