These are Repair Qualification Requirements documents for multiple Circuit Card Assembly (CCA) components used in the AN/MST-T1(V) Mini-MUTES system, dated from July 2022 to October 2025. The documents outline specific qualification criteria for potential repair sources, including requirements for facility capabilities, data verification, repair process verification, and testing procedures. Key components include a Circuit Card Assembly (NSN 5998-01-491-3752), a Trac Processor Assembly (NSN 5998-01-477-1786), and a CCA Transition XM302 (NSN 5998-01-498-8206).
Qualification requirements are comprehensive and include mandatory steps such as notifying the government Small Business Office, demonstrating repair and inspection capabilities, verifying complete technical documentation, and submitting detailed qualification test plans. The documents specify estimated costs for qualification ranging from $2,000 to $13,000, with qualification time estimates between 30-60 days depending on the specific component. Potential repair sources must prove they can meet technical specifications, comply with Unique Identification (UID) requirements, and undergo government evaluation, though approval does not guarantee a contract award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment_9_CDRLs.pdf | ||
| Attachment_6_RDLs.pdf | ||
| Attachment_3_Packaging_Requirements.pdf | ||
| Attachment_4_Packaging_SOW.pdf | ||
| FA825026Q0035.pdf | ||
| Attachment_7_IUIDs.pdf | ||
| Attachment_2_Item_Descriptions.pdf | ||
| Attachment_1_CAVAF.docx | DOCX document | |
| Attachment_5_PWS.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPAIR QUALIFICATION REQUIREMENTS
NSN: 5998-01-491-3752
P/N: 3050945-101 Noun: CIRCUIT CARD ASSEMBLY Application: AN/MST-T1(V) Mini-MUTES
13 Jul 2022 Section C 1/3
SECTION C:
1. QUALIFICATION REQUIREMENTS THAT MUST BE SATISFIED TO BECOME A QUALIFIED SOURCE
a. Prequalification Notice: The offeror shall notify the appropriate government Small Business Office or, if responding to a solicitation, the contracting officer in the appropriate government contracting office, of intent to qualify as a source for this CIRCUIT CARD ASSEMBLY.
b. Facilities, Testing, and Inspection Capabilities: The offeror must certify to the government that they have, or have access to, the required facilities and equipment to repair, inspect, test, package, and store the item. Facility capabilities must include, but are not limited to, the ability to repair/replace digital and analog circuit card components, measure impedances, measure input/output voltages, and mitigate electrostatic discharges. The offeror shall make their facilities, equipment, tooling, and personnel available for evaluation and inspection by the government.
c. Data Verification: The offeror must verify that they have a complete data package. This verification must include a complete list of all procedures, drawings, and specifications, including change notices, in the offeror’s possession including, at a minimum L3HARRIS (66948) drawing 3050945. The offeror may also be required to produce copies of all applicable procedures, drawings, or specifications.
d. Repair Process Verification: The offeror must repair this item to conform to the government requirements as prescribed within the ESA-approved engineering/technical data package. The offeror must show compliance with Unique Identification (UID) requirements in accordance with DFARS 211.274 as prescribed within the ESA-approved engineering/technical data package. The offeror must provide, at their own expense, data showing the results of all quality, performance, and environmental evaluations conducted by the offeror to show compliance with the government requirements as prescribed by 415 SCMS/GUEA. The offeror shall also identify its sources for materials and its standards for internally used processes.
e. Test and Evaluation and/or Verification: The offeror, at their own expense, shall prepare and submit to 415 SCMS/GUEA for their prior approval, a qualification test plan/procedure detailing how they intend to verify compliance with all performance, environmental, mechanical, and quality assurance requirements identified by Drawing 3050945.
f. Qualification Article Verification: N/A.
g. Qualification Requirement Cost Estimate: Estimated likely costs for testing and evaluation, which will be incurred by the potential offering party to become qualified are $2000.00.
h. Qualification Time Completion Estimate: It is the estimate of the engineering support activity that completion of this qualification effort should require 60 days. This is based on complexity of the CIRCUIT CARD ASSEMBLY and other factors.
P/N: 3050945-101 Noun: CIRCUIT CARD ASSEMBLY Application: AN/MST-T1(V) Mini-MUTES
13 Jul 2022 Section C 2/3
i. Qualification Time Limitation: An offeror may not be denied the opportunity to submit and have considered an offer for a contract if the offeror can demonstrate to the satisfaction of the contracting officer that the offeror (or its product) meets these standards for qualification or can meet them before the date specified for award of the contract. The award will not be delayed to provide the vendor with an opportunity to demonstrate its ability to meet the standards specified in this qualification requirement.
j. Evaluation of Proposals Not Previously Qualified: The offeror must be fully qualified in order to be eligible for a contract award. Therefore, the offeror must fulfill all of the requirements stated, in writing, in the qualification requirement before the date specified for award of the contract. Once all requirements are met, the offeror will be listed as an approved repair source for this item. Approval, however, does not guarantee subsequent contract award.
P/N: 3050945-101 Noun: CIRCUIT CARD ASSEMBLY Application: AN/MST-T1(V) Mini-MUTES
13 Jul 2022 Section C 3/3
2. SOURCE QUALIFICATION WAIVER REQUIREMENTS
Sources who meet any of the following Source Qualification Waiver Criteria (QWC) may apply for a waiver of all or part of the qualification requirements. If a waiver is granted and the offeror is awarded a contract, the offeror may still be required to provide a post-contract award first article exhibit to verify production capability:
a. QWC1: The potential source submits written certification that the articles have been supplied to the government or original equipment manufacturer (e.g., DD Form 250, Material Inspection and Receiving Report, Purchase Order invoice, etc).
b. QWC2: The potential source is qualified on the right-hand article and requests to be qualified on the left-hand article. If the right-and left-hand articles are mirror images of each other, then approval can generally be given.
c. QWC3: A source qualified to provide an assembly is usually qualified to provide subassemblies, major components, and items of that assembly.
d. QWC4: A source qualified to provide earlier dash numbers of a basic P/N may be qualified to provide other dash numbers of that same basic P/N, provided there is no increase in complexity, criticality, or other relevant requirements.
e. QWC5: A source qualified to provide a similar or like item can be qualified to provide the required item. However, for approval, the engineering authority must verify that there is no increase in complexity, criticality, or other requirements over that of the similar item. At a minimum, the source shall provide a complete set of drawings for the similar item and written proof, such as purchase orders, shipping documents, etc., to show that the similar item was provided to the original equipment manufacturer or DoD.
f. QWC6: A source previously qualified to provide an item, but which has been purchased, sold, merged, absorbed, reformed, split, etc., may qualify if it can be established that the qualification is currently with the requester and that the requester has the same or equivalent facilities, tooling, equipment, personnel, and utilizes the original forging, castings, etc., in the repair process.
g. QWC7: N/A.
NSN: 5998-01-477-1786
P/N: 3050777-101 Noun: Trac Processor Assembly
15 Nov 2023 Section C 1/3
SECTION C:
1. QUALIFICATION REQUIREMENTS THAT MUST BE SATISFIED TO BECOME A QUALIFIED SOURCE
a. Prequalification Notice: The offeror shall notify the appropriate government Small Business Office or, if responding to a solicitation, the contracting officer in the appropriate government contracting office, of intent to qualify as a source for this Trac Processor Assembly.
b. Facilities, Testing, and Inspection Capabilities: The offeror must certify to the government that they have, or have access to, the required facilities and equipment to repair, inspect, test, package, and store the item. The offeror shall make their facilities, equipment, tooling, and personnel available for evaluation and inspection by the government.
c. Data Verification: The offeror must verify that they have a complete data package. This verification must include a complete list of all procedures, drawings, and specifications, including change notices, in the offeror’s possession, and also including all relevant supplier data, which includes a full data package of supplier data plus relevant installation and user manuals and data sheets. The offeror may also be required to produce copies of all applicable procedures, drawings, or specifications
d. Repair Process Verification: The offeror must repair this item to conform to the government requirements as prescribed within the ESA-approved engineering/technical data package. The offeror must show compliance with Unique Identification (UID) requirements in accordance with DFARS 211.274 as prescribed within the ESA-approved engineering/technical data package. The offeror must provide, at their own expense, data showing the results of all quality, performance, and environmental evaluations conducted by the offeror to show compliance with the government requirements as prescribed by 415 SCMS/GUMBB. The offeror shall also identify its sources for materials and its standards for internally used processes.
e. Test and Evaluation and/or Verification: The offeror, at their own expense, shall prepare and submit to 415 SCMS/GUMBB for their prior approval, a qualification test plan/procedure detailing how they intend to verify compliance with all performance, environmental, mechanical, and quality assurance requirements identified by Drawing 3050777.
f. Qualification Requirement Cost Estimate: Estimated likely costs for testing and evaluation, which will be incurred by the potential offering party to become qualified are $2000.
g. Qualification Time Completion Estimate: It is the estimate of the engineering support activity that completion of this qualification effort should require 30 days. This is based on complexity of the Trac Processor Assembly and other factors.
h. Qualification Time Limitation: An offeror may not be denied the opportunity to submit and have considered an offer for a contract if the offeror can demonstrate to the satisfaction of the contracting officer that the offeror (or its product) meets these standards for qualification or can
P/N: 3050777-101
15 Nov 2023 Section C 2/3 meet them before the date specified for award of the contract. The award will not be delayed to provide the vendor with an opportunity to demonstrate its ability to meet the standards specified in this qualification requirement.
i. Evaluation of Proposals Not Previously Qualified: The offeror must be fully qualified in order to be eligible for a contract award. Therefore, the offeror must fulfill all of the requirements stated, in writing, in the qualification requirement before the date specified for award of the
P/N: 3050777-101
15 Nov 2023 Section C 3/3
Sources who meet any of the following Source Qualification Waiver Criteria (QWC) may apply for a waiver of all or part of the qualification requirements. If a waiver is granted and the offeror is awarded a contract, the offeror may still be required to provide a post-contract award first article exhibit to verify increase in complexity, criticality, or other requirements over that of the similar item. At a minimum, the source shall provide a complete set of drawings for the similar item and written is currently with the requester and that the requester has the same or equivalent facilities, NSN: 5998-01-498-8206
P/N: 3050945-120 Noun: CCA, Transition, XM302
20 Oct 2025 Section C 1/3
SECTION C:
1. QUALIFICATION REQUIREMENTS THAT MUST BE SATISFIED TO BECOME A QUALIFIED SOURCE
a. Prequalification Notice: The offeror shall notify the appropriate government Small Business Office or, if responding to a solicitation, the contracting officer in the appropriate government contracting office, of intent to qualify as a source for this CCA, Transition, XM302.
b. Facilities, Testing, and Inspection Capabilities: The offeror must certify to the government that they have, or have access to, the required facilities and equipment to repair, inspect, test, package, and store the item. The offeror shall make their facilities, equipment, tooling, and personnel available for evaluation and inspection by the government.
c. Data Verification: The offeror must verify that they have a complete data package. This verification must include a complete list of all procedures, drawings, and specifications, including change notices, in the offeror’s possession including, at a minimum HARRIS CORPORATION (66948) drawing 3050945-120. The offeror may also be required to produce copies of all applicable procedures, drawings, or specifications.
d. Repair Process Verification: The offeror must repair this item to conform to the government requirements as prescribed within the ESA-approved engineering/technical data package. The offeror must show compliance with Unique Identification (UID) requirements in accordance with DFARS 211.274 as prescribed within the ESA-approved engineering/technical data package. The offeror must provide, at their own expense, data showing the results of all quality, performance, and environmental evaluations conducted by the offeror to show compliance with the government requirements as prescribed by 415 SCMS/GUMBB. The offeror shall also identify its sources for materials and its standards for internally used processes.
e. Test and Evaluation and/or Verification: The offeror, at their own expense, shall prepare and submit to 415 SCMS/GUMBB for their prior approval, a qualification test plan/procedure detailing how they intend to verify compliance with all performance, environmental, mechanical, and quality assurance requirements identified by ESA-approved engineering/technical data package.
f. Qualification Article Verification: N/A
g. Qualification Requirement Cost Estimate: Estimated likely costs for testing and evaluation, which will be incurred by the potential offering party to become qualified are $13000.
h. Qualification Time Completion Estimate: It is the estimate of the engineering support activity that completion of this qualification effort should require 60 days. This is based on complexity of the CCA, Transition, XM302 and other factors.
P/N: 3050945-120
20 Oct 2025 Section C 2/3
i. Qualification Time Limitation: An offeror may not be denied the opportunity to submit and have considered an offer for a contract if the offeror can demonstrate to the satisfaction of the contracting officer that the offeror (or its product) meets these standards for qualification or can meet them before the date specified for award of the contract. The award will not be delayed to provide the vendor with an opportunity to demonstrate its ability to meet the standards specified in this qualification requirement.
j. Evaluation of Proposals Not Previously Qualified: The offeror must be fully qualified in order to be eligible for a contract award. Therefore, the offeror must fulfill all of the requirements stated, in writing, in the qualification requirement before the date specified for award of the
P/N: 3050945-120
20 Oct 2025 Section C 3/3
Sources who meet any of the following Source Qualification Waiver Criteria (QWC) may apply for a waiver of all or part of the qualification requirements. If a waiver is granted and the offeror is awarded a contract, the offeror may still be required to provide a post-contract award first article exhibit to verify increase in complexity, criticality, or other requirements over that of the similar item. At a minimum, the source shall provide a complete set of drawings for the similar item and written is currently with the requester and that the requester has the same or equivalent facilities,