Attachment 8 - RFI Form.pdf
PDF 63 KB Posted
- Solicitation number
- FA667522R0004
About this file
This document contains a Request for Information form and details of a federal contract opportunity for repairs and renovations to an armament shop at an Air Force base. The RFI form outlines a process for contractors to submit clarification questions by a specified date to the contracting office.
The contract opportunity is for repairs and renovations to Building 1648 Armament Shop to support an incoming F-35 flying mission at the base. Renovations include floor plan changes, additional fixtures, separate male/female locker rooms, and modifications to ductwork. Repairs include refinishing degraded spaces, exterior doors and windows, gutters, and fascia. The single-award, firm-fixed-price contract is estimated between $1,000,000 to $5,000,000. The solicitation will use Lowest Price Technically Acceptable source selection with a tentative release date of March 15th, 2022. The pre-solicitation includes dates for an optional site visit and questions by contractors. The proposal due date is April 18th, 2022. Funds are not presently available and the solicitation will be issued on SAM.gov.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION / CLARIFICATION FORM
FOR CONTRACTOR USE ONLY
CONTRACT NO: RFI NUMBER: DATE (MM/DD/YY)
SUBJECT: DRAWING REFERENCE / DETAIL:
ATTACHMENT SENT UNDER SEPARATE
COVER(__)
RESPONSE NEEDED BY:
REQUEST:
PROPOSED SOLUTION (If applicable):
TO(Contracting Officer): 301 CONF/PK FROM (Contractor):
DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:
REQUEST FOR INFORMATION / CLARIFICATION FORM
FOR GOVERNMENT USE ONLY
FROM CONTRACTING
TO:
For Evaluation and Action
DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:
RFI RESPONSE / CLARIFICATION (refer to page 2)
RFI RESPONSE / CLARIFICATION:-
Government to complete following sections:
TO:(AF Contracting Office)
DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:
TO:(Contractor)
DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:
CONTRACTOR REVIEW
After reviewing the Government response, does the contractor anticipate A change order will be required? YES NO There will be an increase in the cost of the project? YES NO
Reviewer:
DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:
*Contractor- return reviewed form to Contracting Officer. Should the review results in YES for either of the two questions, if any further action is required by the contractor (i.e. submission of change proporsal), they will be notified by the contracting office.
| TOContractor: |
| Reviewer: |
| Text1: |
| Text2: 001 |
| Date3_af_date: |
| Text4: |
| Text5: |
| Check Box6: Off |
| Date7_af_date: |
| Text9: |
| Text10: |
| Text11: |
| Text12: |
| Date13_af_date: |
| Text14: |
| Text16: |
| Date17_af_date: |
| Text18: |
| Text20: |
| Date21_af_date: |
| Text22: |
| Date24_af_date: |
| Text25: |
| Check Box27: Off |
| Check Box28: Off |
| Check Box29: Off |
| Check Box30: Off |
| Date31_af_date: |
| Text32: |
File details come from the government source that posted it. Updated .