Memorandum
Attn: All Date: January 2021 From: Jadwiga Vee Figiel, COR
Subject: Pre-Construction Checklist
Project Name: Bldg. 5 Windows Replacement
The following checklist is a template to be used for the Pre-Construction review of Contractor submissions. This checklist was created locally at NSSC based on experience and the template SOWs for Construction. The COR shall review project specific SOW requirements and add to the list below as required for the project. Members of the Engineering projects team shall add items as appropriate into the template checklists. If the submission has missing, incomplete or incorrect items, then these comments shall be placed in the Submission Review Form. Construction may not commence until the required information is provided.
GENERAL SOW REQUIREMENTS
Document YES NO N/A
GENERAL PROJECT
Schedule Project Schedule. See SOW under Submittals.
Written Plan Quality Control Plan. (QCP)
Written Plan Accident Prevention Plan (APP)
Written Plan Collection & Disposal Waste Management Plan. See SOW under Collection and Disposal of Construction and Demolition (C&D) Waste Streams.
Construction Site Plan
See SOW under Collection and Disposal of Construction and Demolition (C&D) Waste Streams.
Schedule Submittal Register. See SOW under Submittals.
Schedule Underground Survey.
Written notification
Provide Contractor (ACM) Notification Form.
Contact list Provide contact list of all subcontractors.
Construction Site Plan
Construction Site Plan.
General Notes
Temporary Electrical System.
ENVIROMENTAL
Written Plan Work Plan that demonstrates conformance to the Comprehensive Procurement Guidelines (CPG) and Recovered Materials Advisory Notices (RMAN) published by EPA (https://www.epa.gov/smm/consolidated-recovered-materials-advisory-notices-rmans-comprehensive-procurement-guidelines-cpg) with respect to recovered material products, and bio-based recommendations published by USDA. See SOW under Green Procurement.
Written notification
Environmental Protection Plan. See specification section 01 57 20
Submittals List of hazardous materials, SDS sheets and statement of plan for storage. See SOW under Submittals.
SAFETY
Safety meetings
Activity Hazard Analysis
Contact list Designated Site Safety and Health Officer by GC
Written Plan See SOW under Health & Safety Plan. Include
Dust & debris control and dumpster schedule.
Contact list Crane Critical Lift Plan and Operators
Written Confirmation
Written Plan Excavation damage plan
SECURITY
Submittals See SOW under Antiterrorism/Operations Security Requirements.
Submittals See SOW under
Antiterrorism/Operations Security Requirements.
Submittals
Contact list See SOW under Key Personnel.
FIRE INSPECTOR
Fire Protection Inspector approval.
Submittals Hot Work Permit approval
GENERAL NOTES:
ACTION ITEMS: