Attachment 6 - Summary of Work.pdf

PDF 119 KB Posted

Attached to
Design-Build a Ground Based Strategic Deterrent (GBSD) Software Sustainment Center
Solicitation number
W9123821R0001
Issued by

About this file

This solicitation is for a design-build contract to construct a Software Sustainment Center at Hill Air Force Base in Utah. The project involves designing and building a 185,000 square foot secure facility with computer labs, conference rooms, offices, and a 560-stall parking garage. The selected contractor will perform all design work and construction, including civil, architectural, structural, mechanical, electrical and security elements. The estimated value of construction is between $100 million and $250 million. The facility will consolidate government and contractor personnel in a secure, classified environment to support software sustainment work. The U.S. Army Corps of Engineers District Sacramento is the contracting agency. The contractor must follow all security requirements for base access and personnel must complete anti-terrorism training within 30 days of contract award.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Summary of Work GBSD Software Sustainment Center

Hill AFB, UT

1. Scope of Work

The work for this project is to design and construct a Software Sustainment Center at Hill AFB, Utah which consists of an 185,000 SF mixed use Secure Facility with computer labs, auditorium style conference room and multiple secured office spaces. This facility also required a 560 stall parking garage. The Contractor shall provide all labor, equipment, transportation, material and supervision to perform the design and construction of the complete operational facilities. Design and construction shall include all civil, paving, architectural, geotechnical, structural, utilities, landscaping, security, mechanical, electrical, demolition, and communications work to support the necessary construction.

2. Description

2.1 The Contractor shall furnish and install all labor, materials, tools, equipment, and supervision necessary to provide a complete and usable project per the Specific Technical Engineering and Design Criteria, Functional Design Criteria Room by Room Requirements, including all attachments, Base Facility Design Standard, Architectural Compatibility Guide and requirements specified in the contract.

This project, the GBSD Mission Integration Facility (MIF), will allow the consolidation of both government and contractor personnel into one secured government-owned and managed facility.

The Software Sustainment Center includes a four story 185,000 square foot structure generally comprised of enclosed secure office spaces, auditorium, conference rooms, computer laboratories, SAPs, storage areas, restrooms, communications rooms, mechanical/electrical support spaces and a separate parking garage. It will provide the necessary facilities and the required security measures for personnel to perform work in a controlled, and classified environment.

This is a design-build contract therefore the Contractor is required to perform design work prior to construction. The Contractor is responsible and liable for the complete design and shall not assume that the provided design criteria and drawings in this solicitation will alleviate him/her from performing any additional design as required to produce a complete set of construction documents.

The Government’s conceptual facility and site design provided in the RFP documents illustrates intent and functional relationships and does not indicate all necessary construction requirements or components. The Specific Technical Engineering and Design Criteria and Functional Design Criteria Room by Room Requirements describes associated technical, performance and systems requirements. The Contractor is responsible for the complete project design, shall retain all responsibilities, and be recognized as the Designer of Record.

3. General Project Requirements:

Contractor shall follow all security requirements for base access. All Contractor and subcontractor personnel will need to obtain badges for all access on base from the security office.

Summary of Work GBSD Software Sustainment Center

Hill AFB, UT

AT Level I Training: All Contractor employees, including subcontractor employees, requiring access to Army installations, facilities, or controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever applies. The Contractor shall submit certificates of completion for each affected Contractor employee and subcontractor employee to the COR (or to the Contracting Officer, if a COR is not assigned) within 30 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at http://jko.jten.mil/courses/atl1/launch.html The Contractor shall be responsible for the coordination of work performed by their employees and all subcontractors. The Contractor should inspect all work areas prior to submitting a proposal in accordance with FAR 52.236-3, Site Investigation and Conditions Affecting the Work. It shall be the Contractor’s responsibility to verify all current record drawings prior to the start of any and all design and /or construction work. The Contractor shall be responsible for the coordination and proper relationship of this work to the building premises and thoroughly familiarize themselves with all details of the work and working conditions, to verify all dimensions in the field, and advise the Administrative Contracting Officer (ACO) of any discrepancies before performing any work.

The Contractor is responsible for maintaining the site and all other Contractor controlled areas in such a manner as to minimize the risk of injury or accident to site personnel or others who may be in the area. The Contractor is also responsible for furnishing an identification badge/card to each individual working on the site.

4. After award Administrative Contracting Officer (ACO) and post award POC and work coordination:

An Administrative USACE point of contact, ACO, and Contracting Officer Representative will be responsible for verifying that the Contractors’ performance and completion of work is in accordance with applicable requirements.

http://jko.jten.mil/courses/atl1/launch.html

2. Description
An Administrative USACE point of contact, ACO, and Contracting Officer Representative will be responsible for verifying that the Contractors’ performance and completion of work is in accordance with applicable requirements.

File details come from the government source that posted it. Updated .