This document is a Price Worksheet for a federal contract opportunity titled "Solicitation Amendment 0001 for Task Force Safety Assessments of Fire and Electricity/ Unified Facilities Criteria (TF SAFE)". The solicitation is being issued by the Department of the Army Corps of Engineers Engineering Support Center Huntsville.
The Price Worksheet includes pricing details for the base year and option years of the contract. The key tasks include an Electrical Assessment, Inspection and Repair Program, a Facility Inspection Program (UFC Teams), Other Direct Costs for equipment and travel, and Internet and Satellite Communications. The worksheet provides unit prices and required units for each task, with a total base year price of $1,000,000 and a total option year price of $1,000,000. There is also a 6-month option year extension with a total price of $500,000. The document specifies that all tasks labeled as "OPTIONAL" are optional for the government to exercise.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Worksheet
| BASE YEAR | ||||
| Task | Task Description | Unit Price | Units Required | Base Year Total |
| 1 | OPTIONAL Phase - In, Mobilization, and Work Plans | $0.00 | 1 | |
| 1a | OPTIONAL Mobilization and Demobilization for Optional Electrical Teams under Tasks 2b, 2c, and 2d | $0.00 | Up to 9 Teams | |
| 1b | OPTIONAL Mobilization and Demobilization for Optional UFC Team under Task 3b | $0.00 | 1 | |
| 2 | Electrical Assessment, Inspection and Repair Program | |||
| 2a | Key Personnel Package and Three Electrical Teams | $0.00 | 12 months | |
| 2b | OPTIONAL Three Additional Electrical Teams, Iraq and Syria | $0.00 | Up to 12 months | |
| 2c | OPTIONAL Three Additional Electrical Teams | $0.00 | Up to 12 months | |
| 2d | OPTIONAL Three Additional Electrical Teams | $0.00 | Up to 12 months | |
| 3 | Facility Inspection Program (UFC Teams) | |||
| 3a | UFC Inspection Team | $0.00 | 12 months | |
| 3b | OPTIONAL 1 Additional UFC Inspection Team | $0.00 | Up to 12 months | |
| 4 | Other Direct Costs (ODC) | |||
| 4a | Other Direct Costs - Equipment (CPFF) | N/A | 1 | $800,000.00 |
| 4b | NTE Travel (For travel within the CENTCOM AOR only) COST | N/A | 1 | $200,000.00 |
| 5 | Phase - Out - Contract Completion/Demobilization under Tasks 2a and 3a | $0.00 | 1 | |
| 6 | Internet Services and Satelite Communications | $0.00 | 12 months | |
| Total | $1,000,000.00 | |||
| OPTION YEAR | ||||
| Task | Task Description - ALL OPTIONAL | Unit Price | Units Required | Base Year Total |
| 1a | OPTIONAL Mobilization and Demobilization for Optional Electrical Teams under Tasks 2b, 2c, and 2d | $0.00 | Up to 12 Teams | |
| 1b | OPTIONAL Mobilization and Demobilization for Optional UFC Team under Task 3b | $0.00 | 1 | |
| 2 | Electrical Assessment, Inspection and Repair Program | |||
| 2a | OPTIONAL Key Personnel Package and Three Electrical Teams | $0.00 | Up to 12 months | |
| 2b | OPTIONAL Three Additional Electrical Teams, Iraq and Syria | $0.00 | Up to 12 months | |
| 2c | OPTIONAL Three Additional Electrical Teams | $0.00 | Up to 12 months | |
| 2d | OPTIONAL Three Additional Electrical Teams | $0.00 | Up to 12 months | |
| 3 | Facility Inspection Program (UFC Teams) | |||
| 3a | OPTIONAL 1 UFC Inspection Team | $0.00 | Up to 12 months | |
| 3b | OPTIONAL 1 Additional UFC Inspection Team | $0.00 | Up to 12 months | |
| 4 | Other Direct Costs (ODC) | |||
| 4a | OPTIONAL Other Direct Costs - Equipment (CPFF) | N/A | 1 | $800,000.00 |
| 4b | OPTIONAL NTE Travel (For travel within the CENTCOM AOR only) COST | N/A | 1 | $200,000.00 |
| 6 | OPTIONAL Internet Services and Satelite Communications | $0.00 | Up to 12 months | |
| Total | $1,000,000.00 |
| 52.217-8 Option Year (6 months extension) | ||||
| Task | Task Description | Unit Price | Units Required | Base Year Total |
| 1b | OPTIONAL Mobilization and Demobilization for Optional UFC Team under Task 3b | $0.00 | 1 | |
| 2 | Electrical Assessment, Inspection and Repair Program | |||
| 2a | OPTIONAL Key Personnel Package and Three Electrical Teams | $0.00 | Up to 6 months | |
| 2b | OPTIONAL Three Additional Electrical Teams, Iraq and Syria | $0.00 | Up to 6 months | |
| 2c | OPTIONAL Three Additional Electrical Teams | $0.00 | Up to 6 months | |
| 2d | OPTIONAL Three Additional Electrical Teams | $0.00 | Up to 6 months | |
| 3 | Facility Inspection Program (UFC Teams) | |||
| 3a | OPTIONAL 1 UFC Inspection Team | $0.00 | Up to 6 months | |
| 3b | OPTIONAL 1 Additional UFC Inspection Team | $0.00 | Up to 6 months | |
| 4 | Other Direct Costs (ODC) | |||
| 4a | OPTIONAL Other Direct Costs - Equipment (CPFF) | N/A | 1 | $400,000.00 |
| 4b | OPTIONAL NTE Travel (For travel within the CENTCOM AOR only) COST | N/A | 1 | $100,000.00 |
| 6 | OPTIONAL Internet Services and Satelite Communications | $0.00 | Up to 6 months | |
| Total | $500,000.00 |