ATTACHMENT 6 - MASTER SPECIFICATIONS 11272023 - 2125 Pages.pdf

PDF 8 MB Posted

Attached to
Construction Requirements Contract
Solicitation number
SP330024R0002
Issued by

About this file

This document is a multiple-award indefinite-delivery/indefinite-quantity (IDIQ) construction contract solicitation issued by the Defense Logistics Agency (DLA) Distribution. The contract will be for various construction, alteration, maintenance, and repair work at the DLA Distribution Susquehanna facility in New Cumberland and Mechanicsburg, Pennsylvania over a 5-year period. The estimated total contract value is $45 million. The solicitation will be issued as a 100% small business set-aside, with reservations for Women-Owned Small Businesses, Service-Disabled Veteran-Owned Small Businesses, and HUBZone Small Businesses. Award will be made on a best value basis using the lowest price technically acceptable source selection process. The contract ordering period is anticipated to be from August 1, 2024 to July 31, 2029, with individual task order completion periods based on the complexity of each project. The majority of the work is expected to be issued from April through September annually. Each awardee will be guaranteed a minimum of $5,000 during the first year.

View the file

Other files

File Type Posted
ATTACHMENT 1 - A0002 - Bldg 67 Revised Dwgs.pdf PDF
ATTACHMENT 3 - A0002 - 4232 Submittal Register Rev 01.pdf PDF
ATTACHMENT 2 - A0002 - BLDG 67 -Orig Constr Extract.pdf PDF
ATTACHMENT 4 - A0002 - BLDG 67 - DDSP ACM Assessment Extract.pdf PDF
SP330024R0002 A0001.pdf PDF
Site Visit Notes 6-21-2024.pdf PDF
SP330024R0002 SITE VIST ATTENDANCE SHEET.pdf PDF
ATTACHMENT 8 - Blank Payment request.xlsx XLSX spreadsheet
ATTACHMENT 2 - Pre-enrollment Photos - 5 Pages.pdf PDF
ATTACHMENT 7 - Change Order Proposal Format.xlsx XLSX spreadsheet
ATTACHMENT 12 - Task Order 0001 Project Number 4232 Specifications - 457 Pages.pdf PDF
ATTACHMENT 1- - 1818 Pre-enrollment sample - 1 Page.pdf PDF
ATTACHMENT 3 - SF24-16e - BID BOND - 2025 - 2 Pages.pdf PDF
ATTACHMENT 13 - Task Order 0001 Project Number 4232 Submittal Registers - 4 Pages.pdf PDF
ATTACHMENT 10 - Construction Wage Requirement for Task Oder 0001 - 8 Pages.pdf PDF
SP330024R0002 6-6-2024.pdf PDF
ATTACHMENT 5 - SF25A-16e - PAYMENT - 2025 - 2 Pages.pdf PDF
ATTACHMENT 15 - Past Performance Questionnaire - 5 Pages.docx DOCX document
ATTACHMENT 11 - Task Order 0001 Project 4232 Drawings - 22 Pages.pdf PDF
ATTACHMENT 4 - SF25-16e - PERFORMANCE - 2025 - 2 Pages.pdf PDF
ATTACHMENT 9 - Task Order 0001 Notice of Proposed Task Order Request For Proposal Form - 5 Pages.pdf PDF
ATTACHMENT 14 - 24-29 MATOC Eng_Form_4025_2017May - 2 Pages.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY 24-29 MATOC

Master Specifications

Defense Logistics Agency Defense Distribution Center, Susquehanna

New Cumberland, PA

DATE, XX, 2023

Installation Management (DM-FSI)

FY 24-29 MATOC Defense Distribution Center Susquehanna MASTER SPECIFICATIONS New Cumberland, PA

PROJECT TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK

01 14 00 11/22 WORK RESTRICTIONS

01 20 00 11/20, CHG 2: 08/21 PRICE AND PAYMENT PROCEDURES

01 30 00 11/20, CHG 2: 05/22 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 02/15 PROJECT SCHEDULE

01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES

01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND

REPORTING

01 35 26 11/20, CHG 3: 02/22 GOVERNMENTAL SAFETY REQUIREMENTS

01 45 00.10 20 02/10, CHG 3: 02/21 QUALITY CONTROL FOR MINOR CONSTRUCTION

01 50 00 11/20, CHG 2: 08/22 TEMPORARY CONSTRUCTION FACILITIES AND

CONTROLS

01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS

01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND

DISPOSAL

01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS

01 78 23 08/15, CHG 2: 08/21 OPERATION AND MAINTENANCE DATA

01 91 00.15 05/23, CHG 1: 08/23 BUILDING COMMISSIONING

DI VI SI ON 02 - EXI STI NG CONDI TI ONS

02 41 00 08/22 DEMOLITION AND DECONSTRUCTION

DI VI SI ON 03 - CONCRETE

03 01 00 02/18 REHABILITATION OF CONCRETE

03 30 00 02/19, CHG 3: 11/21 CAST-IN-PLACE CONCRETE

03 30 53 05/14 MISCELLANEOUS CAST-IN-PLACE CONCRETE

03 42 13.00 10 05/16 PLANT-PRECAST CONCRETE PRODUCTS FOR

BELOW GRADE CONSTRUCTION

03 62 16 02/18 METALLIC NON-SHRINK GROUTING

DI VI SI ON 05 - METALS

05 05 20 05/22 POST-INSTALLED CONCRETE AND MASONRY

ANCHORS

05 05 23.16 08/18 STRUCTURAL WELDING

05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL

05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING

05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS

05 51 00 02/17, CHG 1: 05/17 METAL STAIRS

05 51 33 02/16, CHG 2: 02/18 METAL LADDERS

05 52 00 02/18, CHG 1: 02/20 METAL RAILINGS

DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES

06 20 00 08/16, CHG 2: 11/18 FINISH CARPENTRY

06 41 16.00 10 08/10, CHG 1: 11/18 PLASTIC-LAMINATE-CLAD ARCHITECTURAL

CABINETS

06 61 16 08/20 SOLID SURFACING FABRICATIONS

DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON

07 21 13 02/16, CHG 2: 08/20 BOARD AND BLOCK INSULATION

07 21 16 11/11, CHG 4: 08/18 MINERAL FIBER BLANKET INSULATION

PROJECT TABLE OF CONTENTS Page 1

07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL

07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING

07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS

DI VI SI ON 08 - OPENI NGS

08 11 13 08/20 STEEL DOORS AND FRAMES

08 14 00 08/16, CHG 1: 08/18 WOOD DOORS

08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS

08 33 23 08/20, CHG 1: 02/22 OVERHEAD COILING DOORS

08 36 13 08/20 SECTIONAL OVERHEAD DOORS

08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE

08 81 00 05/19 GLAZING

08 91 00 08/20 METAL WALL AND DOOR LOUVERS

DI VI SI ON 09 - FI NI SHES

09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD

09 30 10 08/20 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 08/20 ACOUSTICAL CEILINGS

09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING

09 68 00 11/17, CHG 2: 08/20 CARPETING

09 90 00 02/21 PAINTS AND COATINGS

DI VI SI ON 10 - SPECI ALTI ES

10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE

10 14 00.20 08/20 INTERIOR SIGNAGE

10 14 10.00 10 10/23 MECHANICAL SIGNAGE

10 14 20.00 10 10/23 FIRE PROTECTION SYSTEM SIGNAGE

10 21 13 08/20 TOILET COMPARTMENTS

10 28 13 08/20 TOILET ACCESSORIES

DI VI SI ON 11 - EQUI PMENT

11 13 19.13 08/09, CHG 1: 05/19 LOADING DOCK LEVELERS

DI VI SI ON 12 - FURNI SHI NGS

12 21 00 08/17, CHG 2: 11/18 WINDOW BLINDS

DI VI SI ON 21 - FI RE SUPPRESSI ON

21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE

PROTECTION

21 13 16 08/20 DRY PIPE SPRINKLER SYSTEMS, FIRE

PROTECTION

21 13 18 08/20 PREACTION SPRINKLER SYSTEMS, FIRE

PROTECTION

21 13 19 08/20 DELUGE SPRINKLER SYSTEMS, FIRE

PROTECTION

21 95 00.00 10 10/23 FIRE SUPPRESSION REPAIRS AND IMPAIRMENT

DI VI SI ON 22 - PLUMBI NG

22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE

22 05 48.00 20 04/06, CHG 1: 05/15 MECHANICAL SOUND, VIBRATION, AND

SEISMIC CONTROL

PROJECT TABLE OF CONTENTS Page 2

22 07 19.00 40 02/23 PLUMBING PIPING INSULATION

DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)

23 03 00.00 20 08/10, CHG 3: 08/18 BASIC MECHANICAL MATERIALS AND METHODS

23 05 15 05/22 COMMON PIPING FOR HVAC

23 05 48.00 40 05/22 VIBRATION AND SEISMIC CONTROLS FOR

HVAC PIPING AND EQUIPMENT

23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR

HVAC

23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL

SYSTEMS

23 08 00 05/23 COMMISSIONING OF MECHANICAL SYSTEMS

23 09 00 02/19, CHG 3: 05/21 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES

FOR HVAC

23 09 23.01 02/19, CHG 1: 02/20 LONWORKS DIRECT DIGITAL CONTROL FOR

HVAC AND OTHER BUILDING CONTROL SYSTEMS

23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC

AND OTHER BUILDING CONTROL SYSTEMS

23 09 53.00 20 02/10, CHG 2: 08/17 SPACE TEMPERATURE CONTROL SYSTEMS

23 09 93 11/15 SEQUENCES OF OPERATION FOR HVAC CONTROL

23 11 20 05/20 FACILITY GAS PIPING

23 21 13.00 20 04/06, CHG 2: 11/19 LOW TEMPERATURE WATER (LTW) HEATING

SYSTEM

23 21 23 08/17 HYDRONIC PUMPS

23 22 26.00 20 02/10, CHG 1: 05/15 STEAM SYSTEM AND TERMINAL UNITS

23 23 00 08/21 REFRIGERANT PIPING

23 25 00 05/21 CHEMICAL TREATMENT OF WATER FOR

MECHANICAL SYSTEMS

23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION

23 34 23.00 40 02/17 HVAC POWER VENTILATORS

23 36 00.00 40 08/22 AIR TERMINAL UNITS

23 37 13.00 40 08/22 DIFFUSERS, REGISTERS, AND GRILLES

23 52 00 04/08, CHG 5: 11/19 HEATING BOILERS

23 52 43.00 20 05/15, CHG 2: 08/18 LOW PRESSURE WATER HEATING BOILERS

(UNDER 800,000 BTU/HR OUTPUT)

23 57 10.00 10 11/19 FORCED HOT WATER HEATING SYSTEMS USING

WATER AND STEAM HEAT EXCHANGERS

23 64 10 11/16, CHG 2: 08/18 WATER CHILLERS, VAPOR COMPRESSION TYPE

23 64 26 08/09, CHG 6: 11/22 CHILLED, CHILLED-HOT, AND CONDENSER

WATER PIPING SYSTEMS

23 65 00 11/16, CHG 2: 08/18 COOLING TOWERS AND REMOTE

EVAPORATIVELY-COOLED CONDENSERS

23 74 33.00 40 05/17 PACKAGED, OUTDOOR, HEATING AND COOLING

MAKEUP AIR-CONDITIONERS

23 80 20.00 10 05/20 GAS-FIRED HEATING EQUIPMENT

23 81 00 05/18, CHG 1: 02/21 DECENTRALIZED UNITARY HVAC EQUIPMENT

23 81 29 02/20 VARIABLE REFRIGERANT FLOW HVAC SYSTEMS

23 82 00.00 20 02/16, CHG 1: 08/18 TERMINAL HEATING UNITS

23 82 19.00 40 05/17 FAN COIL UNITS

23 82 46.00 40 05/17 ELECTRIC UNIT HEATERS

DI VI SI ON 26 - ELECTRI CAL

26 20 00 08/19, CHG 3: 11/21 INTERIOR DISTRIBUTION SYSTEM

26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS

UNDER 600 VOLTS

26 42 13 05/21 GALVANIC (SACRIFICIAL) ANODE CATHODIC

PROJECT TABLE OF CONTENTS Page 3

PROTECTION (GACP) SYSTEM

26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING

26 56 00 08/21 EXTERIOR LIGHTING

DI VI SI ON 27 - COMMUNI CATI ONS

27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING

SYSTEM

DI VI SI ON 31 - EARTHWORK

31 00 00 08/08, CHG 2: 02/21 EARTHWORK

31 05 19.13 02/21 GEOTEXTILES FOR EARTHWORK

31 11 00 11/18 CLEARING AND GRUBBING

31 23 00.00 20 02/11, CHG 2: 08/15 EXCAVATION AND FILL

31 36 00 02/21 GABIONS

DI VI SI ON 32 - EXTERI OR I MPROVEMENTS

32 01 16.71 02/17 COLD MILLING ASPHALT PAVING

32 01 17.61 05/22 SEALING CRACKS IN ASPHALT PAVING

32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT

32 01 29.61 05/17, CHG 1: 08/17 PARTIAL DEPTH PATCHING OF RIGID PAVING

32 05 33 08/17 LANDSCAPE ESTABLISHMENT

32 11 20 05/22 SUBBASE COURSES FOR RIGID AND FLEXIBLE

PAVING

32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS

32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING

32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS

32 31 13.53 11/21 HIGH-SECURITY CHAIN LINK FENCES AND

GATES

32 92 19 08/17, CHG 1: 08/21 SEEDING

32 93 00 08/17, CHG 1: 08/21 EXTERIOR PLANTS

DI VI SI ON 33 - UTI LI TI ES

33 11 00 02/18, CHG 1: 02/22 WATER UTILITY DISTRIBUTION PIPING

33 30 00 05/18 SANITARY SEWERAGE

33 40 00 11/21 STORMWATER UTILITIES

33 46 13 05/20 FOUNDATION DRAINAGE

33 46 16 05/18 SUBDRAINAGE PIPING

33 61 13.19 02/16 VALVES, PIPING, AND EQUIPMENT IN VALVE

MANHOLES

33 63 13 04/06 EXTERIOR UNDERGROUND STEAM

DISTRIBUTION SYSTEM

33 71 01 05/19, CHG 1: 11/19 OVERHEAD TRANSMISSION AND DISTRIBUTION

33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION

DI VI SI ON 40 - PROCESS I NTERCONNECTI ONS

40 05 13.96 05/10 WELDING PROCESS PIPING

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 4

SECTION 01 11 00

SUMMARY OF WORK

08/ 15, CHG 2: 08/ 21

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Salvage Plan; G

Sequence of Procedure; G

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes individual project as described in the Reqeust for Proposal (RFP), and individual projects (as issued by Task Order) under the awarded Task Order Contract, and incidental related work.

1.2.2 Location

The work is located at the Defense Distibution Center Susquehanna. Refer to the Contract documents provided in the RFP and individual projects (as issued by Task Order) under the awarded Task Order Contract, and incidental work.

1.3 OCCUPANCY OF PREMISES

Building(s) will be occupied during performance of work under this Contract.

Before work is started, arrange with the Contracting Officer a Sequence of Procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways and stairways required to execute the work. The sequence shall be provided in writing and shall be approved by the COR prior to the start of field work. This is not a construction schedule, but a written sequence that will incorporate events during construction and share milestones required. See 01 32 01.00 10.

1.4 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as

SECTION 01 11 00 Page 1 approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.5 LOCATION OF UNDERGROUND UTILITIES

Location of the existing utilities indicated are approximate. Contractor is responsible for requesting existing underground utilities be located prior to beginning work. Contractor is also responsible for verifying the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated to be relocated or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made. See Section 01 78 00, Closeout Submittals for additional information. Contractor is responsible to maintain markings

1.5.1 Notification Prior to Excavation

Notify the Contracting Officer at least 5 working days prior to starting excavation work.

1.6 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within 5 miles of the construction site.

Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Provide a system for property control in the salvage plan. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 2

SECTION 01 14 00

WORK RESTRICTIONS

11/22

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel

1.2 SPECIAL SCHEDULING REQUIREMENTS

a. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.

b. The Installation will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.

c. Permission to interrupt any activity, road, or utility service must be requested in writing and the government has a minimum of 15 calendar days to approve the desired date of interruption.

1.3 CONTRACTOR ACCESS AND USE OF PREMISES

1.3.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.

1.3.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.3.1.2 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines.

SECTION 01 14 00 Page 1

1.3.1.3 Identification Badges and Installation Access

Contractor Badges:

a. All badges are the property of the United States government. Badges must be displayed at all times while on the installation unless prohibited by safety concerns. Badges will not be photographed or copied and will not be displayed off the installation. Any lost or stolen badges will be reported to the COR and Installation Security immediately. The Contractor will ensure that all badges are returned upon the termination of the contract or individual employees.

Contractor is required to maintain a spread sheet with all badge request information including badge expiration date. This spread sheet will be forwarded to the COR on the first of every month

b. All persons, with the exception of delivery truck drivers and persons possessing valid Government Common Access Cards (CACs), entering the Installation must obtain an Identification Badge from Security, Pass and ID. All contractors will receive a badge for the duration of the contract. The construction contractor shall follow the below procedures to obtain and renew Identification Badges for all direct hire and subcontractor employees and visitors

1.Installation access is via electronic enrollment through the Defense Biometric Identification System (DBIDS) pre-enrollment website.

2. The electronic enrollment must be coordinated with the COR and by using website https://dbids-global.dmdc.mil/enroll.

c. Installation Access

1. Obtaining Contractor ID Badge - Enter the Installation at Post #3 off of Old Depot Road and go to the Visitor's Center located just inside the Installation Entrance. Personnel shall acquire their ID Badges at the Visitor's Center building. The hours of operation for Pass and ID is 0700 to 1500. Contractor personnel that have not been included on the DL1818 through the COR will not be issued ID Badges or granted access to the Installation.

2. Privately Owned Vehicles (POVs) - POVs transporting Contractor personnel must enter the Installation via Post 3 off Old Depot Road, provided they are not transporting tools, equipment, or supplies. All persons in Contractor vehicles are required to show ID Badges at the security booths. All vehicles entering the Installation at Post 3 are subject to random vehicle search procedures. POV's can't be parked next to a building, they must be parked in an official parking lot.

3. Contractor and Construction Vehicles - Driving any form of vehicle designed to carry tools, equipment, supplies, or materials necessary for the work are required to enter the installation via Post 4 off of Old York Road (at Normandy Drive). All persons in Contractor vehicles are required to show ID Badges at the Vehicle Search Area. All vehicles entering the Installation at Post 4 are subject to vehicle search procedures.

d. Construction Deliveries

SECTION 01 14 00 Page 2

Delivery notifications must be sent to the COR 24 hours before scheduled delivery.

Deliver equipment and materials to the site in an undamaged condition. Material that is deemed to be damaged or defective by the Contracting Officer Representative from manufacturing, during shipment, or while on-site shall be replaced at the Contractor's expense. Equipment and materials that are deemed to be damaged or defective shall be removed and properly disposed of by the Contractor. New equipment and materials shall be utilized to replace rejected materials or equipment.

Contractors shall receive material and equipment at their own facility and transport this equipment to the Installation and project site themselves. Government is not responsible for damage to material and equipment shipped directly to the Installation.

Contractor must be present to accept shipment of material directly to the Installation. Material that is shipped to the main warehouse (Building 2001) can easily be lost in the midst of the large volume of material constantly moving through the receiving warehouse. Material that is shipped to the Installation and subsequently lost shall be replaced at the Contractors expense.

All contractor deliveries shall enter the Installation at Post 4.

To avoid delays at Post 4, deliveries should be scheduled to arrive after 0800 whenever possible. The Construction Contractor shall follow the following procedure for all deliveries (including pick-ups at the construction site):

1. After being processed by DLA Police in the Post 4 Vehicle Search Area, Delivery Vehicles are directed to proceed onto the Installation and into the vehicle holding area where they must wait for an authorized member of the Construction Contractor to escort them from Post 4 to the construction site. The Construction Contractor's Site Supervisor is responsible for coordinating all material deliveries and providing all required vehicle escorts. Upon completion of material delivery, the Construction Contractor is responsible for escorting the delivery vehicle back to Post 4 to exit the Installation.

e. Delivery Escort Authorization

Personnel that intend to escort deliveries arriving at Gate 4 to the construction site will require special annotation on their contractor badges to enable this activity. Contractors may provide up to 2 names of persons authorized to escort their deliveries on the depot. If the contractor intends to use subcontractors, each sub-contractor is authorized to have one (1) person designated as an escort for their deliveries. To obtain this authorization, note the designated escort with the words:

"Authorization Request for Construction Delivery Escort" on the DL1818 when it is submitted.

1.3.2 Photographs

Cameras may be possessed and operated by authorized persons only. To obtain a Camera Pass, the Contractor must provide the following information to the COR:

SECTION 01 14 00 Page 3

a. Camera Pass Request Form must be provided to the contractor by the COR. Indicate on the request form that the contractor will be under contract with us for numerous ongoing projects. The COR will validate the Contractor's request information and forward the Camera Pass Request Form to Installation Security. If approved, the COR will notify the Contractor that a Camera Pass can be obtained at the Pass & ID Building. Camera Pass requests shall be kept to a minimum and limited to Prime Contractor personnel only. A Camera Pass must be in the possession of the person taking the photographs at all times and presented whenever requested by Government personnel. Failure to maintain or loss of Camera Passes must be reported to COR for action.

Installation Security will be notified as necessary by the COR.

Personnel found to be in the possession of photographic equipment without the proper documentation will have their equipment confiscated, contents reviewed and returned upon their departure of the Installation or other arrangements will be made.

b. Only Digital Still Cameras should be used. Cell phones and tablets are NOT authorized under any circumstances for taking photographs. All images captured on digital cameras must be reviewed by Installation Security prior to removing the Camera from the Installation. Cameras must be brought to the Public Safety Facility, Building 911, on J Avenue at the end of each work day and surrendered to Installation Security Staff for review. Any images found to contain images of unauthorized items or areas will be deleted prior to return to Contractor personnel.

c. Do not take pictures of Contractor or Government Employee ID Badges, identification signs, certain stored materials (as clarified by the COR), security hardware, fire suppression systems, utilities fixtures, or other areas, facilities, or improvements unless images of such are specifically required by the project.

1.3.3 Employee List

The Contractor must provide to the Contracting Officer, in writing, the names of two designated representatives authorized to request personnel and vehicle passes for employees and subcontractor's employees prior to commencement of work under this contract.

1.3.4 Working Hours

Regular working hours will consist of an 8 1/2 hour period, between 7 a.m.

and 3:30 p.m., Monday through Friday, excluding Government holidays.

1.3.5 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.

1.3.6 Occupied and Existing Building

The Contractor shall be working in an existing building and around

SECTION 01 14 00 Page 4 existing buildings which are occupied. Do not enter the building[s] without prior approval of the Contracting Officer.

The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.

Provide dust covers or protective enclosures to protect existing work that remains, and Government material located in the the way of the contractor during the construction period.

Relocate movable furniture away from the Contractor's working area as required to perform the work, protect the furniture, and replace the furniture in their original locations upon completion of the work. Leave attached equipment in place, and protect them against damage, or temporarily disconnect, relocate, protect, and reinstall them at the completion of the work.

1.3.7 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and TV are considered utility cutovers pursuant to the paragraph

WORK OUTSIDE REGULAR HOURS.

d. Operation of Station Utilities: The Contractor shall be responsible for the operation of control devices in the Installation Utilities System, including water, sewer, electrical, and steam services unless indicated otherwise in the contract documents. The Government will provide supervision and direct which control devices to operate. The Contractor shall not operate control devices except when the COR is present. Permission to operate/interrupt a utility service must be requested in writing and the government has a minimum of 15 calendar days to approve the desired date of operation/interruption.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 14 00 Page 5

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 01 14 00 Page 6

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

11/ 20, CHG 2: 08/ 21

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Schedule of Prices; G

1.2 SCHEDULE OF PRICES

1.2.1 Data Required

Provide a detailed breakdown of the Contract price, giving quantities for each of the various kinds of work, unit prices and extended prices.

Contractor overhead and profit including salaries for field office personnel, if applicable, must be proportionately spread over all pay items and not included as individual pay items.

1.2.2 Payment Schedule Instructions

Payments will not be made until the Schedule of Prices has been submitted to and accepted by the Contracting Officer Representative.

1.3 CONTRACT COST BREAKDOWN

The Contractor must furnish within 10 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer Representative as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer Representative to agree with a reasonable cost of the work included in the various items. This Contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.

1.4 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT

1.4.1 Submission of Invoices

If DFARS Clause 252.232-7006 Wide Area WorkFlow Payment Instructions is included in the Contract, provide the documents listed in above paragraph CONTENT OF INVOICE in their entirety as attachments in Wide Area Work Flow (WAWF) for each invoice submitted. If a document cannot be attached in WAWF due to system or size restriction, provide it as instructed by the Contracting Officer Representative.

SECTION 01 20 00 Page 1

1.4.2 Final Invoice

a. A final invoice must be accompanied the Contractor's Final Release. If the Contractor is incorporated, the Final Release must contain the corporate seal. An officer of the corporation must sign and the corporate secretary must certify the Final Release.

1.5 PAYMENTS TO THE CONTRACTOR

Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.

1.5.1 Obligation of Government Payments

The obligation of the Government to make payments required under the provisions of this Contract will, at the discretion of the Contracting Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR

32.103 Progress Payments Under Construction Contracts:

a. Reasonable deductions due to defects in material or workmanship;

b. Claims which the Government may have against the Contractor under or in connection with this Contract;

c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and

d. Failure to maintain accurate "as-built" or record drawings in accordance with FAR 52.236.21.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 20 00 Page 2

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

11/ 20, CHG 2: 05/ 22

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Progress and Completion Pictures

1.3 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.

Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch.

Include a date designator in file names. Photographs provided are for unrestricted use by the Government.

1.4 SUPERVISION

1.4.1 Superintendent Qualifications

Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size, scope of work, and complexity. Submit resume as record of experience. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same

SECTION 01 30 00 Page 1 as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

1.4.2 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.

1.4.3 Duties

The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.4.4 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time, for excess costs, or damages by the Contractor.

1.5 PRECONSTRUCTION CONFERENCE

Immediately after award , prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Conference . The conference must take place within 10 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this conference is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.

1.5.1 Attendees

Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.

1.6 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)

Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning

SECTION 01 30 00 Page 2 the turnover process at the Pre-Construction Conference meeting with a discussion of the Red Zone process and convene at regularly scheduled NRZ Meetings beginning at approximately 75 percent of project completion.

Include the following in the facility Turnover effort:

1.6.1 Red Zone Checklist

a. Contracting Officer's Representative (COR) will provide the Contractor a copy of the Red Zone Checklist template.

b. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. The Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.

1.6.2 Meetings

a. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion.

b. Hold Red Zone meetings every two weeks then increase to weekly the final 30 days of the project.

c. Using the Red Zone Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.

d. During the Red Zone Meetings discuss with the COR any upcoming activities that require Government involvement.

e. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress.

Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.

1.7 MOBILIZATION

Contractor shall mobilize to the jobsite within 20 calendar days of receiving the Notice to Proceed. Mobilize is defined as having equipment and having a physical presence of at least one person from the contractor's team on the jobsite.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 30 00 Page 3

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 01 30 00 Page 4

SECTION 01 32 01.00 10

PROJECT SCHEDULE

02/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (2017) Administration -- Project Schedules

1.2 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Initial Project Schedule; G

Periodic Schedule Update; G

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules must be Microsoft Project (current version). Provide the "mpp" export file in the version of Project used and importable by the Government system.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.

SECTION 01 32 01.00 10 Page 1

Prepare each Project Schedule using the Precedence Diagram Method (PDM).

3.2 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.

3.2.1 Activity Cost Loading

Activity cost loading must be reasonable and without front-end loading.

Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.

3.2.2 Withholdings / Payment Rejection

Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.

In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

3.3.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.

Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.

3.3.3 Procurement Activities

Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.

3.3.4 Mandatory Tasks

Include the following activities/tasks in the initial project schedule and all updates.

a. Submission, review and acceptance of SD-01 Preconstruction Submittals

SECTION 01 32 01.00 10 Page 2

(individual activity for each).

c. Submission of mechanical/electrical/information systems layout drawings.

d. Long procurement activities

e. Submission and approval of O & M manuals.

f. Submission and approval of as-built drawings.

g. Submission and approval of DD1354 data and installed equipment lists.

h. Submission and approval of testing and air balance (TAB Firm).

i. Submission of TAB specialist design review report.

j. Submission and approval of fire protection specialist.

k. Submission and approval of Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.

l. Air and water balancing.

m. Commissioning - Functional Performance Testing.

n. Controls testing plan submission.

o. Controls testing.

p. Performance Verification testing.

q. Other systems testing, if required.

r. Contractor's pre-final inspection.

s. Correction of punch list from Contractor's pre-final inspection.

t. Government's pre-final inspection.

u. Correction of punch list from Government's pre-final inspection.

v. Final inspection.

3.3.5 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

SECTION 01 32 01.00 10 Page 3

3.3.6 Standard Activity Coding Dictionary

Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11 . This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site: http://rms.usace.army.mil .

The SDEF format is as follows:

Field Activity Code Length Description

1 WRKP 3 Workers per day

2 RESP 4 Responsible party

3 AREA 4 Area of work

4 MODF 6 Modification Number

5 BIDI 6 Bid Item (CLIN)

6 PHAS 2 Phase of work

7 CATW 1 Category of work

8 FOW 20 Feature of work*

*Some systems require that FEATURE OF WORK values be placed in several activity code fields. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.

3.3.6.1 Workers Per Day (WRKP)

Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.

3.3.6.2 Responsible Party Coding (RESP)

Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.

a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.

b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);

ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).

SECTION 01 32 01.00 10 Page 4

3.3.6.3 Area of Work Coding (AREA)

Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.

Activities cannot have more than one Work Area Code.

Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.

3.3.6.4 Modification Number (MODF)

Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.

3.3.6.5 Bid Item Coding (BIDI)

Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.

3.3.6.6 Phase of Work Coding (PHAS)

Assign Phase of Work Code to all activities. Examples of phase of work are procurement phase and construction phase. Each activity can have only one Phase of Work code.

a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.

b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.

3.3.6.7 Category of Work Coding (CATW)

Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.

3.3.6.8 Feature of Work Coding (FOW)

Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.

Definable Feature of Work is defined in Section 01 45 00.00 10 QUALITY CONTROL. An activity can have only one Feature of Work Code.

SECTION 01 32 01.00 10 Page 5

3.3.7 Contract Milestones and Constraints

Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.

Mandatory constraints that ignore or effect network logic are prohibited.

No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.

3.3.7.1 Project Start Date Milestone and Constraint

The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.

3.3.7.2 End Project Finish Milestone and Constraint

The last activity in the schedule must be a finish milestone titled "End Project."

Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.

3.3.7.3 Interim Completion Dates and Constraints

Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.

3.3.7.3.1 Start Phase

Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.

3.3.7.3.2 End Phase

Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.

3.3.8 Calendars

Schedule activities on a Calendar to which the activity logically belongs. Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop seasonal Calendar(s) and assign to seasonally affected activities as applicable.

If an activity is weather sensitive it should be assigned to a calendar

SECTION 01 32 01.00 10 Page 6 showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated adverse weather delay work days provided in the Special Contract Clauses. Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends .

3.3.9 Open Ended Logic

Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End Project" may have no successor logic.

Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.

3.3.10 Default Progress Data Disallowed

Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports.