Attachment 5 - Repair Interior Finishes Vosler B2602 - MSS.xls

XLS spreadsheet 54 KB Posted

Attached to
Repair Interior Finishes Vosler
Solicitation number
FA301023R0033
Issued by

About this file

This document is a material submittal schedule for the federal contract opportunity FA301023R0033 to repair interior finishes at Vosler Building 2602 for the Department of the Air Force Air Education and Training Command. The schedule requires the contractor to submit materials data and samples for 13 items, including paint, acoustical panel ceilings, resilient flooring accessories, rubber wall base, tile carpeting, and corner guards. The contractor must provide certificates of compliance, shop drawings, color samples, manufacturer warranties and recommendations, catalog data, and operation instructions for review, with submission dates ranging from 5 to 11 days following notice to proceed. The schedule also includes fields to track submittal numbers, review dates, approvals, resubmittals, and final approval dates.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Material Submittals Schedule

Project Number:
MAHG231026Project Title:
REPAIR INTERIOR FINISHES B2602Solicitation / Contract Number:

FA301023R0033; Attachment #5

Line Number(To be completed by Project Engineer)(To be completed by Contract Administrator)
Number of Copies Required (if not electronically submitted)Remarks
Item or Description of Item, Contract Reference, Type of SubmittalCertificate of ComplianceShop DrawingsSamples (Material sample of each color)Color Selection (Schedules, fan decks, etc.)Manufacturer's RecommendationWarranty-Manufacturer and/or WorkmanshipCatalog DataOperating InstructionsSchedules, Listings, Reports, PlansTechnical DataTest ReportsField ReportsRequired Submission DateDate Received in ContractingDate to Civil EngineeringReturn Suspense DateSubmittal NumbersDate Contractor
NotifiedContractor ResubmittalFinal Approval
ApprovedDisapproved
1HazMat Questionnaire15 Days Prior to Start Date
2HazMat MSDS15 Days Prior to Start Date
3Hazmat Reporting Entry Form15 Days Prior to Start Date
4Hazmat Reporting Entry Form1End of Contract
5Recycling and Landfill Report1End of Contract
6Warranty (Manufacturer's)1End of Contract
71-Year Warranty (Contractor)1End of Contract
809 09 91 00 PAINT113111110 Days Following NTP
909 51 10ACOUSTICAL PANEL CEILINGS113111110 Days Following NTP
1009 65 01 RESILIENT FLOORING ACCESSORIES113111111 Days Following NTP
11SECTION 09 65 13- RUBBER WALL BASE113111110 Days Following NTP
1209 68 13 TILE CARPETING113111110 Days Following NTP
1310 26 13-InPro Corner-Guard113111110 Days Following NTP

&L&"Verdana,Bold"&12Schedule of Material Submittals&C&12Print on Legal size paper ( 8 x 14 ).

&R&P of &N Enter the due date from the Contractor (MM/DD/YY) Enter the date received from the Contractor. (MM/DD/YY) Enter the date submittal was given to CE for review. (MM/DD/YY) Enter the date the submittal is due back from CE

(MM/DD/YY)

Enter the Submittal Number Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

Enter Resubmittal Number Enter the submittal final approval date

(MM/DD/YY)