Attachment 5 Performance Based Payment Milestones.pdf
PDF 92 KB Posted
- Attached to
- TR-232C Transducers
- Solicitation number
- N66604-24-R-0144
About this file
This document is the Attachment 5 - Performance Based Payment Milestones for Solicitation N66604-24-R-0144 for TR-232C Transducers. It outlines the milestone-based progress payment plan for the first article and production CLINs under this contract opportunity.
For the first article CLIN 0001, the contract has 4 milestones worth a total of 80% of the CLIN price: 1) Preliminary Configuration Review (20%), 2) Final Configuration Review (20%), 3) First Article material receipt (20%), and 4) Delivery of First Article transducers (20%). For the production CLINs, there are 3 milestones worth a total of 50% of the CLIN price: 1) Drawings and Production Documentation released (15%), 2) Material Ordered (15%), and 3) 90% of material line items received (20%). The verification methods for each milestone are specified, requiring contractor-provided reports and government acceptance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0003.pdf | ||
| N6660424R0144P0002.pdf | ||
| N6660424R0144P0001.pdf | ||
| N6660424R0144.pdf | ||
| Exhibit A CDRLs_24JAN24 (Signed)-1_Redacted.pdf | ||
| Attachment 1 DD254 SCO Validated and Attachments.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TR-232C CLIN 0001 Milestones (First Article)
Severable/Cumulative Percent CLIN 0001
Price Milestone Completion Verification Method
1. Preliminary Configuration Review (PCR) Completion
Severable 20% PCR is conducted IAW the SOW. TPOC receives, reviews, and accepts contractor-submitted PCR presentation package and supporting technical documentation.
2. Final Configuration Review (FCR) Completion
Cumulative - based on milestone #1 20% FCR is conducted IAW the SOW. TPOC receives, reviews, and accepts contractor-submitted FCR presentation package and supporting technical documentation.
3. First Article material received Cumulative - based on milestones #1 and #2. 20% Contractor provides internal report to TPOC which provides proof of purchased material receipt (receipt report and date received).
4. Delivery of First Article transducers Cumulative - based on milestones #1, #2, and #3. 20% Contractor delivers First Article transducers and the Government receives them
TOTAL: 80%
TR-232C PRODUCTION CLINs Milestones
Severable/Cumulative Percent CLIN Price Milestone Completion Verification Method
1. Drawings and Production Documentation released.
Severable 15%
DCMA representative receives, reviews, and accepts contractor-submitted Product Baseline Drawing listing and supporting technical documentation. Contractor provides internal report to DCMA representative which provides proof of release of production documentation.
2. Material Ordered Cumulative - based on milestone #1 15% Contractor provides internal report to DCMA representative which provides proof that the material was ordered (PO number and date issued).
3. 90% of material line items received. Cumulative - based on milestones #1 and #2 20% Contractor provides internal report to DCMA representative which provides proof that the material was received against the purchase orders (PO) which were placed
TOTAL: 50%
Solicitation N66604-24-R-0144 for TR-232C Transducers Proposed Milestone Progress Payment Plan
Solicitation N66604-24-R-0144 for TR-232C Transducers Proposed Milestone Progress Payment Plan
File details come from the government source that posted it. Updated .