Attachment 5. MAHG231012 Clean Ductwork Lott Hall_MSS Rev1.xlsx
XLSX spreadsheet 29 KB Posted
- Solicitation number
- FA301024R0010
About this file
The provided document is a Material Submittals Schedule for the MAHG 23-1012 Clean Ductwork at Trent Lott Hall B2603 federal contract opportunity. It lists the various required submittals, including hazardous materials questionnaires, reports, safety plans, equipment details, and post-project reports. The submittals have specified due dates, with most due within 5-10 days after the notice to proceed. The contract opportunity is a Historically Underutilized Business Zone (HUBZone) set-aside with an estimated value between $250,000 and $500,000. An organized site visit is scheduled for August 6, 2024. The contract will require air testing and balancing, and the contractor will provide a 1-year warranty. Funds are not currently available, and the government reserves the right to cancel the solicitation.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule
| Project Number: | ||
| MAHG 23 1012 | Project Title: | |
| CLEAN DUCTWORK AT B2603 TRENT LOTT HALL | Solicitation / Contract Number: |
FA301024R0010
Attachment 5.
| Line Number | (To be completed by Project Engineer) | (To be completed by Contract Administrator) | |||||||||||||
| Number of Copies Required (if not electronically submitted) | Remarks | ||||||||||||||
| Item or Description of Item, Contract Reference, Type of Submittal | Contract Reference | ||||||||||||||
| for Submittal | Certificate of Compliance | Shop Drawings | Samples | Color Selection | Manufacturer's Recommendation | Warranty-Manufacturer and/or Workmanship | Catalog Data | Operating Instructions | Schedules, Listings, Reports, Plans | Technical Data | Test Reports | Field Reports | Required Submission Date |
fergusog: Enter the due date from the Contractor (MM/DD/YY) Date Received in Contracting fergusog: Enter the date received from the Contractor. (MM/DD/YY) Date to Civil Engineering fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY) Return Suspense Date fergusog: Enter the date the submittal is due back from CE
(MM/DD/YY)
Submittal Numbers fergusog: Enter the Submittal Number
| Date Contractor | ||
| Notified | Contractor Resubmittal |
fergusog: Enter Resubmittal Number Final Approval fergusog: Enter the submittal final approval date
(MM/DD/YY)
Approved fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
fergusog: Enter Resubmittal Number Disapproved fergusog: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
fergusog: Enter the submittal final approval date
(MM/DD/YY)
| 1 | HazMat Questionnaire | SOW sect 4.4 | 3 | 3 | 3 | 5 Days Prior to Start Date | ||||
| 2 | HazMat MSDS | SOW sect 4.4 | 3 | 3 | 3 | 5 Days Prior to Start Date | ||||
| 3 | Hazmat Reporting Entry Form | SOW sect 4.4 | 3 | 3 | 3 | 5 Days Prior to Start Date | ||||
| 4 | Hazmat Reporting Entry Form | SOW sect 4.4 | 3 | 3 | 3 | End of Contract | ||||
| 5 | Recycling and Landfill Report | SOW sect 4.1 | 3 | 3 | 3 | End of Contract | ||||
| 6 | Asbestos Abatement Report | SOW sect 4.7.3 | 3 | 3 | 3 | 5 Days Prior to Start Date | ||||
| 7 | Project Safety Plan | SOW sect 3.1.1 | 3 | 3 | 3 | 5 Days Prior to Start Date | Provide EDD of equipment, with submittal | |||
| 8 | AF 3065 Project Schedule | SOW sect 3.4.1 | 3 | 3 | 3 | 5 Days Prior to Start Date | Provide EDD of equipment, with submittal | |||
| 9 | Existing Conditions Report | |||||||||
| AHU-1, SF-1 | SOW Appndx A | 1 | 1 | 1 | 5 Days After NTP | |||||
| 10 | Existing Conditions Report | |||||||||
| EF-1 | SOW Appndx A | 1 | 1 | 1 | 5 Days After NTP | |||||
| 11 | Existing Conditions Report | |||||||||
| EF-2 | SOW Appndx A | 1 | 1 | 1 | 5 Days After NTP | |||||
| 12 | Existing Conditions Report | |||||||||
| SF-3 | SOW Appndx A | 1 | 1 | 1 | 5 Days After NTP | |||||
| 13 | Existing Conditions Report | |||||||||
| AHU-2, SF-2 | SOW Appndx A | 1 | 1 | 1 | 10 Days After NTP | |||||
| 14 | Existing Conditions Report | |||||||||
| EF-3 | SOW Appndx A | 1 | 1 | 1 | 10 Days After NTP | |||||
| 15 | Existing Conditions Report | |||||||||
| AHU-3 | SOW Appndx A | 1 | 1 | 1 | 10 Days After NTP | |||||
| 16 | TEMP AC unit |
(25TON DX CL, 72kW ELEC HT) to run on its delivery trailer
125A DISC SW, 480VAC
220lf SA, 50lf RA 20" temp duct
| 3x115ft 125A cable w/ GRND | SOW sect 3.2.4 | ||||||||||||
| HIGH-BAY AREA | 1 | 1 | 1 | 1 | 10 Days After NTP | Provide EDD of equipment, with submittal | |||||||
| 17 | Flexible Duct | SOW Appndx B | 1 | 1 | 1 | 1 | 10 Days After NTP | Provide EDD of equipment, with submittal | |||||
| 18 | Post Project Report |
Gravimetric Analysis Coil Inspections
| AHU-1, SF-1 | SOW Appndx A | 1 | 1 | 1 | 5 Days After Cleaning | |
| 19 | Post Project Report |
Gravimetric Analysis
| EF-1 | SOW Appndx A | 1 | 1 | 1 | 5 Days After Cleaning | |
| 20 | Post Project Report |
Gravimetric Analysis
| EF-2 | SOW Appndx A | 1 | 1 | 1 | 5 Days After Cleaning | |
| 21 | Post Project Report |
Gravimetric Analysis
| SF-3 | SOW Appndx A | 1 | 1 | 1 | 5 Days After Cleaning | |
| 22 | Post Project Report |
Gravimetric Analysis Coil Inspections
| AHU-2, SF-2 | SOW Appndx A | 1 | 1 | 1 | 5 Days After Cleaning | |
| 23 | Post Project Report |
Gravimetric Analysis
| EF-3 | SOW Appndx A | 1 | 1 | 1 | 5 Days After Cleaning | |
| 24 | Post Project Report |
Gravimetric Analysis
| AHU-3 | SOW Appndx A | 1 | 1 | 1 | 5 Days After Cleaning | |
| 25 | AIR Test & Balance |
1st floor; AHU-1, SF-1, EF-1,
| EF-2, and SF-3 | SOW sect 3.2.4.7 | 1 | 1 | 1 | End of Contract | ||||
| 26 | AIR Test & Balance | ||||||||
| 1st floor; AHU-2, SF-2, EF-3 | SOW sect 3.2.4.7 | 1 | 1 | 1 | End of Contract | ||||
| 27 | AIR Test & Balance | ||||||||
| AHU-3 | SOW sect 3.2.4.7 | 1 | 1 | 1 | End of Contract | ||||
| 28 | 1-Year Warranty (Contractor) | SOW sect 5.2 | 1 | End of Contract |
&"Verdana,Bold"&12Schedule of Material Submittals &12Print on Legal size paper ( 8 x 14 ).
&P of &N
File details come from the government source that posted it. Updated .