Attachment 5 - AF 66.pdf

PDF 252 KB Posted

Attached to
Allee Hall HVAC System Federal contract opportunity
Solicitation number
FA301020R0033
Issued by
Department of the Air Force Air Education and Training Command

About this file

This document contains a submittal register and solicitation for an HVAC system replacement project at Keesler Air Force Base. The submittal register outlines 49 line items requiring contractor submission of shop drawings, data, samples, warranties and other documentation. Key submission deadlines are within 14 days of notice to proceed. The solicitation seeks replacement of six air handling units in Building 4331. The North American Industry Classification System code is 238220. The acquisition will utilize Performance Price Trade-off procedures and is set aside for Historically Underutilized Business Zones. The estimated value is between $5-10 million. The solicitation and drawings will be posted on August 4th with a closing date of September 2nd. The contract performance period is 360 days from notice to proceed. Registration in the System for Award Management is required for consideration. The single point of entry for documentation is the Contract Opportunities website. The solicitation identifies the contracting specialist and officer for inquiries. Funding is not presently guaranteed and the government reserves the right to cancel.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 HazMat Questionnaire 3 3 5 Days Prior to Start Date

2 HazMat MSDS 3 5 Days Prior to Start Date

Must be filled out if contractor answers YES to the Hazmat

Questionnaire

3 Hazmat Reporting Entry Form 3 3 5 Days Prior to Start Date

Submit Final Quantities

4 Hazmat Reporting Entry Form 3 3 End of

Contract

5 Recycling and Landfill Report 3 3 End of

Contract

Warranty (Manufacturer's)

End of

Contract

1-Year Warranty (Contractor)

End of

Contract

Chiller - Per Drawing Schedule M100

3 3 3 3 3

Within 14 days

NTP/start date

Door/Door Frames - Per Spec Section 08 11 13 08 21 10

3 3 3

Within 14 days

NTP/start date

DATE TO CIVIL

ENGINEERING

FINAL APPROVAL

RETURN

SUSPENSE DATE

REMARKS

CONTRACTOR

RESUBMITTAL

DATE CONTRACTOR

NOTIFIED

APPROVED

DIS-

APPROVED

SUBMITTAL REGISTER

Project Number

MAHG 07-1039

Project Name

Repair HVAC Traning Facility B4331

TO BE COMPLETED BY PROJECT MANAGER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

C A

T A

L O

G D

A T

A

O P

E R

A T

IN

G

I N

S T

R U

C T

IO

N

S

D A

T A

C E

R T

IF

IC

A T

IO

N

O F

C O

M P

L

IA

N C

E

D O

C U

M E

N T

R

E P

O R

T

REQUIRED

SUBMISSION DATE

I T E M

N U M B E R

ITEM OR DESCRIPTION OF ITEM,

CONTRACT REFERENCE, TYPE

OF SUBMITTAL

S H

O P

D R

A W

IN

G

S

M A

N U

F A

C T

U R

E R

'S R

E C

O M

M E

N D

A T

IO

N

S

M A

N U

F A

C T

U R

E R

'S W

A R

R A

N T

Y

S A

M P

LE

S

NO. OF COPIES REQUIRED

C O

LO

R

S E

LE

C

T

IO

N

Last Revision made on 3 August 2020

1512685222A Highlight

DATE TO CIVIL

ENGINEERING

FINAL APPROVAL

RETURN

SUSPENSE DATE

REMARKS

CONTRACTOR

RESUBMITTAL

DATE CONTRACTOR

NOTIFIED

APPROVED

DIS-

APPROVED

SUBMITTAL REGISTER

Project Number

MAHG 07-1039

Project Name

Repair HVAC Traning Facility B4331

TO BE COMPLETED BY PROJECT MANAGER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

C A

T A

L O

G D

A T

A

O P

E R

A T

IN

G

I N

S T

R U

C T

IO

N

S

D A

T A

C E

R T

IF

IC

A T

IO

N

O F

C O

M P

L

IA

N C

E

D O

C U

M E

N T

R

E P

O R

T

REQUIRED

SUBMISSION DATE

I T E M

N U M B E R

ITEM OR DESCRIPTION OF ITEM,

CONTRACT REFERENCE, TYPE

OF SUBMITTAL

S H

O P

D R

A W

IN

G

S

M A

N U

F A

C T

U R

E R

'S R

E C

O M

M E

N D

A T

IO

N

S

M A

N U

F A

C T

U R

E R

'S W

A R

R A

N T

Y

S A

M P

LE

S

NO. OF COPIES REQUIRED

C O

LO

R

S E

LE

C

T

IO

N

Door Hardware - Per Spec Section 08 71 00

3 3

Within 14 days

NTP/start date

Ceiling Tile/Grid - Per Sec Section 09 51 10

1 1 1 1 3 3

Within 14 days

NTP/start date

Waste Piping-Cast Iron - Per Spec Section 22 00 00

3 3

Within 14 days

NTP/start date

Hydronic Piping-Chill Water Per Spec Section 22 00 00

3 3 Within 14 days NTP/start

Hydronic Piping - Hot Water Per Spec Section 22 00 00

3 3 Within 14 days NTP/start

Hydronic Piping/Valves - Per Spec Section 22 00 00 & 23 00 00

3 3

Within 14 days

NTP/start date

Hydronic Piping/Fittings/Gauges - Per Spec Section 22 00 00 & 23 00 00

3 3

Within 14 days

NTP/start date

FINAL APPROVAL

RETURN

SUSPENSE DATE

REMARKS

CONTRACTOR

RESUBMITTAL

DATE CONTRACTOR

NOTIFIED

APPROVED

DIS-

APPROVED

SUBMITTAL REGISTER

Project Number

MAHG 07-1039

Project Name

Repair HVAC Traning Facility B4331

TO BE COMPLETED BY PROJECT MANAGER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

C A

T A

L O

G D

A T

A

O P

E R

A T

IN

G

I N

S T

R U

C T

IO

N

S

D A

T A

C E

R T

IF

IC

A T

IO

N

O F

C O

M P

L

IA

N C

E

D O

C U

M E

N T

R

E P

O R

T

REQUIRED

SUBMISSION DATE

I T E M

N U M B E R

ITEM OR DESCRIPTION OF ITEM,

CONTRACT REFERENCE, TYPE

OF SUBMITTAL

S H

O P

D R

A W

IN

G

S

M A

N U

F A

C T

U R

E R

'S R

E C

O M

M E

N D

A T

IO

N

S

M A

N U

F A

C T

U R

E R

'S W

A R

R A

N T

Y

S A

M P

LE

S

NO. OF COPIES REQUIRED

C O

LO

R

S E

LE

C

T

IO

N

Piping-Hangers - Per Spec Section 22 00 00/23 00 00

3 3

Within 14 days

NTP/start date

Piping - Insulation - Per Spec Section 23 07 00

3 3

Within 14 days

NTP/start date

Boiler - Per Drawing M100 & Spec Section 23 00 00

3 1 3 3 3

Within 14 days

NTP/start date

Expansion Tank - Per Drawing M100 & Spec Section 23 52 00

1 1 3 3 3

Within 14 days

NTP/start date

Hot Water Make Up Water Assy - Per Spec Section 23 00 00

1 3 3

Within 14 days

NTP/start date

Pumps-Base Mount - Per Drawing M100 & Spec Section 23 00 00

3 3

Within 14 days

NTP/start date

Suction Diffuser - Per Spec Section 23 00 00

3 3

Within 14 days

FINAL APPROVAL

RETURN

SUSPENSE DATE

REMARKS

CONTRACTOR

RESUBMITTAL

DATE CONTRACTOR

NOTIFIED

APPROVED

DIS-

APPROVED

SUBMITTAL REGISTER

Project Number

MAHG 07-1039

Project Name

Repair HVAC Traning Facility B4331

TO BE COMPLETED BY PROJECT MANAGER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

C A

T A

L O

G D

A T

A

O P

E R

A T

IN

G

I N

S T

R U

C T

IO

N

S

D A

T A

C E

R T

IF

IC

A T

IO

N

O F

C O

M P

L

IA

N C

E

D O

C U

M E

N T

R

E P

O R

T

REQUIRED

SUBMISSION DATE

I T E M

N U M B E R

ITEM OR DESCRIPTION OF ITEM,

CONTRACT REFERENCE, TYPE

OF SUBMITTAL

S H

O P

D R

A W

IN

G

S

M A

N U

F A

C T

U R

E R

'S R

E C

O M

M E

N D

A T

IO

N

S

M A

N U

F A

C T

U R

E R

'S W

A R

R A

N T

Y

S A

M P

LE

S

NO. OF COPIES REQUIRED

C O

LO

R

S E

LE

C

T

IO

N

Triple Duty Valve - Per Spec Section 23 00 00

Within 14 days

NTP/start date

Air Vents - Per Spec Section 23 00 00

3 3

Within 14 days

NTP/start date

Chemical Pot Feeder - Per Spec Section 23 64 26

1 3 3

Within 14 days

NTP/start date

Ductwork - Per Spec Section 23 00 00

1 3 3

Within 14 days

NTP/start date

Diffusers/ Grilles - Per Spec Section 23 00 00

1 3 3

Within 14 days

NTP/start date

Fire Dampers - Per Spec Section 23 00 00

1 3 1 3

Within 14 days

NTP/start date

Duct Access Doors - Per Spec Section 23 00 00

1 3 1 3

Within 14 days

FINAL APPROVAL

RETURN

SUSPENSE DATE

REMARKS

CONTRACTOR

RESUBMITTAL

DATE CONTRACTOR

NOTIFIED

APPROVED

DIS-

APPROVED

SUBMITTAL REGISTER

Project Number

MAHG 07-1039

Project Name

Repair HVAC Traning Facility B4331

TO BE COMPLETED BY PROJECT MANAGER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

C A

T A

L O

G D

A T

A

O P

E R

A T

IN

G

I N

S T

R U

C T

IO

N

S

D A

T A

C E

R T

IF

IC

A T

IO

N

O F

C O

M P

L

IA

N C

E

D O

C U

M E

N T

R

E P

O R

T

REQUIRED

SUBMISSION DATE

I T E M

N U M B E R

ITEM OR DESCRIPTION OF ITEM,

CONTRACT REFERENCE, TYPE

OF SUBMITTAL

S H

O P

D R

A W

IN

G

S

M A

N U

F A

C T

U R

E R

'S R

E C

O M

M E

N D

A T

IO

N

S

M A

N U

F A

C T

U R

E R

'S W

A R

R A

N T

Y

S A

M P

LE

S

NO. OF COPIES REQUIRED

C O

LO

R

S E

LE

C

T

IO

N

Duct Connectors - Per Spec Section 23 00 00

Within 14 days

NTP/start date

Ductwork Insulation - Per Spec Section 23 00 00

3 3

Within 14 days

NTP/start date

Dampers - Per Spec Section 23 00 00

3 3

Within 14 days

NTP/start date

HVAC Controls - Per Spec Section 23 00 00

1 3 3 3

Within 14 days

NTP/start date

Supply/Return Difusers - Per Spec Section 23 00 00

3 3

Within 14 days

NTP/start date

34 Louvers - Per Spec 23 00 00 3 3 3

Within 14 days

NTP/start date

Variable Frequency Drives - Per Spec Section 23 81 00

1 3 3 3 3

Within 14 days

FINAL APPROVAL

RETURN

SUSPENSE DATE

REMARKS

CONTRACTOR

RESUBMITTAL

DATE CONTRACTOR

NOTIFIED

APPROVED

DIS-

APPROVED

SUBMITTAL REGISTER

Project Number

MAHG 07-1039

Project Name

Repair HVAC Traning Facility B4331

TO BE COMPLETED BY PROJECT MANAGER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

C A

T A

L O

G D

A T

A

O P

E R

A T

IN

G

I N

S T

R U

C T

IO

N

S

D A

T A

C E

R T

IF

IC

A T

IO

N

O F

C O

M P

L

IA

N C

E

D O

C U

M E

N T

R

E P

O R

T

REQUIRED

SUBMISSION DATE

I T E M

N U M B E R

ITEM OR DESCRIPTION OF ITEM,

CONTRACT REFERENCE, TYPE

OF SUBMITTAL

S H

O P

D R

A W

IN

G

S

M A

N U

F A

C T

U R

E R

'S R

E C

O M

M E

N D

A T

IO

N

S

M A

N U

F A

C T

U R

E R

'S W

A R

R A

N T

Y

S A

M P

LE

S

NO. OF COPIES REQUIRED

C O

LO

R

S E

LE

C

T

IO

N

VAV Boxes - Per Drawings M100 & Spec Section 23 00 00

1 3 3 3 3

Within 14 days

NTP/start date

Within 14 days

NTP/start date

Exhaust Fans - Per Drawing M100 & Spec Section 23 00 00

1 3 3 3 3

Within 14 days

NTP/start date

Cooling Tower Shaft - Per Spec Section 23 00 00

1 3 3

Within 14 days

NTP/start date

Cooling Tower Motor - Per Spec Section 23 00 00

1 3 3

Within 14 days

NTP/start date

Cooling Tower MU Valve - Per Spec Section 23 00 00

Within 14 days

NTP/start date

Cooling Tower VFD - Per Spec Section 23 00 00

1 3 3 3

Within 14 days

FINAL APPROVAL

RETURN

SUSPENSE DATE

REMARKS

CONTRACTOR

RESUBMITTAL

DATE CONTRACTOR

NOTIFIED

APPROVED

DIS-

APPROVED

SUBMITTAL REGISTER

Project Number

MAHG 07-1039

Project Name

Repair HVAC Traning Facility B4331

TO BE COMPLETED BY PROJECT MANAGER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

C A

T A

L O

G D

A T

A

O P

E R

A T

IN

G

I N

S T

R U

C T

IO

N

S

D A

T A

C E

R T

IF

IC

A T

IO

N

O F

C O

M P

L

IA

N C

E

D O

C U

M E

N T

R

E P

O R

T

REQUIRED

SUBMISSION DATE

I T E M

N U M B E R

ITEM OR DESCRIPTION OF ITEM,

CONTRACT REFERENCE, TYPE

OF SUBMITTAL

S H

O P

D R

A W

IN

G

S

M A

N U

F A

C T

U R

E R

'S R

E C

O M

M E

N D

A T

IO

N

S

M A

N U

F A

C T

U R

E R

'S W

A R

R A

N T

Y

S A

M P

LE

S

NO. OF COPIES REQUIRED

C O

LO

R

S E

LE

C

T

IO

N

Lighting Controls - Per Drawings E000- E400

1 3 3 3 3

Within 14 days

NTP/start date

LED Fixtures - Per Drawing E000 - E400

1 3 3 3 3

Within 14 days

NTP/start date

Exit Fixtures - Per Drawing E000 - E400

1 3 3 3

Within 14 days

NTP/start date

Multizone Heat Pump Units W/heat Recovery - Per Drawing M100

1 3 3 3 3 3

Within 14 days

NTP/start date

Conduit & Devices - Per Spec Section 23 03 00 & Drawing E000-E400

3 3

Within 14 days

NTP/start date

Sheetmetal - Per Spec Section 23 00 00

3 1 3 3 Within 14 days NTP/start

As-Builts - Paper & Digital - Per Spec 01000/01150/01780A

Project Completion

FINAL APPROVAL

RETURN

SUSPENSE DATE

REMARKS

CONTRACTOR

RESUBMITTAL

DATE CONTRACTOR

NOTIFIED

APPROVED

DIS-

APPROVED

SUBMITTAL REGISTER

Project Number

MAHG 07-1039

Project Name

Repair HVAC Traning Facility B4331

TO BE COMPLETED BY PROJECT MANAGER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

C A

T A

L O

G D

A T

A

O P

E R

A T

IN

G

I N

S T

R U

C T

IO

N

S

D A

T A

C E

R T

IF

IC

A T

IO

N

O F

C O

M P

L

IA

N C

E

D O

C U

M E

N T

R

E P

O R

T

REQUIRED

SUBMISSION DATE

I T E M

N U M B E R

ITEM OR DESCRIPTION OF ITEM,

CONTRACT REFERENCE, TYPE

OF SUBMITTAL

S H

O P

D R

A W

IN

G

S

M A

N U

F A

C T

U R

E R

'S R

E C

O M

M E

N D

A T

IO

N

S

M A

N U

F A

C T

U R

E R

'S W

A R

R A

N T

Y

S A

M P

LE

S

NO. OF COPIES REQUIRED

C O

LO

R

S E

LE

C

T

IO

N

O&M Manuals - 3 Paper or digital copies - Per Spec Section 01001

3 3 Project Completion

Chiller/Boiler Start-up (1 EA) - Per Spec Section 01001/23 00 00

Project Completion

File details come from the government source that posted it. Updated .