ATTACHMENT 4b - JA SNE Building Systems.pdf

PDF 260 KB Posted

Attached to
Renovate Wellness Center, Bldg 12
Solicitation number
W50S8120Q0012
Issued by

About this file

This document contains a justification for other than full and open competition for a federal contract opportunity issued by the Massachusetts Army National Guard. The justification document outlines plans to award a sole-source contract to SNE Building Systems, Inc. for the procurement and installation of a Tridium AX direct digital control system as part of renovations to the Wellness Center at Barnes Air National Guard Base. Key details include the contracting authority cited as 10 U.S.C. 2304(c)(1) and FAR 6.302-1(a)(2)(ii)(A) and 6.302-1(a)(2)(iii)(A) for only one responsible source being available, the estimated contract value of $20,000, and the technical reasons provided that only the Tridium AX system from SNE will meet the agency's requirements due to compatibility with existing control systems and expertise requirements.

The related federal contract opportunity is a solicitation issued by the 104th Fighter Wing of the Massachusetts Army National Guard for renovation services at the Wellness Center building. It is a total small business set-aside with an estimated value between $100,000 and $250,000. The NAICS code is 236220 and the small business size standard is $36.5 million average annual revenue. The pre-proposal conference is scheduled for August 28, 2020 with a proposal submission deadline of September 11, 2020. The solicitation and plans/specifications are available through SAM.gov.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Control No: 19-5001 Justification Review Document for Other Than Full and Open Competition

Program/Equipment: Tridium AX System with install by SNE Building Inc.

Authority: FAR 6.302-1(a)(2)(iii)(A) and FAR 6.302-1(a)(2)(iii)(A) – Only One Responsible Source and No Other Supplies or Services Will Satisfy Agency Requirements for the listed equipment and the installation.

Amount:

DSN: _698-2800 ____________

Date: _____________________

DSN: _698-1593_____________

Date Reviewed: _____________

DSN: _698-2800_____________

Prepared by:

Name: David Gosselin Title: Deputy BCE E-mail: David.m.gosselin.civ@mail.mil

Contracting Officer:

Name:

Title: Contracting Officer E-Mail: mil@mail.mil

Technical Representative:

Name: David Gosselin Title: Deputy BCE Date Reviewed: _____________

Reviews: I have reviewed this justification and find it adequate to support other than full and open competition.

DSN: ______________________

Date: ______________________

DSN: ______________________

Legal Counsel

Typed Name:

Signature: ______________________

Special Competition Advocate Typed Name:

Signature: ______________________ Date: ______________________

Principal Assistant Responsible for Contracting Typed Name: Commercial:

Signature: ______________________ Date: ______________________

JUSTIFICATION FOR OTHER THAN FULL AND OPEN COMPETITION

SNE Building Systems, Inc.

2 |5 JA - SNE – Wellness Center Control No: 19-5001

Contracting Activity: 104the Fighter Wing, 175 Falcon Dr, Westfield, MA, 01085-1482

Description of Action:

The 104th Fighter Wing Contracting Office intends to award a firm-fixed price contract on or about 30

. Under this contract, the Government requires a sole-source to SNE Building Systems, Inc. (aka SNE), for the primary direct digital controls (DDC) to the installation of the HVAC System in the new office space being created in Building 12. This portion of the construction effort will incorporate SNE DCC components that are compatible with the main DDC control system already in place at Barnes Air National Guard Base.

Description of Supplies/Services:

The Government will require of the awardee, as part of the energy reduction measures to Procure and install a brand-name requirement of Tridium AX system. This system is a single source solution for Direct Digital Controls (DDC).

Procure the services of the only regional approved suppler SNE Building Systems Inc. for the installation and programing of Tridium AX System.

This project involves installation of HVAC controls and regulators with centralized reporting for energy usage. This includes installing interior controls to the facility, all corrective and associated electrical wiring and piping as necessary, hard wired communications to a designated central point, computer hardware, computer software, necessary to provide complete and accurate data, graphs and presentations for energy usage on an hourly basis, peak demand, daily, monthly and yearly summaries, trends, average daily/ monthly usage, mean daily/ monthly usage, quarterly and annually average, mean and totals. Contractor shall verify compatibility and system completeness to ensure a complete system meeting the owner’s needs as described in the Statement of Work.

4. Authority Cited:

The statutory authority permitting Other than Full and Open Competition is 10 U.S.C. 2304(c)(1) as implemented by FAR 6.203-1, Only one responsible source and no other supplies or services will satisfy agency requirements. It is likely that any other source would result in substantial duplication of cost to the Government that will not be recovered through competition.

5. Reason for Authority Cited:

a. FAR 6.302-1(c) provides the use of brand name descriptions when the requirement can only be met by one brand name product the current product is an Tridium AX System. The use of a single product line/manufacturer enables the systematic management and seamless operation of our EMCS within the facilities. Utilizing the common product line for our DDC within our facilities allow for reduced staff to operate and maintain our DDC as well as the equipment the EMCS interfaces with.

This results in reduced maintenance and training costs over the lifecycle of the building. Departing from the standardization would not be sustainable, and would be detrimental to the organization.

b. SNE Building Systems Inc. is the only known source for additional system integration and upgrade to the Tridium AX system that is presently in operation at Barnes ANGB. SNE Building Systems Inc., now owned by Schneider Electric (S.E.). S.E. goes to market with this product only through exclusive territory independent representatives. The representative handling the Westfield, Mass area is SNE Building Systems. Any other manufacturer would void the warranty and could result in conflict issues and ability to have the system work. The estimate to purchase, install and program the equipment is approximately $20,000.

3 |5

Control No: 19-5001

6. Efforts to Obtain Competition:

The solicitation for the Energy Reduction Measures will be a competitive Invitation for Bid (IFB) set aside for small businesses. The brand name components represent a small portion, less than 5% of the overall construction project that is being competed.

7. Actions to Increase Competition:

This J&A will be posted to FedBizOpps with the solicitation and potential suppliers may have the opportunity to propose compatible products for consideration.

8. Market Research:

The following market research techniques were conducted within the previous 12 months.

Previous construction projects that were awarded with the same system which also included the J&A. Project AXQD082415 Renovate Hangar 15 included a cost breakdown for the installation and programing of the Tridium AX System at $303,323.00. This was for a large amount of work and new equipment for the entire hangar and an addition. The other recent completed project was AXQD150601 Energy Reduction (State Funded) which had the DDC costs at $93,670.00.

Referencing online research, and RS Means and adjusted to the local area and market conditions created the cost estimate for the equipment and the work associated with the Tridium AX System.

The subject matter expert in mechanical systems also communicated directly with the manufacture as well as other various manufactures to determine if there were any other compatible systems, none were discovered.

9. Interested Sources:

To date, no other sources have written to express an interest. There are no known alternative systems that are fully compatible with the aforementioned systems based upon lessons learned and experience of the Barnes Air National Guard and National Guard Bureau.

10. Other Facts:

a. Maintenance and repair training for these systems is brand name specific, and it is necessary to integrate the Energy Reduction measures into the existing base infrastructure and facilitate the seamless communication between new updates and the existing system. With multiple brand names, the facility upkeep and maintenance would several degrade to multiple systems and increased time to maintain, and repair all the different systems, as well as additional bench stock and capability issues. The costs over the lifecycle of the facility would also be increased for service and annual maintenance.

b. The Facilities Management spare parts inventory will remain manageable with all systems of the specified brand name. For each different brand name specified, a different software system would be required, resulting in additional costs to the Government for the maintenance of each system. By using the aforementioned systems listed, communication and compatibility issues will be alleviated and result in a fully integrated and functioning base wide system. Having the same brand name on all required systems would be the most cost effective solution for the government.

c. The Air National Guard (ANG) has established the Design Policy (ANGETL 15-01-00, May 2015), that states, “Facility designs shall reflect careful consideration and coordination of standardized features. All designs shall incorporate standardization to the maximum extent possible in accordance with the definitive base standards and base master plans. Certain features

4 |5

Control No: 19-5001 such as base- wide lock and keying systems, direct digital control (DDC) and energy management control system (EMCS), fire detection/reporting systems, security and intrusion detection system (IDS), communications systems and other similar systems located in multiple facilities shall be of the same manufacturer (standardized) to the maximum extent possible.”

11. Technical Certification:

I certify that the supporting data under my cognizance, which are included in the justification are accurate and complete to the best of my knowledge and belief.

Typed Name: David Gosselin, Civ, MA ANG Date:

Title: Deputy Base Civil Engineer Signature:

12. Requirements Certification:

I certify that the supporting data under my cognizance, which are included in the justification are accurate and complete to the best of my knowledge and belief:

Typed Name: David Gosselin, Civ, MA ANG Date:

Title: Deputy Base Civil Engineer Signature:

13. Fair and Reasonable Cost Determination:

I hereby determine that the anticipated cost to the Government for this contract action will be fair and reasonable. The basis of determination is made based on a technical review/cost analysis by Jeremy Dugan and David Gosselin with their knowledge of the same equipment and service for other ANG facilities on Barnes ANG.

Date:Typed Name:

Title: Contracting Officer Signature:

14. Contracting Officer Certification:

I certify that this justification is accurate and complete to the best of my knowledge and belief.

Typed Name: Date:

Title: Contracting Officer Signature:

Approval

GOSSELIN.DAVID.

MARK.1011349702

Digitally signed by

GOSSELIN.DAVID.MARK.10113497

Date: 2019.10.10 09:26:56 -04'00'

GOSSELIN.DAVID.

MARK.1011349702

D gitally s gned by

GOSSELIN DAVID MARK 10113497

Date: 2019 10 10 09:27 16 04 00

SINCLAIR.SARA

H.ANN.1006207

Digitally signed by

SINCLAIR.SARAH.ANN.1006

207495 Date: 2020.08.19 15:30:30 -04'00'

SINCLAIR.SARA

H.ANN.1006207

Digitally signed by

SINCLAIR.SARAH.ANN.100

6207495 Date: 2020.08.19 15:30:48 -04'00'

5 |5

Control No: 19-5001

Based on the foregoing justification, I hereby approve the procurement of the Tridium AX system and services of SNE Building Systems Inc, on the other than full and open competition basis pursuant to the authority of 10. U.S.C. 2304(c)(1), FAR Part 6.302+-1(a)(2)(ii)(A) and 6.302- 1(a)(2)(iii)(A), Only One Responsible Source and No Other Supplies or Services Will Satisfy Agency Requirements, subject to availability of funds, and provided that the services and property herein described have otherwise been authorized for acquisition.

Date: Signature:

Name:

SINCLAIR.SARA

H.ANN.1006207

Digitally signed by

SINCLAIR.SARAH.ANN.1006

207495 Date: 2020.08.19 15:31:14 -04'00'