Attachment_4_-_Subcontracting_Worksheet.docx

DOCX document 98 KB Posted

Attached to
Construct North Unit Visitor Center at BADL
Solicitation number
140PS126B0010
Issued by

About this file

This is a Subcontracting Percentage Worksheet for FAR Clause 52.219-14 related to solicitation 140PS126B0010 for the construction of the North Unit Visitor Center at Badlands National Park (BADL). The worksheet is a template provided by the National Park Service, Department of the Interior, dated 20 August 2026, to assist prime contractors in calculating and demonstrating their subcontracting labor percentages in compliance with federal acquisition regulations.

The worksheet establishes that for general construction work of this type, prime contractors and similarly situated entities must perform a minimum of 15 percent of the work, excluding material costs, with a maximum of 85 percent allowed to be subcontracted to non-similarly situated entities. The calculation methodology requires contractors to input direct labor, fringe benefits, and general and administrative (G&A) costs for both the prime contractor and any subcontractors, then apply the formula (D)/(C)+(D) to derive the subcontracting labor cost percentage. The sample included demonstrates a calculation where direct labor and fringe benefits total $550 for the prime contractor and $150 for the subcontractor, resulting in a subcontracting labor percentage of 21.43 percent, which complies with the 85 percent limitation. Contractors may use this template or submit their own format provided the government can clearly verify compliance with the subcontracting threshold requirements.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of the Interior

NATIONAL PARK SERVICE

CONTRACTING OPERATIONS - STRATEGIC

Washington, D.C., 20242

20 August 2026

SUBJECT: FAR CLAUSE 52.219-14, SUBCONTRACTING PERCENTAGE WORKSHEET

SOLICITATION 140PS126B0010 – Construct N. Unit Visitor Center - BADL

PRIME CONTRACTOR: _________________________ SOURCE: ________________________

SUBCONTRACTOR: ___________________________ SOURCE: ________________________

SAMPLE SAMPLE SAMPLE

To calculate, either follow the below directions OR right click the above Excel ‘Object’ and select ‘Worksheet Object’ then ‘Edit’. You can then input Direct Labor/Fringe Benefits/G&A % and it will calculate for you (as illustrated).

a) To calculate the subcontracting percentage, first add DIRECT LABOR and FRINGE BENEFITS and enter the figures for the prime contractor in space (A) and for the subcontractor (if available)*** in space (B).

b) Next, calculate the LABOR G&A by multiplying the G&A rate by the SUBTOTAL figure in space (A).

c) Calculate the subcontractor's LABOR G&A by multiplying the subcontractor's G&A rate by the subcontractor's SUBTOTAL figure in (B).

d) Add the LABOR G&A to the SUBTOTAL and record that figure in the spaces for TOTAL LABOR COSTS at (C) and (D) respectively.

e) Next, using the formula below, calculate the subcontracting labor percentage.

____(D)____

(C) + (D)

SUBCONTRACTING LABOR COST PERCENTAGE = %

*The firm must demonstrate that their labor overhead is allowable in accordance with FAR 3 l.205- 6(m). Failure to do so will cause the entire overhead to be eliminated from the calculations.

**G&A denotes General and Administrative Costs ***You need to compare as like figures as possible. Therefore, if you have a breakdown of the subcontractor's costs use it in the formulation above. If you do not have a breakdown you need to use the TOTAL SUBCONTRACTING AMOUNT for item (D) even though you must still breakdown the contractor's costs.

In accordance with FAR Clause 52.219-14(e)(3), General construction, it will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 85 percent subcontract amount that cannot be exceeded. Therefore, the prime contractor or similarly situated entities shall perform a minimum of 15 percent of the work, excluding the cost of materials.

Note to Contractor: This form is only a SAMPLE. Your firm may utilize this form for purposes of declaring your subcontracting percentages or you may provide one in your own format, provided the government can clearly understand your firm does NOT exceed the 85% Limitation on Subcontracting for construction work, of this type.

NPS-National Capital Area Page 1 of 1

FOR OFFICIAL USE ONLY

SOURCE SELECTION INFORMATION – SEE FAR 3.104

Preserving unimpaired the natural and cultural resources and values of the national park system for the enjoyment, education, and inspiration of this and future generations.

FOR OFFICIAL USE ONLY

SOURCE SELECTION INFORMATION – SEE FAR 3.104

image1.emf

Microsoft_Excel_Worksheet.xlsx Sheet1

PRIME CONTRACTOR SUBCONTRACTOR

DIRECT LABOR $250.00 $50.00

FRINGE BENEFITS $300.00 $100.00

SUB TOTAL (A)$550 (B)$150

LABOR G&A** @ 10.00% $55.00 10.00% $15.00

TOTAL LABOR COST (C)$605 (D)$165

Subcontracting Labor Percentage 21.43% image2.jpeg image3.jpeg

File details come from the government source that posted it. Updated .