SELFRIDGE ANGB, MICHIGAN

Section 01 33 00 Page 1

SECTION 01 33 00

SUBMITTAL PROCEDURES – Horizontal MATOC Supplement

PART 1 GENERAL

1.1 DEFINITIONS

1.1.1 Submittal Descriptions (SD)

Submittals requirements are specified in the technical sections. Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Preconstruction Submittals

Submittals which are required prior to the Pre-construction Conference:

Certificates of insurance

Surety bonds

List of equipment to be used on the airfield, including dimensions of the equipment

List of proposed Subcontractors

List of proposed products

Construction progress schedule

Submittal register

Schedule of prices

Health and safety plan

Work plan

Quality Control(QC) plan

Environmental protection plan

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

Section 01 33 00 Page 2

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-04 Samples

Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.

Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.

Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.

SD-05 Design Data

Design calculations, mix designs, analyses or other data pertaining to a part of work.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports.

Daily logs and checklists.

Final acceptance test and operational test procedure.

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor, the purpose of which is to further quality

Section 01 33 00 Page 3 of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.

Confined space entry permits.

Text of posted operating instructions.

SD-08 Manufacturer's Instructions

Preprinted material describing installation of a product, system or material, including special notices and (MSDS)concerning impedances, hazards and safety precautions.

SD-10 Operation and Maintenance Data

Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment.

This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.

This data is intended to be incorporated in an operations and maintenance manual or control system.

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Special requirements necessary to properly close out a construction contract.

For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

1.1.2 Approving Authority

Office or designated person authorized to approve submittal.

1.1.3 Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor QC approval.

Submit the following in accordance with this section.

SD-01 Preconstruction Submittals

Submittal Register; G

1.3 PREPARATION

Section 01 33 00 Page 4

1.3.1 Transmittal Form

1.4 VARIATIONS

Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.

1.4.1 Considering Variations

Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).

Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.

1.4.2 Proposing Variations

When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.

Clearly mark the proposed variation in all documentation.

1.4.3 Warranting That Variations Are Compatible

When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.

1.4.4 Review Schedule Is Modified

In addition to normal submittal review period, a period of 10 working days will be allowed for consideration by the Government of submittals with variations.

1.5 SUBMITTAL REGISTER

Prepare and maintain submittal register, as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and (i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required.

Column (c): Lists specification section in which submittal is required.

Section 01 33 00 Page 5

Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.

Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.

Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government.

1.5.1 Use of Submittal Register

Submit submittal register. Submit with QC plan and project schedule.

Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:

Column (a) Activity Number: Activity number from the project schedule.

Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.

Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.

Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.

1.5.2 Contractor Use of Submittal Register

Update the following fields with each submittal throughout contract.

Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.

Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.

Column (l) List date of submittal transmission.

Column (q) List date approval received.

1.5.3 Approving Authority Use of Submittal Register

Update the following fields.

Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.

Column (l) List date of submittal receipt.

Column (m) through (p) List Date related to review actions.

Column (q) List date returned to Contractor.

Section 01 33 00 Page 6

1.5.4 Copies Delivered to the Government

Deliver one copy of submittal register updated by Contractor to Government with each invoice request.

1.6 SCHEDULING

Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.

a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.

b. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."

c. Re-submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.

d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."

1.7 GOVERNMENT APPROVING AUTHORITY

When approving authority is Contracting Officer, the Government will:

a. Note date on which submittal was received.

b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.

c. Identify returned submittals with one of the actions defined in paragraph entitled, "Review Notations," of this section and with markings appropriate for action indicated.

Upon completion of review of submittals requiring Government approval, stamp and date approved submittals. One (1) copy of the approved submittal will be retained by the Contracting Officer and one (1) copy of the submittal will be returned to the Contractor.

1.8 DISAPPROVED OR REJECTED SUBMITTALS

Contractor shall make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or

Section 01 33 00 Page 7 specifications; notice as required under the clause entitled, "Changes," is to be given to the Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work.

Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.

If changes are necessary to submittals, the Contractor shall make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.

1.9 APPROVED/ACCEPTED SUBMITTALS

The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that

Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for.

After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

1.10 APPROVED SAMPLES

Approval of a sample is only for the characteristics or use named in such approval and is not be construed to change or modify any contract requirements. Before submitting samples, the Contractor to assure that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.

Match the approved samples for materials and equipment incorporated in the work. If requested, approved samples, including those which may be damaged in testing, will be returned to the Contractor, at his expense, upon completion of the contract. Samples not approved will also be returned to the Contractor at its expense, if so requested.

Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. Government reserves the right to disapprove any material or equipment which previously has proved unsatisfactory in service.

Samples of various materials or equipment delivered on the site or in place may be taken by the Contracting Officer for testing. Samples failing to meet contract requirements will automatically void previous approvals.

Contractor to replace such materials or equipment to meet contract requirements.

Approval of the Contractor's samples by the Contracting Officer does not relieve the Contractor of his responsibilities under the contract.

PART 2 PRODUCTS

Section 01 33 00 Page 8

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

02 61 00 1 REMOVAL AND DISPOSAL OF

CONTAMINATED SOIL

SECTION 02 61 00 - REMOVAL AND DISPOSAL OF CONTAMINATED MEDIA

PART 1 - GENERAL

1.1 SUMMARY

A. This section describes the Work involved in removal, handling, testing, and disposal of hazardous and nonhazardous soil, debris, excavated waste, and wastewater if such material is encountered or generated during performance of the Work.

1.2 REFERENCES

A. The following is a list of standards which may be referenced in this section:

1. U.S. Code of Federal Regulations (CFR):

a. Environmental Protection Agency (EPA), Title 40, Identification and Listing of Hazardous Waste:

1) Part 261.21, Characteristics of Ignitability.

2) Part 261.22, Characteristics of Corrosivity.

3) Part 261.23, Characteristics of Reactivity.

b. Occupational Safety and Health Administration (OSHA), Title 29, Occupational Safety and Health Standards: Part 1910.120, Hazardous Waste Operations and Emergency Response.

2. Section 201120c of Part 201, Environmental Remediation, of the Natural Resources and Environmental Protection Act, 1994 PA 451, as amended (Act 451).

3. Resources Conservation and Recovery Act (RCRA).

4. Toxic Substances Control Act (TSCA).

1.3 DEFINITIONS

A. Excavated Waste: Buried solid waste, refuse, demolition waste, construction waste, and special waste, and Site soils. Excavated waste does not include demolition debris, solid waste, refuse, construction waste, or special waste created by Contractor incidental to the Work.

B. Free Product: Free-standing petroleum or chemical liquid product present in excavation or floating on water in excavation.

C. Hazardous Soil and Debris: Material which qualifies as a hazardous or toxic waste as defined by the Resources Conservation and Recovery Act (RCRA) or the Toxic Substances Control Act

(TSCA).

02 61 00 2 REMOVAL AND DISPOSAL OF

D. Nonhazardous Soil and Debris: Material which does not qualify as a hazardous or toxic waste as defined by RCRA or TSCA and includes excavated waste as defined above.

E. Wastewater: Water produced by Contractor’s operation, including groundwater removed from the Site, stormwater entering excavation pits despite controls, washdown water, used decontamination water, and other water that requires handling by Contractor to accomplish the Work. Wastewater may be hazardous or nonhazardous and shall require special handling and testing.

F. Media: Waste materials generated by contractor during construction activities.

G. Site or Environmental Restoration Sites (ERP) Site:

H. Sites are areas of concern (AOCs) within the project area that have known soil and/or groundwater contamination. They will be identified for each Delivery Order Requirement.

1.4 SUBMITTALS

A. Informational Submittals:

1. Prior to commencement of the Work submit the following:

a. Permits and certification for soil, debris, and waste haulers.

b. Permits, certification, and acceptance requirements for proposed soil, debris, and wastewater disposal or treatment facilities.

c. Qualifications:

1) Contractor and Subcontractor documentation of experience.

2) Contractor’s Personnel: Documentation personnel proposed for Work with contaminated materials have been 40-hour trained in accordance with

29 CFR 1910.120.

3) Contractor’s Consultant: Documentation of experience and registration.

4) Waste Transporter: Documentation of licensing and equipment capabilities.

5) Offsite Disposal and Treatment Facilities: Documentation of licensing, disposal requirements, and acceptance of the waste.

d. Submit Soil and Debris Analytical and Physical Characterization Testing Plan within 1 week after Notice to Proceed.

e. Inspection reports, including photographs, and other items requested by Contracting Officer.

f. Excavation and Water Control Plan demonstrating controls for migration of water into active excavation areas.

g. Site-specific Health and Safety Plan:

1) In accordance with 29 CFR 1910.120 and this specification.

2) Include Contractor-proposed monitoring, personnel protective gear, worker training and certifications, and emergency procedures.

3) State criteria or measures when air monitoring and work by HAZWOPER-trained personnel are no longer necessary.

02 61 00 3 REMOVAL AND DISPOSAL OF

h. Emergency Response Plan: Details how to handle an emergency during execution of the Work (for example, encountering drums with unknown contents;

encountering pockets of hazardous atmospheres; response to spills caused by excavation of materials by Contractor or Contractor’s equipment; response to fire or injured personnel).

2. During excavation and removal activities submit the following:

a. Daily job progress log detailing information on the review of progress with respect to previously established milestones and schedules, major problems, corrective actions, injury reports, equipment breakdown, and sampling results.

b. Weekly excavation plans.

c. Copies of manifests or bills of lading, and waste disposal or treatment facility receipts, including weight or volume tickets, for waste materials, solid or liquid, removed from Site and transported to disposal facilities.

1.5 QUALITY ASSURANCE

A. Qualifications:

1. Contractor Qualifications: Conform to the following qualifications:

a. Work with contaminated materials must be performed by Contractor personnel formally trained in procedures for contaminated soil and water removal (e.g., HAZWOPER training), having maintained full-time office and with proven history of successfully executing similar projects for a minimum of 3 years.

b. Work must be accomplished by Contractor with proper equipment and personnel experienced in similar work.

c. Contractor personnel shall be 40-hour trained in accordance with

29 CFR 1910.120.

2. Contractor’s Consultant, Licensed in the State of Michigan: Shall have minimum of 3 years’ experience in planning, sampling, and performing quality control in remediation of contaminated sites.

3. Waste Transporter: Licensed waste haulers with trucks equipped with containment and cover systems to transport solid and liquid waste materials on public streets and roads without spillage.

4. Offsite Disposal and Treatment Facilities: Shall be licensed Disposal and/or Treatment facilities to accept the various waste types and quantities to be generated during the Work.

B. Codes and Regulations:

1. Comply with all federal, state, and local regulations in handling, testing, transporting, and disposing materials and in performing the Work.

2. Prior to commencing removal operations, obtain applicable local, state, and federal permits and licenses that directly impact Contractor’s ability to perform the Work.

1.6 SITE SPECIFIC HEALTH AND SAFETY PLAN

02 61 00 4 REMOVAL AND DISPOSAL OF

A. The Contractor is responsible for developing site specific health and safety plans addressing personnel exposures that could be encountered during demolition activities in compliance with all OSHA/MIOSHA regulations on these sites. The health and safety plan will need to address any controls to be implemented by the Contractor to prevent exposures to base personnel during the demolition activities.

B. The Contractor will be required to notify base personnel and/or subcontractors working onsite of the health and safety plan. All personnel onsite including Government personnel shall receive a briefing on the health and safety plan prior to entering construction areas where contaminated soils are present. Documentation of such briefings will need to be maintained by the Contractor and provided to the Government at the end of the Contract.

C. Where levels of contamination in work activities could result in potential exposure above action levels, exclusion zone will be set up by the Contractor to prevent any nonqualified personnel from entering the area.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Plastic Sheeting:

1. Nylon-reinforced polyethylene sheeting, opaque/frosted.

2. Thickness: Minimum 10 mils.

B. Tape and Glue: Capable of sealing joints of adjacent sheets of plastic and capable of adhering under wet conditions.

C. Ballast: Sandbags or other ballast materials of sufficient weight and quantity to maintain polyethylene sheeting securely in place.

PART 3 - EXECUTION

3.1 GENERAL

A. Contractor shall be responsible for the following:

1. Providing means, methods, and equipment necessary for sampling, excavating, collecting, handling, processing, loading, and disposing of hazardous and nonhazardous soil, debris, excavated waste, and wastewater generated as part of the Work.

2. Selecting, providing, and coordinating with qualified transporters, disposal facilities, and treatment facilities for transporting, disposing, and documenting hazardous and nonhazardous waste transportation and disposal in accordance with this Specification.

3. Complying with federal, state, and local requirements for transporting solid and liquid materials from Site through applicable jurisdictions, and be responsible for associated fines, penalties, and other costs for noncompliance.

02 61 00 5 REMOVAL AND DISPOSAL OF

4. Obtaining and submitting acceptance letters and receipts for materials disposed at each facility.

5. Including provisions in its construction sequence and schedule for sampling, analysis, and review of sampling results.

6. Coordinating work methods with Contracting for all actions pertaining to handling, storage, characterization, sampling, transportation, and disposal of all waste media out of the Site.

10 Working days shall be provided for review of proposed methods, which must be approved through the Contracting Officer prior to initiating field activities.

B. Excavation and Water Control Plan:

1. Plan shall include, but not be limited to, the following:

a. Means and sequencing of excavation.

b. Proposed locations, layout, and controls for materials stockpile areas.

c. Numbers and types of proposed equipment.

d. Methods of handling, segregating, and stockpiling excavated materials.

e. Methods of controlling water and sediment in excavation and proposed stockpile areas.

f. Proposed locations, types, and capacities of temporary water storage facilities, if required.

g. Sheeting, shoring, and bracing, as required.

h. Disposal of Groundwater Dewatered from the Site: Disposal shall require special handling procedures. Contractor shall be responsible for containerizing, testing, characterizing, and disposing of groundwater from the Site.

C. Soil and Debris Analytical and Physical Characterization Testing Plan:

1. Plan shall include, but not be limited to, the following:

a. Plan view showing proposed sample locations, depths, and number of samples for characterization and disposal facility acceptance testing, and for confirmatory testing, if required.

b. Sampling and analysis of areas found to contain hazardous materials. Results shall be used to determine if material should be handled and disposed of as hazardous and to define extent of this material.

c. Detail sampling and characterization of other materials excavated from Site.

d. Testing requirements shall include chemical and physical analyses necessary to assess at a minimum the contaminants of concern as listed in the referenced Investigative Reports.

e. Sampling plan shall characterize the materials, and conform to treatment and disposal facility acceptance requirements, if any.

f. Proposed testing laboratory, analyses required, and testing methods.

D. Provide qualified Licensed Site Professional to oversee and supervise sampling, excavation, and waste handling operations at Site and to coordinate with proposed disposal and treatment facilities.

02 61 00 6 REMOVAL AND DISPOSAL OF

3.2 WASTE CHARACTERIZATION SAMPLING AND ANALYSIS

A. Prior to commencing waste removal from Site, perform onsite sampling and laboratory testing to screen Site for potential hazardous waste and to conform to acceptance criteria of proposed disposal or treatment facilities. Sampling and testing shall be done in accordance with approved Soil and Debris Analytical and Physical Characterization Testing Plan.

B. Allow a minimum of 4 weeks in schedule for testing and review by disposal facility and Contracting Officer.

C. At a minimum, test for contaminants of concern listed in the referenced Site Investigative Reports.

3.3 WASTE EXCAVATION AND DEWATERING

A. Hazardous soil, wastewater, and debris may be encountered during excavation for facilities at Site. Material shall be removed, handled, and disposed in accordance with all state requirements for media relocation during work activities under Section 201120c of Part 201, Environmental Remediation, of the Natural Resources and Environmental Protection Act, 1994 PA 451, as amended (Act 451), and other applicable state and federal regulations if contaminated media will be relocated to or from these AOCs.

B. Perform excavation in accordance with requirements of Section 31 20 00, Earthwork, unless otherwise specified in this section and approved Excavation and Water Control Plan.

C. Water control shall be provided in accordance with the approved Excavation and Water Control Plan.

D. Conduct Work in excavated area in accordance with Contractor’s Site-specific safety plan.

E. Excavate methodically and submit weekly excavation plans no later than Thursday of the week preceding the Work.

F. Excavations shall proceed in lifts no greater than 1 foot thick. At Contracting Officer’s request, excavate test pits no greater than 4 feet deep in advance of the excavation for the purpose of sampling and delineating material to be excavated.

G. Immediately stop excavation and notify Contracting Officer upon encountering material unanticipated or outside scope of this Specification. This may include, but is not limited to, free product, tanks, ACM, or solid material other than excavated waste.

H. Over-excavation:

1. Excavate only the amount of soil required to construct the Work shown on Drawings.

2. Over-excavation of additional contaminate soil/debris, solid waste, or soil beyond amount required for construction of foundation and subgrade preparation shall not be performed without written authorization by Contracting Officer.

3. Over-excavation of contaminate soil/debris, solid waste, or soil that is not authorized by Contracting Officer shall be disposed and replaced at Contractor’s own expense.

02 61 00 7 REMOVAL AND DISPOSAL OF

4. Excess dewatering of groundwater to include contaminated groundwater that is not authorized by the Contracting Officer shall be disposed at Contractor’s own expense.

3.4 FREE PRODUCT REMOVAL

A. In the event that free product is encountered in the excavation:

1. Immediately notify Contracting Officer to determine appropriate sampling, removal, and disposal requirements.

2. Remove product in a manner that minimizes the spread of contamination into previously uncontaminated zones by using a containment recovery and storage system to contain and remove product.

3. Provide onsite storage suitable for recovered material. Media contaminated with free product shall be containerize and/or stockpiled in a manner to prevent off site migration of contamination from occurring.

4. Material shall remain onsite until Contractor completes a characterization analysis.

5. Material shall not be transported to a disposal facility until analysis is complete and waste profiles have been approved by the Contracting Officer

3.5 WASTE HANDLING AND DISPOSAL

A. To the extent possible, schedule and coordinate Work such that excavated waste and wastewater can be loaded and removed from Site with minimal handling or storage requirements.

B. Contractor selected Disposal facilites for contaminated media shall be a licensed to received waste generated.

C. Where temporary storage or stockpiling is necessary, provide and maintain adequate containment and environmental controls, including but not limited to containers, dikes, plastic linings, plastic covers, erosion and sediment controls, and other measures of sufficient capacity to store materials without unauthorized release of contaminants into ground, air, or surface water.

D. Site soils shall either be containerized or shall be stored on top of plastic sheeting on an impervious surface and covered with plastic sheeting.

E. Contaminated wastewater that is generated from excavations within the Site shall be containerized, characterized, and disposed of in accordance with means and methods selected by the Contractor and approved by the Contracting Officer. All costs and labor associated with containerization, characterization, and disposal along with any necessary permits shall be the responsibility of the contractor.

F. Provide labor, equipment, and materials to stabilize or process waste materials as necessary to meet minimum requirements for offsite transport and disposal.

02 61 00 8 REMOVAL AND DISPOSAL OF

G. All excess soil for areas outside the Site can be relocated on the installation to areas approved by the Government.

1. If soil relocation areas are not already included and identified on the soil erosion control plan for this project, modifications to the soil erosion control plan will need to be made and coordinated for approval with the Macomb County Soil Erosion office by the Contractor following approval from the Government.

2. If any excess soils for areas outside the Site will be taken off the installation, those soils must be disposed of in a licensed Type II disposal facility and meet the same requirements as if the soils were coming from the Site as specified above, with the exception of the special stockpiling provisions specified above.

H. Transportation:

1. Provide sealed or lined vehicles and other measures necessary to prevent spillage or tracking of waste materials, mud, wastewater, or other debris on local streets or roads.

2. Inspect and document vehicles and containers for proper operation and covering.

3. Inspect vehicles and containers for proper markings, manifests, and other requirements for waste shipment.

4. Perform and document decontamination procedures prior to leaving Site and again before leaving disposal or treatment facility.

I. Obtain and submit receipts of confirmation from disposal or treatment facilities that solid and liquid wastes were accepted for disposal or treatment, including weight tickets or other confirmation of quantities received.

3.6 EQUIPMENT DECONTAMINATION

A. Decontaminate equipment that has come into contact with hazardous soil or debris, solid waste, or impacted water by methods approved by the Contracting Officer.

B. Wastewater and sediment generated by decontamination activities shall be contained and treated or disposed of in accordance with provisions stated in this section.

END OF SECTION 02 61 00

31 10 00 1 SITE CLEARING

SECTION 31 10 00 - SITE CLEARING

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Protecting existing vegetation to remain.

2. Removing existing vegetation.

3. Clearing and grubbing.

4. Stripping and stockpiling topsoil.

5. Removing above- and below-grade site improvements.

6. Disconnecting, capping or sealing, and removing site utilities or abandoning site utilities in place.

7. Temporary erosion- and sedimentation-control measures.

B. Related Sections:

1. Section 01 50 00, Construction Facilities and Temporary Controls, for temporary utility services, construction and support facilities, and security and protection facilities.

2. Section 01 57 00, Erosion and Sediment Control, for erosion control protection on the site.

3. Section 01 74 19, Construction Waste Management and Disposal, and Section 01 18 13, Sustainable Design Requirements, for additional LEED requirements.

1.3 DEFINITIONS

A. Subsoil: All soil beneath the topsoil layer of the soil profile, and typified by the lack of organic matter and soil organisms.

B. Surface Soil: Soil that is present at the top layer of the existing soil profile at the Project site.

In undisturbed areas, the surface soil is typically topsoil; but in disturbed areas such as urban environments, the surface soil can be subsoil.

C. Topsoil: Top layer of the soil profile consisting of existing native surface topsoil or existing in-place surface soil and is the zone where plant roots grow. Its appearance is generally friable, pervious, and black or a darker shade of brown, gray, or red than underlying subsoil; reasonably free of subsoil, clay lumps, gravel, and other objects more than 2 inches (50 mm) in diameter;

and free of subsoil and weeds, roots, toxic materials, or other nonsoil materials.

31 10 00 2 SITE CLEARING

D. Plant-Protection Zone: Area surrounding individual trees, groups of trees, shrubs, or other vegetation to be protected during construction, and indicated on Drawings.

E. Tree-Protection Zone: Area surrounding individual trees or groups of trees to be protected during construction, and indicated on Drawings.

F. Vegetation: Trees, shrubs, groundcovers, grass, and other plants.

1.4 MATERIAL OWNERSHIP

A. Except for stripped topsoil and other materials indicated to be stockpiled or otherwise remain Government’s property, cleared materials shall become Contractor's property and shall be removed from Project site.

1.5 INFORMATIONAL SUBMITTALS

A. Existing Conditions: Documentation of existing trees and plantings, adjoining construction, and site improvements that establishes preconstruction conditions that might be misconstrued as damage caused by site clearing.

1. Use sufficiently detailed photographs or videotape.

2. Include plans and notations to indicate specific wounds and damage conditions of each tree or other plants designated to remain.

B. Record Drawings: Identifying and accurately showing locations of capped utilities and other subsurface structural, electrical, and mechanical conditions.

1.6 QUALITY ASSURANCE

A. Preinstallation Conference: Conduct conference at Project site.

1.7 PROJECT CONDITIONS

A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during site-clearing operations.

1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Government and authorities having jurisdiction.

2. Provide alternate routes around closed or obstructed traffic ways if required by Government or authorities having jurisdiction.

B. Improvements on Adjoining Property: Authority for performing site clearing indicated on property adjoining Government's property will be obtained by Government before award of Contract.

1. Do not proceed with work on adjoining property until directed by Contracting Officer.

31 10 00 3 SITE CLEARING

C. Salvable Improvements: Carefully remove items indicated to be salvaged and store on Government's premises where indicated.

D. Utility Locator Service: Notify utility locator service for area where Project is located before site clearing.

E. Do not commence site clearing operations until temporary erosion- and sedimentation-control and plant-protection measures are in place.

F. The following practices are prohibited within protection zones:

1. Storage of construction materials, debris, or excavated material.

2. Parking vehicles or equipment.

3. Foot traffic.

4. Erection of sheds or structures.

5. Impoundment of water.

6. Excavation or other digging unless otherwise indicated.

7. Attachment of signs to or wrapping materials around trees or plants unless otherwise indicated.

G. Do not direct vehicle or equipment exhaust towards protection zones.

H. Prohibit heat sources, flames, ignition sources, and smoking within or near protection zones.

I. Soil Stripping, Handling, and Stockpiling: Perform only when the topsoil is dry or slightly moist.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Satisfactory Soil Material: Requirements for satisfactory soil material are specified in Section 31 20 00, Earthwork.

1. Obtain approved borrow soil material off-site when satisfactory soil material is not available on-site.

B. Antirust Coating: Fast-curing, lead- and chromate-free, self-curing, universal modified-alkyd primer complying with MPI #79, Alkyd Anticorrosive Metal Primer.

1. Use coating with a VOC content of 420 g/L (3.5 lb/gal.) or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24).

PART 3 - EXECUTION

3.1 PREPARATION

31 10 00 4 SITE CLEARING

A. Protect and maintain benchmarks and survey control points from disturbance during construction.

B. Locate and clearly identify trees, shrubs, and other vegetation to remain or to be relocated. Flag each tree trunk at 54 inches (1372 mm) above the ground.

C. Protect existing site improvements to remain from damage during construction.

1. Restore damaged improvements to their original condition, as acceptable to Government.

3.2 TEMPORARY EROSION AND SEDIMENTATION CONTROL

A. Provide temporary erosion- and sedimentation-control measures to prevent soil erosion and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways, according to erosion- and sedimentation-control Drawings, Section 01 57 00, Erosion and Sediment Control, and requirements of authorities having jurisdiction.

B. Verify that flows of water redirected from construction areas or generated by construction activity do not enter or cross protection zones.

C. Inspect, maintain, and repair erosion- and sedimentation-control measures during construction until permanent vegetation has been established.

D. Remove erosion and sedimentation controls and restore and stabilize areas disturbed during removal.

3.3 TREE AND PLANT PROTECTION

A. General: Protect trees and plants remaining on-site according to requirements in Section 01 57 00, Erosion and Sediment Control.

B. Repair or replace trees, shrubs, and other vegetation indicated to remain or be relocated that are damaged by construction operations, in a manner approved by Contracting Officer.

3.4 EXISTING UTILITIES

A. Government will arrange for disconnecting and sealing indicated utilities that serve existing structures before site clearing, when requested by Contractor.

1. Verify that utilities have been disconnected and capped before proceeding with site clearing.

B. Locate, identify, disconnect, and seal or cap utilities indicated to be removed or abandoned in place.

1. Arrange with utility companies to shut off indicated utilities.

2. Government will arrange to shut off indicated utilities when requested by Contractor.

31 10 00 5 SITE CLEARING

C. Locate, identify, and disconnect utilities indicated to be abandoned in place.

D. Interrupting Existing Utilities: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than 4 weeks in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer's written permission.

E. Excavate for and remove underground utilities indicated to be removed.

3.5 CLEARING AND GRUBBING

A. Remove obstructions, trees, shrubs, and other vegetation to permit installation of new construction.

1. Do not remove trees, shrubs, and other vegetation indicated to remain or to be relocated.

2. Grind down stumps and remove roots, obstructions, and debris to a depth of 18 inches

(450 mm) below exposed subgrade.

3. Use only hand methods for grubbing within protection zones.

4. Chip removed tree branches and stockpile in areas approved by Contracting Officer.

B. Fill depressions caused by clearing and grubbing operations with satisfactory soil material unless further excavation or earthwork is indicated.

1. Place fill material in horizontal layers not exceeding a loose depth of 8 inches (200 mm), and compact each layer to a density equal to adjacent original ground.

3.6 TOPSOIL STRIPPING

A. Remove sod and grass before stripping topsoil.

B. Strip topsoil to depth of 6 inches (150 mm) in a manner to prevent intermingling with underlying subsoil or other waste materials.

1. Remove subsoil and nonsoil materials from topsoil, including clay lumps, gravel, and other objects more than 2 inches (50 mm) in diameter; trash, debris, weeds, roots, and other waste materials.

C. Stockpile topsoil away from edge of excavations without intermixing with subsoil. Grade and shape stockpiles to drain surface water. Cover to prevent windblown dust and erosion by water.

1. Limit height of topsoil stockpiles to 72 inches (1800 mm).

2. Do not stockpile topsoil within protection zones.

3. Stockpile surplus topsoil to allow for respreading deeper topsoil.

31 10 00 6 SITE CLEARING

3.7 SITE IMPROVEMENTS

A. Remove existing above- and below-grade improvements as indicated and necessary to facilitate new construction.

B. Remove slabs, paving, curbs, gutters, and aggregate base as indicated.

1. Unless existing full-depth joints coincide with line of demolition, neatly saw-cut along line of existing pavement to remain before removing adjacent existing pavement. Saw-cut faces vertically.

2. Paint cut ends of steel reinforcement in concrete to remain with two coats of antirust coating, following coating manufacturer's written instructions. Keep paint off surfaces that will remain exposed.

3.8 DISPOSAL OF SURPLUS AND WASTE MATERIALS

A. Remove surplus soil material, unsuitable topsoil, obstructions, demolished materials, and waste materials including trash and debris as per Section 31 20 00, Earthwork.

B. Separate recyclable materials produced during site clearing from other nonrecyclable materials.

Store or stockpile without intermixing with other materials and transport them to recycling facilities. Do not interfere with other Project work.

END OF SECTION 31 10 00

31 20 00 1 EARTHWORK

SECTION 31 20 00 - EARTHWORK

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This section covers the Work necessary to perform:

1. Water control.

2. Excavation.

3. Trench excavation.

4. Subgrade preparation.

5. Fill and backfill.

6. Trench backfill.

7. Grading.

B. The Work consists of furnishing all labor, materials and equipment necessary to accomplish the Work.

C. Related Sections:

1. Section 01 32 00, Construction Progress Schedules, for recording pre-excavation and earthwork progress.

2. Section 01 50 00, Construction Facilities and Temporary Controls, for temporary controls, utilities, and support facilities; also for temporary site fencing if not in another Section.

3. Section 01 57 00, Erosion and Sediment Control.

4. Section 02 61 00, Removal and Disposal of Contaminated Media, for earthwork within areas of concern.

5. Section 03 30 00, Cast-in-Place Concrete, for concrete mix design requirements, cement properties and concrete or controlled low strength material (CLSM) placement.

6. Divisions 21, 22, 23, 26, 27, 28, and 33 Sections for installing underground mechanical and electrical utilities and buried mechanical and electrical structures as included in individual Delivery Order Requirements.

7. Section 31 10 00, Site Clearing, for site stripping, grubbing, stripping and stockpiling topsoil, and removal of above- and below-grade improvements and utilities.

8. Section 31 63 20, Deep Ground Improvement, for excavation, subgrade preparation and fill and backfill under structures footing and slab on grades.

9. Section 32 92 00, Turf and Grasses, for finish grading in turf and grass areas, including preparing and placing planting soil for turf areas.

31 20 00 2 EARTHWORK

1.3 REFERENCES

A. The following is a list of standards which may be referenced in this section:

1. American National Standards Institute (ANSI): Z535.1, Safety Color Code.

2. American Public Works Association (APWA): Uniform Color Code for Tempo-rary Marking of Underground Utility Locations.

3. ASTM International (ASTM):

a. C33, Standard Specification for Concrete Aggregates.

b. C94/C94M, Standard Specification for Ready-Mixed Concrete.

c. C117, Standard Test Method for Materials Finer Than 75-Micrometers

(No. 200) Sieve in Mineral Aggregates by Washing.

d. C136, Standard Method for Sieve Analysis of Fine and Coarse Aggregates.

e. C150, Standard Specification for Portland Cement.

f. C618, Standard Specification for Coal Fly Ash and Raw or Calcined Natural

Pozzolan for Use as a Mineral Admixture in Concrete.

g. D75, Standard Practice for Sampling Aggregates.

h. D1140, Standard Test Method for Amount of Material in Soils Finer than the No. 200 (75 micrometer) Sieve.

i. D1556, Standard Test Method for Density and Unit Weight of Soil in Place by the Sand-Cone Method.

j. D1557, Test Method for Laboratory Compaction Characteristics of Soil Us-ing Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3)).

k. D2487, Standard Practice for Classification of Soils for Engineering Pur-poses (Unified Soil Classification System)

l. D3740, Standard Practice for Minimum Requirements for Agencies En-gaged in Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction.

m. D3776, Standard Test Method for Mass per Unit Area (Weight) of Fabric.

n. D4253, Standard Test Methods for Maximum Index Density and Unit

Weight of Soils Using a Vibratory Table.

o. D4254, Standard Test Method for Minimum Index Density and Unit Weight of Soils and Calculation of Relative Density.

p. D4318, Standard Test Methods for Liquid Limit, Plastic Limit, and Plastici-ty Index of Soils.

q. D4832, Standard Test Method for Preparation and Testing of Controlled

Low Strength Material (CLSM) Test Cylinders.

r. D4991, Standard Test Method for Leakage Testing of Empty Rigid Contain-ers by Vacuum Method.

s. D5971, Test Method for Sampling Freshly Mixed Controlled Low Strength

Materials

t. D6023, Test Method for Unit Weight, Yield and Air Content of Controlled

Low Strength Materials.

u. D6103, Test Method for Flow Consistency of Controlled Low Strength Ma-terials.

v. D6938, Standard Test Methods for In-Place Density and Water Content of

Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth).

31 20 00 3 EARTHWORK

w. E329 , Standard Specification for Agencies Engaged in Construction Inspec-tion and/or Testing.

4. Occupational Safety and Health Administration (OSHA): Regulations and Stand-ards for Underground Construction, 29 CFR Part 1926, Subpart S, Underground Construction, and Subpart P, Excavations.

1.4 DEFINITIONS

A. Relative Compaction:

1. Ratio, in percent, of as-compacted field dry density to laboratory maximum dry density as determined in accordance with ASTM D1557.

2. Apply corrections for oversize material to either as-compacted field dry density or maximum dry density, as determined by Contracting Officer.

B. Optimum Moisture Content:

1. Determined in accordance with ASTM Standard specified to determine maximum dry density for relative compaction.

2. Determine field moisture content on basis of fraction passing 3/4-inch sieve.

C. Backfill: Soil material or controlled low-strength material used to fill an excavation.

D. Prepared Ground Surface: Ground surface after completion of required demolition,…