Attachment 4 - SOW.pdf
PDF 130 KB Posted
- Attached to
- Eaton/Wright Line Furniture - ITEC Federal contract opportunity
- Solicitation number
- FA875122Q0371
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 1 -Brand Name_Wrightline.pdf | ||
| Attachment 5 - Wage Determination.pdf | ||
| Attachment 2- Wright Line Parts List.xlsx | XLSX spreadsheet | |
| Attachment 3- Furniture Drawing.pdf | ||
| Attachment 6 - Reps and Certs.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
PROVIDE EATON/WRIGHT LINE LAB FURNITURE
RELOCATE ITEC TO BUILDING 106
AT
AIR FORCE RESEARCH LABORATORY
ROME, NY
17 May 2022
1.01 SCOPE
A. The scope of this effort consists of furnishing all design services, delivery and labor, equipment, devices, and materials, for new and existing components and parts and to perform all work required to PROVIDE EATON/WRIGHT LINE LAB FURNITURE, located at Air Force Research Laboratory ITEC, ROME, NY. This procurement will consist of installing existing furniture from our current inventory as well as supplemental new parts and pieces.
1.02 PRINCIPAL FEATURES
A. The work to be performed involves the following principal features:
1. Develop estimates with part numbers and descriptions for all pieces listed on attached parts list. All parts must be new. Eaton/Wright Line brand parts will be the only accepted product line, as our existing parts are from Eaton/Wright Line.
Parts are proprietary, Eaton/Wright Line will be the only brand accepted.
2. All product to be quoted in the following finishes:
Metal Frame: Black
Metal: NuGrey
Fabric: FR701 Grey Mix
Laminate: Greystone (ESD)
Trim: NuGrey
3. After AFRL/RIOC approval, order and deliver all furniture and materials to work area site. Transport existing inventory from Bldg. 2, Warehouse to installation site in Bldg. 106 (Warehouse is located across from installation site).
4. Install all furniture, including all accessories. Remove all packing material and boxes from the work site.
5. Bldg. 2 Warehouse has a useable loading dock. Bldg. 106 (Installation bldg.) has a vehicle bay with overhead door, no loading dock. Installation will be on the 1st floor installation directly across from the vehicle bay.
‐‐ End of SOW‐‐