Attachment 4 Schedule of Items.pdf

PDF 46 KB Posted

Attached to
Fort Simcoe Job Corps Center Water System Renovation
Solicitation number
12441926R0002
Issued by

About this file

This is a Schedule of Items for the Fort Simcoe Water System Renovation project dated August 5, 2024. The document outlines a comprehensive water infrastructure renovation consisting of 24 base items and 3 optional items, with quantities and unit prices to be completed by the contractor.

Base items include mobilization, erosion controls, utility locates, and construction signage. Primary work involves constructing approximately 8,798 linear feet of 6-inch PVC C-900 waterline using open excavation or approved alternative methods, including trench excavation, pipe installation, backfill, fittings, thrust blocks, disinfection, and testing. The project requires water service replacement for 18 buildings (two duplexes, Nation Hall, Student Services, Student Health, Education, Gym, Maintenance, Brick Trade, WPO, Dental Storage, Auto, Fuel Building, Heavy Equipment, Trucking, Warehouse, Admin, and Carpentry). Additional base work includes pavement restoration (2,450 square feet), sidewalk replacement (80 square feet), installation of 7 fire hydrants, 37 6-inch gate valves with restrained joints, 9 3-inch and 2 4-inch backflow prevention valves for irrigation, asbestos cement pipe removal and disposal, instrumentation upgrades for three wells and reservoir, water sampling stations, upgrades to Wells 1, 2, and 3, reservoir improvements, fill station improvements, and 4 8-inch gate valves with restrained joints. A 3-percent TERO fee applies to the subtotal. Optional items include construction of an additional 828 linear feet of 6-inch PVC C-900 waterline, 1 additional 6-inch gate valve with restrained joints, and pavement restoration for 81 square feet.

View the file

Other files

File Type Posted
Attachment 5 Davis-Bacon Wage Determinations.pdf PDF
Attachment 3 Specifications.pdf PDF
Attachment 2 Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Fort Simcoe Water System Renovation Schedule of Items

8/5/2024 Item No Description Pay Unit

Pay Quantity and (Estimated Quantity) Unit Price Total

Base Items

0001 Mobilization LS 1

0002 Erosion Controls LS 1

0003 Utility Locates LS 1

0004 Construction Signage LS 1

Construct 6" PVC C-900 Waterline - Open Excavation or other approved method (Includes trench excavation, pipe, backfill, fittings, thrust blocks, disinfection and testing, and other miscellaneous work associated with installation and interconnection of new water main with existing and new lines.)

LS 1 (8798 LF)

0006 Not Used Not Used 1

Water Service Replacement - Building (All Sizes)Includes connection to water main, indicated pipe sizes, corporation stops & boxes, connection to existing building service entrance, and when indicated curb valves & boxes. 2 duplexes, Nation Hall, Student Services, Student Health, Education, Gym, Maintenance, Brick Trade, WPO, Dental Storage, Auto, Fuel Bldg, Heavy Equipment, Trucking, Warehouse, Admin, Carpentry

EA 18

Pavement Restoration - Quantity is based upon open excavation pipe installation.

LS 1 (2450 SF)

Sidewalk Replacement - Quantity is based upon open excavation pipe installation.

LS 1 (80 SF)

Fire Hydrant - Includes connection to main, pipe, joints, gate valve, valve box, hydrant.

EA 7

6" Gate Valve with Restrained Joint - Valves for hydrants are included in fire hydrant assembly item.

EA 37

Backflow Prevention Valve for Irrigation - up to 3-Inch (Includes all pipe, elbows, restraints and appurtenances)

EA 9

Backflow Prevention Valve for Irrigation - 4-Inch (Includes all pipe, elbows, restraints and appurtenances)

EA 2

0014 Asbestos Cement Pipe Removal and Disposal LS 1

Instrumentation Upgrades - Includes Wells 1,2,3, Reservoir, and Maintenance Bldg.

LS 1

Water Sampling Stations - Includes connection to main, curb valve & box,indicated fittings, riser, vent, housing, and tap.

EA 2

0017 Well 1 Upgrades LS 1

0018 Well 2 Upgrades LS 1

0019 Well 3 Upgrades LS 1

0020 Reservoir Improvements LS 1

Fill Station Improvements - Includes replacement of valves and valve boxes, connection of existing, fire fill to new water main, and installation of discharge screen.

LS 1

0022 Not Used Not Used Not Used

0023 8" Gate Valve With Restrained Joints EA 4

0024 TERO Fee (3% of Subtotal) LS 1

TOTAL BASE ITEMS:

Optional Items

Construct 6" PVC C-900 Waterline (Includes trench excavation, backfill, fittings, thrust blocks, disinfetion and testing)

LS 1 (828 LF)

0026 6" Gate Valve With Restrained Joints EA 1 0027 Pavement Restoration LS 1 (81 SF)

TOTAL OPTIONAL ITEMS:

TOTAL BASE + OPTIONAL ITEMS:

Schedule of Items