This document contains a solicitation for a remediation and site services contract at the Niagara Falls Storage Site in New York. The U.S. Army Corps of Engineers seeks to award a five-year IDIQ single award task order contract, including Task Order 1 which is a mix of FFP and CPFF line items, to remediate the Balance of Plant and Groundwater Operable Units and provide other site services. The solicitation includes a five-year ordering period and the January 19, 2023 site visit requires registration with the Contracting Officer. Questions are due by January 24, 2023 and proposals are due February 15, 2023. The template attachment provides pricing details for the remediation tasks.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule
| CLIN Type | ||||||||
| Task | Description | CLIN | Total Price | |||||
| 1 | Mobilization | 0001 | FFP | $ ‐ | ||||
| 4 | Demobilization | 0002 | FFP | $ ‐ | ||||
| 2a | Impacted Media Remediation (Soil and road bedding, Building 401 foundation and | |||||||
| utilities, Building 431/432 trench, and EU4 CVOC plume) | 0003 | CPFF | $ ‐ | |||||
| 3a | Transportation and Disposal (Wastes contaminated with ROCs) | 0004 | FFUP | $ ‐ | ||||
| 3b | Transportation and Disposal (Wastes contaminated with COCs) | 0005 | FFUP | $ ‐ | ||||
| 3c | Transportation and Disposal (Wastes contaminated with both ROCs and COCs) | 0006 | FFUP | $ ‐ | ||||
| 2b | Impacted Media Remediation (Building 430 foundation) | 0007 | (Option) | CPFF | $ ‐ | |||
| 3d | Transportation and Disposal (Building 430 foundation) | 0008 | (Option) | FFUP | $ ‐ | |||
| 2c | Impacted Media Remediation (Building 431/432 foundation) | 0009 | (Option) | CPFF | $ ‐ | |||
| 3e | Transportation and Disposal (Building 431/432 foundation) | 0010 | (Option) | FFUP | $ ‐ | |||
| 2d | Impacted Media Remediation (Building 433 foundation, sidewalls, and roof) | 0011 | (Option) | CPFF | $ ‐ | |||
| 3f | Transportation and Disposal (Building 433 foundation, sidewalls, and roof) | 0012 | (Option) | FFUP | $ ‐ | |||
| Total (CLIN 0001 ‐ 0012) | $ ‐ |
CLIN 0003
CLIN 0003: Impacted Media Remediation (Soil and road bedding, Building 401 foundation and utilities, Building 431/432 trench, and EU4 CVOC plume)
| Labor |
| Subcontractor |
| Travel |
| ODCs |
| Materials |
| Equipment |
| SUBTOTAL |
| G&A |
| SUBTOTAL |
| Fee |
| TOTAL TASK 2a (CLIN 0003) |
3-331XX 02
331XX 02 Monitoring, Sampling, Testing, and Analysis CLIN 0003: Impacted Media Remediation (Soil and road bedding, Building 401 foundation and utilities, Building 431/432 trench, and EU4 CVOC plume)
| 331XX0201 - Meteorological Monitoring | 331XX0202 - Radiation Monitoring | 331XX0203 - Air Monitoring and Sampling | 331XX0204 - Monitoring Wells | 331XX0205 - Sampling Surface Water/Groundwater/Liquid Waste | 331XX0206 - Sampling Soil and Sediment | 331XX0208 - Sampling Radioactive Contaminated Media | 331XX0209 - Laboratory Chemical Analysis | 331XX0210 - Radioactive Waste Analysis | 331XX0211 - Geotechnical Testing | ||||||||||||||||||||||||||||||||||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate |
| Subcontractor Labor Categories (by rate year) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total | |||||||||||||||||||||||||||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total Labor | |||||||||||||||||||||||||||||||||||||||||||||||||
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | ||||||||||
| Sub ODC (if applicable) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Subtotal | |||||||||||||||||||||||||||||||||||||||||||||||||
| G&A | |||||||||||||||||||||||||||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total ODC | |||||||||||||||||||||||||||||||||||||||||||||||||
| Travel | |||||||||||||||||||||||||||||||||||||||||||||||||
| Sub Travel (if applicable) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Subtotal | |||||||||||||||||||||||||||||||||||||||||||||||||
| G&A | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total | |||||||||||||||||||||||||||||||||||||||||||||||||
| Materials | |||||||||||||||||||||||||||||||||||||||||||||||||
| Sub Materials (if applicable) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Subtotal | |||||||||||||||||||||||||||||||||||||||||||||||||
| G&A | |||||||||||||||||||||||||||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total | |||||||||||||||||||||||||||||||||||||||||||||||||
| Equipment | |||||||||||||||||||||||||||||||||||||||||||||||||
| Sub Equipment (if applicable) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Subtotal | |||||||||||||||||||||||||||||||||||||||||||||||||
| G&A | |||||||||||||||||||||||||||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total |
3-331XX 03
331XX 03 Site Work CLIN 0003: Impacted Media Remediation (Soil and road bedding, Building 401 foundation and utilities, Building 431/432 trench, and EU4 CVOC plume)
| 331XX0302 - Clearing and Grubbing | 331XX0303 - Earthwork | 331XX0304 - Roads/Parking/Curbs/Walks | 331XX0305 - Fencing | Totals for 331XX 03 | |||||||||||||||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | |||||||||||||||||||||||||
| Total | |||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||||||||||||||
| Subtotal | ||||||||||||||||||||
| G&A | ||||||||||||||||||||
| Fee | ||||||||||||||||||||
| Total ODC | ||||||||||||||||||||
| Travel | ||||||||||||||||||||
| Sub Travel (if applicable) | ||||||||||||||||||||
| Subtotal | ||||||||||||||||||||
| G&A | ||||||||||||||||||||
| Total | ||||||||||||||||||||
| Materials | ||||||||||||||||||||
| Sub Materials (if applicable) | ||||||||||||||||||||
| Subtotal | ||||||||||||||||||||
| G&A | ||||||||||||||||||||
| Fee | ||||||||||||||||||||
| Total | ||||||||||||||||||||
| Equipment | ||||||||||||||||||||
| Sub Equipment (if applicable) | ||||||||||||||||||||
| Subtotal | ||||||||||||||||||||
| G&A | ||||||||||||||||||||
| Fee | ||||||||||||||||||||
| Total |
3-331XX 05
331XX 05 Surface Water Collection and Control CLIN 0003: Impacted Media Remediation (Soil and road bedding, Building 401 foundation and utilities, Building 431/432 trench, and EU4 CVOC plume)
| 331XX0507 - Sediment Barriers | 331XX0509 - Pumping/Draining Collection | Totals for 331XX 05 | |||||||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | |||||||||||||||
| Total | |||||||||||||||
| Fee | |||||||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total ODC | ||||||||||||
| Travel | ||||||||||||
| Sub Travel (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Total | ||||||||||||
| Materials | ||||||||||||
| Sub Materials (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total | ||||||||||||
| Equipment | ||||||||||||
| Sub Equipment (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total |
3-331XX 08
331XX 08 Solids Collection and Containment CLIN 0003: Impacted Media Remediation (Soil and road bedding, Building 401 foundation and utilities, Building 431/432 trench, and EU4 CVOC plume)
| 331XX0801 - Contaminated Soil Collection | Totals for 331XX 08 | |||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | ||||||||||
| Total | ||||||||||
| Fee | ||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total ODC | ||||||||
| Travel | ||||||||
| Sub Travel (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Total | ||||||||
| Materials | ||||||||
| Sub Materials (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total | ||||||||
| Equipment | ||||||||
| Sub Equipment (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total |
3-331XX 09
331XX 09 Liquids/Sediments/Sludges Collection and Containment CLIN 0003: Impacted Media Remediation (Soil and road bedding, Building 401 foundation and utilities, Building 431/432 trench, and EU4 CVOC plume)
| 331XX0907 - Lagoons/Basins/Tanks/Dikes/Pump System | Totals for 331XX 09 | |||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | ||||||||||
| Total | ||||||||||
| Fee | ||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total ODC | ||||||||
| Travel | ||||||||
| Sub Travel (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Total | ||||||||
| Materials | ||||||||
| Sub Materials (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total | ||||||||
| Equipment | ||||||||
| Sub Equipment (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total |
3-331XX 19
331XX 19 Disposal (Commercial) CLIN 0003: Impacted Media Remediation (Soil and road bedding, Building 401 foundation and utilities, Building 431/432 trench, and EU4 CVOC plume)
| 331XX1920 - Container Handling | Totals for 331XX 19 | |||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | ||||||||||
| Total | ||||||||||
| Fee | ||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total ODC | ||||||||
| Travel | ||||||||
| Sub Travel (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Total | ||||||||
| Materials | ||||||||
| Sub Materials (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total | ||||||||
| Equipment | ||||||||
| Sub Equipment (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total |
3-331XX 20
331XX 20 Site Restoration CLIN 0003: Impacted Media Remediation (Soil and road bedding, Building 401 foundation and utilities, Building 431/432 trench, and EU4 CVOC plume)
| 331XX2001 - Earthwork | 331XX2004 - Revegetation and Planting | Totals for 331XX 20 | |||||||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | |||||||||||||||
| Total | |||||||||||||||
| Fee | |||||||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total ODC | ||||||||||||
| Travel | ||||||||||||
| Sub Travel (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Total | ||||||||||||
| Materials | ||||||||||||
| Sub Materials (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total | ||||||||||||
| Equipment | ||||||||||||
| Sub Equipment (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total |
3-331XX 22
331XX 22 General Requirements CLIN 0003: Impacted Media Remediation (Soil and road bedding, Building 401 foundation and utilities, Building 431/432 trench, and EU4 CVOC plume)
331XX2201 - Supervision and Management 331XX2204 - Engineering, Surveying, and Quality Control 331XX2206 - First Aid, Fire Protection, Traffic Control and Security 331XX2207 - Health and Safety 331XX2208 - Temporary Construction Facilities (Ownership) 331XX2209 - Temporary Construction Facilities (Operation) 331XX2210 - Project Utilities Totals for 331XX 02
Labor Categories (by rate year) Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost
| Subcontractor Labor Categories (by rate year) | ||||||||||||||||||||||||||||||||
| Total | ||||||||||||||||||||||||||||||||
| Fee | ||||||||||||||||||||||||||||||||
| Total Labor | ||||||||||||||||||||||||||||||||
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||||||||||||||||||||||||||
| Subtotal | ||||||||||||||||||||||||||||||||
| G&A | ||||||||||||||||||||||||||||||||
| Fee | ||||||||||||||||||||||||||||||||
| Total ODC | ||||||||||||||||||||||||||||||||
| Travel | ||||||||||||||||||||||||||||||||
| Sub Travel (if applicable) | ||||||||||||||||||||||||||||||||
| Subtotal | ||||||||||||||||||||||||||||||||
| G&A | ||||||||||||||||||||||||||||||||
| Total | ||||||||||||||||||||||||||||||||
| Materials | ||||||||||||||||||||||||||||||||
| Sub Materials (if applicable) | ||||||||||||||||||||||||||||||||
| Subtotal | ||||||||||||||||||||||||||||||||
| G&A | ||||||||||||||||||||||||||||||||
| Fee | ||||||||||||||||||||||||||||||||
| Total | ||||||||||||||||||||||||||||||||
| Equipment | ||||||||||||||||||||||||||||||||
| Sub Equipment (if applicable) | ||||||||||||||||||||||||||||||||
| Subtotal | ||||||||||||||||||||||||||||||||
| G&A | ||||||||||||||||||||||||||||||||
| Fee | ||||||||||||||||||||||||||||||||
| Total |
CLIN 0003 Rollup CLIN 0003: Impacted Media Remediation (Soil and road bedding, Building 401 foundation and utilities, Building 431/432 trench, and EU4 CVOC plume)
| Labor Categories (by rate year) | Category Units | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | |||||
| Total | |||||
| Fee | |||||
| Total Labor | |||||
| ODCs | Qty | Total Units | Unit Rate | Cost | |
| Sub ODC (if applicable) | |||||
| Subtotal | |||||
| G&A | |||||
| Fee | |||||
| Total ODC | |||||
| Travel | |||||
| Sub Travel (if applicable) | |||||
| Subtotal | |||||
| G&A | |||||
| Total | |||||
| Materials | |||||
| Sub Materials (if applicable) | |||||
| Subtotal | |||||
| G&A | |||||
| Fee | |||||
| Total | |||||
| Equipment | |||||
| Sub Equipment (if applicable) | |||||
| Subtotal | |||||
| G&A | |||||
| Fee | |||||
| Total |
CLIN 0007
CLIN 0007: Impacted Media Remediation (Building 430 Foundation)
Total Cost
| Labor |
| Subcontractor |
| Travel |
| ODCs |
| Materials |
| Equipment |
| SUBTOTAL |
| G&A |
| SUBTOTAL |
| Fee |
| TOTAL TASK 2b (CLIN 0003) |
7-331XX 02
331XX 02 Monitoring, Sampling, Testing, and Analysis CLIN 0007: Impacted Media Remediation (Building 430 Foundation)
| 331XX0201 - Meteorological Monitoring | 331XX0202 - Radiation Monitoring | 331XX0203 - Air Monitoring and Sampling | 331XX0204 - Monitoring Wells | 331XX0205 - Sampling Surface Water/Groundwater/Liquid Waste | 331XX0206 - Sampling Soil and Sediment | 331XX0208 - Sampling Radioactive Contaminated Media | 331XX0209 - Laboratory Chemical Analysis | 331XX0210 - Radioactive Waste Analysis | 331XX0211 - Geotechnical Testing | ||||||||||||||||||||||||||||||||||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate |
| Subcontractor Labor Categories (by rate year) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total | |||||||||||||||||||||||||||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total Labor | |||||||||||||||||||||||||||||||||||||||||||||||||
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | ||||||||||
| Sub ODC (if applicable) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Subtotal | |||||||||||||||||||||||||||||||||||||||||||||||||
| G&A | |||||||||||||||||||||||||||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total ODC | |||||||||||||||||||||||||||||||||||||||||||||||||
| Travel | |||||||||||||||||||||||||||||||||||||||||||||||||
| Sub Travel (if applicable) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Subtotal | |||||||||||||||||||||||||||||||||||||||||||||||||
| G&A | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total | |||||||||||||||||||||||||||||||||||||||||||||||||
| Materials | |||||||||||||||||||||||||||||||||||||||||||||||||
| Sub Materials (if applicable) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Subtotal | |||||||||||||||||||||||||||||||||||||||||||||||||
| G&A | |||||||||||||||||||||||||||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total | |||||||||||||||||||||||||||||||||||||||||||||||||
| Equipment | |||||||||||||||||||||||||||||||||||||||||||||||||
| Sub Equipment (if applicable) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Subtotal | |||||||||||||||||||||||||||||||||||||||||||||||||
| G&A | |||||||||||||||||||||||||||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total |
7-331XX 03
331XX 03 Site Work CLIN 0007: Impacted Media Remediation (Building 430 foundation)
| 331XX0302 - Clearing and Grubbing | 331XX0303 - Earthwork | 331XX0304 - Roads/Parking/Curbs/Walks | 331XX0305 - Fencing | Totals for 331XX 03 | |||||||||||||||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | |||||||||||||||||||||||||
| Total | |||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||||||||||||||
| Subtotal | ||||||||||||||||||||
| G&A | ||||||||||||||||||||
| Fee | ||||||||||||||||||||
| Total ODC | ||||||||||||||||||||
| Travel | ||||||||||||||||||||
| Sub Travel (if applicable) | ||||||||||||||||||||
| Subtotal | ||||||||||||||||||||
| G&A | ||||||||||||||||||||
| Total | ||||||||||||||||||||
| Materials | ||||||||||||||||||||
| Sub Materials (if applicable) | ||||||||||||||||||||
| Subtotal | ||||||||||||||||||||
| G&A | ||||||||||||||||||||
| Fee | ||||||||||||||||||||
| Total | ||||||||||||||||||||
| Equipment | ||||||||||||||||||||
| Sub Equipment (if applicable) | ||||||||||||||||||||
| Subtotal | ||||||||||||||||||||
| G&A | ||||||||||||||||||||
| Fee | ||||||||||||||||||||
| Total |
7-331XX 05
331XX 05 Surface Water Collection and Control CLIN 0007: Impacted Media Remediation (Building 430 foundation)
| 331XX0507 - Sediment Barriers | 331XX0509 - Pumping/Draining Collection | Totals for 331XX 05 | |||||||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | |||||||||||||||
| Total | |||||||||||||||
| Fee | |||||||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total ODC | ||||||||||||
| Travel | ||||||||||||
| Sub Travel (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Total | ||||||||||||
| Materials | ||||||||||||
| Sub Materials (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total | ||||||||||||
| Equipment | ||||||||||||
| Sub Equipment (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total |
7-331XX 08
331XX 08 Solids Collection and Containment CLIN 0007: Impacted Media Remediation (Building 430 foundation)
| 331XX0801 - Contaminated Soil Collection | Totals for 331XX 08 | |||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | ||||||||||
| Total | ||||||||||
| Fee | ||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total ODC | ||||||||
| Travel | ||||||||
| Sub Travel (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Total | ||||||||
| Materials | ||||||||
| Sub Materials (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total | ||||||||
| Equipment | ||||||||
| Sub Equipment (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total |
7-331XX 09
331XX 09 Liquids/Sediments/Sludges Collection and Containment CLIN 0007: Impacted Media Remediation (Building 430 foundation)
| 331XX0907 - Lagoons/Basins/Tanks/Dikes/Pump System | Totals for 331XX 09 | |||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | ||||||||||
| Total | ||||||||||
| Fee | ||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total ODC | ||||||||
| Travel | ||||||||
| Sub Travel (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Total | ||||||||
| Materials | ||||||||
| Sub Materials (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total | ||||||||
| Equipment | ||||||||
| Sub Equipment (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total |
7-331XX 19
331XX 19 Disposal (Commercial) CLIN 0007: Impacted Media Remediation (Building 430 foundation)
| 331XX1920 - Container Handling | Totals for 331XX 19 | |||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | ||||||||||
| Total | ||||||||||
| Fee | ||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total ODC | ||||||||
| Travel | ||||||||
| Sub Travel (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Total | ||||||||
| Materials | ||||||||
| Sub Materials (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total | ||||||||
| Equipment | ||||||||
| Sub Equipment (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total |
7-331XX 20
331XX 20 Site Restoration CLIN 0007: Impacted Media Remediation (Building 430 foundation)
| 331XX2001 - Earthwork | 331XX2004 - Revegetation and Planting | Totals for 331XX 20 | |||||||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | |||||||||||||||
| Total | |||||||||||||||
| Fee | |||||||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total ODC | ||||||||||||
| Travel | ||||||||||||
| Sub Travel (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Total | ||||||||||||
| Materials | ||||||||||||
| Sub Materials (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total | ||||||||||||
| Equipment | ||||||||||||
| Sub Equipment (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total |
7-331XX 22
331XX 22 General Requirements CLIN 0007: Impacted Media Remediation (Building 430 foundation)
331XX2201 - Supervision and Management 331XX2204 - Engineering, Surveying, and Quality Control 331XX2206 - First Aid, Fire Protection, Traffic Control and Security 331XX2207 - Health and Safety 331XX2208 - Temporary Construction Facilities (Ownership) 331XX2209 - Temporary Construction Facilities (Operation) 331XX2210 - Project Utilities Totals for 331XX 02
Labor Categories (by rate year) Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost
| Subcontractor Labor Categories (by rate year) | ||||||||||||||||||||||||||||||||
| Total | ||||||||||||||||||||||||||||||||
| Fee | ||||||||||||||||||||||||||||||||
| Total Labor | ||||||||||||||||||||||||||||||||
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||||||||||||||||||||||||||
| Subtotal | ||||||||||||||||||||||||||||||||
| G&A | ||||||||||||||||||||||||||||||||
| Fee | ||||||||||||||||||||||||||||||||
| Total ODC | ||||||||||||||||||||||||||||||||
| Travel | ||||||||||||||||||||||||||||||||
| Sub Travel (if applicable) | ||||||||||||||||||||||||||||||||
| Subtotal | ||||||||||||||||||||||||||||||||
| G&A | ||||||||||||||||||||||||||||||||
| Total | ||||||||||||||||||||||||||||||||
| Materials | ||||||||||||||||||||||||||||||||
| Sub Materials (if applicable) | ||||||||||||||||||||||||||||||||
| Subtotal | ||||||||||||||||||||||||||||||||
| G&A | ||||||||||||||||||||||||||||||||
| Fee | ||||||||||||||||||||||||||||||||
| Total | ||||||||||||||||||||||||||||||||
| Equipment | ||||||||||||||||||||||||||||||||
| Sub Equipment (if applicable) | ||||||||||||||||||||||||||||||||
| Subtotal | ||||||||||||||||||||||||||||||||
| G&A | ||||||||||||||||||||||||||||||||
| Fee | ||||||||||||||||||||||||||||||||
| Total |
CLIN 0007 Rollup
| CLIN 0007: Impacted Media Remediation (Building 430 foundation) | |||||
| Labor Categories (by rate year) | Category Units | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | |||||
| Total | |||||
| Fee | |||||
| Total Labor | |||||
| ODCs | Qty | Total Units | Unit Rate | Cost | |
| Sub ODC (if applicable) | |||||
| Subtotal | |||||
| G&A | |||||
| Fee | |||||
| Total ODC | |||||
| Travel | |||||
| Sub Travel (if applicable) | |||||
| Subtotal | |||||
| G&A | |||||
| Total | |||||
| Materials | |||||
| Sub Materials (if applicable) | |||||
| Subtotal | |||||
| G&A | |||||
| Fee | |||||
| Total | |||||
| Equipment | |||||
| Sub Equipment (if applicable) | |||||
| Subtotal | |||||
| G&A | |||||
| Fee | |||||
| Total |
CLIN 09 Summary CLIN 0009: Impacted Media Remediation (Building 431/432 Foundation)
Total Cost
| Labor |
| Subcontractor |
| Travel |
| ODCs |
| Materials |
| Equipment |
| SUBTOTAL |
| G&A |
| SUBTOTAL |
| Fee |
| TOTAL TASK 2c (CLIN 0009) |
9-331XX 02
331XX 02 Monitoring, Sampling, Testing, and Analysis CLIN 0009: Impacted Media Remediation (Building 431/432 Foundation)
| 331XX0201 - Meteorological Monitoring | 331XX0202 - Radiation Monitoring | 331XX0203 - Air Monitoring and Sampling | 331XX0204 - Monitoring Wells | 331XX0205 - Sampling Surface Water/Groundwater/Liquid Waste | 331XX0206 - Sampling Soil and Sediment | 331XX0208 - Sampling Radioactive Contaminated Media | 331XX0209 - Laboratory Chemical Analysis | 331XX0210 - Radioactive Waste Analysis | 331XX0211 - Geotechnical Testing | ||||||||||||||||||||||||||||||||||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate |
| Subcontractor Labor Categories (by rate year) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total | |||||||||||||||||||||||||||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total Labor | |||||||||||||||||||||||||||||||||||||||||||||||||
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | ||||||||||
| Sub ODC (if applicable) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Subtotal | |||||||||||||||||||||||||||||||||||||||||||||||||
| G&A | |||||||||||||||||||||||||||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total ODC | |||||||||||||||||||||||||||||||||||||||||||||||||
| Travel | |||||||||||||||||||||||||||||||||||||||||||||||||
| Sub Travel (if applicable) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Subtotal | |||||||||||||||||||||||||||||||||||||||||||||||||
| G&A | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total | |||||||||||||||||||||||||||||||||||||||||||||||||
| Materials | |||||||||||||||||||||||||||||||||||||||||||||||||
| Sub Materials (if applicable) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Subtotal | |||||||||||||||||||||||||||||||||||||||||||||||||
| G&A | |||||||||||||||||||||||||||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total | |||||||||||||||||||||||||||||||||||||||||||||||||
| Equipment | |||||||||||||||||||||||||||||||||||||||||||||||||
| Sub Equipment (if applicable) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Subtotal | |||||||||||||||||||||||||||||||||||||||||||||||||
| G&A | |||||||||||||||||||||||||||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total |
9-331XX 03
331XX 03 Site Work CLIN 0009: Impacted Media Remediation (Building 431/432 Foundation)
| 331XX0302 - Clearing and Grubbing | 331XX0303 - Earthwork | 331XX0304 - Roads/Parking/Curbs/Walks | 331XX0305 - Fencing | Totals for 331XX 03 | |||||||||||||||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | |||||||||||||||||||||||||
| Total | |||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||||||||||||||
| Subtotal | ||||||||||||||||||||
| G&A | ||||||||||||||||||||
| Fee | ||||||||||||||||||||
| Total ODC | ||||||||||||||||||||
| Travel | ||||||||||||||||||||
| Sub Travel (if applicable) | ||||||||||||||||||||
| Subtotal | ||||||||||||||||||||
| G&A | ||||||||||||||||||||
| Total | ||||||||||||||||||||
| Materials | ||||||||||||||||||||
| Sub Materials (if applicable) | ||||||||||||||||||||
| Subtotal | ||||||||||||||||||||
| G&A | ||||||||||||||||||||
| Fee | ||||||||||||||||||||
| Total | ||||||||||||||||||||
| Equipment | ||||||||||||||||||||
| Sub Equipment (if applicable) | ||||||||||||||||||||
| Subtotal | ||||||||||||||||||||
| G&A | ||||||||||||||||||||
| Fee | ||||||||||||||||||||
| Total |
9-331XX 05
331XX 05 Surface Water Collection and Control CLIN 0009: Impacted Media Remediation (Building 431/432 Foundation)
| 331XX0507 - Sediment Barriers | 331XX0509 - Pumping/Draining Collection | Totals for 331XX 05 | |||||||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | |||||||||||||||
| Total | |||||||||||||||
| Fee | |||||||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total ODC | ||||||||||||
| Travel | ||||||||||||
| Sub Travel (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Total | ||||||||||||
| Materials | ||||||||||||
| Sub Materials (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total | ||||||||||||
| Equipment | ||||||||||||
| Sub Equipment (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total |
9-331XX 08
331XX 08 Solids Collection and Containment CLIN 0009: Impacted Media Remediation (Building 431/432 Foundation)
| 331XX0801 - Contaminated Soil Collection | Totals for 331XX 08 | |||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | ||||||||||
| Total | ||||||||||
| Fee | ||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total ODC | ||||||||
| Travel | ||||||||
| Sub Travel (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Total | ||||||||
| Materials | ||||||||
| Sub Materials (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total | ||||||||
| Equipment | ||||||||
| Sub Equipment (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total |
9-331XX 09
331XX 09 Liquids/Sediments/Sludges Collection and Containment CLIN 0009: Impacted Media Remediation (Building 431/432 Foundation)
| 331XX0907 - Lagoons/Basins/Tanks/Dikes/Pump System | Totals for 331XX 09 | |||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | ||||||||||
| Total | ||||||||||
| Fee | ||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total ODC | ||||||||
| Travel | ||||||||
| Sub Travel (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Total | ||||||||
| Materials | ||||||||
| Sub Materials (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total | ||||||||
| Equipment | ||||||||
| Sub Equipment (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total |
9-331XX 19
331XX 19 Disposal (Commercial) CLIN 0009: Impacted Media Remediation (Building 431/432 Foundation)
| 331XX1920 - Container Handling | Totals for 331XX 19 | |||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | ||||||||||
| Total | ||||||||||
| Fee | ||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total ODC | ||||||||
| Travel | ||||||||
| Sub Travel (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Total | ||||||||
| Materials | ||||||||
| Sub Materials (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total | ||||||||
| Equipment | ||||||||
| Sub Equipment (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total |
9-331XX 20
331XX 20 Site Restoration CLIN 0009: Impacted Media Remediation (Building 431/432 Foundation)
| 331XX2001 - Earthwork | 331XX2004 - Revegetation and Planting | Totals for 331XX 20 | |||||||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | |||||||||||||||
| Total | |||||||||||||||
| Fee | |||||||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total ODC | ||||||||||||
| Travel | ||||||||||||
| Sub Travel (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Total | ||||||||||||
| Materials | ||||||||||||
| Sub Materials (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total | ||||||||||||
| Equipment | ||||||||||||
| Sub Equipment (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total |
9-331XX 22
331XX 22 General Requirements CLIN 0009: Impacted Media Remediation (Building 431/432 Foundation)
331XX2201 - Supervision and Management 331XX2204 - Engineering, Surveying, and Quality Control 331XX2206 - First Aid, Fire Protection, Traffic Control and Security 331XX2207 - Health and Safety 331XX2208 - Temporary Construction Facilities (Ownership) 331XX2209 - Temporary Construction Facilities (Operation) 331XX2210 - Project Utilities Totals for 331XX 02
Labor Categories (by rate year) Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost
| Subcontractor Labor Categories (by rate year) | ||||||||||||||||||||||||||||||||
| Total | ||||||||||||||||||||||||||||||||
| Fee | ||||||||||||||||||||||||||||||||
| Total Labor | ||||||||||||||||||||||||||||||||
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||||||||||||||||||||||||||
| Subtotal | ||||||||||||||||||||||||||||||||
| G&A | ||||||||||||||||||||||||||||||||
| Fee | ||||||||||||||||||||||||||||||||
| Total ODC | ||||||||||||||||||||||||||||||||
| Travel | ||||||||||||||||||||||||||||||||
| Sub Travel (if applicable) | ||||||||||||||||||||||||||||||||
| Subtotal | ||||||||||||||||||||||||||||||||
| G&A | ||||||||||||||||||||||||||||||||
| Total | ||||||||||||||||||||||||||||||||
| Materials | ||||||||||||||||||||||||||||||||
| Sub Materials (if applicable) | ||||||||||||||||||||||||||||||||
| Subtotal | ||||||||||||||||||||||||||||||||
| G&A | ||||||||||||||||||||||||||||||||
| Fee | ||||||||||||||||||||||||||||||||
| Total | ||||||||||||||||||||||||||||||||
| Equipment | ||||||||||||||||||||||||||||||||
| Sub Equipment (if applicable) | ||||||||||||||||||||||||||||||||
| Subtotal | ||||||||||||||||||||||||||||||||
| G&A | ||||||||||||||||||||||||||||||||
| Fee | ||||||||||||||||||||||||||||||||
| Total |
CLIN 0009 Rollup CLIN 0009: Impacted Media Remediation (Building 431/432 Foundation)
| Labor Categories (by rate year) | Category Units | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | |||||
| Total | |||||
| Fee | |||||
| Total Labor | |||||
| ODCs | Qty | Total Units | Unit Rate | Cost | |
| Sub ODC (if applicable) | |||||
| Subtotal | |||||
| G&A | |||||
| Fee | |||||
| Total ODC | |||||
| Travel | |||||
| Sub Travel (if applicable) | |||||
| Subtotal | |||||
| G&A | |||||
| Total | |||||
| Materials | |||||
| Sub Materials (if applicable) | |||||
| Subtotal | |||||
| G&A | |||||
| Fee | |||||
| Total | |||||
| Equipment | |||||
| Sub Equipment (if applicable) | |||||
| Subtotal | |||||
| G&A | |||||
| Fee | |||||
| Total |
CLIN 0011 Summary CLIN 0011: Impacted Media Remediation (Building 433 Foundation, Sidewalls, and Roof)
Total Cost
| Labor |
| Subcontractor |
| Travel |
| ODCs |
| Materials |
| Equipment |
| SUBTOTAL |
| G&A |
| SUBTOTAL |
| Fee |
| TOTAL TASK 2d (CLIN 0011) |
11-331XX 02
331XX 02 Monitoring, Sampling, Testing, and Analysis CLIN 0011: Impacted Media Remediation (Building 433 Foundation, Sidewalls, and Roof)
| 331XX0201 - Meteorological Monitoring | 331XX0202 - Radiation Monitoring | 331XX0203 - Air Monitoring and Sampling | 331XX0204 - Monitoring Wells | 331XX0205 - Sampling Surface Water/Groundwater/Liquid Waste | 331XX0206 - Sampling Soil and Sediment | 331XX0208 - Sampling Radioactive Contaminated Media | 331XX0209 - Laboratory Chemical Analysis | 331XX0210 - Radioactive Waste Analysis | 331XX0211 - Geotechnical Testing | ||||||||||||||||||||||||||||||||||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate |
| Subcontractor Labor Categories (by rate year) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total | |||||||||||||||||||||||||||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total Labor | |||||||||||||||||||||||||||||||||||||||||||||||||
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | ||||||||||
| Sub ODC (if applicable) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Subtotal | |||||||||||||||||||||||||||||||||||||||||||||||||
| G&A | |||||||||||||||||||||||||||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total ODC | |||||||||||||||||||||||||||||||||||||||||||||||||
| Travel | |||||||||||||||||||||||||||||||||||||||||||||||||
| Sub Travel (if applicable) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Subtotal | |||||||||||||||||||||||||||||||||||||||||||||||||
| G&A | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total | |||||||||||||||||||||||||||||||||||||||||||||||||
| Materials | |||||||||||||||||||||||||||||||||||||||||||||||||
| Sub Materials (if applicable) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Subtotal | |||||||||||||||||||||||||||||||||||||||||||||||||
| G&A | |||||||||||||||||||||||||||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total | |||||||||||||||||||||||||||||||||||||||||||||||||
| Equipment | |||||||||||||||||||||||||||||||||||||||||||||||||
| Sub Equipment (if applicable) | |||||||||||||||||||||||||||||||||||||||||||||||||
| Subtotal | |||||||||||||||||||||||||||||||||||||||||||||||||
| G&A | |||||||||||||||||||||||||||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||||||||||||||||||||||||||
| Total |
11-331XX 03
331XX 03 Site Work CLIN 0011: Impacted Media Remediation (Building 433 Foundation, Sidewalls, and Roof)
| 331XX0302 - Clearing and Grubbing | 331XX0303 - Earthwork | 331XX0304 - Roads/Parking/Curbs/Walks | 331XX0305 - Fencing | Totals for 331XX 03 | |||||||||||||||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | |||||||||||||||||||||||||
| Total | |||||||||||||||||||||||||
| Fee | |||||||||||||||||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||||||||||||||
| Subtotal | ||||||||||||||||||||
| G&A | ||||||||||||||||||||
| Fee | ||||||||||||||||||||
| Total ODC | ||||||||||||||||||||
| Travel | ||||||||||||||||||||
| Sub Travel (if applicable) | ||||||||||||||||||||
| Subtotal | ||||||||||||||||||||
| G&A | ||||||||||||||||||||
| Total | ||||||||||||||||||||
| Materials | ||||||||||||||||||||
| Sub Materials (if applicable) | ||||||||||||||||||||
| Subtotal | ||||||||||||||||||||
| G&A | ||||||||||||||||||||
| Fee | ||||||||||||||||||||
| Total | ||||||||||||||||||||
| Equipment | ||||||||||||||||||||
| Sub Equipment (if applicable) | ||||||||||||||||||||
| Subtotal | ||||||||||||||||||||
| G&A | ||||||||||||||||||||
| Fee | ||||||||||||||||||||
| Total |
11-331XX 05
331XX 05 Surface Water Collection and Control CLIN 0011: Impacted Media Remediation (Building 433 Foundation, Sidewalls, and Roof)
| 331XX0507 - Sediment Barriers | 331XX0509 - Pumping/Draining Collection | Totals for 331XX 05 | |||||||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | |||||||||||||||
| Total | |||||||||||||||
| Fee | |||||||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total ODC | ||||||||||||
| Travel | ||||||||||||
| Sub Travel (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Total | ||||||||||||
| Materials | ||||||||||||
| Sub Materials (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total | ||||||||||||
| Equipment | ||||||||||||
| Sub Equipment (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total |
11-331XX 08
331XX 08 Solids Collection and Containment CLIN 0011: Impacted Media Remediation (Building 433 Foundation, Sidewalls, and Roof)
| 331XX0801 - Contaminated Soil Collection | Totals for 331XX 08 | |||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | ||||||||||
| Total | ||||||||||
| Fee | ||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total ODC | ||||||||
| Travel | ||||||||
| Sub Travel (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Total | ||||||||
| Materials | ||||||||
| Sub Materials (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total | ||||||||
| Equipment | ||||||||
| Sub Equipment (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total |
11-331XX 09
331XX 09 Liquids/Sediments/Sludges Collection and Containment CLIN 0011: Impacted Media Remediation (Building 433 Foundation, Sidewalls, and Roof)
| 331XX0907 - Lagoons/Basins/Tanks/Dikes/Pump System | Totals for 331XX 09 | |||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | ||||||||||
| Total | ||||||||||
| Fee | ||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total ODC | ||||||||
| Travel | ||||||||
| Sub Travel (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Total | ||||||||
| Materials | ||||||||
| Sub Materials (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total | ||||||||
| Equipment | ||||||||
| Sub Equipment (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total |
11-331XX 19
331XX 19 Disposal (Commercial) CLIN 0011: Impacted Media Remediation (Building 433 Foundation, Sidewalls, and Roof)
| 331XX1920 - Container Handling | Totals for 331XX 19 | |||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | ||||||||||
| Total | ||||||||||
| Fee | ||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total ODC | ||||||||
| Travel | ||||||||
| Sub Travel (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Total | ||||||||
| Materials | ||||||||
| Sub Materials (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total | ||||||||
| Equipment | ||||||||
| Sub Equipment (if applicable) | ||||||||
| Subtotal | ||||||||
| G&A | ||||||||
| Fee | ||||||||
| Total |
11-331XX 20
331XX 20 Site Restoration CLIN 0011: Impacted Media Remediation (Building 433 Foundation, Sidewalls, and Roof)
| 331XX2001 - Earthwork | 331XX2004 - Revegetation and Planting | Totals for 331XX 20 | |||||||||||||
| Labor Categories (by rate year) | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost | Category Qty | Hours | Total Hours | Hourly Labor Rate | Cost |
| Subcontractor Labor Categories (by rate year) | |||||||||||||||
| Total | |||||||||||||||
| Fee | |||||||||||||||
| Total Labor |
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total ODC | ||||||||||||
| Travel | ||||||||||||
| Sub Travel (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Total | ||||||||||||
| Materials | ||||||||||||
| Sub Materials (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total | ||||||||||||
| Equipment | ||||||||||||
| Sub Equipment (if applicable) | ||||||||||||
| Subtotal | ||||||||||||
| G&A | ||||||||||||
| Fee | ||||||||||||
| Total |
11-331XX 22
331XX 22 General Requirements CLIN 0011: Impacted Media Remediation (Building 433 Foundation, Sidewalls, and Roof)
331XX2201 - Supervision and Management 331XX2204 - Engineering, Surveying, and Quality Control 331XX2206 - First Aid, Fire Protection, Traffic Control and Security 331XX2207 - Health and Safety 331XX2208 - Temporary Construction Facilities (Ownership) 331XX2209 - Temporary Construction Facilities (Operation) 331XX2210 - Project Utilities Totals for 331XX 02
Labor Categories (by rate year) Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost Category Qty Hours Total Hours Hourly Labor Rate Cost
| Subcontractor Labor Categories (by rate year) | ||||||||||||||||||||||||||||||||
| Total | ||||||||||||||||||||||||||||||||
| Fee | ||||||||||||||||||||||||||||||||
| Total Labor | ||||||||||||||||||||||||||||||||
| ODCs | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost | Qty | Units | Unit Rate | Cost |
| Sub ODC (if applicable) | ||||||||||||||||||||||||||||||||
| Subtotal | ||||||||||||||||||||||||||||||||
| G&A | ||||||||||||||||||||||||||||||||
| Fee | ||||||||||||||||||||||||||||||||
| Total ODC | ||||||||||||||||||||||||||||||||
| Travel | ||||||||||||||||||||||||||||||||
| Sub Travel (if applicable) | ||||||||||||||||||||||||||||||||
| Subtotal | ||||||||||||||||||||||||||||||||
| G&A | ||||||||||||||||||||||||||||||||
| Total | ||||||||||||||||||||||||||||||||
| Materials | ||||||||||||||||||||||||||||||||
| Sub Materials (if applicable) |