This is a project history form (ASW-14-ABQ0001) used to collect construction project experience from offerors responding to a federal contract solicitation. The form requires offerors to document three completed construction projects, with all information provided being the offeror's responsibility to ensure currency and completeness.
For each project, offerors must provide: firm name, project name and location, owner/organization, general scope of work, whether the contract involved the FAA, the offeror's role (prime or subcontractor), original and final completion dates, original and final contract amounts, extent and type of subcontracted work, any terminations or liquidated damages assessed, and owner reference contact information including current telephone number and email address. The form explicitly warns that any information left incomplete will render the offeror non-responsive to the solicitation. This template accommodates documentation of three separate projects across two pages, with Project #3 contained in Attachment #1.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 697DCK-26-R-00095 Amendment 0001 - Update Dates.pdf | ||
| Attachment 5 WD IL20260008.pdf | ||
| 697DCK-26-R-00095.pdf | ||
| Attachment 1 Part I-Section C-Description_ZAU IIJA Underground Utility Improvments.pdf | ||
| Attachment 2 Specifications-22001033_ZAU IIJA Underground Utility Improvments.pdf | ||
| Attachment 3 Full Project Drawings_22001033_ZAU.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ASW-14-ABQ0001
Note: It is the offeror's responsibility to ensure that all information provided is current.
Additionally any information not completed on this form will deem the offeror non-responsive
Project #1
Firm’s Name:
Name of Project:
Location of Project:
Owner/Organization:
General Scope of Construction Project:
Is this an FAA Contract Yes No
Summary of Your Role in this Project: Prime Subcontractor
Original Completion Date Final Completion Date
Original Contract Amount Final Contract Amount
Extent and Type of Work You Subcontracted:
Were You Terminated or Assessed Liquidated Damages? (If yes, explain)
Owner’s Point of Contact for Reference (Name and Company)
Current Telephone Number of Reference POC and current email address:
Project #2
Firm’s Name:
Name of Project:
Location of Project:
Owner/Organization:_
General Scope of Construction Project:
Is this an FAA Contract Yes No
Summary of Your Role in this Project: Prime Subcontractor
Original Completion Date Final Completion Date
Original Contract Amount Final Contract Amount
Extent and Type of Work You Subcontracted:
Were You Terminated or Assessed Liquidated Damages? (If yes, explain)
Owner’s Point of Contact for Reference (Name and Company)
Current Telephone Number of Reference POC and current email address:
ASW-14-ABQ0001
Attachment #1
Project #3
Firm’s Name:
Name of Project:
Location of Project:
Owner/Organization:
General Scope of Construction Project:
Is this an FAA Contract Yes No
Summary of Your Role in this Project: Prime Subcontractor
Original Completion Date Final Completion Date
Original Contract Amount Final Contract Amount
Extent and Type of Work You Subcontracted:
Were You Terminated or Assessed Liquidated Damages? (if yes, explain)
Owner’s Point of Contact for Reference (Name and Company)
Current Telephone Number of Reference POC and current email address: